Recent Technological up-gradations at
LPG Plant
Horton Sphere
Mounded Bullet Pump House area
Mounded Bullet Area
Water Reservoir
Office area
LPG Recovery Plant
Cooling Towers
24-02-2012 2
Background
24-02-2012 3
LPG plant was commissioned way back in 1982; ageing plant Outdated technology- unavailability of spares Unix based Control system; MIS reporting was
not user friendly High maintenance cost; Plant availability was less due to high
downtime Complex operating conditions
Aim
Approach
To provide ease of operation through higher accuracy with precision, more flexibility and superior reliability for smoother operation with cutting edge technology
Existing set up was re-evaluated for parameters like safety, productivity, quality, cost effectiveness etc. Compliance with highest industry standards that are prevailing in contemporary industries was considered as bench mark.
Recent Major Technology Up-gradation at LPG Plant
Commissioning Status
3. 18/05/2010
Project Details
Up-gradation of old cylinder filling system with PLC based electronic cylinder filling system along with upstream & downstream ancillaries; aprox Rs 2.8 crores
Mounded Bullet Project; Rs. 35 crores
7. Expected Commissioning - July 2011
6. 04/02/2011
Front-end up-gradation of DCS system with state-of-the-art 800Xa system of M/s ABB, replacing the old UNIX based system; Rs 1.2 crores
5. 31/01/2011 Replacement of old 3nos. Of transformers with new ones; Rs. 1.2 crores
Terminal automation system in LPG FP 8. Ongoing
24-02-2012 4
1. 28/02/2010 C&I system up gradation for heater system with BMS; approx Rs. 2.0 crores
2. 23/02/2010
Up-gradation of PLC system of LPG recovery plant with latest Ethernet based processor system and SOFT SCREEN PROGRAMMABLE PANELVIEW HMI was commissioned for replacing the old relay based ESD panel and alarm annunciator in control room; Rs. 50 lakhs
4. 10/06/2010
Expander-Compressor C&I up-gradation Rs. 3.2 crores
24-02-2012 5
Key Steps/ Initiative 1. Initiatives taken for various technological advancement 2. Focus on Safety, Productivity, Quality, Cost effectiveness etc
Input Periodical Reviews Plant visits Pit Level meetings Tool Box meetings
Output Achievement of quantum improvement in the performance of plant
Performance measure
Improvement in Productivity
Reduction in no of breakdowns
Enhanced safe working environment
Ensure safe working condition System compliance evaluation during Friday weekly meeting ISO recommendations Internal/ Technical audit recommendations Compliance to quality standards IS-4576
Operational Fundamentals
Description of Project execution thro’ Turtle Diagram
24-02-2012 6
Before
After
24-02-2012 7
Before
After
24-02-2012 8
Before
After
24-02-2012 9
Before
After
Benefits- both tangible & intangible
S- Enhanced Safety Q- Improved Quality P- Increased Productivity C- Cost reduction D- Delivery of targets M- High Employee Moral
24-02-2012 10
₪ Increased production volume ₪ Reduction in no of breakdowns ₪ Ease of operation ₪ Windows based DCS system for easy MIS reporting and trend monitoring ₪ Improved spare management ₪ At par with best contemporary industry standards ₪ Mass flow meter based LPG metering system introduced for better precision and mass balancing ₪ System compliance as well as adherence to ISO/ audit recommendations ₪ Reliable safety system in place
24-02-2012 11
Some of the minor but significant up-gradations
₪ Flare metering system – First of its kind in “OIL” ₪ Digital weigh bridge with IMS facility ₪Telescopic Conveyor System ₪Auto evacuation system & other filling accessories ₪Online GC with APC ₪Electronic versa valves for SDV control
Initiatives/ activities on the move
₪ Up-gradation of old field instruments with SMART digital instruments. ₪ Commissioning of Digital level transmitters in place of the old pneumatic transmitters for accurate level control ₪Digital control valves are introduced for replacing the old control valves ₪ Replaced the old relay logic based control system which was working in series with the PLC control system in LPG recovery plant entirely with in-house expertise
24-02-2012 12
24-02-2012 13
24-02-2012 14
Empty Cylinder Shed
Filled Cylinder Shed
Condensate Filling Point
LPG Tanker Filling point
Tanker Evacuation Point