Revised December 4, 2014 - Land Use Meeting Agenda Item #12
Subject FDOT Draft Tentative Work Program Briefings None Contact and/or Presenter Information Clarke Davis Transportation Planning Division Manager [email protected] 941.708.7450 x7272 Action Requested Recommend the Sarasota-Manatee Metropolitan Planning Organization Board endorse the Florida Department of Transportation’s Draft Tentative Work Program for FY15/16-FY19/20. Enabling/Regulating Authority n/a Background Discussion
The Florida Department of Transportation’s Work Program is a five year schedule of State and Federal funded capital improvements; it also includes some local operations and maintenance support. Table 1 shows the approximate flow of the work program development process. The process is currently at the steps in November and December of Year 1. Some programmed funds are prioritized by the Metropolitan Planning Organization (MPO) based on County priorities. Therefore and as a stakeholder, the MPO Board reviews the program and provides recommendations during the regional agency and public involvement process leading up to the 2015 legislative session.
The discussion for this agenda item will include an overview of the projects in the Draft Tentative Work Program for FY15/16-FY19/20. It is scheduled for MPO Board consideration on December 15, 2014. County Attorney Review Not Reviewed (No apparent legal issues) Explanation of Other Reviewing Attorney N/A Instructions to Board Records Please return a copy of the approved agenda item to Clarke Davis, [email protected], 941.708.7450 x7272
Manatee County Government Administrative ChambersFirst Floor, Chambers
December 4, 2014 - 9:00 a.m.
Cost and Funds Source Account Number and Name n/a Amount and Frequency of Recurring Costs n/a Attachment: Work Program Process.pdf Attachment: 2016-2020 Tentative Work Program-Manatee.pdf
Manatee County Government Administrative ChambersFirst Floor, Chambers
December 4, 2014 - 9:00 a.m.
Table 1
FDOT Work Program / MPO Transportation Improvement ProgramApproximate Calendar of Events
Who What
Year 1 Jan MPO & FDOT staff Request any new projects that will require cost estimates
Feb County staff Submit potential new projects
Mar
County Commission Adopt County's project priorities
Apr
May County staff Submit adopted priorities and project detail sheets to MPO
Jun MPO and local staff Prepare composite project priority lists
MPO committees Provide project priority recommendations
Jul MPO Board Adopt MPO project priority lists
Aug
Sep
FDOT staff Develop new work program based in part on MPO priorities
Oct
Nov FDOT staff Provide draft tentative work program to MPOs
Dec MPO Board Endorse draft tentative work program (public hearing)
Year 2 Jan
FDOT staff Prepare tentative work program for legislature
Feb
Mar [ Legislative session begins ]
Apr MPO staff Prepare draft TIP based on tentative program
May Legislature Pass proposed budget
Governor Approve budget including work program
Jun MPO Board Adopt TIP aligned with adopted work program (public hearing)
Jul [ Work Program & TIP are in effect ]
When
The process starts in Jan of Year 1 to have a program in effect on Jul 1 of Year 2. Therefore each Jan, the
end phase of a program's process overlaps the early part of the next. In addition to the overall process,
there can be program amendments throughout the year. The work program and TIP must be aligned, so
changes to one will prompt changes to the other. The MPO Board considers the TIP and each amendment
in an advertised public hearing.
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1
July 1, 2015 Through June 30, 2020
COUNTYMANATEE
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1
-
DRAFT
2016 2020
TENTATIVE WORK PROGRAM REPORT
Tentative Work Program Fiscal Years
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –
Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES
Page: 112/3/2014Run Date: SnapShot Date: 11/12/2014
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1
COUNTYMANATEE
MISSION STATEMENT The Department will provide a safe, interconnected statewide transportation system for Florida's citizens and visitors that ensures the mobility of people and goods, while enhancing economic prosperity and sustaining the quality of our environment.
