Revised December 4, 2014 - Land Use Meeting Agenda Item #12 Subject FDOT Draft Tentative Work Program Briefings None Contact and/or Presenter Information Clarke Davis Transportation Planning Division Manager [email protected] 941.708.7450 x7272 Action Requested Recommend the Sarasota-Manatee Metropolitan Planning Organization Board endorse the Florida Department of Transportations Draft Tentative Work Program for FY15/16-FY19/20. Enabling/Regulating Authority n/a Background Discussion The Florida Department of Transportations Work Program is a five year schedule of State and Federal funded capital improvements; it also includes some local operations and maintenance support. Table 1 shows the approximate flow of the work program development process. The process is currently at the steps in November and December of Year 1. Some programmed funds are prioritized by the Metropolitan Planning Organization (MPO) based on County priorities. Therefore and as a stakeholder, the MPO Board reviews the program and provides recommendations during the regional agency and public involvement process leading up to the 2015 legislative session. The discussion for this agenda item will include an overview of the projects in the Draft Tentative Work Program for FY15/16-FY19/20. It is scheduled for MPO Board consideration on December 15, 2014. County Attorney Review Not Reviewed (No apparent legal issues) Explanation of Other Reviewing Attorney N/A Instructions to Board Records Please return a copy of the approved agenda item to Clarke Davis, [email protected], 941.708.7450 x7272 Manatee County Government Administrative Chambers First Floor, Chambers December 4, 2014 - 9:00 a.m.

Upload: others

Post on 01-Oct-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Manatee County Government Administrative Chambers First ... · 12/4/2014  · November and December of Year 1.€ Some programmed funds are prioritized by the Metropolitan Planning

Revised December 4, 2014 - Land Use Meeting Agenda Item #12

Subject FDOT Draft Tentative Work Program Briefings None Contact and/or Presenter Information Clarke Davis Transportation Planning Division Manager [email protected] 941.708.7450 x7272 Action Requested Recommend the Sarasota-Manatee Metropolitan Planning Organization Board endorse the Florida Department of Transportation’s Draft Tentative Work Program for FY15/16-FY19/20. Enabling/Regulating Authority n/a Background Discussion

The Florida Department of Transportation’s Work Program is a five year schedule of State and Federal funded capital improvements; it also includes some local operations and maintenance support.  Table 1 shows the approximate flow of the work program development process.  The process is currently at the steps in November and December of Year 1.  Some programmed funds are prioritized by the Metropolitan Planning Organization (MPO) based on County priorities.  Therefore and as a stakeholder, the MPO Board reviews the program and provides recommendations during the regional agency and public involvement process leading up to the 2015 legislative session.

The discussion for this agenda item will include an overview of the projects in the Draft Tentative Work Program for FY15/16-FY19/20.   It is scheduled for MPO Board consideration on December 15, 2014. County Attorney Review Not Reviewed (No apparent legal issues) Explanation of Other Reviewing Attorney N/A Instructions to Board Records Please return a copy of the approved agenda item to Clarke Davis, [email protected], 941.708.7450 x7272

Manatee County Government Administrative ChambersFirst Floor, Chambers

December 4, 2014 - 9:00 a.m.

Page 2: Manatee County Government Administrative Chambers First ... · 12/4/2014  · November and December of Year 1.€ Some programmed funds are prioritized by the Metropolitan Planning

Cost and Funds Source Account Number and Name n/a Amount and Frequency of Recurring Costs n/a Attachment:  Work Program Process.pdf Attachment:  2016-2020 Tentative Work Program-Manatee.pdf

Manatee County Government Administrative ChambersFirst Floor, Chambers

December 4, 2014 - 9:00 a.m.

Page 3: Manatee County Government Administrative Chambers First ... · 12/4/2014  · November and December of Year 1.€ Some programmed funds are prioritized by the Metropolitan Planning

Table 1

FDOT Work Program / MPO Transportation Improvement ProgramApproximate Calendar of Events

Who What

Year 1 Jan MPO & FDOT staff Request any new projects that will require cost estimates

Feb County staff Submit potential new projects

Mar

County Commission Adopt County's project priorities

Apr

May County staff Submit adopted priorities and project detail sheets to MPO

Jun MPO and local staff Prepare composite project priority lists

MPO committees Provide project priority recommendations

Jul MPO Board Adopt MPO project priority lists

Aug

Sep

FDOT staff Develop new work program based in part on MPO priorities

Oct

Nov FDOT staff Provide draft tentative work program to MPOs

Dec MPO Board Endorse draft tentative work program (public hearing)

Year 2 Jan

FDOT staff Prepare tentative work program for legislature

Feb

Mar [ Legislative session begins ]

Apr MPO staff Prepare draft TIP based on tentative program

May Legislature Pass proposed budget

Governor Approve budget including work program

Jun MPO Board Adopt TIP aligned with adopted work program (public hearing)

Jul [ Work Program & TIP are in effect ]

When

The process starts in Jan of Year 1 to have a program in effect on Jul 1 of Year 2. Therefore each Jan, the

end phase of a program's process overlaps the early part of the next. In addition to the overall process,

there can be program amendments throughout the year. The work program and TIP must be aligned, so

changes to one will prompt changes to the other. The MPO Board considers the TIP and each amendment

in an advertised public hearing.

