maerskhighlander...the rig was 889 days lti free and 9-10 months ahead of the planned schedule. 10...

24
Highlander 400ft jack-up Maersk

Upload: others

Post on 29-Aug-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: MaerskHighlander...the rig was 889 days LTI free and 9-10 months ahead of the planned schedule. 10 Maersk Highlander UK Maersk Highlander 11 Built in: 2016 Countries operated in: UK

Highlander400ft jack-up

Maersk

Page 2: MaerskHighlander...the rig was 889 days LTI free and 9-10 months ahead of the planned schedule. 10 Maersk Highlander UK Maersk Highlander 11 Built in: 2016 Countries operated in: UK

Maersk Highlander2

We want to make it Simple to Be Safe.

Simple to Be Safe

Maersk Drilling truly wants to bring our people Out Of Harm’s Way. We are challenging the way we work with safety, not only as a priority but as a commitment.

This starts with asking our frontline colleagues what they need to stay safe and efficient. We are thinking out of the box for ways to eliminate risk. Nobody should ever be in doubt as to how to perform a task safely.

We are removing complexity and reducing administration so we have more time for safety conversations. We are innovating new solutions to digitise and make our work processes more visible.

4. Introduction3. Contents 6. Strategy 8. Rig capabilities 10. Experience 12. Dimensions 16. Equipment 22. Rig drawings

Page 3: MaerskHighlander...the rig was 889 days LTI free and 9-10 months ahead of the planned schedule. 10 Maersk Highlander UK Maersk Highlander 11 Built in: 2016 Countries operated in: UK

Maersk Highlander 3

12. DimensionsGet an overview of the rig’s dimensions and storage.

6. StrategyEvery hour spent on a well counts. We aim to make drilling smarter.

16. EquipmentFully equipped to deliver safe and efficient operations.

10. ExperienceStrong experience is vital to enable efficient operations.

22. Rig drawingsSee the full picture with a top and side view of the rig.

8. Rig capabilitiesA rig’s capabilities drive successful operations for our clients.

4. Introduction3. Contents 6. Strategy 12. Dimensions 16. Equipment 22. Rig drawings

Contents

8. Rig capabilities 10. Experience

4. IntroductionA committed workforce of on- and offshore professionals.

Page 4: MaerskHighlander...the rig was 889 days LTI free and 9-10 months ahead of the planned schedule. 10 Maersk Highlander UK Maersk Highlander 11 Built in: 2016 Countries operated in: UK

Maersk Highlander4

4. Introduction3. Contents 6. Strategy 8. Rig capabilities 10. Experience 12. Dimensions 16. Equipment 22. Rig drawings

Delivering operational excellence with innovation

We are a leader in the harsh environment sector and have a strong track record in deepwater drilling. Our fleet is one of the youngest and most advanced in the industry, comprising advanced drillships, deepwater semi-submersibles and high-end jack-up rigs.

For over 40 years, we’ve been working closely with our customers to deliver safe and efficient drilling campaigns. Our highly skilled and committed workforce of on- and offshore professionals is recognised for their technical skills, operational excellence and for solving complex problems.

Today, we’re increasingly providing third-party services and partnering with our customers on innovative technologies and new commercial models. Together, we’re reducing the complexity, cost, and risk of drilling campaigns to improve the competitiveness of offshore oil and gas for our customers.

Jørn MadsenCEO, Maersk Drilling

Maersk Drilling provides offshore drilling services to oil companies in major oil basins around the world.

Page 5: MaerskHighlander...the rig was 889 days LTI free and 9-10 months ahead of the planned schedule. 10 Maersk Highlander UK Maersk Highlander 11 Built in: 2016 Countries operated in: UK

Maersk Highlander 5

“ Our fleet is one of the youngest and most advanced in the industry, comprising advanced drillships, deepwater semi-submersibles and high-end jack-up rigs. ”

4. Introduction3. Contents 6. Strategy 8. Rig capabilities 10. Experience 12. Dimensions 16. Equipment 22. Rig drawings

Page 6: MaerskHighlander...the rig was 889 days LTI free and 9-10 months ahead of the planned schedule. 10 Maersk Highlander UK Maersk Highlander 11 Built in: 2016 Countries operated in: UK

Maersk Highlander

Smarter Drilling for Better Value

6

4. Introduction3. Contents 6. Strategy 10. Experience8. Rig capabilities 12. Dimensions 16. Equipment 22. Rig drawings

Page 7: MaerskHighlander...the rig was 889 days LTI free and 9-10 months ahead of the planned schedule. 10 Maersk Highlander UK Maersk Highlander 11 Built in: 2016 Countries operated in: UK

Maersk Highlander 7

Smarter Drilling for Better Value is Maersk Drilling’s response to this. It combines innovative technologies with new commercial models to reduce waste and inefficiency across all the activities delivered on a well.