July 1, 2015 Through June 30, 2020
DRAFTTENTATIVE WORK PROGRAM REPORT
Robin StublenCommunications SpecialistDistrict One Headquarters801 North BroadwayP.O. Box 1249Bartow, FL 33831(863) 519-2362
Debbie TowerCommunications DirectorSouthwest Area Office10041 Daniels ParkwayFort Myers, FL 33913(239) 461-4300
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –
Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES
Page: 212/3/2014Run Date: SnapShot Date: 11/12/2014
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1
COUNTYMANATEE
July 1, 2015 Through June 30, 2020
CURRENTLY REPORTED ACTIVE FUND CODES
DRAFTTENTATIVE WORK PROGRAM REPORT
ACSU Advance Construction (SU)
BRRP State Bridge Repair And Rehab
DDR District Dedicated Revenue
DIH State In-house Product Support
DITS Statewide ITS - State 100%
DPTO State PTO
DS State Primary Highways and PTO
FTA Federal Transit Administration
GMR General Revenue for SIS
HSP Highway Safety Program
LF Local Funds
LFP Local Fund for Participating
PORT Seaports
SA STP, Any Area
SU STP, Urban Areas > 200k
TRIP Trans Regional Incentive Prog
ACNP
ACTU
NHRE
TALT
TALU
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –
Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES
Page: 312/3/2014Run Date: SnapShot Date: 11/12/2014
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1TENTATIVE WORK PROGRAM REPORT
July 1, 2015 Through June 30, 2020 COUNTYMANATEE
DRAFT
HIGHWAYS
FPN: 4331421 Project/Location: 10TH AVENUE FROM RIVERSIDE DRIVE TO 17TH
STREET
Project Length: 0.001
Desc: PD&E/EMO STUDY
Comments:
Begin Mile Post: 0.000 End Mile Post: 0.001
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
PDE SU $454,500
PE SU $500,000
$454,500 $500,000Project Total:
FPN: 4366821 Project/Location: 10TH STREET (US 301) FROM 5TH AVENUE DR W.
TO E. OF 3RD AVENUE W.
Project Length: 0.328
Desc: RAIL SAFETY PROJECT
Comments:
Begin Mile Post: 0.196 End Mile Post: 0.524
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
PE DIH $10,000
PE DS $240,330
RRU DS $650,000
CST DIH $21,580
CST DS $1,374,556
$250,330 $671,580 $1,374,556Project Total:
FPN: 4298661 Project/Location: 14TH AVENUE WEST AT 17TH STREET
WEST
Project Length: 0.013
Desc: INTERSECTION IMPROVEMENT
Comments:
Begin Mile Post: 1.000 End Mile Post: 1.012
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
CST SU $472,170
$472,170Project Total:
FPN: 4313502 Project/Location: 15TH ST E/301 BLVD E FROM TALLEVAST ROAD
TO US 41
Project Length: 4.741
Desc: ADD LANES & RECONSTRUCT
Comments:
Begin Mile Post: 1.679 End Mile Post: 6.243
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
PE SU $5,600,000
$5,600,000Project Total:
FPN: 4369821 Project/Location: 51ST STREET WEST FROM 53RD STREET WEST
TO 53RD AVENUE WEST
Project Length: 0.030
Desc: ADD TURN LANE(S)
Comments:
Begin Mile Post: 0.000 End Mile Post: 0.030
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
PE SU $120,000
CST DS $286
CST SU $223,265
$120,000 $223,551Project Total:
FPN: 4298711 Project/Location: 57TH ST E AT SR 64
Project Length: 0.400
Desc: INTERSECTION IMPROVEMENT
Comments:
Begin Mile Post: 1.800 End Mile Post: 2.200
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
CST SU $449,777
$449,777Project Total:
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –
Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES
Page: 412/3/2014Run Date: SnapShot Date: 11/12/2014
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1TENTATIVE WORK PROGRAM REPORT
July 1, 2015 Through June 30, 2020 COUNTYMANATEE
DRAFT
FPN: 4351131 Project/Location: 63RD AVE E AT 33RD STREET E
Project Length: 0.470
Desc: ADD LEFT TURN LANE(S)
Comments:
Begin Mile Post: 1.530 End Mile Post: 2.000
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
ROW LFP $221,823
CST SU $1,848,817
$221,823 $1,848,817Project Total:
FPN: 4350901 Project/Location: 9TH AVE E AT 15TH ST EAST
Project Length: 0.200
Desc: ADD TURN LANE(S)
Comments:
Begin Mile Post: 0.332 End Mile Post: 0.532
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
ROW SU $443,456
CST SU $1,059,321
$443,456 $1,059,321Project Total:
FPN: 4369831 Project/Location: BLACKSTONE PARK AT 14TH AVE W, 23RD AVE W
& BUSINESS 41 (VALENCIA DR)
Project Length: 0.001
Desc: SIDEWALK
Comments:
Begin Mile Post: 0.000 End Mile Post: 0.001
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
PE TALU $165,000
CST DS $1,572
CST TALU $394,247
$165,000 $395,819Project Total:
FPN: 4136391 Project/Location: BRADENTON TRAFFIC SIGNALS
REIMBURSEMENT
Project Length: 0.790
Desc: TRAFFIC SIGNALS
Comments:
Begin Mile Post: 6.559 End Mile Post: 7.349
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
OPS DDR $122,816 $126,501 $130,296 $134,205 $138,231
$122,816 $126,501 $130,296 $134,205 $138,231Project Total:
FPN: 4371451 Project/Location: CORTEZ ROAD (SR 684) AT 43RD STREET
WEST
Project Length: 0.001
Desc: ADD TURN LANE(S)
Comments:
Begin Mile Post: 5.979 End Mile Post: 5.980
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
PE DIH $1,000
PE LFP $31,350
PE TRIP $31,350
CST DIH $1,000
CST LFP $240,300
CST TRIP $240,300
$63,700 $481,600Project Total:
FPN: 4351201 Project/Location: ELLENTON GILLETTE RD AT 69TH ST
E
Project Length: 0.200
Desc: ADD LEFT TURN LANE(S)
Comments:
Begin Mile Post: 3.502 End Mile Post: 3.702
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
CST SU $676,473
$676,473Project Total:
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –
Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES
Page: 512/3/2014Run Date: SnapShot Date: 11/12/2014
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1TENTATIVE WORK PROGRAM REPORT
July 1, 2015 Through June 30, 2020 COUNTYMANATEE
DRAFT
FPN: 4332771 Project/Location: EMERGENCY VEHICLE PRIORITY SYSTEM
MANATEE COUNTY
Project Length: 0.001
Desc: ATMS - ARTERIAL TRAFFIC MGMT
Comments:
Begin Mile Post: 0.000 End Mile Post: 0.001
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
CST SU $1,631,700
$1,631,700Project Total:
FPN: 4136401 Project/Location: HOLMES BEACH TRAFFIC SIGNALS
REIMBURSEMENT
Project Length: 0.100
Desc: TRAFFIC SIGNALS
Comments:
Begin Mile Post: 0.000 End Mile Post: 0.100
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
OPS DDR $6,080 $6,263 $6,451 $6,644 $6,844
$6,080 $6,263 $6,451 $6,644 $6,844Project Total:
FPN: 4363211 Project/Location: I 75 (SR 93) SOUTH OF UNIVERSITY BLVD NORTH
OF US 301
Project Length: 11.400
Desc: WETLAND MITIGATION/RESTORATION
Comments:
Begin Mile Post: 0.000 End Mile Post: 11.400
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
ENV DS $935,000 $394,900 $311,500
$935,000 $394,900 $311,500Project Total:
FPN: 4370841 Project/Location: I-75 (SR 93) AT SR 64 INTERCHANGE
Project Length: 0.570
Desc: LIGHTING
Comments:
Begin Mile Post: 7.008 End Mile Post: 7.578
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
CST DDR $2,467,551
CST DIH $315,900
$2,783,451Project Total:
FPN: 2010327 Project/Location: I-75 (SR 93) AT UNIVERSITY PARKWAY
(MANATEE)
Project Length: 0.460
Desc: LANDSCAPING
Comments:
Begin Mile Post: 0.000 End Mile Post: 0.460
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
CST DIH $62,766
CST DS $553,000
$615,766Project Total:
FPN: 2010325 Project/Location: I-75 (SR 93) AT US 301 INTERCHANGE
Project Length: 1.150
Desc: INTERCHANGE - ADD LANES
Comments:
Begin Mile Post: 10.250 End Mile Post: 11.400
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
ENV DS $430,000
$430,000Project Total:
FPN: 4370821 Project/Location: I-75 (SR 93) FROM I-275 INTERCHANGE TO CR 683
MOCASSIN WALLOW
Project Length: 2.410
Desc: LIGHTING
Comments:
Begin Mile Post: 14.108 End Mile Post: 16.518
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
DSB DDR $5,799,201
DSB DIH $558,463
$6,357,664Project Total:
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –
Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES
Page: 612/3/2014Run Date: SnapShot Date: 11/12/2014
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1TENTATIVE WORK PROGRAM REPORT
July 1, 2015 Through June 30, 2020 COUNTYMANATEE
DRAFT
FPN: 4340261 Project/Location: I-75 (SR 93) FROM N OF I-275 TO MANATEE
COUNTY LINE
Project Length: 5.320
Desc: ITS FREEWAY MANAGEMENT
Comments:
Begin Mile Post: 15.251 End Mile Post: 20.571