Page 4: Manatee County Government Administrative Chambers First ... · 12/4/2014  · November and December of Year 1.€ Some programmed funds are prioritized by the Metropolitan Planning

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1

July 1, 2015 Through June 30, 2020

COUNTYMANATEE

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1

-

DRAFT

2016 2020

TENTATIVE WORK PROGRAM REPORT

Tentative Work Program Fiscal Years

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –

Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES

Page: 112/3/2014Run Date: SnapShot Date: 11/12/2014

Page 5: Manatee County Government Administrative Chambers First ... · 12/4/2014  · November and December of Year 1.€ Some programmed funds are prioritized by the Metropolitan Planning

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1

COUNTYMANATEE

MISSION STATEMENT The Department will provide a safe, interconnected statewide transportation system for Florida's citizens and visitors that ensures the mobility of people and goods, while enhancing economic prosperity and sustaining the quality of our environment.

July 1, 2015 Through June 30, 2020

DRAFTTENTATIVE WORK PROGRAM REPORT

Robin StublenCommunications SpecialistDistrict One Headquarters801 North BroadwayP.O. Box 1249Bartow, FL 33831(863) 519-2362

Debbie TowerCommunications DirectorSouthwest Area Office10041 Daniels ParkwayFort Myers, FL 33913(239) 461-4300

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –

Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES

Page: 212/3/2014Run Date: SnapShot Date: 11/12/2014

Page 6: Manatee County Government Administrative Chambers First ... · 12/4/2014  · November and December of Year 1.€ Some programmed funds are prioritized by the Metropolitan Planning

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1

COUNTYMANATEE

July 1, 2015 Through June 30, 2020

CURRENTLY REPORTED ACTIVE FUND CODES

DRAFTTENTATIVE WORK PROGRAM REPORT

ACSU Advance Construction (SU)

BRRP State Bridge Repair And Rehab

DDR District Dedicated Revenue

DIH State In-house Product Support

DITS Statewide ITS - State 100%

DPTO State PTO

DS State Primary Highways and PTO

FTA Federal Transit Administration

GMR General Revenue for SIS

HSP Highway Safety Program

LF Local Funds

LFP Local Fund for Participating

PORT Seaports

SA STP, Any Area

SU STP, Urban Areas > 200k

TRIP Trans Regional Incentive Prog

ACNP

ACTU

NHRE

TALT

TALU

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –

Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES

Page: 312/3/2014Run Date: SnapShot Date: 11/12/2014

Page 7: Manatee County Government Administrative Chambers First ... · 12/4/2014  · November and December of Year 1.€ Some programmed funds are prioritized by the Metropolitan Planning

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1TENTATIVE WORK PROGRAM REPORT

July 1, 2015 Through June 30, 2020 COUNTYMANATEE

DRAFT

HIGHWAYS

FPN: 4331421 Project/Location: 10TH AVENUE FROM RIVERSIDE DRIVE TO 17TH

STREET

Project Length: 0.001

Desc: PD&E/EMO STUDY

Comments:

Begin Mile Post: 0.000 End Mile Post: 0.001

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

PDE SU $454,500

PE SU $500,000

$454,500 $500,000Project Total:

FPN: 4366821 Project/Location: 10TH STREET (US 301) FROM 5TH AVENUE DR W.

TO E. OF 3RD AVENUE W.

Project Length: 0.328

Desc: RAIL SAFETY PROJECT

Comments:

Begin Mile Post: 0.196 End Mile Post: 0.524

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

PE DIH $10,000

PE DS $240,330

RRU DS $650,000

CST DIH $21,580

CST DS $1,374,556

$250,330 $671,580 $1,374,556Project Total:

FPN: 4298661 Project/Location: 14TH AVENUE WEST AT 17TH STREET

WEST

Project Length: 0.013

Desc: INTERSECTION IMPROVEMENT

Comments:

Begin Mile Post: 1.000 End Mile Post: 1.012

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

CST SU $472,170

$472,170Project Total:

FPN: 4313502 Project/Location: 15TH ST E/301 BLVD E FROM TALLEVAST ROAD

TO US 41

Project Length: 4.741

Desc: ADD LANES & RECONSTRUCT

Comments:

Begin Mile Post: 1.679 End Mile Post: 6.243

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

PE SU $5,600,000

$5,600,000Project Total:

FPN: 4369821 Project/Location: 51ST STREET WEST FROM 53RD STREET WEST

TO 53RD AVENUE WEST

Project Length: 0.030

Desc: ADD TURN LANE(S)

Comments:

Begin Mile Post: 0.000 End Mile Post: 0.030

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

PE SU $120,000

CST DS $286

CST SU $223,265

$120,000 $223,551Project Total:

FPN: 4298711 Project/Location: 57TH ST E AT SR 64

Project Length: 0.400

Desc: INTERSECTION IMPROVEMENT

Comments:

Begin Mile Post: 1.800 End Mile Post: 2.200

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

CST SU $449,777

$449,777Project Total:

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –

Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES

Page: 412/3/2014Run Date: SnapShot Date: 11/12/2014

Page 8: Manatee County Government Administrative Chambers First ... · 12/4/2014  · November and December of Year 1.€ Some programmed funds are prioritized by the Metropolitan Planning

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1TENTATIVE WORK PROGRAM REPORT

July 1, 2015 Through June 30, 2020 COUNTYMANATEE

DRAFT

FPN: 4351131 Project/Location: 63RD AVE E AT 33RD STREET E

Project Length: 0.470

Desc: ADD LEFT TURN LANE(S)

Comments:

Begin Mile Post: 1.530 End Mile Post: 2.000

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

ROW LFP $221,823

CST SU $1,848,817

$221,823 $1,848,817Project Total:

FPN: 4350901 Project/Location: 9TH AVE E AT 15TH ST EAST

Project Length: 0.200

Desc: ADD TURN LANE(S)

Comments:

Begin Mile Post: 0.332 End Mile Post: 0.532

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

ROW SU $443,456

CST SU $1,059,321

$443,456 $1,059,321Project Total:

FPN: 4369831 Project/Location: BLACKSTONE PARK AT 14TH AVE W, 23RD AVE W

& BUSINESS 41 (VALENCIA DR)

Project Length: 0.001

Desc: SIDEWALK

Comments:

Begin Mile Post: 0.000 End Mile Post: 0.001

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

PE TALU $165,000

CST DS $1,572

CST TALU $394,247

$165,000 $395,819Project Total:

FPN: 4136391 Project/Location: BRADENTON TRAFFIC SIGNALS

REIMBURSEMENT

Project Length: 0.790

Desc: TRAFFIC SIGNALS

Comments:

Begin Mile Post: 6.559 End Mile Post: 7.349

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

OPS DDR $122,816 $126,501 $130,296 $134,205 $138,231

$122,816 $126,501 $130,296 $134,205 $138,231Project Total:

FPN: 4371451 Project/Location: CORTEZ ROAD (SR 684) AT 43RD STREET

WEST

Project Length: 0.001

Desc: ADD TURN LANE(S)

Comments:

Begin Mile Post: 5.979 End Mile Post: 5.980

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

PE DIH $1,000

PE LFP $31,350

PE TRIP $31,350

CST DIH $1,000

CST LFP $240,300

CST TRIP $240,300

$63,700 $481,600Project Total:

FPN: 4351201 Project/Location: ELLENTON GILLETTE RD AT 69TH ST

E

Project Length: 0.200

Desc: ADD LEFT TURN LANE(S)

Comments:

Begin Mile Post: 3.502 End Mile Post: 3.702

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

CST SU $676,473

$676,473Project Total:

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –

Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES

Page: 512/3/2014Run Date: SnapShot Date: 11/12/2014

Page 9: Manatee County Government Administrative Chambers First ... · 12/4/2014  · November and December of Year 1.€ Some programmed funds are prioritized by the Metropolitan Planning

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1TENTATIVE WORK PROGRAM REPORT

July 1, 2015 Through June 30, 2020 COUNTYMANATEE

DRAFT

FPN: 4332771 Project/Location: EMERGENCY VEHICLE PRIORITY SYSTEM

MANATEE COUNTY

Project Length: 0.001

Desc: ATMS - ARTERIAL TRAFFIC MGMT

Comments:

Begin Mile Post: 0.000 End Mile Post: 0.001

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

CST SU $1,631,700

$1,631,700Project Total:

FPN: 4136401 Project/Location: HOLMES BEACH TRAFFIC SIGNALS

REIMBURSEMENT

Project Length: 0.100

Desc: TRAFFIC SIGNALS

Comments:

Begin Mile Post: 0.000 End Mile Post: 0.100

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

OPS DDR $6,080 $6,263 $6,451 $6,644 $6,844

$6,080 $6,263 $6,451 $6,644 $6,844Project Total:

FPN: 4363211 Project/Location: I 75 (SR 93) SOUTH OF UNIVERSITY BLVD NORTH

OF US 301

Project Length: 11.400

Desc: WETLAND MITIGATION/RESTORATION

Comments:

Begin Mile Post: 0.000 End Mile Post: 11.400

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

ENV DS $935,000 $394,900 $311,500

$935,000 $394,900 $311,500Project Total:

FPN: 4370841 Project/Location: I-75 (SR 93) AT SR 64 INTERCHANGE

Project Length: 0.570

Desc: LIGHTING

Comments:

Begin Mile Post: 7.008 End Mile Post: 7.578

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

CST DDR $2,467,551

CST DIH $315,900

$2,783,451Project Total:

FPN: 2010327 Project/Location: I-75 (SR 93) AT UNIVERSITY PARKWAY

(MANATEE)

Project Length: 0.460

Desc: LANDSCAPING

Comments:

Begin Mile Post: 0.000 End Mile Post: 0.460

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

CST DIH $62,766

CST DS $553,000

$615,766Project Total:

FPN: 2010325 Project/Location: I-75 (SR 93) AT US 301 INTERCHANGE

Project Length: 1.150

Desc: INTERCHANGE - ADD LANES

Comments:

Begin Mile Post: 10.250 End Mile Post: 11.400

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

ENV DS $430,000

$430,000Project Total:

FPN: 4370821 Project/Location: I-75 (SR 93) FROM I-275 INTERCHANGE TO CR 683

MOCASSIN WALLOW

Project Length: 2.410

Desc: LIGHTING

Comments:

Begin Mile Post: 14.108 End Mile Post: 16.518

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

DSB DDR $5,799,201

DSB DIH $558,463

$6,357,664Project Total:

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –

Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES

Page: 612/3/2014Run Date: SnapShot Date: 11/12/2014

Page 10: Manatee County Government Administrative Chambers First ... · 12/4/2014  · November and December of Year 1.€ Some programmed funds are prioritized by the Metropolitan Planning

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1TENTATIVE WORK PROGRAM REPORT

