major rates

8
MAJOR RATES 1 Excavating basements; not exceeding 2.00m deep m 3  350.00 2 Excavating for footings; not exceeding 1.50m deep m 3  300.00 3 Remove excavated materials off site m 3  400.00 4 150mm thick Hardcore bed blinded with fine materials m 3  3,000.00 5 Mass concrete grade 15 m 3  3,500.00 6 Reinforced concrete grade 30 m 3  5,000.00 7 Mild steel rod reinforcement kg 42.00 8 High tensile rod reinforcement kg 43.00 9 Sawn formwork to soffits of suspended slabs m 2  900.00 10 Sawn formwork to columns and walls m 2  850.00 11 "Kliplok Colorbond" 0.64mm profiled steel sheeting m 2  1,100.00 12 Aluminum casement windows, single glazed m 2  9,500.00 13 Structural steelwork- beams, stanchions and the like kg 105.00 14 Steelwork-a ngles, channels, flats and the like kg 95.00 15 25mm cement and sand (1:3) paving m 2  350.00 16 20mm cement and sand (1:4) plaster to walls m 2  350.00 17 Ceramic tiles bedded to floor screed (m/s) m 2  1,300.00 18 12mm fibrous plasterboard ceiling lining m 2  1,300.00 19 Two coats of emulsion paint to plastered surfaces m 2  450.00 20 Average expected preliminaries % 8-15 * The above costs are based on lump sum fixed price contract rate exclusive of preliminaries and contingencies unless otherwise stated ESTIMATING RULES OF THUMB Densities of Common Materials Concrete 2400 kg/m3 Water 1000 kg/m3 Cement 1441 kg/m3 Softwood 700 kg/m3 Sand 1600 kg/m3 Hardwood 1100 kg/m3 Gravel 1350 kg/m3 Aluminum 2750 kg/m3 Steel 7850 kg/m3 Soil (compact) 2100 kg/m3 Concrete: Minimum Recommended Cement Factor Based on Concrete Strength (in bags of 40kg cement) Strength Ordinary Design Mix Pumpcrete Design Psi Mpa 1 ½” Gravel Size ¾” Gravel Size ¾” 8000 55 21 22 23 7000 48 19 20 21 6000 41 17 18 19 5000 35 15 16 17 4000 28 11.75 12.75 14.5 3000 21 9 10 11.5

Upload: maryknoll-sab

Post on 02-Mar-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Major Rates

7/26/2019 Major Rates

http://slidepdf.com/reader/full/major-rates 1/8

MAJOR RATES1 Excavating basements; not exceeding 2.00m deep m 3 350.002 Excavating for footings; not exceeding 1.50m deep m 3 300.003 Remove excavated materials off site m 3 400.004 150mm thick Hardcore bed blinded with fine materials m 3 3,000.005 Mass concrete grade 15 m 3 3,500.006 Reinforced concrete grade 30 m 3 5,000.00

7 Mild steel rod reinforcement kg 42.008 High tensile rod reinforcement kg 43.009 Sawn formwork to soffits of suspended slabs m 2 900.0010 Sawn formwork to columns and walls m 2 850.0011 "Kliplok Colorbond" 0.64mm profiled steel sheeting m 2 1,100.0012 Aluminum casement windows, single glazed m 2 9,500.0013 Structural steelwork-beams, stanchions and the like kg 105.0014 Steelwork-angles, channels, flats and the like kg 95.0015 25mm cement and sand (1:3) paving m 2 350.0016 20mm cement and sand (1:4) plaster to walls m 2 350.00

17 Ceramic tiles bedded to floor screed (m/s) m 2 1,300.0018 12mm fibrous plasterboard ceiling lining m 2 1,300.0019 Two coats of emulsion paint to plastered surfaces m 2 450.0020 Average expected preliminaries % 8-15

* The above costs are based on lump sum fixed price contract rate exclusive ofpreliminaries and contingencies unless otherwise stated

ESTIMATING RULES OF THUMB

Densities of Common MaterialsConcrete 2400 kg/m3 Water 1000 kg/m3Cement 1441 kg/m3 Softwood 700 kg/m3Sand 1600 kg/m3 Hardwood 1100 kg/m3Gravel 1350 kg/m3 Aluminum 2750 kg/m3Steel 7850 kg/m3 Soil (compact) 2100 kg/m3