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
PE DIH $1,000
PE DITS $75,000
DSB DIH $381,607
DSB DITS $3,276,515
$1,000 $3,733,122Project Total:
FPN: 2010324 Project/Location: I-75 (SR93) AT UNIVERSITY
INTERCHANGE
Project Length: 0.460
Desc: INTERCHANGE - ADD LANES
Comments:
Begin Mile Post: 0.000 End Mile Post: 0.460
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
INC SA $2,500,000
$2,500,000Project Total:
FPN: 4349291 Project/Location: I-75 S OF MOCCASIN WALLOW RD TO
HILLSBOROUGH C/L
Project Length: 4.857
Desc: RESURFACING
Comments:
Begin Mile Post: 15.714 End Mile Post: 20.571
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
CST ACNP $8,609,803
$8,609,803Project Total:
FPN: 4350382 Project/Location: MANATEE COUNTY SCOUR COUNTERMEASURE
AT VARIOUS LOCATIONS
Project Length: 0.802
Desc: BRIDGE-REPAIR/REHABILITATION
Comments:
Begin Mile Post: 0.480 End Mile Post: 1.204
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
CST BRRP $2,141,371
CST DIH $169,987
$2,311,358Project Total:
FPN: 4126731 Project/Location: MANATEE COUNTY TRAFFIC SIGNALS
REIMBURSEMENT
Project Length: 5.519
Desc: TRAFFIC SIGNALS
Comments:
Begin Mile Post: 0.560 End Mile Post: 6.079
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
OPS DDR $128,899 $307,015 $316,225 $329,034 $338,905
OPS DITS $169,173
$298,072 $307,015 $316,225 $329,034 $338,905Project Total:
FPN: 4371061 Project/Location: MANATEE/SARASOTA TMC OPS FUND COUNTY
WIDE
Project Length: 0.001
Desc: OTHER ITS
Comments:
Begin Mile Post: 0.000 End Mile Post: 0.001
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
OPS DS $429,000 $429,000
$429,000 $429,000Project Total:
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –
Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES
Page: 712/3/2014Run Date: SnapShot Date: 11/12/2014
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1TENTATIVE WORK PROGRAM REPORT
July 1, 2015 Through June 30, 2020 COUNTYMANATEE
DRAFT
FPN: 4353691 Project/Location: MOCCASIN WALLOW ROAD AT US 41
Project Length: 0.200
Desc: ADD TURN LANE(S)
Comments:
Begin Mile Post: 11.469 End Mile Post: 11.669
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
ROW SU $60,099
CST SU $236,166
$60,099 $236,166Project Total:
FPN: 4332131 Project/Location: MORGAN JOHNSON ROAD FROM RIVERSIDE
TERRACE TO SR 64
Project Length: 0.657
Desc: SIDEWALK
Comments:
Begin Mile Post: 1.543 End Mile Post: 2.200
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
PE ACTU $45,000
PE TALU $8,000 $78,020
CST TALT $58,179
CST TALU $437,081
$53,000 $78,020 $495,260Project Total:
FPN: 4136421 Project/Location: PALMETTO TRAFFIC SIGNALS
REIMBURSEMENT
Project Length: 0.751
Desc: TRAFFIC SIGNALS
Comments:
Begin Mile Post: 0.505 End Mile Post: 1.256
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
OPS DDR $33,440 $34,444 $35,477 $36,541 $37,638
$33,440 $34,444 $35,477 $36,541 $37,638Project Total:
FPN: 1961421 Project/Location: SARASOTA/MANATEE MPO IDENTIFIED
OPERATIONAL IMPROVEMENTS - FUNDING
Project Length: 0.000
Desc: FUNDING ACTION
Comments:
Begin Mile Post: 0.000 End Mile Post: 0.000
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
CST SU $61,396 $1,134,340 $5,192,830
$61,396 $1,134,340 $5,192,830Project Total:
FPN: 1961143 Project/Location: SR 45 (US 41/TAMIAMI TRAIL) AT PINEY POINT
RD AND DOCK ST (PORT MANATEE)
Project Length: 0.655
Desc: INTERSECTION IMPROVEMENT
Comments:
Begin Mile Post: 8.229 End Mile Post: 8.884
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
INC SA $400,000
$400,000Project Total:
FPN: 4081853 Project/Location: SR 64 (MANATEE AVE)TO PERICO BAY
BOULEVARD
Project Length: 1.936
Desc: BRIDGE REPLACEMENT
Comments:
Begin Mile Post: 0.216 End Mile Post: 2.152
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
PE DDR $5,065,117
PE DIH $200,000
PE DS $934,883
$6,200,000Project Total:
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –
Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES
Page: 812/3/2014Run Date: SnapShot Date: 11/12/2014
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1TENTATIVE WORK PROGRAM REPORT
