lowes creek maryland precinct traffic, transport and
TRANSCRIPT
Lowes Creek Maryland Precinct
Traffic, Transport and Access Assessment
September 2018
GHD | Lowes Creek Maryland Part Precinct Rezoning Proposal| i
Executive summary
GHD has been commissioned to undertake a Traffic Assessment for the Lowes Creek Maryland
(LCM) Precinct and wider Context Plan area.
The Greater Sydney Region Plan: A Metropolis of Three Cities indicates that Sydney’s
population is projected to add an additional 1.7 million people by 2036 and approximately
725,000 additional homes to accommodate the growing population. Providing this
accommodation and supporting infrastructure is a key challenge Sydney will face over the next
20 years and beyond.
The LCM Precinct is located in the South West Growth Area (SWGA) consisting of 10,188
hectares of semi-rural land in the Liverpool, Camden and Campbelltown Local Government
Areas.
For planning purposes, the SWGA has been separated into 14 precincts, half of which have
been rezoned or partly rezoned. It is anticipated that upon full development, the SWGA will
provide approximately 80,000 homes for 256,000 residents.
Preliminary estimates (provided by the DPE) indicate that the:
LCM Precinct could accommodate approximately 6,983 dwellings
The other Context Plan areas could accommodate 9,950 dwellings.
Additionally, a series of retail, commercial, recreational and educational land uses are also
proposed to cater to LCM Precinct’s future residents.
Roads and Maritime Services (RMS) is upgrading The Northern Road and Bringelly Road as
part of the Australian and NSW Governments’ Western Sydney Infrastructure Plan (WSIP). The
WSIP will deliver $3.6 billion in road infrastructure improvements over the next 10 years, which
includes $1.6 billion allocated to The Northern Road and $509 million for Bringelly Road.
The Northern Road upgrade consists of conversion from a two lanes to a four lane divided road,
with the provision of a median allowing for 6 lanes to be provided in the future. The upgrade
includes the provision of 4 metre shoulders, which can be converted into bus lanes.
In accordance with instructions from RMS (see Appendix A) a three-tiered modelling process
has been adopted for the LCM Precinct Traffic and Transport Study, as follows:
Tier 1 – Strategic modelling using the EMME model provided by RMS.
Tier 2 – Mesoscopic modelling using AIMSUN to take into account the consideration of
time dynamics of the traffic demand.
Tier 3 – SIDRA intersection modelling using the traffic volumes identified in the previous
modelling processes, accounting for the existing/proposed infrastructure on the adjoining
road network.
The horizon years included in each of the modelling tiers is displayed in the table below.
Scenario 2015 2021 2026 2031 2036 2041
Tier 1: Strategic Modelling (Emme)
Tier 2: Mesoscopic Modelling (Aimsun)
Tier 3: Intersection modelling (SIDRA)
The key conclusions and recommendations drawn from each modelling tier is as follows:
Strategic modelling:
GHD | Lowes Creek Maryland Rezoning 2125621 |
GHD | Lowes Creek Maryland Rezoning 2125621 | ii
– By 2036 volume to capacity ratios of greater than 100 percent are shown over multiple
sections along The Northern Road particularly in proximity to Bringelly Road
intersection during both the AM and PM peak periods.
– The Northern Road should be widened to three lanes in either direction between 2031
and 2036, to facilitate capacity that can accommodate the expected travel demand.
Mesoscopic modelling:
– Volume to capacity ratios exceed 75 percent in the northbound direction along nearly
all sections of The Northern Road during the AM peak hour. This result indicates that
the two lanes per direction along The Northern Road should be widened to three lanes
in each direction after 2031.
SIDRA modelling:
– The signalised intersections of interest (internal and external) are expected to
predominantly operate with a good Level of Service (LOS) in the 2021 and 2026
horizon years.
– All the internal signalised intersection are expected to operate with a good LOS up to
and including the 2031 horizon year.
– The delays at intersections on The Northern Road with poor LOS (in Scenario A) are
predominantly associated with vehicles on the east and west approaches, as priority is
allocated to north and south through movements.
– Accordingly, left turn continuous lanes from the approaches onto The Northern Road
(Scenario B) improve overall intersection performance considerably and may delay the
requirement to upgrade The Northern Road to three lanes in either direction.
– All the internal roundabouts are expected to operate with a good LOS up to 2031.
Key features of the proposed road hierarchy are as follows:
Four-lane sub-arterial roads (60 km/h) bounding the northern, southern and western
perimeter of the precinct area that connects directly to The Northern Road and the
adjacent precincts.
Two-lane collector roads (50 km) that provide access to the interior of the precinct and
key land uses (such as the school and town centre) and connect to the sub-arterial roads
and local roads (in accordance with the proposed road hierarchy).
Both the sub-arterial and collector road networks will be designed to accommodate bus
routes (3.5 m travel lanes required).
Key intersections along the collector and sub-arterial road networks are signalised with
roundabouts to provide additional access and U-turn opportunities.
Additional access along sub-arterial roads and collector roads should only be provided
through left in / left out priority controlled intersections.
Local streets (50 km/h) that provide access to individual properties.
The recommended road and intersection types within the LCM Precinct are displayed in the
figure below.
GHD | Lowes Creek Maryland Part Precinct Rezoning Proposal| i
Table of contents
1. Introduction..................................................................................................................................... 1
1.1 Introduction .......................................................................................................................... 1
1.2 Purpose of this report........................................................................................................... 1
1.3 Key Challenges .................................................................................................................... 2
1.4 Scope and limitations ........................................................................................................... 2
1.5 Report Structure ................................................................................................................... 2
2. Existing and Proposed Infrastructure ............................................................................................. 3
2.1 Regional Context ................................................................................................................. 3
2.2 Site Context ......................................................................................................................... 6
2.3 Planning and Land Use Context .......................................................................................... 6
2.4 Current Transport Context ................................................................................................. 10
2.5 Future Road Network ......................................................................................................... 12
2.6 Future Public Transport ..................................................................................................... 13
2.7 Future Active Transport ..................................................................................................... 14
2.8 Surveys .............................................................................................................................. 14
2.9 Existing Operational Performance Analysis ...................................................................... 18
3. Proposed Development ................................................................................................................ 22
3.1 Introduction ........................................................................................................................ 22
3.2 Proposed Land Uses ......................................................................................................... 23
3.3 Trip Generation Assessment ............................................................................................. 28
3.4 Trip Distribution .................................................................................................................. 35
3.5 Proposed Context Plan Road Network and Access .......................................................... 35
4. Traffic and Transport Assessment ............................................................................................... 42
4.1 Modelling Methodology ...................................................................................................... 42
4.2 Strategic Modelling ............................................................................................................ 42
4.3 Mesoscopic Modelling........................................................................................................ 50
4.4 SIDRA Modelling ................................................................................................................ 72
4.5 Road Network Master Plan ................................................................................................ 84
4.6 Travel Demand Management ............................................................................................ 87
5. Summary and Conclusion ............................................................................................................ 88
5.1 Introduction ........................................................................................................................ 88
5.2 Future Transport ................................................................................................................ 88
5.3 Proposed Land Uses ......................................................................................................... 88
5.4 Road Network and Access ................................................................................................ 90
5.5 Modelling Methodology ...................................................................................................... 90
5.6 Road Network and Access ................................................................................................ 92
GHD | Lowes Creek Maryland Rezoning 2125621 | ii
Appendices
Appendix A – RMS Modelling Method
Appendix B – Proposed Intersection Upgrades on The Northern Road
Appendix C – Traffic Survey Outputs
Appendix D – EMME Model Outputs
Appendix E – AIMSUN Calibration and Validation Report
Appendix F – Strategic Modelling Details (EMME to AIMSUN)
Appendix G – AIMSUN Delay Calculations
Appendix H – SIDRA Network Layouts
Appendix I – SIDRA Network Outputs
Table index
Table 2-1 – Journey to Work Data ......................................................................................................... 11
Table 2-2 – Level of Service Criteria ...................................................................................................... 19
Table 2-3 – SIDRA Modelling Parameters ............................................................................................. 20
Table 2-4 - Current Intersection Performance ........................................................................................ 21