We provide solutions that plan, orchestrate and integrate the services involved in a drilling campaign. By improving co-ordination and simplifying

interfaces across the supply chain, we aim to reduce overall NPT, increase efficiency and improve safety for our customers.

We’re also building new types of alliances with our customers that take a longer-term time horizon, align incentives and create value for the partners. Together, we’re lowering the cost per barrel and improving the competitiveness of offshore oil and gas.

Offshore oil and gas is in a race to produce the most competitive barrel of oil. With dozens of different suppliers and multiple interfaces involved, the process of delivering a well safely, on time and within budget has become more complex for operators than it needs to be.

Non-productive time (NPT) is often 20–25% across all

suppliers on a well

20–25% NPT

It can take over 60 suppliers and 6,000 invoices to drill

an offshore well

60+ suppliers

Every hour spent on a well counts – there’s a lot to play for

Our joint challenge:

4. Introduction3. Contents 6. Strategy 10. Experience8. Rig capabilities 12. Dimensions 16. Equipment 22. Rig drawings

Page 8: MaerskHighlander...the rig was 889 days LTI free and 9-10 months ahead of the planned schedule. 10 Maersk Highlander UK Maersk Highlander 11 Built in: 2016 Countries operated in: UK

Rig capabilities

Maersk Highlander8

4. Introduction3. Contents 6. Strategy 10. Experience8. Rig capabilities 12. Dimensions 16. Equipment 22. Rig drawings

A flat main deck with conventional cantilever box and derrick. The cantilever and derrick can be skidded between well locations with minimum rig up and rig down. This also allows for full drilling loads, irrespective of movement from centre line to port or starboard.

The NOV drilling package enables offline handling of all tubular types and incorporates automated sequencing of operations as well as anti-collision systems. Specifically designed material handling capabilities allow for deployment of XMTs and the ability to handle HP risers.

The Maersk Highlander is a 400ft Friede Goldman jack-up 2000E rig, with design optimisation inputs from Maersk Drilling.

Page 9: MaerskHighlander...the rig was 889 days LTI free and 9-10 months ahead of the planned schedule. 10 Maersk Highlander UK Maersk Highlander 11 Built in: 2016 Countries operated in: UK

Maersk Highlander 9

6,175 bbls total mud pit volume including slugging pits

Harsh environment (North Sea, HPHT, H2S)

jack-up rig

935m3/6175bbls

circulating system

117m/ 547ft legs give a maximum operating water depth capability of up to 400ft

15,000psi BOP with shear boost, 10,000psi annular preventer and 15,000psi choke and kill manifolds

NOV ADS-10Q, 600HP draw-works grooved for 2” drill-line

King posts for burner booms, sprinklers and fixed lines for oil/gas, seawater and air pre-installed at the dedicated testing area

Fully automatedpipe handling and provision

for offline activities

Support deck Fixed at starboard aft. side of the rig. Designed for storing

equipment when working over platforms

Four cranes: 3 electric hydraulic deck cranes with 40m (131ft) boom, 75MT static and 40MT dynamic load. 1 knuckle boom

crane with 25m (82ft) reach, 12MT load, 5MT winch

7500psi

Main

features

74.8ft (22.8m) diameter octagonal

helideck suitable for Sikorsky S-92

helicopter

3,766MT variable deck load

Maximum drilling depth

9144m/ 30,000ft

BOP tensioner system2x136Ton

6 x NOV VSM 300 high-performance shale shakers and two NOV vacuum degassers

POB135

4. Introduction3. Contents 6. Strategy 10. Experience8. Rig capabilities 12. Dimensions 16. Equipment 22. Rig drawings

Page 10: MaerskHighlander...the rig was 889 days LTI free and 9-10 months ahead of the planned schedule. 10 Maersk Highlander UK Maersk Highlander 11 Built in: 2016 Countries operated in: UK

Experience

8. Rig capabilities4. Introduction3. Contents 6. Strategy 10. Experience 12. Dimensions 16. Equipment 22. Rig drawings

Operating in MPD modeDuring the start-up phase the rig was modified to be able to operate in MPD mode. This conversion was installed and tested within budget and time.

The drill crew were trained on the MPD techniques on the Highlander simulator at RGU (Robert Gordon’s

University) along with Maersk Training centre and 3rd party personnel. By applying this method, the rig and crew successfully drilled four ultra HPHT 12¼” and 8½” well sections in the Culzean field.