July 1, 2015 Through June 30, 2020 COUNTYMANATEE

DRAFT

FPN: 4340261 Project/Location: I-75 (SR 93) FROM N OF I-275 TO MANATEE

COUNTY LINE

Project Length: 5.320

Desc: ITS FREEWAY MANAGEMENT

Comments:

Begin Mile Post: 15.251 End Mile Post: 20.571

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

PE DIH $1,000

PE DITS $75,000

DSB DIH $381,607

DSB DITS $3,276,515

$1,000 $3,733,122Project Total:

FPN: 2010324 Project/Location: I-75 (SR93) AT UNIVERSITY

INTERCHANGE

Project Length: 0.460

Desc: INTERCHANGE - ADD LANES

Comments:

Begin Mile Post: 0.000 End Mile Post: 0.460

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

INC SA $2,500,000

$2,500,000Project Total:

FPN: 4349291 Project/Location: I-75 S OF MOCCASIN WALLOW RD TO

HILLSBOROUGH C/L

Project Length: 4.857

Desc: RESURFACING

Comments:

Begin Mile Post: 15.714 End Mile Post: 20.571

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

CST ACNP $8,609,803

$8,609,803Project Total:

FPN: 4350382 Project/Location: MANATEE COUNTY SCOUR COUNTERMEASURE

AT VARIOUS LOCATIONS

Project Length: 0.802

Desc: BRIDGE-REPAIR/REHABILITATION

Comments:

Begin Mile Post: 0.480 End Mile Post: 1.204

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

CST BRRP $2,141,371

CST DIH $169,987

$2,311,358Project Total:

FPN: 4126731 Project/Location: MANATEE COUNTY TRAFFIC SIGNALS

REIMBURSEMENT

Project Length: 5.519

Desc: TRAFFIC SIGNALS

Comments:

Begin Mile Post: 0.560 End Mile Post: 6.079

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

OPS DDR $128,899 $307,015 $316,225 $329,034 $338,905

OPS DITS $169,173

$298,072 $307,015 $316,225 $329,034 $338,905Project Total:

FPN: 4371061 Project/Location: MANATEE/SARASOTA TMC OPS FUND COUNTY

WIDE

Project Length: 0.001

Desc: OTHER ITS

Comments:

Begin Mile Post: 0.000 End Mile Post: 0.001

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

OPS DS $429,000 $429,000

$429,000 $429,000Project Total:

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –

Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES

Page: 712/3/2014Run Date: SnapShot Date: 11/12/2014

Page 11: Manatee County Government Administrative Chambers First ... · 12/4/2014  · November and December of Year 1.€ Some programmed funds are prioritized by the Metropolitan Planning

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1TENTATIVE WORK PROGRAM REPORT

July 1, 2015 Through June 30, 2020 COUNTYMANATEE

DRAFT

FPN: 4353691 Project/Location: MOCCASIN WALLOW ROAD AT US 41

Project Length: 0.200

Desc: ADD TURN LANE(S)

Comments:

Begin Mile Post: 11.469 End Mile Post: 11.669

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

ROW SU $60,099

CST SU $236,166

$60,099 $236,166Project Total:

FPN: 4332131 Project/Location: MORGAN JOHNSON ROAD FROM RIVERSIDE

TERRACE TO SR 64

Project Length: 0.657

Desc: SIDEWALK

Comments:

Begin Mile Post: 1.543 End Mile Post: 2.200

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

PE ACTU $45,000

PE TALU $8,000 $78,020

CST TALT $58,179

CST TALU $437,081

$53,000 $78,020 $495,260Project Total:

FPN: 4136421 Project/Location: PALMETTO TRAFFIC SIGNALS

REIMBURSEMENT

Project Length: 0.751

Desc: TRAFFIC SIGNALS

Comments:

Begin Mile Post: 0.505 End Mile Post: 1.256

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

OPS DDR $33,440 $34,444 $35,477 $36,541 $37,638

$33,440 $34,444 $35,477 $36,541 $37,638Project Total:

FPN: 1961421 Project/Location: SARASOTA/MANATEE MPO IDENTIFIED

OPERATIONAL IMPROVEMENTS - FUNDING

Project Length: 0.000

Desc: FUNDING ACTION

Comments:

Begin Mile Post: 0.000 End Mile Post: 0.000

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

CST SU $61,396 $1,134,340 $5,192,830

$61,396 $1,134,340 $5,192,830Project Total:

FPN: 1961143 Project/Location: SR 45 (US 41/TAMIAMI TRAIL) AT PINEY POINT

RD AND DOCK ST (PORT MANATEE)

Project Length: 0.655

Desc: INTERSECTION IMPROVEMENT

Comments:

Begin Mile Post: 8.229 End Mile Post: 8.884

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

INC SA $400,000

$400,000Project Total:

FPN: 4081853 Project/Location: SR 64 (MANATEE AVE)TO PERICO BAY

BOULEVARD

Project Length: 1.936

Desc: BRIDGE REPLACEMENT

Comments:

Begin Mile Post: 0.216 End Mile Post: 2.152

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

PE DDR $5,065,117

PE DIH $200,000

PE DS $934,883

$6,200,000Project Total:

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –

Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES

Page: 812/3/2014Run Date: SnapShot Date: 11/12/2014

Page 12: Manatee County Government Administrative Chambers First ... · 12/4/2014  · November and December of Year 1.€ Some programmed funds are prioritized by the Metropolitan Planning

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1TENTATIVE WORK PROGRAM REPORT

