7/21/2019 Mammoet LNG Modular Construction
1/41
EngineeredHeavyLogistics: MovingDeadlinesForwardinLNGModularConstruction
SNAME ARCTIC NOVEMBER 20, 2013
-
7/21/2019 Mammoet LNG Modular Construction
2/41
2
PRESENTATION CONTENT
1. Modularization
2. Engineered Heavy Logistics
3. LNG: Australia to British Columbia
4. Lessons Learned
5. Questions
-
7/21/2019 Mammoet LNG Modular Construction
3/41
3
SAFETY MOMENT
The Mammoet Minute, only six steps
in 60 seconds:
Stop
Think
Look around
Assess the RiskTake Action
Start your task.
-
7/21/2019 Mammoet LNG Modular Construction
4/41
44
-
7/21/2019 Mammoet LNG Modular Construction
5/41
5
WHY MODULARIZATION?
Limited / strained labor force
Limited workforce accommodation
Limited equipment availability
Harsh environment
Limited plot plan area or greenfield development Restricted geographic location
Environmentally sensitive
Limited time window
-
7/21/2019 Mammoet LNG Modular Construction
6/41
6
ENGINEERED HEAVY LOGISTICS
6
-
7/21/2019 Mammoet LNG Modular Construction
7/41
7
-
7/21/2019 Mammoet LNG Modular Construction
8/41
8
HOW DOES MODULARIZATION SAVE TIME?
-
7/21/2019 Mammoet LNG Modular Construction
9/41
9
WHAT MUST BE CONSIDERED
BEFORE WE START TO DESIGN MODULES?
-
7/21/2019 Mammoet LNG Modular Construction
10/41
10
WHERE WILL THE MODULES BE FABRICATED?
-
7/21/2019 Mammoet LNG Modular Construction
11/41
11
AVAILABILITY OF SUITABLE VESSELS
-
7/21/2019 Mammoet LNG Modular Construction
12/41
12
INCORPORATING TRANSPORTATION LOADS IN THEDESIGN OF STRUCTURAL STEEL
-
7/21/2019 Mammoet LNG Modular Construction
13/41
13
WHAT SIZE OF MODULES CAN BE REALISTICALLY MOVED?
-
7/21/2019 Mammoet LNG Modular Construction
14/41
-
7/21/2019 Mammoet LNG Modular Construction
15/41
-
7/21/2019 Mammoet LNG Modular Construction
16/41
16
-
7/21/2019 Mammoet LNG Modular Construction
17/41
17
Limited / strained local labor force
Access to offshore labor force
Remote / Harsh environment
Limited plot area / green field development
Environmentally sensitive Schedule / cost / safety driven projects
-
7/21/2019 Mammoet LNG Modular Construction
18/41
-
7/21/2019 Mammoet LNG Modular Construction
19/41
19
GORGON PROJECT SCOPE OVERVIEW
56 Modules (MOD) (SPMT) Range between 450 6500 Tonnes
9 Column's (PDR) (CRANE) Range between 138 and 1112 Tonnes
233 Pipe racks (PAR) (SPMT / CRANE) Range between 12 and 1500 Tonnes
32 Substation Buildings (CRANE)
6 Compressor/Turbine lines (CRANE)
6 Waste Heat Recovery stacks (SPMT/CRANE)
Additional scope : 140+ small pre-assembled structures (Load-out / Load-in AMC Yard Perth)
-
7/21/2019 Mammoet LNG Modular Construction
20/41
20
GORGON SITE OVERVIEW
MOF
JETTY / MOF
CAUSEWAY
LNG PLANT
FLARE
-
7/21/2019 Mammoet LNG Modular Construction
21/41
21
GORGON SITE OVERVIEW
-
7/21/2019 Mammoet LNG Modular Construction
22/41
22
SITE PLAN (EXCL. FLARE + MOF)
-
7/21/2019 Mammoet LNG Modular Construction
23/41
23
ROLL ON / ROLL OFF
-
7/21/2019 Mammoet LNG Modular Construction
24/41
24
TRAIN 1 LNG MODULE (6000+ TE)
-
7/21/2019 Mammoet LNG Modular Construction
25/41
25
2ND LNG TRAIN MODULE (TAJB)
-
7/21/2019 Mammoet LNG Modular Construction
26/41
26
AMINE ABSORBER (1112 TE)
-
7/21/2019 Mammoet LNG Modular Construction
27/41
27
AMINE ABSORBER RIGGING
-
7/21/2019 Mammoet LNG Modular Construction
28/41
28
AMINE ABSORBER LIFT
-
7/21/2019 Mammoet LNG Modular Construction
29/41
29
PIPE-RACK TRANSPORT IMPRESSION
-
7/21/2019 Mammoet LNG Modular Construction
30/41
30
PIPE-RACK TRANSPORT IMPRESSION
-