Culzean first gas – 10% below initial budgetIn June 2019, a milestone was reached by Maersk Highlander and Total at the Culzean platform when the first gas started to flow. The achievement was delivered well ahead of schedule and with capex savings of more than £390m.

This is just the latest of a long list of accomplishments since Maersk Highlander commenced operations

in August 2016. Since arriving at Culzean, the rig has successfully drilled 3 HPHT wells, and performed major upgrades to Well Control and Mud systems, all supported by a safe and efficient performance from the rig crew. By June 2019, the rig was 889 days LTI free and 9-10 months ahead of the planned schedule.

Maersk Highlander10

Page 11: MaerskHighlander...the rig was 889 days LTI free and 9-10 months ahead of the planned schedule. 10 Maersk Highlander UK Maersk Highlander 11 Built in: 2016 Countries operated in: UK

UK

Maersk Highlander 11

Built in: 2016

Countries operated in: UK

Customers worked with: Maersk Oil Total

Operational experience: HPHT MPD Completions Well Testing

8. Rig capabilities4. Introduction3. Contents 6. Strategy 10. Experience 12. Dimensions 16. Equipment 22. Rig drawings

Page 12: MaerskHighlander...the rig was 889 days LTI free and 9-10 months ahead of the planned schedule. 10 Maersk Highlander UK Maersk Highlander 11 Built in: 2016 Countries operated in: UK

Maersk Highlander12

Main dimensions Imperial Metric

Hull length overall 243ft 74.16m

Hull width overall 270ft 82.3m

Hull depth 31ft 9.45m

Length of legs 547ft 166.89m

Cantilever – max reach aft of stem 75ft 22.86m

Transverse (STB/PS) 30ft 9.14m

Equivalent spudcan diameter 59ft 17.99m

Main dimensions

12. Dimensions4. Introduction3. Contents 6. Strategy 8. Rig capabilities 10. Experience 16. Equipment 22. Rig drawings

Page 13: MaerskHighlander...the rig was 889 days LTI free and 9-10 months ahead of the planned schedule. 10 Maersk Highlander UK Maersk Highlander 11 Built in: 2016 Countries operated in: UK

Maersk Highlander 13

Maximum design limits

Operational capabilities Imperial Metric

Max water depth 400ft 122m

Wind speed 70 knots 36m/sec

Penetration 10ft 3m

Drilling depth 30,000ft 9,144m

Variable deck load capacity (incl. drilling loads) Imperial Metric

Legs down 3m (location move) 3,766MT

Legs down 13.8m (field move) 3,766MT

Unrestricted (North Sea move) 3,766MT

Variable load (jacking condition) 3,766MT

12. Dimensions4. Introduction3. Contents 6. Strategy 8. Rig capabilities 10. Experience 16. Equipment 22. Rig drawings

Page 14: MaerskHighlander...the rig was 889 days LTI free and 9-10 months ahead of the planned schedule. 10 Maersk Highlander UK Maersk Highlander 11 Built in: 2016 Countries operated in: UK

Maersk Highlander14

12. Dimensions4. Introduction3. Contents 6. Strategy 8. Rig capabilities 10. Experience 16. Equipment 22. Rig drawings

Environmental limits Imperial Metric

Max wave height 72ft 22m

Air gap 100ft 30.5m

Environmental design limits

Page 15: MaerskHighlander...the rig was 889 days LTI free and 9-10 months ahead of the planned schedule. 10 Maersk Highlander UK Maersk Highlander 11 Built in: 2016 Countries operated in: UK

Maersk Highlander 15

Storage capabilities Imperial Metric

Liquid mud (active) 6,175bbls 935m3

Base oil storage 1,723bbls 274m3

Brine storage (heavy brine accepted e.g. bromide) 1,723bbls 274m3

Drill water 9,265bbls 1473m3

Potable water 2,654bbls 422m3

Fuel oil 3,830bbls 609m3

Bulk barite/bentonite 18,000cu-ft 510m3

Max hook load 2,000,000klbs 907.2MT

Max setback load 950,000klbs 475MT

Sack storage 4,950 sacks 4,950 sacks

Storage capabilities

12. Dimensions4. Introduction3. Contents 6. Strategy 8. Rig capabilities 10. Experience 16. Equipment 22. Rig drawings

Page 16: MaerskHighlander...the rig was 889 days LTI free and 9-10 months ahead of the planned schedule. 10 Maersk Highlander UK Maersk Highlander 11 Built in: 2016 Countries operated in: UK

Maersk Highlander16

4. Introduction3. Contents 6. Strategy 12. Dimensions 16. Equipment 22. Rig drawings8. Rig capabilities 10. Experience

Well control equipment

The Highlander is designed so that handling and operating of well control equipment has minimum impact on the well delivery and time schedule. Handling systems and hoses remain connected, minimising installation time.