Table 3-1 – Proposed LCM Precinct Residential Yield .......................................................................... 25
Table 3-2 – Proposed LCM Retail/Commercial Land Uses ................................................................... 26
Table 3-3 – Updated LCM Retail/Commercial Land Uses ..................................................................... 27
Table 3-4 – LCM Precinct Trip Generation 2021 (Stage 1) ................................................................... 31
Table 3-5 – LCM Precinct Trip Generation 2026 (Stage 2) ................................................................... 31
Table 3-6 – LCM Precinct Trip Generation 2031 (Stage 3) ................................................................... 32
Table 3-7 – LCM Precinct Trip Generation 2036 (Stage 4) ................................................................... 32
Table 3-8 – LCM Precinct Trip Generation 2041 (Stage 5) ................................................................... 32
Table 3-9 – Other Context Plan Areas Trip Generation 2026 (Stage 2) ................................................ 32
Table 3-10 – Other Context Plan Areas Trip Generation 2031 (Stage 3) .............................................. 33
Table 3-11 - Other Context Plan Areas – 2036 (Stage 4) ...................................................................... 33
Table 3-12 - Other Context Plan Areas – 2036 (Stage 5) ...................................................................... 34
Table 3-13 - Trip Generation Summary ................................................................................................. 34
Table 4-1 – Transport Modelling: Horizon Years Included .................................................................... 42
Table 4-2 – Strategic Modelling Scenarios ............................................................................................ 43
Table 4-3 – Alignment of LCM Staging with STFM Model Years ........................................................... 43
Table 4-4 – Mesoscopic Modelled Periods ............................................................................................ 50
Table 4-5 – Mesoscopic Modelling Lane Types and Assumed Capacities ............................................ 52
GHD | Lowes Creek Maryland Part Precinct Rezoning Proposal| iii
Table 4-6 – Intersection Upgrades along The Northern Road ............................................................... 53
Table 4-7 – Summary of Mesoscopic Modelling Results ....................................................................... 63
Table 4-8 - 2021 LOS Summary ............................................................................................................ 75
Table 4-9 – 2026 LOS Summary............................................................................................................ 77
Table 4-10 - 2031 SIDRA Results Summary (two travel lanes in either direction on The
Northern Road) .................................................................................................................. 79
Table 4-11 - 2031 LOS Summary (three travel lanes in either direction on The Northern
Road) ................................................................................................................................. 81
Table 4-12 - 2031 SIDRA Roundabout Summary .................................................................................. 83
Figure index
Figure 2-1 – SWGA Location ................................................................................................................... 4
Figure 2-2 – SWGA Conext Plan ............................................................................................................. 5
Figure 2-3 – NSW Long Term Master Plan .............................................................................................. 8
Figure 2-4 - Western Sydney Road Infrastructure Upgrades ................................................................... 9
Figure 2-5 – The Northern Road (4 Lane) Cross Section (at intersections) .......................................... 12
Figure 2-6 – Proposed North South Rail Line and SWRL Extension ..................................................... 14
Figure 2-7 – Traffic Survey Locations .................................................................................................... 16
Figure 2-8 – Greendale Road Traffic Profile .......................................................................................... 17
Figure 2-9 – Bringelly Road Traffic Profile ............................................................................................. 17
Figure 2-10 – The Northern Road (north of Bringelly Road) Traffic Profile ........................................... 18
Figure 2-11 - The Northern Road (adjacent to the site) Traffic Profile ................................................... 18
Figure 2-12 – Current Signal Phasing Greendale Road, Bringelly Road and The Northern
Road................................................................................................................................... 20
Figure 3-1 – Context Plan and LCM Rezoning Area Boundaries .......................................................... 23
Figure 3-2 – LCM Precinct Indicative Layout Plan ................................................................................. 24
Figure 3-3 – LCM Preliminary Intersection Locations/Type ................................................................... 36
Figure 3-4 – LCM Indicative Road Network and Land Use Development Staging ................................ 38
Figure 3-5 – Road Reserve Requirements for Sub-Arterial Roads ........................................................ 39
Figure 3-6 – Road Reserve Requirements for Collector Roads ............................................................ 40
Figure 3-7 – Road Reserve Requirements for Local Roads .................................................................. 41
Figure 4-1 – LCM Strategic Modelling Results for 2021 – V/C Ratios ................................................... 45
Figure 4-2 – LCM Strategic Modelling Results for 2026 – V/C Ratios ................................................... 46
Figure 4-3 – LCM Strategic Modelling Results for 2031 – V/C Ratios ................................................... 47
Figure 4-4 – LCM Strategic Modelling Results for 2036– V/C Ratios .................................................... 48
Figure 4-5 – LCM Strategic Modelling Results for 2041 – V/C Ratios ................................................... 49
GHD | Lowes Creek Maryland Rezoning 2125621 | iv
Figure 4-6 – LCM Mesoscopic Modelling Study Area and Long Term Road Network .......................... 51
Figure 4-7 – Access Principle 1: Full Access across the Median ......................................................... 56
Figure 4-8 – Access Principle 2: Partial Access via Left-In/Left-Outs ................................................... 57
Figure 4-9 – Access Principle 3: Combination of Principles 1 and 2 .................................................... 57
Figure 4-10 – Mesoscopic Modelling Intersection Treatments .............................................................. 58
Figure 4-11 – Future Travel Demand within the Study Area .................................................................. 59
Figure 4-12 – Intersection Optimisation Process ................................................................................... 61
Figure 4-13 – Optimised Traffic Progression along The Northern Road ............................................... 62
Figure 4-14 – Mesoscopic Modelling Results for 2021 (Stage 1) – Traffic Volumes and V/C
Ratios ................................................................................................................................. 64
Figure 4-15 – Mesoscopic Modelling Results for 2021 (Stage 1) – Average Delay .............................. 65
Figure 4-16 – Mesoscopic Modelling Results for 2026 (Stages 2 & 3) – Traffic Volumes and
V/C Ratios .......................................................................................................................... 66
Figure 4-17 – Mesoscopic Modelling Results for 2026 (Stages 2 & 3) – Average Delay ...................... 67
Figure 4-18 – Mesoscopic Modelling Results for 2031 (Stages 3 & 4) – Traffic Volumes and
V/C Ratios .......................................................................................................................... 68
Figure 4-19 – Mesoscopic Modelling Results for 2031 (Stages 3 & 4) – Average Delay ...................... 69
Figure 4-20 – Potential Sydney Outer Orbital ........................................................................................ 71
Figure 4-21 – Indicative Road geometry on The Northern Road ........................................................... 72
Figure 4-22 – Indicative Signal Phasing ................................................................................................. 73
Figure 4-23 – LCM 2021 SIDRA Network .............................................................................................. 75
Figure 4-24 – LCM 2026 SIDRA Network .............................................................................................. 76
Figure 4-25 – LCM 2031 Road Network (two travel lanes in either direction on The Northern
Road) ................................................................................................................................. 78
Figure 4-26 – LCM 2031 Road Network (three travel lanes in either direction on The
Northern Road) .................................................................................................................. 80
Figure 4-27 – LCM 2031 internal Roundabout Locations ...................................................................... 82
Figure 4-28 – Indicative Roundabout Geometry .................................................................................... 83
Figure 4-29 – Lowes Creek Maryland Proposed Road Hierarchy ......................................................... 85
Figure 4-30 – LCM Staged Implementation of the Road Network ......................................................... 86
GHD | Lowes Creek Maryland Part Precinct Rezoning Proposal| v
List of Abbreviations
AIS Association of Independent Schools (of NSW)
DCP Development Control Plan
DoE Department of Education
DoS Degree of Saturation
DPE Department of Planning and Environment
GFA Gross Floor Area
GLFA Gross Leasable Floor Area
JTW
LCM
Journey to Work
Lowes Creek Maryland
LGA Local Government Area
LILO Left in/Left out
LOS Level of Service
RMS Roads and Maritime Services
SWGA South West Growth Area
SWRL South West Rail Link
TfNSW Transport for New South Wales
V/C Volume-over-capacity ratio
WSIP Western Sydney Infrastructure Plan
GHD | Lowes Creek Maryland Rezoning 2125621 | 1
1. Introduction
1.1 Introduction
GHD has been commissioned by Macarthur Developments Pty Ltd on behalf of the Department
of Planning and Environment (DPE) to undertake a Traffic and Transport Assessment for the
Lowes Creek Maryland (LCM) Precinct.
Macarthur Developments entered into a Voluntary Planning Agreement (VPA – 1) with the
Minister for Planning and Environment on 25 September 2015. The VPA requires planning to be
undertaken for two areas:
1. Preparation of a Context Plan for the broader LCM and South Creek West land release
area.
2. Preparation of an Indicative Layout Plan (ILP) for Lowes Creek Precinct to deliver
housing and services infrastructure necessary to accelerate the Precinct.