7/21/2019 Mammoet LNG Modular Construction
31/41
31
INSTALLATION CHALLENGES
Tight operations Constant changing site conditions Unexpected additional scope
Maintaining delivery schedule Large amount of auxiliary equipment Shortage of laydown area
-
7/21/2019 Mammoet LNG Modular Construction
32/41
32
LESSONS LEARNED
-
7/21/2019 Mammoet LNG Modular Construction
33/41
33
LESSONS LEARNED
1. 100% engineering completion before start of fabrication
Failure to accomplish this will result in potential for significant increase in on site direct / indirect hours
-
7/21/2019 Mammoet LNG Modular Construction
34/41
34
LESSONS LEARNED
2. Early involvement of EHL (Engineered Heavy Logistics)
Including an EHL as an overall advisor will optimise the logistics chain in time and money
Optimization of sea fastening, grillage and lashing equipment thru smart engineering
Determine logistics envelop
Highlight bottleneck for logistics strategy
Standardize lifting and transport supports as much as possible for all items
An EHL approaches design from an optimized construction point of view. Historically, in the offshore
industry, modularisation has been a lump sum based execution strategy. Therefore, the EHL will view
onshore projects from the same mindset.
-
7/21/2019 Mammoet LNG Modular Construction
35/41
35
LESSONS LEARNED
3. Select construction strategy at early stage Build high modules (only SPMT)
Build lower modules (SPMT with cranes)
Define maximum weights to optimize crane use (i.e. single crane for all lifts)
Including legs on the modules allows for flexible placement and storage
-
7/21/2019 Mammoet LNG Modular Construction
36/41
36
LESSONS LEARNED
4. Interface management
Strong technical and operational experience for integration of marine and land contractors
Involved parties: MWS, marine contractor, customs, Client, site contractor, stevedores, longshoreman,
engineering design contractor, sea fastening fabricator, etc.
Clearly understand responsibilities of all parties prior to operations
-
7/21/2019 Mammoet LNG Modular Construction
37/41
37
LESSONS LEARNED
5. Management of the unexpected
We do not live in an ideal world. Always have a plan B (and perhaps even C)
Prepare for receiving cargo day or night
Sufficient support equipment (module stands, load spreader mats and miscellaneous equipment)
Where possible, have 2 discharge locations to reduce potential for expensive demurrage for transport
vessel and equipment
-
7/21/2019 Mammoet LNG Modular Construction
38/41
38
LESSONS LEARNED
6. Module Alignment
Module Alignment requires strong spotters to ensure proper positioning and no damage to piperacks
and equipment There will be misalignment within the module blocks. Differences in temperatures will make every pipe
extend or retrack.
Make sure you can compensate misalignment of this piping by using sleeves, or spacers and adequate
measuring and shimming equipment is available
Understand boundaries of approval with all parties
-
7/21/2019 Mammoet LNG Modular Construction
39/41
39
LESSONS LEARNED
7. Shipping / Importation of Equipment
In environmentally sensitive areas special preparations (cleaning of equipment, customs paperwork,
inspections) are required Custom clearance for modules can be significant scheduling
8. Local Contractors
Well versed in local labor regulations and requirements
Experience with camp based work
9. Communication
-
7/21/2019 Mammoet LNG Modular Construction
40/41
40
MOVING DEADLINES FORWARD
40
-
7/21/2019 Mammoet LNG Modular Construction
41/41