main inplant traning report
TRANSCRIPT
-
7/31/2019 Main Inplant Traning Report
1/14
INDUSTRIAL VISIT
(AT 2X500 MW BHUSAVAL THERMAL POWER PLANT)
UNDER
VISIT BY: MAYUR BHAGWAN VANJARI
STUDENTS OF:TRIMURTI INSTITUTE OF TECHNOLOG JALGAON, MAHARASHTRA.
-
7/31/2019 Main Inplant Traning Report
2/14
ABSTRACT
This report is based on our observations during our visit to the Bhusaval
Thermal Power Plant (2X500 MW). Nowadays various modifications havebeen done in the conventional method of generation in order to increase
the efficiency of the plant. So all the new and recent technologies have
been used in this plant and all such new machines and technologies were
observed and studied.
-
7/31/2019 Main Inplant Traning Report
3/14
INTRODUCTION
In a thermal power plant, thermal energy generated after burning coal is
converted into the electrical energy. Steam generated in the boiler is
introduced into the turbine, which rotates the turbine blades at particular
speed and hence drives the generator to produce electricity. The main fuel
used for producing steam is coal. After we drive the generator on, the
magnetic flux is generated in the rotor winding, which is cut by the stator
winding and current is induced in the stator winding. This is the basic
principal of generation of the electricity but various factors have to be
taken into consideration for the efficient generation. Hence it includes
various systems and cycles such as turbine cycle, ash handling system, coalhandling system etc. so this report contains a study of all the systems and
all analysis are reported in brief.
-
7/31/2019 Main Inplant Traning Report
4/14
UNIT OVERVIEW
For generating power, all the systems of the power plant need to work in
synchronised manner. In power plant, there are various systems which
work separately, but these are interconnected for generation purposes
which are as follows.
1. Boiler and ESP2. Turbine section3. Coal handling plant4. Ash handling plant5. Oil handling plant6. Other supporting systems such as
i.
Air conditioning systemii. Ventilation systemiii. EOT cranes, transformers etc.
There are in all 8 coal mills in this 1000 MW project out of which
6 mills are work for each of 500 MW unit. The mills are used for
crushing the coal into fine powders. This fine powdered coal is
taken to the furnace where it is burned. This heat energy so
produced is used to produce steam into the boiler, which is used
to drive the turbine blades and connected to the exciter to
generate the electricity. Three types of turbines are used namely
High Pressure Turbines (HPT), Intermediate Pressure Turbines
(IPT) and Low Pressure Turbines (LPT). The steam generated is
firstly passes to the HPT and the steam coming out is taken back
to the furnace and reheated and then given to the IPT. The
steam through the IPT is given directly to the LPT.
After the steam is used to drive the turbine blades, it needs to be
condensed. The steam is taken to the condenser for the
condensation. The resulting liquid is taken to the low pressure
heater (LPH) for heating. Then this is taken to the Deaerator,
where the air and the water are separated. Then the water is
taken to the High Pressure Heater for heating.
-
7/31/2019 Main Inplant Traning Report
5/14
BOILER
The steam required to drive the turbine is generated in the
boiler. Water tube boiler is used in this power plant. The coal in
the powdered is taken from the mills. There are 8 mills, 4 on the
either side of the boiler. The coal is feeded from the 4 corners of
the boiler.
Initially some temperature is required to burn the coal. So firstly
the combustion in the boiler is carried out using LDO (Light Diesel
Oil). Then this heat is used in the combustion of HFO (Heavy
Furnace oil). Using this combustion process a sufficient heat
conditions are achieved for the burning of the coal.
The height of the boiler used in this plant is 80 meters. Many
number of water tubes are present around the furnace. The
combustion of the coal in the furnace generates sufficient heat
to convert steam into the water.
There are three steam lines through the boiler, a main steam line
and the other 2 through the HT turbine (for super heating
purpose).
At the 8 meter height, a ring header is present to supply water to
the boiler tubes.