Preliminary estimates (provided by the DPE) indicate that the:
LCM Precinct could accommodate approximately 6,983 dwellings.
The other Context Plan areas could accommodate approximately 9,950 dwellings.
Effective transport planning and management will be required within the Context Plan area to
ensure the provision of an extensive network of traffic and transport facilities that will provide
multi-modal travel options for future residents and visitors.
It is necessary to identify strategic traffic and transport improvements, with an aim to ensure the
transportation needs of the rezoned areas are managed in a sustainable and integrated way, as
the SWGA is developed.
1.2 Purpose of this report
This Traffic and Transport Assessment has been undertaken with the following key objectives to
support the proposed rezoning of the LCM Precinct and the overall Context Plan area:
To inform future planning controls to ensure a coordinated and efficient approach to land
use planning and transport infrastructure.
To provide an integrated approach to determining the optimal mix of land uses and
density concentrations as a means of minimising (where possible) trip generation and
transport-related demand.
To ascertain the cumulative and regional traffic and transport impacts associated with the
rezoning and general growth in the SWGA.
To maximise efficiency and safety of the existing and proposed transport systems in
proximity to the subject site.
Develop a preferred road and transport network to serve LCM Precinct that supports the
provision of a public transport network and is sensitive to the future needs of the
surrounding community.
GHD | Lowes Creek Maryland Rezoning 2125621 | 2
1.3 Key Challenges
Some of the key challenges associated with the development of the lands subject to the
rezoning application are as follows:
Locate key access points to the rezoning land and minimise its impacts on the
surrounding higher order roads, particularly The Northern Road.
Ensure the safety and functionality of key access points to the Context Plan area.
Evaluate the traffic impacts of the LCM Precinct and overall Context Plan area in the
context of the proposed road/intersection upgrades on The Northern Road.
Evaluate the effects of the future M9 and M12 motorways that will provide access to the
employment precincts to the north of the subject site (including the Western Sydney
Airport).
1.4 Scope and limitations
The modelling methodology included in the assessment has been reviewed and approved by
Roads and Maritime Services (RMS) and includes the following steps:
Strategic modelling using the EMME model provided by RMS.
Mesoscopic modelling using AIMSUN to take into account the consideration of time
dynamics of the traffic demand.
SIDRA intersection modelling using the traffic volumes identified in the previous modelling
processes, accounting for the existing/proposed infrastructure on the adjoining road
network.
The letter detailing the modelling approach specified by RMS with respect to the Traffic and
Transport Assessment is included in Appendix A.
All source data employed in the preparation of the traffic and transport assessment has been
diligently collated and checked by GHD. However, given the level of detail of the assessment
and the reliance on assumptions, the accuracy of modelling predictions will be influenced by
unknowns or changes to what has been assumed to occur in the future.
Every effort has been made to ensure the veracity and accuracy of the analysis included in this
report.
1.5 Report Structure
This remainder of this report is structured as follows:
Section 2 (Existing and Proposed Infrastructure): presents a discussion of the land
use planning, transport planning and policy context within which the precinct planning
process was undertaken.
Section 3 (Proposed Development): outlines the scope of the development, including
the proposed access strategy, key planning considerations and the expected trip
generation characteristics.
Section 4 (Traffic and Transport Assessment): presents the results of the strategic
transport network and intersection assessment undertaken for each tier of modelling.
Additionally, it identifies the “preferred” road network hierarchy.
Section 5 (Summary and Conclusions): summarises the key findings of this study.
GHD | Lowes Creek Maryland Rezoning 2125621 | 3
2. Existing and Proposed Infrastructure
This section outlines the location of the site, its environmental context, connections to the local
transport network, other development proposals that are under consideration in the area and
the proposed upgrades to the adjoining road network.
2.1 Regional Context
The subject site is located in Western Sydney within the SWGA, which is approximately 10,188
ha in size and includes parts of Liverpool, Camden and Campbelltown Local Government Areas
(LGA).
The SWGA is divided into 14 precincts that are progressively being released for planning and
rezoned, to accommodate the ongoing population growth in Western Sydney.
The growth area is proposed to provide 80,000 homes for 256,000 residents. The projected
yields for precincts within or in proximity to the Context Plan include:
Oran Park – 7,540 dwellings, a town centre and new schools.
Pondicherry – 5,000 dwellings, one town centre and several neighbourhood centres.
South Creek West – 2,000 dwellings and several neighbourhood centres and
employment areas.
Maryland – 9,000 dwellings and several neighbourhood centres and employment areas.
The SWGA Status Map is displayed in Figure 2-1.
GHD | Lowes Creek Maryland Rezoning 2125621 | 4
Figure 2-1 – SWGA Location
Lowes Creek Marylands
GHD | Lowes Creek Maryland Rezoning 2125621 | 5
The location of the SWGA in the wider context of Western Sydney is displayed in Figure 2-2.
Figure 2-2 – SWGA Conext Plan
.
GHD | Lowes Creek Maryland Rezoning 2125621 | 6
2.2 Site Context
The Context Plan area is proposed to be developed primarily for residential land uses. It is
proposed to include a centrally located town centre with a concentration of retail and
commercial developments, lower order neighbourhood centres, schools and recreational
facilities.
The Context Plan area is approximatley 1,400 hectares and currently occupied by
predominately large landholdings.
The subject site predominantly operates as a rural farmland, but includes the following
properties:
Hi-Quality Group – A transport and waste management company, located at 761 The
Northern Road, Bringelly.
Birling Avian Laboratories – A laboratory and research centre.
Boral Bringelly Brickworks, located at Lot 2 Greendale Road, Bringelly.
Bringelly Village Shopping Centre, located at the corner of Greendale Road and The
Northern Road.
A small number of low-density residential dwellings.
The Camden Local Environmental Plan (2010) currently zones the context plan RU1 Primary
Production, RU4 Primary Production Small Lots, and B1 Neighbourhood Centre (Bringelly
Village Shopping Centre).
2.3 Planning and Land Use Context
Planning for the rezoning of the LCM Precinct is guided by a number of policy documents,
including:
The Camden Local Environmental Plan (2010).
State Environmental Planning Policy (Sydney Regional Growth Centres) 2006.
Camden Growth Centre Precincts DCP (2015).
In addition, the following documents provide the strategic context of the proposal and the
adjoining road network.
2.3.1 Greater Sydney Regional Plan - A Metropolis of Three Cities
The South West Growth Area is identified as being located within the Western Parkland City,
which is intended to grow from a population of 740,000 people in 2016 to 1.1 million by 2036.
Visions / strategies for the Western Parkland City include:
The Badgerys Creek Aerotropolis and Western Sydney Airport are economic catalysts for
the district.
A polycentric city capitalising on established centres of Liverpool, Greater Penrith and
Campbelltown – Macarthur, promoting a 30 min city.
Sustainability, liveability and placemaking are core considerations in driving productivity.
Improving transport connections across the Western Parkland City.
Prioritising public transport investments to improve north-south and east-west
connections to the metropolitan cluster.
GHD | Lowes Creek Maryland Rezoning 2125621 | 7
2.3.2 Western City District Plan (2018)
The Western City District Plan (District Plan) is a 20-year plan to manage growth in Western
Sydney. Key directions in the District Plan include:
Providing housing supply, choice and affordability, with access to jobs, services and
public transport.
Creating and renewing great places and local centres, and respecting the District’s
heritage.
Establishing the land use and transport structure to deliver a liveable, productive and
sustainable Western Parkland City.
2.3.3 Future Transport 2056
Future Transport Strategy 2056, provides a 40 year vision for customer mobility in NSW and is
intended to guide transport investments to support a modern transport network across a
“metropolis” of three cities.
The vision for Greater Sydney is one where people can access jobs and services in their
nearest metropolitan city and strategic centre within 30 minutes by public transport,
Committed initiatives (0 – 10 years) in the Western Parkland City include:
The Western Sydney Infrastructure Plan.
The Western Sydney Growth Roads Program.
Initiatives for investigation (0 – 10 years) include:
Infrastructure to support rapid bus connections between WSA-Badgerys Creek
Aerotropolis and Greater Penrith, Liverpool, Blacktown and Campbelltown-Macarthur.
Leppington to WSA-Badgerys Creek Aerotropolis rail link.
Infinitives for investigation (10 – 20 years) include:
Outer Sydney Orbital (motorway and freight rail) from Great Western Highway and
Western Line to WSA-Badgerys Creek Aerotropolis.