July 1, 2015 Through June 30, 2020 COUNTYMANATEE
DRAFT
FPN: 4366841 Project/Location: SR 64 (MANATEE AVE) FROM E. OF 7TH STREET
W. TO E. OF 5TH STREET W.
Project Length: 0.106
Desc: RAIL SAFETY PROJECT
Comments:
Begin Mile Post: 1.194 End Mile Post: 1.300
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
PE DIH $10,000
PE DS $90,000
RRU DS $250,000
CST DIH $10,530
CST DS $315,797
$100,000 $260,530 $315,797Project Total:
FPN: 4351361 Project/Location: SR 64 FROM E OF EXISTING TRAIL TO ANNA
MARIA BRIDGE
Project Length: 2.000
Desc: BIKE PATH/TRAIL
Comments:
Begin Mile Post: 0.000 End Mile Post: 2.000
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
PE TALU $60,000
CST DS $15,106
CST TALU $363,170
$60,000 $378,276Project Total:
FPN: 4350731 Project/Location: SR 64 FROM KAY RD TO E OF I-75
INTERCHANGE
Project Length: 0.767
Desc: RESURFACING
Comments:
Begin Mile Post: 5.773 End Mile Post: 6.540
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
CST DDR $52,650
CST DIH $33,014
CST NHRE $1,821,969
$1,907,633Project Total:
FPN: 4365511 Project/Location: SR 684 FROM 119TH ST WEST TO 86TH ST
WEST
Project Length: 2.068
Desc: SKID HAZARD OVERLAY
Comments:
Begin Mile Post: 1.188 End Mile Post: 3.256
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
PE DIH $10,000
PE HSP $300,000
CST DIH $55,300
CST DS $55,475
CST HSP $2,177,415
$310,000 $2,288,190Project Total:
FPN: 4302042 Project/Location: SR 684 FROM SR 789 (GULF DRIVE) TO 123RD
STREET WEST
Project Length: 0.900
Desc: REPLACE MOVABLE SPAN BRIDGE
Comments:
Begin Mile Post: 0.000 End Mile Post: 0.900
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
PE DDR $7,250,000
PE DIH $200,000
$7,450,000Project Total:
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –
Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES
Page: 912/3/2014Run Date: SnapShot Date: 11/12/2014
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1TENTATIVE WORK PROGRAM REPORT
July 1, 2015 Through June 30, 2020 COUNTYMANATEE
DRAFT
FPN: 4312071 Project/Location: SR 70 FROM 301 BLVD/15TH ST E TO LOCKWOOD
RIDGE ROAD
Project Length: 2.497
Desc: RESURFACING
Comments:
Begin Mile Post: 0.000 End Mile Post: 2.497
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
CST DDR $7,258,070
CST DIH $174,409
$7,432,479Project Total:
FPN: 4369241 Project/Location: SR 70 FROM 30TH AT 30TH STREET
EAST
Project Length: 0.200
Desc: INTERSECTION IMPROVEMENT
Comments:
Begin Mile Post: 1.148 End Mile Post: 1.348
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
PE SU $150,000
$150,000Project Total:
FPN: 4313731 Project/Location: SR 70 FROM LOCKWOOD RIDGE ROAD TO TARA
BLVD
Project Length: 2.342
Desc: RESURFACING
Comments:
Begin Mile Post: 2.465 End Mile Post: 4.807
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
RRU DS $4,000,000
CST DDR $259,353
CST DIH $209,868
CST SA $6,010,380
$10,479,601Project Total:
FPN: 4145062 Project/Location: SR 70 FROM LORRAINE RD TO SINGLETARY RD
(MYAKKA)
Project Length: 15.670
Desc: PD&E/EMO STUDY
Comments:
Begin Mile Post: 22.134 End Mile Post: 31.713
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
PDE DIH $430,000
PDE DS $3,870,000
$4,300,000Project Total:
FPN: 4365461 Project/Location: SR 70 FROM US 41 TO 540' EAST OF US
41
Project Length: 0.102
Desc: INTERSECTION IMPROVEMENT
Comments:
Begin Mile Post: 0.000 End Mile Post: 0.102
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
PE DIH $10,000
PE HSP $50,000
CST DIH $10,530
CST DS $4,611
CST HSP $92,184
$60,000 $107,325Project Total:
FPN: 4366761 Project/Location: SR 789 (LONGBOAT KEY) FROM NORTH SHORE
RD TO COQUINA PARK ENT
Project Length: 0.710
Desc: PD&E/EMO STUDY
Comments:
Begin Mile Post: 4.467 End Mile Post: 5.177
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
PDE SA $2,325,000
$2,325,000Project Total:
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –
Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES
Page: 1012/3/2014Run Date: SnapShot Date: 11/12/2014
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1TENTATIVE WORK PROGRAM REPORT
July 1, 2015 Through June 30, 2020 COUNTYMANATEE
DRAFT
FPN: 4369861 Project/Location: SR 789/GULF OF MEXICO DR FROM BROADWAY
TO LONGBOAT PASS BRIDGE
Project Length: 0.350
Desc: SIDEWALK
Comments:
Begin Mile Post: 4.211 End Mile Post: 4.561
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
PE TALU $115,000
ENV TALT $100,000
CST DS $2,439
CST TALU $264,783
$115,000 $100,000 $267,222Project Total:
FPN: 4332561 Project/Location: SR 93 (I-75) AT RR OVERPASS
Project Length: 0.901
Desc: RESURFACING
Comments:
Begin Mile Post: 12.451 End Mile Post: 13.352
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
ENV DS $50,000
CST ACNP $1,252,667
CST DS $78,547
$1,381,214Project Total:
FPN: 4279952 Project/Location: SR43 (US 301) FROM CR 675 TO MOCCASIN
WALLOW ROAD
Project Length: 1.212
Desc: LANDSCAPING
Comments:
Begin Mile Post: 10.457 End Mile Post: 11.669
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
CST DDR $559,086
$559,086Project Total:
FPN: 4279951 Project/Location: SR43 (US301) FROM CR 675 TO MOCCASIN
WALLOW RD
Project Length: 1.212
Desc: ADD LANES & RECONSTRUCT
Comments:
Begin Mile Post: 10.457 End Mile Post: 11.669
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
INC DDR $300,000
$300,000Project Total:
FPN: 4352861 Project/Location: US 301 AT ERIE RD/OLD TAMPA HWY
Project Length: 0.200
Desc: ADD LEFT TURN LANE(S)
Comments:
Begin Mile Post: 6.127 End Mile Post: 6.327
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
PE SU $168,000
CST SU $580,263
$168,000 $580,263Project Total:
FPN: 4345051 Project/Location: US 301 AT SR 70
Project Length: 0.500
Desc: INTERSECTION IMPROVEMENT
Comments:
Begin Mile Post: 3.810 End Mile Post: 4.310
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
PE HSP $110,000
ENV SA $10,000 $20,000
CST DDR $19,648
CST HSP $496,198
CST SA $10,530
$120,000 $546,376Project Total:
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –
Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES
Page: 1112/3/2014Run Date: SnapShot Date: 11/12/2014
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1TENTATIVE WORK PROGRAM REPORT
July 1, 2015 Through June 30, 2020 COUNTYMANATEE
DRAFT
FPN: 4312121 Project/Location: US 301 FROM 19TH AVENUE TO 69TH
AVENUE
Project Length: 0.720
Desc: RESURFACING
Comments:
Begin Mile Post: 3.995 End Mile Post: 4.715
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
ENV DS $200,000
CST DDR $2,992,354
CST DIH $46,215
$3,238,569Project Total:
FPN: 4332151 Project/Location: US 41 (14ST ST W) AT 9TH AVE (MLK)
Project Length: 0.000
Desc: INTERSECTION IMPROVEMENT
Comments:
Begin Mile Post: 0.000 End Mile Post: 0.000
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
PDE DIH $4,500
PDE DS $450,000
$454,500Project Total:
FPN: 1961142 Project/Location: US 41 (SR 45) FROM I-275 TO HILLSBOROUGH
CL
Project Length: 4.694
Desc: RESURFACING
Comments:
Begin Mile Post: 5.088 End Mile Post: 9.782
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
ENV DS $100,000
$100,000Project Total:
FPN: 4295061 Project/Location: US 41 / SR 45 FROM 63RD AVE W TO 53RD AVE
W
Project Length: 1.247
Desc: LIGHTING
Comments:
Begin Mile Post: 3.019 End Mile Post: 4.266
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
ROW HSP $487,626
$487,626Project Total:
FPN: 4335491 Project/Location: US 41 AT US 301 (10TH STREET E) IN
PALMETTO
Project Length: 0.200
Desc: SIDEWALK
Comments:
Begin Mile Post: 0.508 End Mile Post: 0.708
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
CST DDR $22,705
CST SU $667,630
$690,335Project Total:
FPN: 4365091 Project/Location: US 41 BUSINESS (9THSTREET WEST) FROM 3RD
AVENUE TO MANATEE AVE (SR64)
Project Length: 0.134
Desc: ADD RIGHT TURN LANE(S)
Comments:
Begin Mile Post: 0.213 End Mile Post: 0.347
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
PE DIH $10,000
PE DS $300,000
CST SA $483,905
$310,000 $483,905Project Total:
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –
Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES
Page: 1212/3/2014Run Date: SnapShot Date: 11/12/2014
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1TENTATIVE WORK PROGRAM REPORT
July 1, 2015 Through June 30, 2020 COUNTYMANATEE
DRAFT
FPN: 4335471 Project/Location: US 41 BUSINESS AT 3RD AVE
Project Length: 0.248
Desc: ADD RIGHT TURN LANE(S)
Comments:
Begin Mile Post: 2.288 End Mile Post: 2.488
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
CST DS $5,395
CST SU $131,318
$136,713Project Total:
FPN: 4335931 Project/Location: US 41 BUSINESS FROM GREEN BRIDGE TO
RIVERSIDE DRIVE
Project Length: 0.168
Desc: BIKE LANE/SIDEWALK
Comments:
Begin Mile Post: 1.211 End Mile Post: 1.379
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
CST ACSU $930,904
CST DDR $61,233
CST SU $30,810
$1,022,947Project Total:
FPN: 4335921 Project/Location: US 41 FROM 69TH AVE (BAY DRIVE) TO CORTEZ
ROAD
Project Length: 3.032
Desc: BIKE LANE/SIDEWALK
Comments:
Begin Mile Post: 2.252 End Mile Post: 5.284
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
PE SU $410,000
CST DDR $49,116
CST SU $1,232,640
$410,000 $1,281,756Project Total:
FPN: 4353491 Project/Location: US 41 GREEN BRIDGE MULTI-USE
PATH
Project Length: 1.032
Desc: BIKE PATH/TRAIL
Comments:
Begin Mile Post: 0.347 End Mile Post: 1.379
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
PE ACTU $200,000
PE TALU $210,000
CST DS $53,950
CST TALT $2,275,779
$410,000 $2,329,729Project Total:
HIGHWAYS TOTAL 2015/16 2016/17 2017/18 2018/19 2019/20
$55,757,941 $28,079,795 $13,239,226 $7,369,919 $12,279,161
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –
Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES
Page: 1312/3/2014Run Date: SnapShot Date: 11/12/2014
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1TENTATIVE WORK PROGRAM REPORT
July 1, 2015 Through June 30, 2020 COUNTYMANATEE
DRAFT
MISCELLANEOUS
FPN: 4368021 Project/Location: ATMS BLUETOOTH SYSTEM AT VARIOUS
LOCATIONS THROUGHOUT
Project Length: 0.001
Desc: ATMS - ARTERIAL TRAFFIC MGMT
Comments:
Begin Mile Post: 0.001 End Mile Post: 0.002
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
CAP SU $400,000
$400,000Project Total:
FPN: 4371021 Project/Location: ATMS MASTERPLAN & CONCEPT OF
OPERATIONS FOR REGIONAL TRAFFIC MGMT
SYST
Project Length: 0.001
Desc: ATMS - ARTERIAL TRAFFIC MGMT
Comments:
Begin Mile Post: 0.000 End Mile Post: 0.001
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
PE SU $260,000
$260,000Project Total:
FPN: 4369541 Project/Location: ATMS PROJECT TRAVELER INFORMATION
WEBSITE FOR THE RTMC
Project Length: 0.001
Desc: ATMS - ARTERIAL TRAFFIC MGMT
Comments:
Begin Mile Post: 0.000 End Mile Post: 0.001
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
PE SU $300,000
$300,000Project Total:
MISCELLANEOUS TOTAL 2015/16 2016/17 2017/18 2018/19 2019/20
$960,000
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –
Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES
Page: 1412/3/2014Run Date: SnapShot Date: 11/12/2014
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1TENTATIVE WORK PROGRAM REPORT
July 1, 2015 Through June 30, 2020 COUNTYMANATEE
DRAFT
FLP: INTERMODAL
FPN: 4225901 Project/Location: PORT MANATEE CAPITAL IMPROVEMENTS
COLD STORAGE WAREHOUSE
Project Length: 0.000
Desc: SEAPORT CAPACITY PROJECT
Comments:
Begin Mile Post: 0.000 End Mile Post: 0.000
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
CAP DPTO $474,864
CAP LF $477,185
$952,049Project Total:
FPN: 4206191 Project/Location: PORT MANATEE INTERMODAL CONTAINER AND
CARGO TRANSFER YARD PH I
Project Length: 0.000
Desc: SEAPORT CAPACITY PROJECT
Comments:
Begin Mile Post: 0.000 End Mile Post: 0.000
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
CAP DDR $47,820
CAP LF $47,820
$95,640Project Total:
FLP: INTERMODAL TOTAL 2015/16 2016/17 2017/18 2018/19 2019/20
$1,047,689
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –
Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES
Page: 1512/3/2014Run Date: SnapShot Date: 11/12/2014
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1TENTATIVE WORK PROGRAM REPORT
July 1, 2015 Through June 30, 2020 COUNTYMANATEE
DRAFT
FLP: SEAPORT
FPN: 4334571 Project/Location: PORT MANATEE BERTH REHAB &
RECONSTRUCT CAPITAL IMPROVEMENTS
Project Length: 0.000
Desc: SEAPORT PRESERVATION PROJECT
Comments:
Begin Mile Post: 0.000 End Mile Post: 0.000
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
CAP LF $666,667
CAP PORT $2,000,000
$2,666,667Project Total:
FPN: 4333021 Project/Location: PORT MANATEE RAIL TO DOCKSIDE CAPITAL
IMPROVEMENTS
Project Length: 0.000
Desc: SEAPORT CAPACITY PROJECT
Comments:
Begin Mile Post: 0.000 End Mile Post: 0.000
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
CAP GMR $2,000,000