-
7/31/2019 Main Inplant Traning Report
6/14
ELECTROSTATIC PRECIPITOR
This part comes into picture for handling of ash coming out from
boiler section after combustion of coal. It is based on
electrostatic phenomenon. The ash coming out of furnace
contains many ions. Ionisation is done to extract this ash.
This portion consists of series of positively charged plates and
negatively charged coils placed alternately. Ash gets stick to the
plates. These plates are vibrated using hammers which are
coupled to the shaft of rapper motor.
As soon as the plates are hammered, due to vibration, ash
falls down and gets accumulate in hopper. Hopper looks like a
funnel which is provided with heater at its bottom to keep ash
temperature favourable (120 ). Air is also blown into the
hopper through pipes for easier flow of ash down to vacuum
container.
After that ash stored in buffer hopper and is transported to silo
through pipes. Pressurised air is used to make thetransportation. From silo sufficient amount of water is mixed
with the ash to form the slurry. This slurry is transported out of
the plant to the ash bund. This ash is further utilised for cement
and brick manufacturing.
On the other hand smoke and various gases are sent into air
through chimney. ID fan (induced draft) is used for thisoperation. Induced draft fan sucks the smoke and gases from the
hopper and sends them into air.
The chimney is structured with the height of 275m.
-
7/31/2019 Main Inplant Traning Report
7/14
TURBINE CYCLE
There are three turbines present in this power plant namely High Pressure
Turbines (HPT), Low Pressure Turbines (LPT), Intermediate Pressure
Turbines (IPT). HPT is placed first followed by the IPT and LPT. The place
where all the turbines are place is called as the Turbine generator building.
To all these turbines a generator is connected to generate the electricity.
The turbines are placed at the 17 meter height. Between 0 meter and 17
meter all the machineries and equipments are placed required to
condense the generated steam.
The turbines are initially driven using the oil before the steam is passed
and the machineries required for this oil (mainly oil tank, pump etc.) are
kept at the 0 meter height. This oil is used to lubricate the shaft.
The steam is initially to the HTP. Then the heat coming through the HTP is
taken back to the furnace for reheating before it is given to the ITP. Then
this steam is given to the LTP directly. The resulting steam is taken back to
the condenser.
The steam required to drive the turbines should not be acidic for it does
not damage the turbine blades. The pH levels are checked whether the
steam is of the appropriate quality or not.
-
7/31/2019 Main Inplant Traning Report
8/14
OIL HANDLING PLANT
In oil handling plant, oil handled are LDO (Light diesel oil) and HFO (high
furnace oil).
These oils are stored in cans of volume 2000 kl. There are two cans for
HFO and single for LDO. LDO has light viscosity and burns very easily, whileHFO is high viscous and takes time for combustion.
Pressure, transmission, temperature and withdrawing oil from containers
of train is controlled by control room.
LDO is costly as compared to HFO. Initially LDO is used for combustion.
The reason behind this is LDO burns easily. Then HFO is used and then
finally coal.
-
7/31/2019 Main Inplant Traning Report
9/14
COAL HANDLING PLANT
Wagon tipplers are used to collect the coal from the wagon of
the train. Wagon tippler rotates the wagon 180 and coal is
collected in the container.
Then coal is transported to the bunker through the belt which
has an inclination of 15 and taken to the height of 60m of the
bunker.
There are crushers in between coal extraction point and bunkers.
The operation of crusher is to divide the carrier belt into two
ways one goes to unit 4 and another to unit 5.
Since during extraction of coal from wagons there forms huge
amount of dust, these dust is removed using air ducts provided
all over the carrier belt section.
When carrier reaches above the bunker a machine is used to
withdraw coal into different bunkers. Each bunker has capacity
of 800 tons.
-
7/31/2019 Main Inplant Traning Report
10/14
PLANT CONTROL ROOM
All the major parameters of every section of plant are controlled from
Plant control room. PCR consists of two sections, one is operation and
other is control and instrumentation room.