Western Sydney Freight Line.
2.3.4 NSW Long Term Transport Master Plan
The NSW Long Term Transport Master Plan (Transport for NSW, 2012) identifies The Northern
Road as one of the corridors that will face “increased demand” in accordance with the ongoing
development of the western suburbs of Sydney. Additionally, in Section 5.8 “Providing essential
greenfield infrastructure for growth centres”, the plan identifies the upgrade of The Northern
Road as a “medium to longer term” priority.
GHD | Lowes Creek Maryland Rezoning 2125621 | 8
Figure 2-3 – NSW Long Term Master Plan
2.3.5 South West Growth Area Context Plan
The South West Growth Area Context Plan provided a strategic framework on delivery on new
communities in the SWGA. The context plan was prepared in 2006 during the establishments of
the North West and South West Growth Areas.
The Context Plan is currently under review and will ultimately be superseded by the South West
Land Use and Infrastructure Implementation Plan (SWLUIIP).
The SWLUIIP will be a strategic document to enable coordination of infrastructure to unlock new
communities.
Western Sydney Infrastructure Plan
RMS is currently upgrading The Northern Road and Bringelly Road as part of the Australian and
NSW governments’ Western Sydney Infrastructure Plan (WSIP), which will deliver $3.6 billion in
road infrastructure improvements over the next 10 years.
As displayed below in Figure 2-4, upgrades include investment of $1.6 billion for The Northern
Road and $509 million for Bringelly Road. Current information indicates that the works
associated with the WSIP will be completed in 2019.
South West Growth Centre
Northern Road
GHD | Lowes Creek Maryland Rezoning 2125621 | 9
Figure 2-4 - Western Sydney Road Infrastructure Upgrades
2.3.6 The Northern Road Corridor Strategy
The Northern Road Corridor Strategy (RMS, 2009) sets out the need and a vision for the
upgrade of The Northern Road as a principal transport corridor for the South West Growth Area.
The Northern Road upgrade strategy is being delivered in stages and will facilitate the Long
Term Transport Master Plan and WSIP objectives to improve connectivity to and from the South
West Growth Area.
Subject Site
Northern Road
GHD | Lowes Creek Maryland Rezoning 2125621 | 10
2.4 Current Transport Context
2.4.1 Public Transport
The 856 bus route, Bringelly to Liverpool via Leppington Station and Prestons, operates on
Bringelly Road and The Northern Road north of the Context Plan area. The 856 buses run very
infrequently with 5-6 services/day/direction with the majority of activity occurring during periods
of peak road network activity.
There are no current public transport routes operating on The Northern Road in proximity to the
subject site.
Leppington Station is located approximately 7 km to the east of the subject site. Leppington
Station is located on the T2 Inner West and Leppington Line and T5 Cumberland Line, which
provide direct connectivity to a number of Sydney’s key commercial, and population centres
including Liverpool, Parramatta, Strathfield, and the Sydney CBD.
The 856 bus route provides a feeder service to Leppington Station. In addition, a large park and
ride facility is provided at the station. It is expected park and ride service may provide some
utility to the future residents of the Context Plan area.
School bus services operate in the area, serving both Bringelly Public School and Rossmore
Primary School.
2.4.2 Road Network
The location of the LCM Precinct in the context of the adjoining road network is displayed in
Figure 2-7.
A brief description of the major road network in proximity to the subject site is provided below.
The Northern Road
The Northern Road is an arterial road (which forms part of the A9 Western Sydney Bypass),
runs adjacent to the east of the subject site and is managed by RMS. The Northern Road
connects Narellan in the south-west through to the Great Western Highway.
The Northern Road was constructed as a single carriageway with a travel lane in either
direction. However, as part of the WSIP, The Northern Road is currently being upgraded by
RMS from two lanes to a four-lane divided road (and bus jump off lanes at intersections), with
the provision of a wide median allowing for 6 traffic lanes be provided in the future.
Prior to construction, in the vicinity of the subject site, The Northern Road operated with an 80
km/h speed limit. Speeds are currently reduced to account for construction activity. Upon
completion of roadworks, RMS have indicated it will operate with an 80 km/h speed limit.
Bringelly Road
Bringelly Road is an arterial road which is managed by RMS and connects The Northern Road
at Bringelly, through to Camden Valley Way at Horningsea Park.
Bringelly Road is approximately 10 km in length and is an undivided carriageway with one lane
in each direction, unsealed shoulders and a sign posted speed limit of 80 km/h. However,
residential precincts are sign posted at 60 km/h speed limit. Rossmore Public School is located
on Bringelly Road west of North Avenue. In the vicinity of the school, there is a school zone with
a posted speed limit of 40 km/h.
The Australian and NSW governments have provided $509 million to upgrade Bringelly Road
between Camden Valley Way and The Northern Road to support the development of growth
areas, employment and the proposed Western Sydney Airport at Badgerys Creek.
GHD | Lowes Creek Maryland Rezoning 2125621 | 11
This 10 km project will include the upgrade of Bringelly Road from two lanes to a six lane
divided road between the eastern side of Upper Canal Bridge and the western side of the
Eastwood Road Intersection, through the future Leppington Town Centre. The rest of Bringelly
Road will also be upgraded from two lanes to a four lane divided road with a central median.
Greendale Road
Greendale Road is a collector road under the management of Liverpool City Council, which
connects from Park Road at Wallacia, through Greendale rural area to Bringelly Road and The
Northern Road signalised intersection at Bringelly. Greendale Road is around 16 km in length
and is an undivided carriageway with one lane in each direction with unsealed shoulders.
Greendale Road typically has a sign posted speed limit of 80 km/h with residential precincts
sign posted at 60 km/h speed limit.
2.4.3 Active Transport
Concrete footpaths are located on the north side of Greendale Road in proximity to the primary
school and on the western side of The Northern Road in proximity to the school and shopping
centre. However, concrete footpaths are typically not provided on the roads in proximity to the
Context Plan area.
The Camden Council Bicycle Map (1996) identifies The Northern Road as a “regional route’
(proposed). However, given the road’s narrow shoulders and high design speeds, it has not
been suitable for inclusion as part of a bicycle network. The widening of The Northern Road (as
described in Section 2.5) provides the opportunity to develop improved active transport facilities.
Walking and cycling opportunities via dedicated infrastructure in proximity to the subject site are
currently limited.
2.4.4 Journey to Work Trips
Data has been obtained from the Bureau of Transport Statistics for the Journey to Work (JTW)
for the residence of the Camden LGA and the Transport Zones located on either side of The
Northern Road between Oran Park and Bringelly. The JTW data is provided in Table 2-1.
Table 2-1 – Journey to Work Data
Mode Zones within Context Plan Camden LGA
Vehicle driver 86% 83%
Vehicle passenger 4% 5%
Train 4% 7%
Bus - 1%
Walk only 2% 1%
Other modes 4% 3%
Total 100% 100%
The data in Table 2-1 indicates very similar patterns between the Transport Zones located in
proximity to the subject site and the Camden LGA, with the use of private vehicle being the
predominant mode of travel (88 percent to 90 percent of work trips), and relatively small portions
of people utilising active and public transport.
GHD | Lowes Creek Maryland Rezoning 2125621 | 12
2.5 Future Road Network
2.5.1 The Northern Road
The MR154 The Northern Road Upgrade between Old Northern Road and Mersey Road (SKM
2012) provides an assessment of the existing and horizon year operation of intersections along
the Old Northern Road. The scope of works included the development of a “SATURN” model for
2016 (based on the existing geometry), 2026 (4-lane configuration) and 2036 (6 lane
configuration).
The key features of The Northern Road upgrade are:
Two lanes in each direction with a four metre wide shoulder and wide central median
allowing for widening to six lanes when required in the future.
Additional short right and left turning lanes.
A grade separated interchange at Bringelly Road to the east of Bringelly Village shops
and the existing intersection with Bringelly Road/Greendale Road.
A three metre wide shared pedestrian and cyclist path on the eastern side of The
Northern Road and designated turning lanes at traffic lights.
Bicycle and pedestrian crossing provisions at traffic lights.
Bus priority lanes at traffic lights and indented bus bays.
Nine intersection upgrades with new traffic lights (seven of which are located within the
Context Plan area).
The four lane cross section (at intersections) of The Northern Road is displayed in Figure 2-5.