Concrete: Minimum Recommended Cement Factor Based on Concrete Strength(in bags of 40kg cement)

Strength Ordinary Design Mix Pumpcrete DesignPsi Mpa 1 ½” Gravel Size ¾” Gravel Size ¾” 8000 55 21 22 237000 48 19 20 216000 41 17 18 195000 35 15 16 174000 28 11.75 12.75 14.53000 21 9 10 11.5

Page 2: Major Rates

7/26/2019 Major Rates

http://slidepdf.com/reader/full/major-rates 2/8

ReinforcementBar Diameter Weight/m

(mm) (kg/m)6 0.2228 0.395

10 0.61612 0.88816 1.579

20 2.46625 3.85428 4.83432 6.31336 7.99040 9.864

Structure Design – Concrete RatiosThe following is a range of concrete ratios for building superstructure design in Manila:

Concrete/ floor area 0.4 m3

/m2

to 0.55 m3

/m2

Formwork/floor area 2.0 m 2/m 2 to 3.0 m 2/m 2 Reinforcement 180 kg/m 3 to 280 kg/m 3

Average External Wall/ Floor RatioResidential Apartments 0.35 m 2/m 2 Office, Hotel 0.4 m 2/m 2 Industrial 0.4 m 2/m 2

Average Internal Wall/ Floor RatioResidential Apartments 1.0 m 2/m 2 Office, Hotel 0.5 m 2/m 2 Industrial 1.5 m 2/m 2

Dimensions for standard parking space, loading/ unloading bays and lay-bys

Length Width Headroom(m) (m) (m)

Private Cars, Taxis and Light Vans 5 2.5 2.4Coaches and Buses 12 3.0 3.8

Lorries 11 3.5 4.1Container Vehicles 16 3.5 4.5

* Minimum headroom means the clearance between the floor and the lower most projection from the ceiling includingany lightings units, ventilation duct, conduits or similar.** The above ratios are indicative and for reference purpose only. They do not account for buildings with special shapes,configurations or particularly small footprints.

Page 3: Major Rates

7/26/2019 Major Rates

http://slidepdf.com/reader/full/major-rates 3/8

Conversion

1 MPa 145 psi1 m 3.281 ft1 km 0.621 mi1.5 hp 1 TR

Construction Costs for Philippines

PESO/m2

DESCRIPTION BUILDINGM & E TOTAL

SERVICESTOTAL

DOMESTICApartments, high rise, average standard 27,000 – 34,000 7,000 – 10,700 34,000 – 44,700Apartments, high rise, high end 37,500 – 43,800 9,700 – 15,400 47,200 – 59,200Terraced houses, average standard 23,000 – 26,400 2,700 – 4,600 25,700 – 31,000Detached houses, high end 46,000 – 51,000 7,900 – 12,150 53,900 – 63,150

OFFICE/COMMERCIAL

Medium/high rise offices, average standard 25,000 – 27,500 9,450 – 13,300 34,450 – 40,800High rise offices, prestige quality 40,200 – 45,500 13,150 – 17,100 53,350 – 62,600Out-of-town shopping center, ave. standard 23,800 – 27,100 6,925 – 12,580 30,725 – 39,680Retail malls, high end 32,500 – 41,500 8,150 – 14,800 40,650 – 56,300

HOTELSBudget hotels – 3 star, mid market 34,000 – 46,700 12,400 – 16,050 46,400 – 62,750Business hotels – 4/5 star 35,100 – 46,800 13,500 – 20,400 48,600 – 67,200Luxury hotels – 5 star 49,100 – 54,200 14,250 – 23,600 63,350 – 77,800

INDUSTRIAL

Industrial units, shell only (conventionalsingle storey framed units)

13,200 – 14,200 3,950 – 7,200 17,150 – 21,400

Owner operated factories, low rise, lightweight industry

15,400 – 16,600 3,950 – 7,200 19,350 – 23,800

OTHERSUnderground/basement car parks (<3 levels) 16,800 – 17,300 3,950 – 7,200 20,750 – 24,500Multi storey car parks, above ground (<4levels)

14,200 – 16,500 3,550 – 6,800 17,750 – 23,300

Schools (primary & secondary) 19,500 – 22,200 7,050 – 13,000 26,550 – 35,200Students residences 22,500 – 24,800 7,000 – 10,500 29,500 – 35,300

Sports clubs, multi-purpose sports/leisurecenters(dry sports) with a/c and including FF& E

45,500 – 53,100 6,200 – 9,720 51,700 – 62,820

General hospitals – public sector 41,600 – 48,600 12,600 – 20,350 54,200 – 68,950

* Costs are at 4 th quarter 2014 levels. Manila building costs are expected to increase by approximately 0.5% per month(compounded) during 2015.

