Page 1: Madison Elementary School District #38 Construction update Bond & Capital 6/5/12

Madison Elementary Madison Elementary School District #38School District #38

Construction updateConstruction update

Bond & CapitalBond & Capital

6/5/126/5/12

Page 2: Madison Elementary School District #38 Construction update Bond & Capital 6/5/12

Meadows exterior painting

Page 3: Madison Elementary School District #38 Construction update Bond & Capital 6/5/12

Rose Lane Administration

Demolition

Page 4: Madison Elementary School District #38 Construction update Bond & Capital 6/5/12

Rose Lane Administration

New Office layout

Page 5: Madison Elementary School District #38 Construction update Bond & Capital 6/5/12

Meadows windows replacement

Page 6: Madison Elementary School District #38 Construction update Bond & Capital 6/5/12

Park cooling tower

Page 7: Madison Elementary School District #38 Construction update Bond & Capital 6/5/12

Meadows stair replacement (capital)

Page 8: Madison Elementary School District #38 Construction update Bond & Capital 6/5/12

District Office Partition replacement (capital) and Roof replacement (bond)

Page 9: Madison Elementary School District #38 Construction update Bond & Capital 6/5/12

More summer projects• Meadows- Kitchen/Cafe remodel• Heights- Lighting replacement• Park- Lighting replacement• Rose Lane- Lighting replacement• Camelview- Field work• Heights- Field work• Rose Lane- Exterior paint• Meadows- Exterior paint• District Office- Interior paint

Page 10: Madison Elementary School District #38 Construction update Bond & Capital 6/5/12

More summer projects• Heights- Roof replacement• District Office- Roof replacement• Park- HVAC replacement• Heights- Carpet replacement• Heights- Rubberized play surface• District Office- Restroom remodel• MTA- Installation of marquee• Meadows- Paint interior of gymnasium• Rose Lane – Fire lane repair (adjacent ways)• Madison #1 – Fire lane paving (adjacent ways)

Page 11: Madison Elementary School District #38 Construction update Bond & Capital 6/5/12

Warranty repair order #22Campus: Madison Traditional Academy Warranty Request Number: __22 Warranty Requested By: TBD Date Requested: _5-6-12_______________________________ Campus Contact Name: __TBD Campus Contact Number: _602-663-3871- Description of Service Item: (Please provide as much information as possible in order to expedite service. Including

but not limited to precise location, problem description, and model/serial # for any HVAC unit issues.) I have 3 corridor dome lights out, (#1) west of room 143, (#2) east of room 137, (#3) in front of room 130, also 1 plastic dome cover came off in front of room 137, and another is coming off west of room 130. Verified, Please send out electrical contractor Patrick Calvin Cassification: ___ Emergency ___ Urgent (24Hrs) __X__ Normal (1wk)

Contractor Use:

Sub Responsible: McCarthy Contact: Jason T Grant

Sub Contact Name: Mobile Phone: 602-751-4306

Sub Phone #: email: [email protected]

Warranty issue history:

_______________________________________________________________________

_______________________________________________________________________

____________________________________________________________________

Description of Work Complete: (Include what happened and how it was fixed)

Page 12: Madison Elementary School District #38 Construction update Bond & Capital 6/5/12

Warranty repair schedule