Figure 2-5 – The Northern Road (4 Lane) Cross Section (at intersections)
The intersection layouts presented in the detailed drawings and SKM report have helped inform
the road geometry included in the traffic modelling undertaken in this report.
Additionally RMS have prepared detailed design drawings of the proposed intersection
upgrades on The Northern Road and these are included in Appendix B.
2.5.2 Bringelly Road
The Australian and NSW Governments have provided $509 million to upgrade Bringelly Road
between Camden Valley Way and The Northern Road to support the development of growth
areas, employment and the proposed Western Sydney Airport at Badgerys Creek.
As part of the WSIP works, RMS are planning to grade-separate the interchange of The
Northern Road and Bringelly Road. The Northern Road/Bringelly Road Grade Separated
Interchange Traffic and Transport Assessment indicates that while the intersection is currently
GHD | Lowes Creek Maryland Rezoning 2125621 | 13
operating with an acceptable level of service, with no improvements, it is expected to operate
unacceptably by 2019. Additional modelling indicated that the proposed grade separated layout
would be required to facilitate an acceptable level of service.
The grade separation proposal includes the following:
Relocating the interchange approximately 300 m to the east of its current location.
Providing a new signalised junction on Bringelly Road.
Providing dual right lanes for all movements to and from The Northern Road.
RMS’s detailed design drawings display the intended layout of the proposed grade separated
interchange as indicated in Appendix B.
2.5.3 Other Roads
The Australian and NSW Government are proposing to build the M12 Motorway, which would
provide direct access to the proposed Western Sydney Airport. The proposal is for an east-west
motorway between the M7 Motorway and The Northern Road to the north of the subject site.
The M9 Motorway (Outer Sydney Orbital) is proposed to consist of an orbital road running from
the Central Coast to Illawarra via a corridor to the west of the M7 and the LCM Precinct. In 2014
the NSW Government announced provided $4.6 million for planning the M9 Motorway.
There is no available information indicating when these roads will be constructed and become
operational. The preliminary M12 and M9 are displayed in Figure 4-20.
2.6 Future Public Transport
As described previously, the proposed The Northern Road upgrade includes the provision of
bus lanes in either direction. Currently, no bus services operate on The Northern Road in
proximity to the LCM Precinct. However, as the South West Growth Area is developed,
increased population densities may encourage the introduction of new bus routes in the region.
Sydney’s Bus Future (2013) specifies that rapid service routes will be provided for western
growth areas. Accordingly, The Northern Road could potentially be included on any future rapid
bus routes.
The South West Rail Link (SWRL, which commenced operation in 2015) is a NSW Government
initiative to provide additional connectivity to facilitate the mobility of resident / visitors in the
developing suburbs of Southwest Sydney and includes an 11.4 km rail line between Glenfield
and Leppington.
In order to facilitate the possible future extension of the SWRL (as part of the North South Rail
Line), the NSW Government is protecting a public transport corridor in Western Sydney. The
extension corridor is proposed to connect Leppington Station to Bringelly and meet up with the
proposed North South Rail Line.
A number of new stations are proposed for this extension. The preliminary routes and station
locations of the North South Rail Link are displayed in Figure 2-6.
GHD | Lowes Creek Maryland Rezoning 2125621 | 14
Figure 2-6 – Proposed North South Rail Line and SWRL Extension
TfNSW sought feedback on the transport corridors, which closed on 1 June 2018. Corridor
identification is currently in the post-exhibition stage.
For the purposes of analysis and as specified by RMS, it has been assumed that North South
Rail Link in proximity to the site will not become operational in the horizon years of analysis,
undertaken in this assessment.
2.7 Future Active Transport
The Northern Road upgrade includes the:
Provision of signalised junctions with pedestrian phasing between Peter Brock Drive and
Mersey Road, including intersections adjacent to the LCM Precinct at Lowes Creek Road,
Maryland Link Road Number 2 and Maryland Link Road Number 3.
The introduction of a 3 m wide shared path along the length on The Northern Road.
The introduction of on-road bicycle paths on Maryland Link Road 3, Maryland Link Road
2, Maryland Link Road 1 and Lowes Creek Road in proximity to the subject site.
Upon completion, The Northern Road upgrades will facilitate a significantly improved active
transport environment for residents and visitors of the proposed development and its surrounds.
The LCM Precinct internal road network will be developed (in accordance with the Camden
Growth Centre Development Control Plan) to expedite the mobility of pedestrians and bicycle
riders (see Section 3.5.1).
2.8 Surveys
In order to identify the current vehicle activity in proximity to the subject site (and to calibrate the
base AIMSUN model), turning movement surveys were undertaken on Wednesday 31st August
2016 at the following intersections:
Greendale Road/Tyson Road
Subject Site
GHD | Lowes Creek Maryland Rezoning 2125621 | 15
Greendale Road/Hutchinson Road
Greendale Road/Bringelly Road/The Northern Road
The Northern Road/Loftus Road
The Northern Road/Robinson Road
The Northern Road/Belmore Road
The Northern Road/Carrington Road.
The Greendale Road/Bringelly Road/The Northern Road intersection is signalised, whilst the
other intersections are currently priority controlled.
The surveys were undertaken in 15 minute increments on a weekday between the following
times in order to identify the peak periods of road network activity:
6:00 am – 10:00 am
3:00 pm – 7:00 pm.
Analysis of the survey data indicated that the peak hours of road network activity occurred
between:
7:15 am – 8:15 am
4:30 pm – 5:30 pm.
Additionally, week-long tube counts (automatic traffic counts) were undertaken at the following
locations:
Greendale Road west of The Northern Road
The Northern Road north of Greendale Road/Bringelly Road
Bringelly Road east of The Northern Road
The Northern Road adjacent to the development subject site.
The locations of the surveys are displayed below in Figure 2-7 and the survey outputs are
included in Appendix C.
GHD | Lowes Creek Maryland Rezoning 2125621 | 16
Figure 2-7 – Traffic Survey Locations
A review of the survey data indicates that:
The traffic volumes identified on each weekday of the tube counts are consistent with
each other, with no significant variations.
The volumes identified at the intersections of interest were consistent with the average
weekday travel volumes identified in the tube counts.
The outputs of the tube counts displaying average weekday traffic volumes for Greendale Road,
Bringelly Road and The Northern Road are presented below in Figure 2-8 to Figure 2-11.
13
4
2
Intersection Traffic Count Location
Automatic Traffic Count Location
N
1 23
45
6
7
Greendale Road
Bringelly Road
The Northern Road
GHD | Lowes Creek Maryland Rezoning 2125621 | 17
Figure 2-8 – Greendale Road Traffic Profile
Figure 2-9 – Bringelly Road Traffic Profile
0
20
40
60
80
100
120
0:0
0
1:0
0
2:0
0
3:0
0
4:0
0
5:0
0
6:0
0
7:0
0
8:0
0
9:0
0
10
:00
11
:00
12
:00
13
:00
14
:00
15
:00
16
:00
17
:00
18
:00
19
:00
20
:00
21
:00
22
:00
23
:00
No.
Vehic
les
Time
Eastbound Westbound
0
50
100
150
200
250
300
350
400
450
0:0
0
1:0
0
2:0
0
3:0
0
4:0
0
5:0
0
6:0
0
7:0
0
8:0
0
9:0
0
10
:00
11
:00
12
:00
13
:00
14
:00
15
:00
16
:00
17
:00
18
:00
19
:00
20
:00
21
:00
22
:00
23
:00
No.
Vehic
les
Time
Eastbound Westbound
GHD | Lowes Creek Maryland Rezoning 2125621 | 18
Figure 2-10 – The Northern Road (north of Bringelly Road) Traffic Profile
Figure 2-11 - The Northern Road (adjacent to the site) Traffic Profile
The above figures indicate distinct morning and afternoon peaks. This is consistent with
individuals driving to work in the morning and returning to their homes in the afternoon /
evenings.
2.9 Existing Operational Performance Analysis
2.9.1 Midblock Capacity
A midblock link capacity analysis of the existing road network was undertaken using the
Austroads Guide to Traffic Management Part 3 – Traffic Studies and Analysis, Section 5.2.1 and
explanatory notes.
Volume to capacity ratio (V/C) for the peak direction traffic volumes at each of the four tube
count locations was calculated by adopting a capacity of 900 vehicles per lane per hour (based
on a single lane in either direction).
As can be seen from the above figures The Northern Road currently experiences volumes in
excess of its capacity during periods of peak road network activity.