Cameron 18¾” 15,000psi, double BOP

Cameron 18¾” 10,000psi annular

1 x 125MT BOP forklift crane

Cameron control system

NT2 connector rather than bolted flange connection for reduced nipple uptimes

BOP can be tested offline to full working pressure as hoses are connected at all times

Glycol unit installed at the choke manifold

15K BOP hoses and control hoses are permanently rigged up to reduce nipple up/down time

Equipment

Page 17: MaerskHighlander...the rig was 889 days LTI free and 9-10 months ahead of the planned schedule. 10 Maersk Highlander UK Maersk Highlander 11 Built in: 2016 Countries operated in: UK

Maersk Highlander 17

Drill floor

Maersk Highlander is fitted out with an NOV topside and driller’s cabin, a design that allows offline handling of tubulars to be carried out at the same time as main well centre operations. It incorporates anti-collision systems.

NOV TDX 1000, 907MT capacity link-tilt and block retract system, with pipe handler

Max continuous torque of 91,000ftlbs at 100rpm, intermittent torque of 84,800ft-lbs

NOV Amphion integrated drilling control system, with the ability to read and store casing make-up graphs

Driller and AD in the same driller’s cabin enables better communication. Redundancy within controls since driller and AD chair are identical

2,000,000lbs capacity NOV 4,600HP draw-works grooved for 2” drill-line

Dual pipe handling. While one string is working at the main well centre, offline casing, tubing, drillpipe and bottom hole assembling can be built or laid out from the mouseholes, reducing the time spent on the critical path

Derrick max setback load: 475MT. Dimensions: 170ft x 40ft x 45ft (52m x 12m x 14m)

Extra Drillers chair for MPD operations

NOV auto iron roughneck ST-160 tubular size range: 3½”–9½” DC. Fitted with automatic MUD Bucket system. As well as 1 x ST120 Iron roughneck. Pipe racking system consisting of two NOV PRS 4i automated hydrarackers, adjustable casing fingerboard, DP/ DC fingerboard and bellyboard with tubular capacity of 4”–14”

Pipe transfer system consisting of NOV raised catwalk to transfer tubulars to the well centre and mousehole

Smart zone management system

4. Introduction3. Contents 6. Strategy 12. Dimensions 16. Equipment 22. Rig drawings8. Rig capabilities 10. Experience

Page 18: MaerskHighlander...the rig was 889 days LTI free and 9-10 months ahead of the planned schedule. 10 Maersk Highlander UK Maersk Highlander 11 Built in: 2016 Countries operated in: UK

Maersk Highlander18

4. Introduction3. Contents 6. Strategy 12. Dimensions 16. Equipment 22. Rig drawings8. Rig capabilities 10. Experience

Fluids system

Three high-efficiency gear-driven mud pumps, fitted with p-quip type fastening, provide a high-quality working environment.

The pumps are NOV 14-P-220, 2,200HP triplex pumps rated for 7,500psi with anti-sync mode, which obtains better signals from downhole tools back to surface.

The mud mixing system consists of:

Mud system partially auto/remote operated

Dust collector/recirculation system for bulk system

Cell feeders and controls for automatic dosing from surge tanks

Sack cutting machine with dust extraction

Mud mixing hopper with manual sack table and venturi mixer

Big bag station with dust extraction and metering screw for automatic dosing

Liquid skid for automatic dosing of liquid additives to mixing system

Roller table for internal handling of sacks to manual sack table

6 x NOV VSM 300 high-performance shale shakers located in the cantilever deck to minimise the flow distance from the well centre, with up to 1,800gpm capacity and two vertical degassers

Accommodation

Accommodation is wrapped around the bow leg with office space overlooking the main, cantilever decks and drill floor.

Port block is a quiet area with cabins, while starboard block holds all offices, recreation rooms and service facilities. Maximum POB is 137 persons. The layout allows separation between offices and accommodation, leading to a better working and sleeping environment for the rig crew.

Page 19: MaerskHighlander...the rig was 889 days LTI free and 9-10 months ahead of the planned schedule. 10 Maersk Highlander UK Maersk Highlander 11 Built in: 2016 Countries operated in: UK

Maersk Highlander 19

Material handling

Highlander has two distinct handling zones; the cantilever and the main deck. The cantilever, equipped with a pipe deck pipe handler (KBC), allows drilling equipment to be handled by the drill crew while the rig cranes accommodate the rest of the equipment.