PCR involves microprocessor based systems in which plant parameters are
controlled automatically or manually on computer by operator.
Using designed software, all essential controls are given on computer
screen.
It can be controlled by the operator operating particular section on
computer screen seating in operational room in PCR section.
For example, if there is increase in humidity in steam, it will be displayedon computer screen this is done using sensors.
To control the humidity temperature of air is increased all over from PCR.
Similarly, all operations can be controlled using PCR such as, working of
motor etc.
PCR is basically electronic system involving PLC and SCADA using
microprocessors and microcontrollers.
-
7/31/2019 Main Inplant Traning Report
11/14
GENERATOR
Basic principle:
Generator is the synchronous machine which converts mechanical energy
into electrical energy by the principle of electromechanical energy
conversion. It consists of stator core, stator winding, rotor, rotor core and
yoke.
500 MW GENERATORS
Generator used in this power station is 500 mw capacity turbogenerator.
It is called turbogenerator because it is driven mechanically by steam
turbine.
Controlled dc excitation is given to rotor winding. Dc excitation iscontrolled by automatic voltage convertor. Brushless excitation system is
used which consist of pilot exciter, main exciter and rolling diode
arrangement.
An EMF is induced in the stator winding by action of flux cutting. This
induced EMF is nothing but three phase voltage across generator which is
21 KV in this case. Supply frequency is controlled by steam input to the
turbine.
-
7/31/2019 Main Inplant Traning Report
12/14
-
7/31/2019 Main Inplant Traning Report
13/14
SWITCH YARD
The switch yard of the power plant is for the transmission purpose of the
generated power. All the power is supplied to the switch yard in bulk
which then supplies it to the various sub stations. Basically a transmission
of 400 KV is to be stepped down for transmission and provided to the
consumers. 400 KV is supplied to some of the large consumers like big
industries, then some large consumers demand 220 KV or 132 KV supply
and 11 KV or 22KV is to be supplied at various levels. At the domestic
levels the generated voltage needs to be stepped down to 400 V. all this
lines of transmission pass through the switch yard.
At the stage of plant erection, ate auxiliaries need a supply. This
transmission of power to the plant from other stations is taken care by the
switch yard. The power from the other stations comes to the switch yard
through bus bars and is stepped down to 11 kV for the plant use by station
transformers.
The switch yard mainly consists of the transmission lines, isolators,
breakers, current transformers, potential transformers. Isolators are used
to de-energize the electrical circuits for the maintenance purpose. A
circuit breaker is an automatically operated switch designed to protect the
electrical circuit from damage due to overload and short circuit. CT and PT
are used basically for the measurement purposes.
When the power is generated, the plant auxiliaries are run on this
generated power. That means the plant uses its own power to run its
auxiliaries. Unit auxiliary transformer is used for this purpose. The unit
auxiliary transformer is a power transformer that provides power to the
station auxiliaries during normal operation. This transformer is connected
directly to the main generator and as such will provide the cheapest
power for the station use since any power from the transmission lines has
losses associated with it due to the line losses and transformer losses from
whatever step up transformer provided that power. These unit auxiliary
transformer is a three winding transformer having one primary winding
rated 22 kV and two secondary windings rated 6.6 kV and 4.2 kV. This
allows the transformer to power two different voltage level buses in the
plant .This transformers take the power generated in the plant, step itdown and supply it to the auxiliaries that need to run the power plant.
-
7/31/2019 Main Inplant Traning Report
14/14
The UATs secondary windings are connected to the non -segregated
phase bus duct. This bus work conveys the power to the different medium
voltage switch gears located in the plant. Switch gear is the collective term
used all the equipment used for protection, measurement and controlling
electric power. In this plant design there are two sets of switch gear buses
rated at 6.6 kV and 4.2 kV. Each 6.6kV bus can be energised by the UAT.
The same is true for 4.2 kV switch gear.