0
200
400
600
800
1000
1200
0:0
0
1:0
0
2:0
0
3:0
0
4:0
0
5:0
0
6:0
0
7:0
0
8:0
0
9:0
0
10
:00
11
:00
12
:00
13
:00
14
:00
15
:00
16
:00
17
:00
18
:00
19
:00
20
:00
21
:00
22
:00
23
:00
No.
Vehic
les
Time
Northbound Southbound Capacity
0
200
400
600
800
1000
1200
0:0
0
1:0
0
2:0
0
3:0
0
4:0
0
5:0
0
6:0
0
7:0
0
8:0
0
9:0
0
10
:00
11
:00
12
:00
13
:00
14
:00
15
:00
16
:00
17
:00
18
:00
19
:00
20
:00
21
:00
22
:00
23
:00
No.
Vehic
les
Time
Northbound Southbound Capacity
GHD | Lowes Creek Maryland Rezoning 2125621 | 19
2.9.2 Intersection Performance.
The SIDRA 7 intersection modelling software was used to assess the proposed peak hour
operating performance of the intersections of interest. The criteria for evaluating the operational
performance of intersections is provided by the Guide to Traffic Generating Developments
(RMS, 2002) and reproduced in Table 2-2.
The criteria are based on a qualitative measure (i.e. Level of Service (LOS)), which is applied to
each band of average vehicle delay. It is noted that LOS ‘D’ is generally an acceptable
operating condition on urban roads.
Table 2-2 – Level of Service Criteria
LOS Average Delay (secs/vehicle)
Traffic Signals/Roundabouts Priority Controlled
A < 14 Good operation Good operation
B 15 to 28 Good with acceptable delays
and spare capacity
Acceptable delays and
spare capacity
C 29 to 42 Satisfactory Satisfactory, but accident
study required
D 43 to 56 Operating near capacity Near capacity and accident
study required
E 57 to 70
At capacity; at signals, incidents
will cause excessive delays
Roundabouts require other
control modes
At capacity, requires other
control mode
F > 70 Over Capacity
Unstable operation
Over Capacity
Unstable operation
Source: Guide to Traffic Generating Developments (RMS 2002)
Notes:
1. The average delay for priority-controlled intersections is selected from the movement on the approach with the highest average delay.
2. The level of service (LOS) for priority-controlled intersections is based on the highest average delay per vehicle for the most critical movement.
3. The degree of saturation (DoS) is defined as the ratio of the arrival flow (demand) to the capacity of each approach.
GHD | Lowes Creek Maryland Rezoning 2125621 | 20
The parameters utilised in the SIDRA analysis are displayed in Table 2-3.
Table 2-3 – SIDRA Modelling Parameters
Model Parameters Parameter Settings
SIDRA version 7
Site Process Network module
Pedestrian Unit Time for Volumes 60 minutes
Peak Flow Period 30 minutes
Volume (per 60 minutes) 50 pedestrians
Peak Flow Factor 95%
Traffic Volumes Unit Time for Volumes 60 minutes
Peak Flow Period 30 minutes
Volume Data Method Separate
Peak Flow Factor 95%
Phasing & Timing Signal Analysis Method Fixed-Time/Pre-timed
Yellow Time 4 seconds
Red Time 2 seconds
If signal optimisation is needed
Optimum Cycle Time
Model Settings Level of Service Method Delay (RMS NSW)
Level of Service Target LOS D
Performance Measure Degree of Saturation
Percentile Queue 95%
The phasing data for the Greendale Road, Bringelly Road and The Northern Road intersection
has been provided by RMS and is presented in Figure 2-12.
Figure 2-12 – Current Signal Phasing Greendale Road, Bringelly Road and The
Northern Road
As indicated above, right turning vehicles on The Northern Road are required to filter through
straight movements from the opposite direction.
The results of the current morning and evening performance at the intersections of interest, are
presented in Table 2-4.
Legend:
GHD | Lowes Creek Maryland Rezoning 2125621 | 21
Table 2-4 - Current Intersection Performance
Intersection Morning peak Evening peak
AVG
delay
(sec)
LOS DoS 95th %
Queue
(m)
AVG
delay
(sec)
LOS DoS 95th %
Queue
(m)
Greendale Road/Tyson
Road 0.3 A 0.06 0.1 0.5 A 0.65 0.1
Greendale
Road/Hutchinson Road 1.3 A 0.06 0.7 1.6 A 0.06 0.8
Greendale
Road/Bringelly
Road/The Northern
Road
27.6 C 0.89 371 44.8 D 1.07 387
The Northern
Road/Loftus Road 0.3 A 0.55 1.9 0.2 A 0.54 0.7
The Northern
Road/Robinson Road 0.2 A 0.56 0.2 0.4 A 0.53 1.7
The Northern
Road/Belmore Road 0.2 A 0.56 0.9 0.1 A 0.54 0.2
The Northern
Road/Carrington Road 1.2 A 0.65 2.8 1.9 A 0.53 13.5
The data in Table 2-4 indicates that the intersections of interest are currently operating with an
overall acceptable LOS.
However, with respect to the Greendale Road, Bringelly Road and The Northern Road
intersection the following is noted:
In the morning peak right turning vehicles on Bringelly Road and Greendale Road
operate with delays consistent with a LOS E and relatively long queues form on the north
leg of The Northern Road.
In the evening peak right turns from Bringelly Road operate with delays consistent with a
LOS F, right turns on The Northern Road (south) and Greendale Road operate with
delays consistent with a LOS E and relatively long queues form on the north leg of The
Northern Road.
These results indicate that the signalised intersection is approaching capacity and will require
mitigation measure in the future. This analysis is consistent with RMS proposal to grade-
separate the intersection of Greendale Road, Bringelly Road and The Northern Road.
The results in Table 2-4 are consistent with the 2015 analysis detailed in The Northern
Road/Bringelly Road Grade Separated Interchange Traffic and Transport Assessment, which
indicated that the intersection is currently operating with an average delay of 33 seconds in
morning peak periods and 41 seconds in evening peak periods.
GHD | Lowes Creek Maryland Rezoning 2125621 | 22
3. Proposed Development
3.1 Introduction
Macarthur Developments has entered into a Voluntary Planning Agreement (VPA – 1) with the
Minister for Planning and Environment to undertake the following:
1. Preparation of a context plan for the broader LCM and South Creek West land release
area.
2. Preparation of an Indicative Layout Plan for Lowes Creek Maryland Precinct to deliver
housing and service infrastructure necessary to accelerate the Precinct.
As described previously the subject site is located within the SWGA and has been identified as
an area that can accommodate significant residential growth.
The Context Plan area includes pockets of lands between the LCM Precinct and Oran Park (to
the south of the subject site) and between the LCM Precinct and Greendale Road to the north of
the subject site). These areas (which are not owned by the Macarthur Developments) may
become isolated if not accounted in terms of Context Planning. Accordingly, the analysis
undertaken in this report has accounted for the potential yields and traffic impacts associated
with these sites.
The site boundaries for the Context Plan area, is presented below in Figure 3-1.
GHD | Lowes Creek Maryland Rezoning 2125621 | 23
Figure 3-1 – Context Plan and LCM Rezoning Area Boundaries
Source: Lowes Creek Maryland Context Plan Principles
3.2 Proposed Land Uses
The land uses associated with the LCM Precinct and Context Plan areas are described in
greater detail in this section.
LCM Precinct
Northern Area
Southern Area
GHD | Lowes Creek Maryland Rezoning 2125621 | 24
The land uses and staging data described in this section have been based upon the available
information at the strategic planning stage of the precinct development. They may be subject to
minor changes at a later time as a result of site specific constraints identified in other technical
studies undertaken in subsequent planning stages for the proposed LCM Precinct.
The ILP for the LCM Precinct (issued on the 13th August 2018), is displayed in Figure 3-2.
Figure 3-2 – LCM Precinct Indicative Layout Plan
GHD | Lowes Creek Maryland Rezoning 2125621 | 25
3.2.1 Residential Land Uses
It is proposed to provide a variety of different dwelling types within the LCM Precinct, as follows:
High density residential dwelling of up to five stories (high density) with up to 60 dwellings
per hectare near mixed use and highway services.
Medium density residential dwelling with up to 35 dwellings per hectare.
Low density residential dwelling with an average density 20 dwellings per hectare.
It is proposed to construct the apartments in Stage 3 of the development (see Table 3-1 below).
The residential land use schedule for the LCM Precinct, by stage is displayed below in Table
3-1.