Cranes:

NOV PC1891 KCE knuckle boom crane with a lifting capacity of 12MT to transport tubulars from pipe deck to the tubular feeding machine. The KBC can supply the drill floor during heavy weather, as most equipment is stored in the cantilever, reducing dependence on deck cranes. It also has a greater operability criterion than a lattice boom crane (up to 70 knots)

3 x Seatrac deck cranes with 131MT boom, 75MT maximum hoist capacity and 13MT whip line capacities

Hamco support deck Hinged and fixed in one position Load capacity of 0.9T/m2 Footprint 45 m2 Starboard aft. side of the rig

The conductor tensioning unit, which consists of splittable tension support ring and lateral support device (currently not in use, removed due to over platform operations)

Power supply

6 x Caterpillar Model C175-16 diesel engines and AVK 3508B generators, each producing 2,340kW

Power management system has prioritisation and increased black-out prevention built into it

Having six large, powerful engines provides flexibility and redundancy

4. Introduction3. Contents 6. Strategy 12. Dimensions 16. Equipment 22. Rig drawings8. Rig capabilities 10. Experience

Page 20: MaerskHighlander...the rig was 889 days LTI free and 9-10 months ahead of the planned schedule. 10 Maersk Highlander UK Maersk Highlander 11 Built in: 2016 Countries operated in: UK

Maersk Highlander20

4. Introduction3. Contents 6. Strategy 12. Dimensions 16. Equipment 22. Rig drawings8. Rig capabilities 10. Experience

Third-party service stations

Super combo room located in the cantilever

Wire line well logging unit and tool house

MPD setup and equipment

MWD directional services

Mud logging unit and tool house

Other third-party services

ROV unit and tool house

Main deck slops treatment

Well test area

Each service station is arranged as follows:

Power (440VAC) main and emergency supply as necessary

F&G connection

PA/GA system connection

Telephone connection

PC connection for connection to the CN network

ESD connections as appropriate

Page 21: MaerskHighlander...the rig was 889 days LTI free and 9-10 months ahead of the planned schedule. 10 Maersk Highlander UK Maersk Highlander 11 Built in: 2016 Countries operated in: UK

Maersk Highlander 21

4. Introduction3. Contents 6. Strategy 12. Dimensions 16. Equipment 22. Rig drawings8. Rig capabilities 10. Experience

Page 22: MaerskHighlander...the rig was 889 days LTI free and 9-10 months ahead of the planned schedule. 10 Maersk Highlander UK Maersk Highlander 11 Built in: 2016 Countries operated in: UK

22 Maersk Highlander

Rig drawings

4. Introduction3. Contents 6. Strategy 12. Dimensions 16. Equipment 22. Rig drawings8. Rig capabilities 10. Experience

Top view

Page 23: MaerskHighlander...the rig was 889 days LTI free and 9-10 months ahead of the planned schedule. 10 Maersk Highlander UK Maersk Highlander 11 Built in: 2016 Countries operated in: UK

23Maersk Highlander

Side view

4. Introduction3. Contents 6. Strategy 12. Dimensions 16. Equipment 22. Rig drawings8. Rig capabilities 10. Experience

Page 24: MaerskHighlander...the rig was 889 days LTI free and 9-10 months ahead of the planned schedule. 10 Maersk Highlander UK Maersk Highlander 11 Built in: 2016 Countries operated in: UK

DISCLAIMER: The content of this brochure is indicative only and does not constitute a legal specification of any kind.

Head office:Maersk DrillingLyngby Hovedgade 852800 Kgs. LyngbyDenmarkTelephone: +45 63 36 00 00www.maerskdrilling.com

Visiting offices:

DenmarkLyngby Hovedgade 852800 Kgs. LyngbyDenmark

NorwayMoseidveien 19P.O. Box 134 Forus4065 StavangerNorway

AberdeenCity WharfShiprowAberdeen AB11 5BY United Kingdom

Ghana2nd Floor, One Airport SquarePlot 21Airport CityAccraGhana

Singapore200 Cantonment Road#06-02 SouthpointSingapore 089763

USA2500 City West BoulevardSuite 1850HoustonTexas 77042USA

Follow us to learn more

www.linkedin.com/company/maerskdrilling

www.facebook.com/maerskdrilling

www.twitter.com/maerskdrilling

www.instagram.com/maerskdrilling