July 1, 2015 Through June 30, 2020 COUNTYMANATEE

DRAFT

FPN: 4366841 Project/Location: SR 64 (MANATEE AVE) FROM E. OF 7TH STREET

W. TO E. OF 5TH STREET W.

Project Length: 0.106

Desc: RAIL SAFETY PROJECT

Comments:

Begin Mile Post: 1.194 End Mile Post: 1.300

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

PE DIH $10,000

PE DS $90,000

RRU DS $250,000

CST DIH $10,530

CST DS $315,797

$100,000 $260,530 $315,797Project Total:

FPN: 4351361 Project/Location: SR 64 FROM E OF EXISTING TRAIL TO ANNA

MARIA BRIDGE

Project Length: 2.000

Desc: BIKE PATH/TRAIL

Comments:

Begin Mile Post: 0.000 End Mile Post: 2.000

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

PE TALU $60,000

CST DS $15,106

CST TALU $363,170

$60,000 $378,276Project Total:

FPN: 4350731 Project/Location: SR 64 FROM KAY RD TO E OF I-75

INTERCHANGE

Project Length: 0.767

Desc: RESURFACING

Comments:

Begin Mile Post: 5.773 End Mile Post: 6.540

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

CST DDR $52,650

CST DIH $33,014

CST NHRE $1,821,969

$1,907,633Project Total:

FPN: 4365511 Project/Location: SR 684 FROM 119TH ST WEST TO 86TH ST

WEST

Project Length: 2.068

Desc: SKID HAZARD OVERLAY

Comments:

Begin Mile Post: 1.188 End Mile Post: 3.256

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

PE DIH $10,000

PE HSP $300,000

CST DIH $55,300

CST DS $55,475

CST HSP $2,177,415

$310,000 $2,288,190Project Total:

FPN: 4302042 Project/Location: SR 684 FROM SR 789 (GULF DRIVE) TO 123RD

STREET WEST

Project Length: 0.900

Desc: REPLACE MOVABLE SPAN BRIDGE

Comments:

Begin Mile Post: 0.000 End Mile Post: 0.900

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

PE DDR $7,250,000

PE DIH $200,000

$7,450,000Project Total:

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –

Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES

Page: 912/3/2014Run Date: SnapShot Date: 11/12/2014

Page 13: Manatee County Government Administrative Chambers First ... · 12/4/2014  · November and December of Year 1.€ Some programmed funds are prioritized by the Metropolitan Planning

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1TENTATIVE WORK PROGRAM REPORT

July 1, 2015 Through June 30, 2020 COUNTYMANATEE

DRAFT

FPN: 4312071 Project/Location: SR 70 FROM 301 BLVD/15TH ST E TO LOCKWOOD

RIDGE ROAD

Project Length: 2.497

Desc: RESURFACING

Comments:

Begin Mile Post: 0.000 End Mile Post: 2.497

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

CST DDR $7,258,070

CST DIH $174,409

$7,432,479Project Total:

FPN: 4369241 Project/Location: SR 70 FROM 30TH AT 30TH STREET

EAST

Project Length: 0.200

Desc: INTERSECTION IMPROVEMENT

Comments:

Begin Mile Post: 1.148 End Mile Post: 1.348

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

PE SU $150,000

$150,000Project Total:

FPN: 4313731 Project/Location: SR 70 FROM LOCKWOOD RIDGE ROAD TO TARA

BLVD

Project Length: 2.342

Desc: RESURFACING

Comments:

Begin Mile Post: 2.465 End Mile Post: 4.807

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

RRU DS $4,000,000

CST DDR $259,353

CST DIH $209,868

CST SA $6,010,380

$10,479,601Project Total:

FPN: 4145062 Project/Location: SR 70 FROM LORRAINE RD TO SINGLETARY RD

(MYAKKA)

Project Length: 15.670

Desc: PD&E/EMO STUDY

Comments:

Begin Mile Post: 22.134 End Mile Post: 31.713

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

PDE DIH $430,000

PDE DS $3,870,000

$4,300,000Project Total:

FPN: 4365461 Project/Location: SR 70 FROM US 41 TO 540' EAST OF US

41

Project Length: 0.102

Desc: INTERSECTION IMPROVEMENT

Comments:

Begin Mile Post: 0.000 End Mile Post: 0.102

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

PE DIH $10,000

PE HSP $50,000

CST DIH $10,530

CST DS $4,611

CST HSP $92,184

$60,000 $107,325Project Total:

FPN: 4366761 Project/Location: SR 789 (LONGBOAT KEY) FROM NORTH SHORE

RD TO COQUINA PARK ENT

Project Length: 0.710

Desc: PD&E/EMO STUDY

Comments:

Begin Mile Post: 4.467 End Mile Post: 5.177

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

PDE SA $2,325,000

$2,325,000Project Total:

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –

Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES

Page: 1012/3/2014Run Date: SnapShot Date: 11/12/2014

Page 14: Manatee County Government Administrative Chambers First ... · 12/4/2014  · November and December of Year 1.€ Some programmed funds are prioritized by the Metropolitan Planning

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1TENTATIVE WORK PROGRAM REPORT

July 1, 2015 Through June 30, 2020 COUNTYMANATEE

DRAFT

FPN: 4369861 Project/Location: SR 789/GULF OF MEXICO DR FROM BROADWAY

TO LONGBOAT PASS BRIDGE

Project Length: 0.350

Desc: SIDEWALK

Comments:

Begin Mile Post: 4.211 End Mile Post: 4.561

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

PE TALU $115,000

ENV TALT $100,000

CST DS $2,439

CST TALU $264,783

$115,000 $100,000 $267,222Project Total:

FPN: 4332561 Project/Location: SR 93 (I-75) AT RR OVERPASS

Project Length: 0.901

Desc: RESURFACING

Comments:

Begin Mile Post: 12.451 End Mile Post: 13.352

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

ENV DS $50,000

CST ACNP $1,252,667

CST DS $78,547

$1,381,214Project Total:

FPN: 4279952 Project/Location: SR43 (US 301) FROM CR 675 TO MOCCASIN

WALLOW ROAD

Project Length: 1.212

Desc: LANDSCAPING

Comments:

Begin Mile Post: 10.457 End Mile Post: 11.669

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

CST DDR $559,086

$559,086Project Total:

FPN: 4279951 Project/Location: SR43 (US301) FROM CR 675 TO MOCCASIN

WALLOW RD

Project Length: 1.212

Desc: ADD LANES & RECONSTRUCT

Comments:

Begin Mile Post: 10.457 End Mile Post: 11.669

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

INC DDR $300,000

$300,000Project Total:

FPN: 4352861 Project/Location: US 301 AT ERIE RD/OLD TAMPA HWY

Project Length: 0.200

Desc: ADD LEFT TURN LANE(S)

Comments:

Begin Mile Post: 6.127 End Mile Post: 6.327

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

PE SU $168,000

CST SU $580,263

$168,000 $580,263Project Total:

FPN: 4345051 Project/Location: US 301 AT SR 70

Project Length: 0.500

Desc: INTERSECTION IMPROVEMENT

Comments:

Begin Mile Post: 3.810 End Mile Post: 4.310

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

PE HSP $110,000

ENV SA $10,000 $20,000

CST DDR $19,648

CST HSP $496,198

CST SA $10,530

$120,000 $546,376Project Total:

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –

Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES

Page: 1112/3/2014Run Date: SnapShot Date: 11/12/2014

Page 15: Manatee County Government Administrative Chambers First ... · 12/4/2014  · November and December of Year 1.€ Some programmed funds are prioritized by the Metropolitan Planning

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1TENTATIVE WORK PROGRAM REPORT

July 1, 2015 Through June 30, 2020 COUNTYMANATEE

DRAFT

FPN: 4312121 Project/Location: US 301 FROM 19TH AVENUE TO 69TH

AVENUE

Project Length: 0.720

Desc: RESURFACING

Comments:

Begin Mile Post: 3.995 End Mile Post: 4.715

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

ENV DS $200,000

CST DDR $2,992,354

CST DIH $46,215

$3,238,569Project Total:

FPN: 4332151 Project/Location: US 41 (14ST ST W) AT 9TH AVE (MLK)

Project Length: 0.000

Desc: INTERSECTION IMPROVEMENT

Comments:

Begin Mile Post: 0.000 End Mile Post: 0.000

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

PDE DIH $4,500

PDE DS $450,000

$454,500Project Total:

FPN: 1961142 Project/Location: US 41 (SR 45) FROM I-275 TO HILLSBOROUGH

CL

Project Length: 4.694

Desc: RESURFACING

Comments:

Begin Mile Post: 5.088 End Mile Post: 9.782

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

ENV DS $100,000

$100,000Project Total:

FPN: 4295061 Project/Location: US 41 / SR 45 FROM 63RD AVE W TO 53RD AVE

W

Project Length: 1.247

Desc: LIGHTING

Comments:

Begin Mile Post: 3.019 End Mile Post: 4.266

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

ROW HSP $487,626

$487,626Project Total:

FPN: 4335491 Project/Location: US 41 AT US 301 (10TH STREET E) IN

PALMETTO

Project Length: 0.200

Desc: SIDEWALK

Comments:

Begin Mile Post: 0.508 End Mile Post: 0.708

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

CST DDR $22,705

CST SU $667,630

$690,335Project Total:

FPN: 4365091 Project/Location: US 41 BUSINESS (9THSTREET WEST) FROM 3RD

AVENUE TO MANATEE AVE (SR64)

Project Length: 0.134

Desc: ADD RIGHT TURN LANE(S)

Comments:

Begin Mile Post: 0.213 End Mile Post: 0.347

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

PE DIH $10,000

PE DS $300,000

CST SA $483,905

$310,000 $483,905Project Total:

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –

Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES

Page: 1212/3/2014Run Date: SnapShot Date: 11/12/2014

Page 16: Manatee County Government Administrative Chambers First ... · 12/4/2014  · November and December of Year 1.€ Some programmed funds are prioritized by the Metropolitan Planning

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1TENTATIVE WORK PROGRAM REPORT

July 1, 2015 Through June 30, 2020 COUNTYMANATEE

DRAFT

FPN: 4335471 Project/Location: US 41 BUSINESS AT 3RD AVE

Project Length: 0.248

Desc: ADD RIGHT TURN LANE(S)

Comments:

Begin Mile Post: 2.288 End Mile Post: 2.488

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

CST DS $5,395

CST SU $131,318

$136,713Project Total:

FPN: 4335931 Project/Location: US 41 BUSINESS FROM GREEN BRIDGE TO

RIVERSIDE DRIVE

Project Length: 0.168

Desc: BIKE LANE/SIDEWALK

Comments:

Begin Mile Post: 1.211 End Mile Post: 1.379

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

CST ACSU $930,904

CST DDR $61,233

CST SU $30,810

$1,022,947Project Total:

FPN: 4335921 Project/Location: US 41 FROM 69TH AVE (BAY DRIVE) TO CORTEZ

ROAD

Project Length: 3.032

Desc: BIKE LANE/SIDEWALK

Comments:

Begin Mile Post: 2.252 End Mile Post: 5.284

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

PE SU $410,000

CST DDR $49,116

CST SU $1,232,640

$410,000 $1,281,756Project Total:

FPN: 4353491 Project/Location: US 41 GREEN BRIDGE MULTI-USE

PATH

Project Length: 1.032

Desc: BIKE PATH/TRAIL

Comments:

Begin Mile Post: 0.347 End Mile Post: 1.379

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

PE ACTU $200,000

PE TALU $210,000

CST DS $53,950

CST TALT $2,275,779

$410,000 $2,329,729Project Total:

HIGHWAYS TOTAL 2015/16 2016/17 2017/18 2018/19 2019/20

$55,757,941 $28,079,795 $13,239,226 $7,369,919 $12,279,161

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –

Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES

Page: 1312/3/2014Run Date: SnapShot Date: 11/12/2014

Page 17: Manatee County Government Administrative Chambers First ... · 12/4/2014  · November and December of Year 1.€ Some programmed funds are prioritized by the Metropolitan Planning

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1TENTATIVE WORK PROGRAM REPORT

July 1, 2015 Through June 30, 2020 COUNTYMANATEE

DRAFT

MISCELLANEOUS

FPN: 4368021 Project/Location: ATMS BLUETOOTH SYSTEM AT VARIOUS

LOCATIONS THROUGHOUT

Project Length: 0.001

Desc: ATMS - ARTERIAL TRAFFIC MGMT

Comments:

Begin Mile Post: 0.001 End Mile Post: 0.002

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

CAP SU $400,000

$400,000Project Total:

FPN: 4371021 Project/Location: ATMS MASTERPLAN & CONCEPT OF

OPERATIONS FOR REGIONAL TRAFFIC MGMT

SYST

Project Length: 0.001

Desc: ATMS - ARTERIAL TRAFFIC MGMT

Comments:

Begin Mile Post: 0.000 End Mile Post: 0.001

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

PE SU $260,000

$260,000Project Total:

FPN: 4369541 Project/Location: ATMS PROJECT TRAVELER INFORMATION

WEBSITE FOR THE RTMC

Project Length: 0.001

Desc: ATMS - ARTERIAL TRAFFIC MGMT

Comments:

Begin Mile Post: 0.000 End Mile Post: 0.001

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

PE SU $300,000

$300,000Project Total:

MISCELLANEOUS TOTAL 2015/16 2016/17 2017/18 2018/19 2019/20

$960,000

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –

Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES

Page: 1412/3/2014Run Date: SnapShot Date: 11/12/2014

Page 18: Manatee County Government Administrative Chambers First ... · 12/4/2014  · November and December of Year 1.€ Some programmed funds are prioritized by the Metropolitan Planning

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1TENTATIVE WORK PROGRAM REPORT

July 1, 2015 Through June 30, 2020 COUNTYMANATEE

DRAFT

FLP: INTERMODAL

FPN: 4225901 Project/Location: PORT MANATEE CAPITAL IMPROVEMENTS

COLD STORAGE WAREHOUSE

Project Length: 0.000

Desc: SEAPORT CAPACITY PROJECT

Comments:

Begin Mile Post: 0.000 End Mile Post: 0.000

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

CAP DPTO $474,864

CAP LF $477,185

$952,049Project Total:

FPN: 4206191 Project/Location: PORT MANATEE INTERMODAL CONTAINER AND

CARGO TRANSFER YARD PH I

Project Length: 0.000

Desc: SEAPORT CAPACITY PROJECT

Comments:

Begin Mile Post: 0.000 End Mile Post: 0.000

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

CAP DDR $47,820

CAP LF $47,820

$95,640Project Total:

FLP: INTERMODAL TOTAL 2015/16 2016/17 2017/18 2018/19 2019/20

$1,047,689

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –

Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES

Page: 1512/3/2014Run Date: SnapShot Date: 11/12/2014

Page 19: Manatee County Government Administrative Chambers First ... · 12/4/2014  · November and December of Year 1.€ Some programmed funds are prioritized by the Metropolitan Planning

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1TENTATIVE WORK PROGRAM REPORT

July 1, 2015 Through June 30, 2020 COUNTYMANATEE

DRAFT

FLP: SEAPORT

FPN: 4334571 Project/Location: PORT MANATEE BERTH REHAB &

RECONSTRUCT CAPITAL IMPROVEMENTS

Project Length: 0.000

Desc: SEAPORT PRESERVATION PROJECT

Comments:

Begin Mile Post: 0.000 End Mile Post: 0.000

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

CAP LF $666,667

CAP PORT $2,000,000

$2,666,667Project Total:

FPN: 4333021 Project/Location: PORT MANATEE RAIL TO DOCKSIDE CAPITAL

IMPROVEMENTS

Project Length: 0.000

Desc: SEAPORT CAPACITY PROJECT

Comments:

Begin Mile Post: 0.000 End Mile Post: 0.000

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

CAP GMR $2,000,000

CAP LF $2,000,000

$4,000,000Project Total:

FLP: SEAPORT TOTAL 2015/16 2016/17 2017/18 2018/19 2019/20

$2,666,667 $4,000,000

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –

Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES

Page: 1612/3/2014Run Date: SnapShot Date: 11/12/2014

Page 20: Manatee County Government Administrative Chambers First ... · 12/4/2014  · November and December of Year 1.€ Some programmed funds are prioritized by the Metropolitan Planning

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1TENTATIVE WORK PROGRAM REPORT

July 1, 2015 Through June 30, 2020 COUNTYMANATEE

DRAFT

FLP: TRANSIT

FPN: 4369271 Project/Location: MANATEE CO MCAT SERV DEV

OPERATING/ADMIN ASSIST OPERATING FOR

FIXED RT

Project Length: 0.000

Desc: OPERATING FOR FIXED ROUTE

Comments:

Begin Mile Post: 0.000 End Mile Post: 0.000

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

OPS DDR $285,791

OPS DPTO $14,209

OPS LF $300,000

$600,000Project Total:

FPN: 4101411 Project/Location: MANATEE COUNTY AREA TRANSIT (MCAT)

OPERATING ASSISTANCE BLOCK GRANT

Project Length: 0.000

Desc: OPERATING FOR FIXED ROUTE

Comments:

Begin Mile Post: 0.000 End Mile Post: 0.000

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

OPS DPTO $885,243 $884,836 $907,711 $937,678 $984,562

OPS LF $885,243 $884,836 $907,711 $937,678 $984,562

$1,770,486 $1,769,672 $1,815,422 $1,875,356 $1,969,124Project Total:

FPN: 4108951 Project/Location: MANATEE COUNTY AREA TRANSIT - OPERATING

ASSISTANCE - CORRIDOR

Project Length: 0.000

Desc: URBAN CORRIDOR IMPROVEMENTS

Comments:

Begin Mile Post: 0.000 End Mile Post: 0.000

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

OPS DPTO $484,220 $756,831 $807,140 $813,451 $837,864

OPS LF $484,220 $756,831 $807,140 $813,451 $837,864

$968,440 $1,513,662 $1,614,280 $1,626,902 $1,675,728Project Total:

FPN: 4308451 Project/Location: MANATEE COUNTY AREA TRANSIT (MCAT)

OPERATING ASSISTANCE

Project Length: 0.000

Desc: OPERATING FOR FIXED ROUTE

Comments:

Begin Mile Post: 0.000 End Mile Post: 0.000

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

OPS DPTO $1,087,500

OPS LF $1,087,500

$2,175,000Project Total:

FPN: 4101481 Project/Location: MANATEE COUNTY -MCAT FTA 5307

Project Length: 0.000

Desc: CAPITAL FOR FIXED ROUTE

Comments:

Begin Mile Post: 0.000 End Mile Post: 0.000

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

CAP FTA $2,843,935 $2,843,935 $2,843,935 $2,843,935 $3,002,710

CAP LF $710,984 $710,984 $710,984 $710,984 $750,678

$3,554,919 $3,554,919 $3,554,919 $3,554,919 $3,753,388Project Total:

FPN: 4352131 Project/Location: MANATEE COUNTY TRANSIT OPERATING

ASSISTANCE

Project Length: 0.000

Desc: OPERATING FOR FIXED ROUTE

Comments:

Begin Mile Post: 0.000 End Mile Post: 0.000

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

OPS DPTO $385,791

OPS LF $385,791

$771,582Project Total:

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –

Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES

Page: 1712/3/2014Run Date: SnapShot Date: 11/12/2014

Page 21: Manatee County Government Administrative Chambers First ... · 12/4/2014  · November and December of Year 1.€ Some programmed funds are prioritized by the Metropolitan Planning

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1TENTATIVE WORK PROGRAM REPORT

July 1, 2015 Through June 30, 2020 COUNTYMANATEE

DRAFT

FPN: 4101482 Project/Location: MANATEE COUNTY-MCATFTA SECTION 5307

OPERATING ASSISTANCE

Project Length: 0.000

Desc: OPERATING FOR FIXED ROUTE

Comments:

Begin Mile Post: 0.000 End Mile Post: 0.000

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

OPS FTA $850,000 $850,000 $850,000 $850,000 $750,000

OPS LF $850,000 $850,000 $850,000 $850,000 $750,000

$1,700,000 $1,700,000 $1,700,000 $1,700,000 $1,500,000Project Total:

FPN: 4345172 Project/Location: MANATEE MCAT FTA 5339 CAPITAL

ASSISTANCE

Project Length: 0.000

Desc: CAPITAL FOR FIXED ROUTE

Comments:

Begin Mile Post: 0.000 End Mile Post: 0.000

Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20

CAP FTA $408,943 $408,943 $408,943 $408,943 $408,943

CAP LF $102,236 $102,236 $102,236 $102,236 $102,236

$511,179 $511,179 $511,179 $511,179 $511,179Project Total:

FLP: TRANSIT TOTAL 2015/16 2016/17 2017/18 2018/19 2019/20

$9,876,606 $11,224,432 $9,195,800 $9,268,356 $9,409,419

COUNTY TOTALSMANATEE

Phase Fund Total2015/16 2016/17 2017/18 2018/19 2019/20

$70,308,903 $39,304,227 $26,435,026 $16,638,275 $21,688,580COUNTY Total: $174,375,011

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –

Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES

Page: 1812/3/2014Run Date: SnapShot Date: 11/12/2014