Table 3-1 – Proposed LCM Precinct Residential Yield
Stage Timing Low Density Medium Density
High Density Total
Stage 1 2017 to
2021 500 240 0 740
Stage 2 2022 to
2026 1,080 300 0 1380
Stage 3 2027 to
2031 1,000 340 0 1340
Stage 4 2032 to
2036 1,000 340 400 1740
Stage 5 2037 to
2041 1,000 340 520 1860
Total 4,580 1,560 920 7,0601
The information contained in Table 3-1 indicates that by 2041, 7,060 dwelling will be
constructed on the LCM Precinct subject site.
Utilising a rate of 16 dwellings per hectare (as specified by the DPE) the following yields are
expected in the other Context Plan areas:
Southern area – 4,200 dwellings
Northern area – 5,750 dwellings.
When full development is complete, the overall Context Plan area is expected to provide 17,510
dwellings.
There is currently no development program/schedule for the development of the northern and
southern areas (which are displayed in Figure 3-1) however, it is expected that the
development of the southern area will commence prior to the northern area.
For the purposes of analysis (based on discussions with DPE), it has been assumed that:
Construction of the southern area will commence in Stage 2 (from 2022).
Construction of the northern area will commence in Stage 3 (from 2027).
1 The modelling was undertaken assuming 7,060 dwellings. As a result of subsequent studies relating to drainage basons and
riparian corrdidors the net developable area of LCM Precinct is cuurently 6,983 dwellings.
GHD | Lowes Creek Maryland Rezoning 2125621 | 26
For each area, 1,250 lots will be developed in each stage of development.
It is noted that the delivery timeframe for dwellings will be dependent on development rollout,
which may differ from the timeframes detailed above. However, for the purposes of analysis,
these assumptions have been discussed and agreed with the DPE.
3.2.2 Retail and Commercial Uses
The Draft Lowes Creek Maryland Precinct Economic (Retail and Employment) Analysis 2016
provides a preliminary estimate of retail/commercial land uses that are proposed to be
developed within the Context Plan area.
A summary of the each of the retail/commercial uses for each location identified in the above
figure, is presented below in Table 3-2.
Table 3-2 – Proposed LCM Retail/Commercial Land Uses
Area
Discount
Department Store
(GFA m2)
Supermarket
(GFA m2)
Speciality
Retail
(GFA m2)
Commercial
(GFA m2)
Town Centre 7,500 8,000 9,500 5,000
Mixed Use
Precinct - - 3,000 1,000
Convenience
Centre - 2,000 1,000 1,000
Maryland South
Village - 4,000 1,500 1,000
Bringelly Village - 4,000 2,000 1,500
Total 7,500 18,000 17,000 9,500
Within the LCM Precinct, the following retail/commercial facilities are proposed:
A “local centre” with a concentration of retail and commercial facilities. The local centre is
expected to be anchored by a supermarket and include a number of speciality stores and
discount department stores. Commercial facilities, such as banks, hairdressers, etc., will
also be provided. Upon completion it is expected that the local centre will operate as a
sub-regional centre, predominantly serving the residents of the Context Plan area.
A “mixed use precinct” adjacent to the local centre - primarily expected to serve residents
of the high density developments.
A small “convenience centre” located at the north east corner of the subject site is
proposed to include a supermarket and speciality stores will operate as a “neighbourhood
centre” to service areas that do not have good access to the local centre.
Within the northern and southern areas, the following retail/commercial facilities are proposed.
The “Bringelly Village”, is proposed to be connected to the existing retail facilities
currently located at the corner of Greendale Road and The Northern Road and include a
small supermarket and speciality retail.
Maryland South Village, is proposed to be a supermarket based neighbourhood centre.
GHD | Lowes Creek Maryland Rezoning 2125621 | 27
A highway service/employment area within the LCM Precinct with left in/left out
access/egress provided from The Northern Road. This area is intended to provide local
opportunities for a range of service businesses and semi-industrial land uses such as
vehicle repair, warehousing, showrooms and big-box retail. Retail and Employment Study
indicates that the highway services/employment area will have a GFA of approximately
11,000 sqm.
Based upon information included in an Indicative Layout Plan (ILP V07) issued by the DPE in
December 2017, the size of the local centre has been reduced to 20,000 sqm and the
Convenience Centre to the Mixed Use Precinct to 2,000 sqm. The updated retail / commercial
yields are presented in Table 3-3.
Table 3-3 – Updated LCM Retail/Commercial Land Uses2
Area
Discount
Department
Store (GFA m2)
Supermarket
(GFA m2)
Speciality
Retail
(GFA m2)
Commercial
(GFA m2)
Town Centre 5,000 5,333 6,333 3,333
Mixed Use Precinct - - 1,500 500
Convenience Centre - 2,000 1,000 1,000
Maryland South
Village - 4,000 1,500 1,000
Bringelly Village - 4,000 2,000 1,500
Total 5,000 15,333 12,333 7,333
To enable residents of the Context Plan area to access the employment area without exiting the
development onto The Northern Road, it has been assumed that there will be some internal
connectivity between the Context Plan area and the bulky goods/employment area. RMS have
indicated that they will only support ingress from The Northern Road into the southern bulky
goods site, with egress provided via the internal road network.
The following has been assumed with respect to the timing of the development of the retail
facilities:
Local Centre:
– In Stage 1 (2018 to 2021), 70 percent of the supermarket and a third of the speciality
retail/commercial will be developed
– In Stage 2 (2022 to 2026), the remaining 30 percent of the supermarket, two-thirds of
the speciality retail/commercial and the discount department store will be developed.
Mixed use development will be developed in Stage 3 (2027 to 2031).
Convenience centre will be developed in Stage 4 (2032 to 2036).
Maryland South Village will be developed in Stage 3 (2027 to 2031).
Bringelly Village will be developed in Stage 4 (2032 to 2036).
Highway services/employment area 50 percent will be developed in Stage 3 (2027 to
2031) and 50 percent in Stage 4 (2032 to 2036).
2 As a result of ongoing precinct planning the expected retail and commercial comonents of the LCM Preccinct have been
subject to minor changes with the mixed use centre increased to 4,000 m2 and the highway services reduced to 9,000 m2.
GHD | Lowes Creek Maryland Rezoning 2125621 | 28
3.2.3 Recreational and Educational Uses
Recreational facilities including parks, sports ovals and playing fields will be provided to serve
the residents of the LCM Precinct. The sports/ovals and playing fields are proposed to be
concentrated to the north of the local centre, while parks will be distributed throughout the
precinct to provide convenient access for residents.
The proposed development will include the following educational facilities:
One primary school and one high school within the LCM Precinct subject site.
An additional two primary schools and one high school within the remaining Context Plan
area.
Demand for educational facilities will increase as the Context Plan area is developed as the
residential population grows. Accordingly, the following, has been assumed with respect to the
timing of the development of the educational facilities:
A primary school and high school will be constructed within the LCM Precinct in Stage 1
(2017 to 2021).
Within the southern area, a primary school will be constructed in Stage 3 (2027 to 2031)
and a high school in Stage 4 (2032 to 2036).
Within the northern area, a primary school will be constructed in Stage 3 (2027 to 2031).
Information provided by the Department of Education (DoE) indicates that for both primary and
high schools, student populations are typically in the order of 0.2 students per dwelling.
Accordingly, upon full development, the Context Plan is expected to have a population of 3,500
primary school students and 3,500 high school students.3
For the purposes of analysis, it has been assumed that these student populations will be
distributed approximately evenly between the proposed schools, therefore:
Each high school is expected to have a population of approximately 1,750 students
(based upon two high schools within the Context Plan area).
Each primary school is expected to have a population of approximately 1,170 students
(based upon three primary schools within the Context Plan area).
3.3 Trip Generation Assessment
3.3.1 Trip Generation Rates
The trip generation assessment for the Context Plan and the LCM Precinct has been
undertaken in accordance with the:
The Guide to Traffic Generating Developments Updated traffic surveys – Technical
Direction TDT2013/04a.
The RMS Guide to Traffic Generating Developments.
The ITE Trip Generation Manual (5th addition).
The Technical Note provides the following trip rates that are applicable to the proposed
development:
Low density dwellings – 0.95 trips per dwelling in AM peak periods and 0.99 trips per
dwelling in PM peak periods.
3 This was calculated on the premise that upon full development the Context Plan area will
accommodate approximately 17,000 dwelling.
GHD | Lowes Creek Maryland Rezoning 2125621 | 29
High density dwellings (as applicable to the 6 storey apartment blocks) – 0.19 trips per
dwelling in the AM peak hour and 0.15 trips per dwelling in the PM peak period.
