m6 motorway ppp project, hungary: a case study david asteraki, ing bank nv
DESCRIPTION
M6 Motorway PPP Project, Hungary: A Case Study David Asteraki, ING Bank NV IFSL PPP Seminar, Athens 26 th May 2005. PPP Road Projects A great international success. Widely used across Europe, North America, Asia, Australia, South Africa, etc. - PowerPoint PPT PresentationTRANSCRIPT
1 M6 Motorway PPP Project, Hungary: A Case StudyIFSL PPP Seminar, Athens, 26th May 2005
M6 Motorway PPP Project, Hungary: A Case Study
David Asteraki, ING Bank NV
IFSL PPP Seminar, Athens26th May 2005
2 M6 Motorway PPP Project, Hungary: A Case StudyIFSL PPP Seminar, Athens, 26th May 2005
PPP Road ProjectsA great international success
Widely used across Europe, North America, Asia, Australia, South Africa, etc.
Numerous studies have demonstrated value for money
There is keen interest from: Construction contractors
Operators
Financial investors
Debt financiers (banks, bond investors, bond insurers)
Procurement can be quick and efficient
3 M6 Motorway PPP Project, Hungary: A Case StudyIFSL PPP Seminar, Athens, 26th May 2005
M6 Motorway Procurement TimetableAn international record
M6 Motorway, Hungary
Based on availability payments
1st stage tender (pre-qualification) launched 31 January 2004
2nd stage tenders (3) submitted19 July 2004
Project Contract signed 2 October 2004
Financial Close 15 December 2004
10½ months in total
ING advised Hungarian Government
M8 Fermoy Bypass, Ireland
Based on mix of real tolls and construction & operating grants
Pre-qualification launched June 2002
Initial tenders (4) submitted November 2002
BaFOs (2) submitted December 2003
Project Contract signed and Financial Close June 2004
2 years in total
ING arranged and provided debt finance
4 M6 Motorway PPP Project, Hungary: A Case StudyIFSL PPP Seminar, Athens, 26th May 2005
M6 Motorway Project, Hungary
Awarded by National Motorway Company on behalf of Ministry of Economy and Transport
Awarded to consortium of Bilfinger Berger, Porr & Swietelsky
Final design, construction, financing, operation and maintenance of motorway over 22 years
58 km of dual two-lane motorway, 10 junctions, 54 bridges between Érdi tető (SW of Budapest) and M8 at Dunaújváros
Includes some works to local roads
Total Project value approximately €480 million
€411 million of debt finance with tenor of 20.5 years
5 M6 Motorway PPP Project, Hungary: A Case StudyIFSL PPP Seminar, Athens, 26th May 2005
Hungary: Planned Motorway Network to 2015M6 forms key part
6 M6 Motorway PPP Project, Hungary: A Case StudyIFSL PPP Seminar, Athens, 26th May 2005
M6 Motorway Project: A Great Success
Procured in record time
Construction timetable meets Government objectives
Good risk transfer to private sector
4 strong international consortia submitted 1st stage bids
3 strong 2nd stage bids received
Government’s risk allocation broadly maintained
Good Value for Money Construction, O&M and finance costs all competitive
7 M6 Motorway PPP Project, Hungary: A Case StudyIFSL PPP Seminar, Athens, 26th May 2005
Why was the M6 Project such a success?
Strong political support and commitment
Supportive public sector decision making process
Sensible approach to market
Standard risk allocation
Standard Project Contract and Financiers’ Direct Agreement
Availability-based payment mechanism No net traffic risk
High quality public sector advisors
8 M6 Motorway PPP Project, Hungary: A Case StudyIFSL PPP Seminar, Athens, 26th May 2005
Strong Political Support and Commitment
Government as a whole committed to PPP projects
Strong personal support from Minister of Economy and Transport Istvan Csillag and his deputy Imre Rethy
Absence of real tolls paid by motorists reduced political risk
Renegotiation of M5 Motorway Project gave good precedent Political imperative to remove real tolls required PPP structure
Initial support and commitment made decision making and approval much easier
9 M6 Motorway PPP Project, Hungary: A Case StudyIFSL PPP Seminar, Athens, 26th May 2005
Effective public sector decision making process
Negotiating team had: Clear, realistic mandate with delegated decision authority
Ready access to ultimate decision makers (Ministers Csillag & Rethy)
Strong leader (Fruzsina Biro) with commercial experience
Commitment and willingness to work hard!