CAP LF $2,000,000
$4,000,000Project Total:
FLP: SEAPORT TOTAL 2015/16 2016/17 2017/18 2018/19 2019/20
$2,666,667 $4,000,000
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –
Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES
Page: 1612/3/2014Run Date: SnapShot Date: 11/12/2014
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1TENTATIVE WORK PROGRAM REPORT
July 1, 2015 Through June 30, 2020 COUNTYMANATEE
DRAFT
FLP: TRANSIT
FPN: 4369271 Project/Location: MANATEE CO MCAT SERV DEV
OPERATING/ADMIN ASSIST OPERATING FOR
FIXED RT
Project Length: 0.000
Desc: OPERATING FOR FIXED ROUTE
Comments:
Begin Mile Post: 0.000 End Mile Post: 0.000
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
OPS DDR $285,791
OPS DPTO $14,209
OPS LF $300,000
$600,000Project Total:
FPN: 4101411 Project/Location: MANATEE COUNTY AREA TRANSIT (MCAT)
OPERATING ASSISTANCE BLOCK GRANT
Project Length: 0.000
Desc: OPERATING FOR FIXED ROUTE
Comments:
Begin Mile Post: 0.000 End Mile Post: 0.000
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
OPS DPTO $885,243 $884,836 $907,711 $937,678 $984,562
OPS LF $885,243 $884,836 $907,711 $937,678 $984,562
$1,770,486 $1,769,672 $1,815,422 $1,875,356 $1,969,124Project Total:
FPN: 4108951 Project/Location: MANATEE COUNTY AREA TRANSIT - OPERATING
ASSISTANCE - CORRIDOR
Project Length: 0.000
Desc: URBAN CORRIDOR IMPROVEMENTS
Comments:
Begin Mile Post: 0.000 End Mile Post: 0.000
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
OPS DPTO $484,220 $756,831 $807,140 $813,451 $837,864
OPS LF $484,220 $756,831 $807,140 $813,451 $837,864
$968,440 $1,513,662 $1,614,280 $1,626,902 $1,675,728Project Total:
FPN: 4308451 Project/Location: MANATEE COUNTY AREA TRANSIT (MCAT)
OPERATING ASSISTANCE
Project Length: 0.000
Desc: OPERATING FOR FIXED ROUTE
Comments:
Begin Mile Post: 0.000 End Mile Post: 0.000
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
OPS DPTO $1,087,500
OPS LF $1,087,500
$2,175,000Project Total:
FPN: 4101481 Project/Location: MANATEE COUNTY -MCAT FTA 5307
Project Length: 0.000
Desc: CAPITAL FOR FIXED ROUTE
Comments:
Begin Mile Post: 0.000 End Mile Post: 0.000
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
CAP FTA $2,843,935 $2,843,935 $2,843,935 $2,843,935 $3,002,710
CAP LF $710,984 $710,984 $710,984 $710,984 $750,678
$3,554,919 $3,554,919 $3,554,919 $3,554,919 $3,753,388Project Total:
FPN: 4352131 Project/Location: MANATEE COUNTY TRANSIT OPERATING
ASSISTANCE
Project Length: 0.000
Desc: OPERATING FOR FIXED ROUTE
Comments:
Begin Mile Post: 0.000 End Mile Post: 0.000
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
OPS DPTO $385,791
OPS LF $385,791
$771,582Project Total:
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –
Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES
Page: 1712/3/2014Run Date: SnapShot Date: 11/12/2014
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1TENTATIVE WORK PROGRAM REPORT
July 1, 2015 Through June 30, 2020 COUNTYMANATEE
DRAFT
FPN: 4101482 Project/Location: MANATEE COUNTY-MCATFTA SECTION 5307
OPERATING ASSISTANCE
Project Length: 0.000
Desc: OPERATING FOR FIXED ROUTE
Comments:
Begin Mile Post: 0.000 End Mile Post: 0.000
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
OPS FTA $850,000 $850,000 $850,000 $850,000 $750,000
OPS LF $850,000 $850,000 $850,000 $850,000 $750,000
$1,700,000 $1,700,000 $1,700,000 $1,700,000 $1,500,000Project Total:
FPN: 4345172 Project/Location: MANATEE MCAT FTA 5339 CAPITAL
ASSISTANCE
Project Length: 0.000
Desc: CAPITAL FOR FIXED ROUTE
Comments:
Begin Mile Post: 0.000 End Mile Post: 0.000
Phase Fund 2015/16 2016/17 2017/18 2018/19 2019/20
CAP FTA $408,943 $408,943 $408,943 $408,943 $408,943
CAP LF $102,236 $102,236 $102,236 $102,236 $102,236
$511,179 $511,179 $511,179 $511,179 $511,179Project Total:
FLP: TRANSIT TOTAL 2015/16 2016/17 2017/18 2018/19 2019/20
$9,876,606 $11,224,432 $9,195,800 $9,268,356 $9,409,419
COUNTY TOTALSMANATEE
Phase Fund Total2015/16 2016/17 2017/18 2018/19 2019/20
$70,308,903 $39,304,227 $26,435,026 $16,638,275 $21,688,580COUNTY Total: $174,375,011
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC –
Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities PHASE CODES
Page: 1812/3/2014Run Date: SnapShot Date: 11/12/2014