Page 4: Major Rates

7/26/2019 Major Rates

http://slidepdf.com/reader/full/major-rates 4/8

PESO/m 2

DESCRIPTION TOTALSERVICES

ELECTRICALSERVICES

MECHANICALSERVICES

FIRESERVICES

LIFTS/ESCALATOR

PLUMBINGSERVICES

DOMESTIC Apartments, high rise, averagestandard

7,000 – 10,700 3,600 – 4,300 600 – 1,400 600 – 900 800 – 2,000 1,400 – 2,100

Apartments, high rise, high end 9,700 – 15,400 3,900 – 6,300 2,100 – 3,000 700 – 1,300 900 – 2,100 2,100 – 2,700Terraced houses, average standard 2,700 – 4,600 1,400 – 1,800 600 – 1,300 - - 700 – 1,500Detached houses, high end 7,900 – 12,150 3,000 – 5,500 2,500 – 2,950 - - 2,400 – 3,700

OFFICE/COMMERCIALMedium/ high rise offices, averagestandard

9,450 – 13,300 3,300 – 4,700 3,000 – 4,000 650 – 900 1,600 – 2,200 900 – 1,500

High rise offices prestige quality 13,150 – 17,100 4,800 – 6,000 4,000 – 5,000 650 – 1,200 2,200 – 2,900 1,500 – 2000Out-of-town shopping center,average standard

6,925 – 12,580 3,060 – 5,100 2,125 – 3,825 550 – 765 595 – 1,700 595 – 1,190

Retail malls, high end 8,150 – 14,800 3,600 – 6,000 2,500 – 4,500 650 - 900 700 – 2,000 700 – 1,400

HOTELSBudget hotels – 3 star, mid market 12,400 – 16,050 4,700 – 5,500 3,300 – 4,500 650 – 950 1,800 – 2,300 1,950 – 2,800Business hotels – 4/5 star 13,500 – 20,400 5,100 – 6,500 3,800 – 6,200 600 – 1,000 1,700 – 2,900 2,300 – 3,800

Luxury hotels – 5 star 14,250 – 23,600 5,400 – 9,000 4,000 – 6,500 650 – 1,100 1,800 – 3,000 2,400 – 4,000

INDUSTRIALIndustrial units, shell only(conventional single storey framedunits)

3,950 – 7,200 2,000 – 3,500 650 – 1,500 600 – 900 - 700 – 1,300

Owner operated factories, low rise,lightweight industry

3,950 – 7,200 2,000 – 3,500 650 – 1,500 600 – 900 - 700 – 1,300

OTHERSUnderground/basement car parks(<3 levels)

3,950 – 7,200 2,000 – 3,500 650 – 1,500 600 – 900 - 700 – 1,300

Multi storey car parks, aboveground (<4 levels)

3,550 – 6,800 1,800 – 3,300 450 – 1,300 600 – 900 - 700 – 1,300

Schools (primary & secondary) 7,050 – 13,000 3,300 – 4,900 600 – 3,500 650 – 900 1,600 – 2,200 900 – 1,500Students residences 7,000 – 10,500 3,600 – 4,300 600 – 1,400 600 – 900 800 – 1,800 1,400 – 2,100Sports clubs, multi-purposesports/leisure centers (dry sports)with a/c and including FF & E

6,200 – 9,720 2,900 – 3,770 1,500 – 1,950 400 – 700 -- 1,500 1,400 – 1,800

General hospitals – public sector 12,600 – 20,350 5,000 – 7,700 4,200 – 6,500 750 – 1,500 900 – 1,800 1,750 – 2,850

*Costs are at 4 th quarter 2014 levels

Page 5: Major Rates

7/26/2019 Major Rates

http://slidepdf.com/reader/full/major-rates 5/8

Trends:

Page 6: Major Rates

7/26/2019 Major Rates

http://slidepdf.com/reader/full/major-rates 6/8

M & E MAJOR PLANT COSTS FOR THE PHILIPPINES

DESCRIPTION UNIT COST (Php)1. Water cooled electric chiller per TR 16,000 – 28,0002. Air-cooled electric chillers per TR 25,000 – 35,0003. Cooling towers; induced draft per GPM 2,300 – 3,0004. Air Handling Units (AHU) per TR 13,000 – 19,0005. Packaged Water-Cooled Units

(PWCU)per TR 18,000 – 27,000

6. Fire Pumps; electric motor driven per HP 17,000 – 22,0007. Fire Pumps; diesel engine driven per HP 22,000 – 26,0008. Standby generator sets per kVA 5,500 – 9,5009. Power transformers, with built-inprimary protections; padmount

per kVA 1,600 – 6,000

10. Power transformers, with primaryprotection; silicon oil filled

per kVA 1,300 – 4,400

11. Power transformers, with primaryprotection cast resin

per kVA 2,000 – 5,000

12. Sewage Treatment Plant,

Sequencing Batch Reactor (SBR);including civil works

per m3

/day 20,000 – 30,000

* Rates are based on direct supply of imported equipment and materials by the developer** Rates include all government imposed taxes, import duties, brokerage fees and allowances for local materials andinstallation cost*** Rates exclude preliminaries and contingencies**** Rates are by on fixed price tenders received in 4 th quarter 2014

FIT-OUT COSTS FOR PHILIPPINES

DESCRIPTION PESO/m2 HOTELSPublic Areas (Front of House):3-star Hotel 18,000 – 22,0004-star Hotel 24,000 – 28,0005-star Hotel 30,000 upGuest rooms:3-star hotel 16,000 – 18,0004-star hotel 20,000 – 25,0005-star hotel 30,000 – 40,000

Notes:1. Includes furniture,floor,wall and ceiling finishes,drapery,sanitary fittings and light fittings2. Excludes partitioning,M&E works,building shell,Chandelier,operational items and equipment (e.g.bed,cutlery,crockery,linen,television,refrigerator,etc.),opening expenses,stage equipment and computersystems

Page 7: Major Rates

7/26/2019 Major Rates

http://slidepdf.com/reader/full/major-rates 7/8

COMMERCIALShopping centers 20,000 – 25,000Notes:1. Mall/Public areas only; tenant area to be barefinish2. See notes 1,2 & 3 below

NOTE:1. Costs are at December 2014 levels2. Costs include wall, floor, ceiling finishes, doors, FF&E, M&E Works service reticulation, preliminaries

Forex US$1:44.5

DESCRIPTION PESO/m2 OFFICESStandard offices *Executive offices **Banking lobby ***

* Medium quality systems furniture** High quality furniture and finishes*** Imported stone finishes; double volume spaces

Note:See notes 1, 2 & 3 below

RESTAURANTSGeneral dining restaurant 20,000 – 25,000Fine dining restaurant

Note:Includes furniture,floor,wall and ceiling finishes,minoralteration to air-conditioning and fire servicesinstallation to suit lay-out,exhaust for kitchen butexcludes exhaust flue,operational items (e.g. cutlery,crockery,linen,utensils,etc.)

3. Costs exclude operational equipment and supplies, structure, external enclosure, major M&E plant, financingand developers costs, professional and marketing fees.

DESCRIPTION PESO/m2 THEATRES / CINEMASTheatres * 40,000 – 65,000Cinemas ** 25,000 – 40,000

* Includes stage rigging and equipment, draperies,AV equipment projectors, screens, acoustics andseatings** Includes screens, projection equipment, seats,finishes, ticketing booth

Page 8: Major Rates

7/26/2019 Major Rates

http://slidepdf.com/reader/full/major-rates 8/8

AUDITORIUMS 35,000 – 60,000

BUSINESS CLUBS 50,000 – 70,000

BAR/ BILLIARDS* 32,000 – 40,000

* Excluding kitchen equipment

NOTE:1. Costs are at December 2014 Levels2. Costs include wall, floor, ceiling finishes, doors, FF&E, M&E Works service reticulation, preliminaries.

Forex US$1:44.503. Costs exclude operational equipment and supplies, structure, external enclosure, major M&E plant, financing

and developers costs, professional and marketing fees

Average Loads VolumeLorry (24 ton) 10.0 m3Concrete truck (24 ton) 5.5 m3