There were no rival decision makers All parties bought into negotiating team’s mandate
10 M6 Motorway PPP Project, Hungary: A Case StudyIFSL PPP Seminar, Athens, 26th May 2005
Sensible approach to market
Announcement in international press
Well developed initial information package Project description
Initial design
Indicative risk matrix
Payment mechanism
Transparent criteria for selecting tenderers
Well developed Invitation to Tender/Negotiate Full draft Project Contract including schedules
Transparent criteria for selecting winning tender
11 M6 Motorway PPP Project, Hungary: A Case StudyIFSL PPP Seminar, Athens, 26th May 2005
Standard risk allocationBased on market standards that have built up over time
No significant deviations that favoured the public sector: Minimised delays and legal costs during negotiations
Maximised value for money due to familiarity with risk
No unmanageable risks Public sector bears risk of approvals, land acquisition, etc.
Eurostat rules now favourable to standard PPP projects: Private sector need bear only minimum of construction risk and either
demand risk or availability risk for Project to be off balance sheet
Key issue is compensation on termination for default Compensation 65% of value of Project to the Government
No automatic full repayment of debt
12 M6 Motorway PPP Project, Hungary: A Case StudyIFSL PPP Seminar, Athens, 26th May 2005
Project Contract and Financiers’ Direct Agreement
Based on existing precedents (UK OGC Guidance) Familiarity among tenderers and advisors shortened negotiations
Risk allocation is more obvious
Limited need for new drafting, minimising legal costs
UK OGC Guidance is widely accepted
English language used, even though under Hungarian law Made project more attractive to international tenderers
Eliminated translation costs and time
13 M6 Motorway PPP Project, Hungary: A Case StudyIFSL PPP Seminar, Athens, 26th May 2005
Availability-based payment mechanismPrivate sector bearing traffic risk reduces value for money
Private sector has very limited ability to manage or mitigate However, investors and financiers have been willing to bear it
Private sector bearing ANY net traffic risk lengthens procurement period and adds to tender costs Tenderers and their financiers both require detailed analysis
Financiers particularly are conservative and require higher margins and cover ratios
“Green field” project reduce predictability of traffic volumes
Overall, likely to lead to more expensive project
14 M6 Motorway PPP Project, Hungary: A Case StudyIFSL PPP Seminar, Athens, 26th May 2005
How do availability payments work?
Predefined level of gross payments (focus of tender) Payment deductions for unavailability depending on:
Length of road affected
Number of lanes affected
The use of contraflow (on grounds of reduced safety)
Duration of unavailability
Time of day (higher in peak hours), day of week, season
Lanes “unavailable” if not usable or unsafe Periods of maintenance included, to incentivise minimum disruption
Exclusions for external events (snow, accidents)
Additional deductions for poor performance of services
15 M6 Motorway PPP Project, Hungary: A Case StudyIFSL PPP Seminar, Athens, 26th May 2005
Strengths and weaknesses of availability payments
No politically difficult real tolls
No private sector traffic risk premium Minimises Project cost
Procurement period minimised No need to undertake traffic studies
BUT
Not favoured by EU (prefer “user pays”)
High impact on public sector budget
16 M6 Motorway PPP Project, Hungary: A Case StudyIFSL PPP Seminar, Athens, 26th May 2005
Public sector advisorsFinancial, legal, technical
Extensive international experience True for team members as well as company
Depth of resources
Fee rates may be high for quality advisors, BUT their experience leads to: More efficient procurement with likely lower overall cost
Better value for money project
Using cheap but inexperienced advisors is false economy