The Guide to Traffic Generating provides the following rates for shopping centres:
Discount department stores – 51 trips per 1,000 sqm GLFA.
Supermarkets – 155 trips per 1,000 sqm GLFA.
Speciality stores – 46 trips per 1,000 sqm GLFA.
Offices – 22 trips per 1,000 sqm GLFA.
These rates are applicable to Thursday evening trade and are consistent with a “worst case”
scenario.
The trip generation characteristics of the highway service/employment area on the northern
periphery of the LCM Precinct subject site has been assessed in accordance with the trip rates
for “Business Parks”.
Business parks are identified as providing a range of developments including industrial,
manufacturing, warehousing, commercial, retail and recreational land uses, which is consistent
with the expected land uses in this area.
The trip generation rate applicable to business parks is 1.1 vehicle trips per 100 sqm GLFA.
RMS do not provide trip rates for educational facilities. Accordingly, the trip generation
characteristics of the proposed primary schools and high schools have been identified in
accordance with the rates detailed in the ITE Trip Generation Manual (5th addition), as follows:
Primary school – 0.3 trips/student in morning peak periods.
High school - 0.41 trips/student in morning peak periods and 0.08 trips/student evening
peak period.
3.3.2 Mode Split
As displayed in the JTW data (Table 2-1) public transport utilisation in the proximity to the
subject site is low (in the order of 4 percent). The introduction of a rapid bus route on The
Northern Road may facilitate an increased public transport mode share.
Accordingly, for the purposes of analysis, it is assumed that 5 percent of the peak hour trips
generated by the residential components of the proposed Context Plan will utilise public
transport.
3.3.3 Trip Generation Characteristics
Residences
For the purposes of analysis, it has been assumed that for residential land uses, trips will be 80
percent outbound and 20 percent inbound in morning peak periods and 80 percent inbound and
20 percent outbound in evening peak periods.
Retail
Retail developments (shopping centres) typically generate negligible trips during morning peak
hour periods. For the retail facilities it has been assumed that during peak evening periods of
road network activity, trips will be 50 percent inbound and 50 percent outbound. It has further
been assumed that gross leasable retail areas will be 75 percent of gross floor areas.
For mixed use developments a portion of trips are typically internal, namely trips that both begin
and end within the development. This could consist of a resident walking or driving to an onsite
retail/commercial facility. As a result, a mixed-use development that generates a given number
GHD | Lowes Creek Maryland Rezoning 2125621 | 30
of total trips creates less demand on the external road system than single-use developments
generating the same number of trips.
The proposed developments retail/commercial components are intended to operate as a sub-
regional centre and neighbourhood centres and are expected to predominantly serve residents
of the Context Plan area. They are expected to generate little (if any) external trips.
Accordingly, for the purposes of analysis, it has been assumed that all the trips they generate
will be internal to the development.
In accordance with the proximity of the retail and residential facilities and the proposed provision
of an active transport network, it has also been assumed that 10 percent of the retail trips will
utilise walking/cycling as the mode of travel.
During periods of peak road network activity, a significant portion of the trips generated by the
retail facilities will be passer-by trips (also referred to as drop-in trips). Passer-by trips/drop in
are applicable to retail developments and consist of traffic on the adjoining road network that
enters a site as an intermediate stop to another destination.
The volume of passer-by trips is typically dependent on the nature of retail facilities. Service
stations and fast food restaurants typically experience extremely high volumes of passer-by trips
(approximately 50 percent).
The Queensland Department of Main Roads Guidelines for Assessments of Road Impacts of
Development specifies the following rates for passer-by trips for “shopping centres”:
Shopping centres of less than 3,000 sqm, - 19 percent passer-by trips.
Shopping centres of 3,000 sqm – 20,000 sqm – 28 percent passer-by trips.
The retail components of the Context Plan area will typically be between 3,000 sqm – 20,000
sqm, accordingly a passer-by rate of 28 percent has been utilised in the analysis.
The highway services/employment area is proposed to be left in from Northern Road with
vehicle exiting via the internal road network.
In accordance with some of the proposed land uses such as warehousing, vehicle repair and
storage units and its location on The Northern Road, it is expected that a portion of trips it
generates will be external to the Context Plan. Further, as only northbound vehicles on The
Northern Road will have direct access to the employment area, it is expected that there will be a
reduction in passer-by trips, compared to other proposed retail facilities.
Accordingly, the following assumptions have been made with respect to the highway
services/employment area:
14 percent of trips will be passer-by trips.
Of the remaining trips, 50 percent will be internal to the Context Plan and 50 percent will
be external.
Schools
The ITE Trip Generation Manual suggests that:
Primary school trips are 60 percent inbound and 40 percent outbound in morning peak
periods.
High schools are 68 percent inbound and 32 percent outbound in morning peak periods
and 29 percent inbound and 71 percent outbound in evening peak periods.
GHD | Lowes Creek Maryland Rezoning 2125621 | 31
The schools provided within the Context Plan will predominantly serve the nearby residents.
However, it is recognised that some students will be educated at private and independent
schools in the surrounding areas,
School statistics provided by the Association of Independent Schools of NSW (AIS) indicates
that 12 percent of primary school students and 22 percent of high school students attend
independent schools. These rates have been applied to the Context Plan’s expected school
population to quantify the expected external trips
Given the expected proximity of the schools and residences within the Context Plan and the
proposed provision of active transport facilities, it is expected that a significant proportion of
students will walk to/from school.
The NSW Travelsmart Schools Program 2006 – 2007 Summary Report provides survey outputs
of modes of travel children utilise to ingress/egress five schools, the location/name of these
schools is not provided. The data indicates that on average 35 percent of students walk to
school in the morning and 43 percent walk home from school in the afternoons and these rates
have been utilised in the trip generation assessment. The Summary Report does not provide
information with respect to cycling.
3.3.4 Trip Generation
In accordance with the above specifications/assumptions, the expected trip generation
characteristics of the LCM Precinct (per stage of development) are presented below in Table
3-4 - Table 3-8.
Table 3-4 – LCM Precinct Trip Generation 2021 (Stage 1)
Land Use Morning peak Evening peak
Inbound Outbound Inbound Outbound
Dwellings 141 562 586 147
Supermarket (internal trips) - - 141 141
Specialty Retail (internal trips) - - 24 24
Commercial (internal trips) - - 6 6
Primary School (internal and external trips) 145 87 - -
High School (internal and external trips) 355 153 30 66
Total 641 802 786 383
Table 3-5 – LCM Precinct Trip Generation 2026 (Stage 2)
Land Use Morning peak Evening peak
Inbound Outbound Inbound Outbound
Dwellings 262 1,049 1,093 273
Supermarket (internal trips) - - 60 60
Specialty Retail (internal trips) - - 47 47
Commercial (internal trips) - - 12 12
GHD | Lowes Creek Maryland Rezoning 2125621 | 32
Land Use Morning peak Evening peak
Inbound Outbound Inbound Outbound
Discount Department Store - - 62 62
Total 262 1,049 1,274 455
Table 3-6 – LCM Precinct Trip Generation 2031 (Stage 3)
Land Use Morning peak Evening peak
Inbound Outbound Inbound Outbound
Dwellings 255 1,018 1,061 265
Highway Services - - 18 18
Total 255 1,018 1,079 283
Table 3-7 – LCM Precinct Trip Generation 2036 (Stage 4)
Land Use Morning peak Evening peak
Inbound Outbound Inbound Outbound
Dwellings 256 1,025 1,054 263
Supermarket (internal trips) - - 75 75
Speciality Retail (internal) - - 11 11
Commercial (internal) - - 5 5
Highway Services (internal and external trips) 18 18
Total 256 1,025 1,163 373
Table 3-8 – LCM Precinct Trip Generation 2041 (Stage 5)
Land Use Morning peak Evening peak
Inbound Outbound Inbound Outbound
Low Density Dwellings 117 469 489 122
The expected trip generation characteristics of the other Context Plan Areas (northern and
southern see Figure 3-1) per stage of development are presented in Table 3-9 to Table 3-12.
Table 3-9 – Other Context Plan Areas Trip Generation 2026 (Stage 2)
Land Use Morning peak Evening peak
Inbound Outbound Inbound Outbound
Low Density Dwellings (south) 226 903 941 235
GHD | Lowes Creek Maryland Rezoning 2125621 | 33
Table 3-10 – Other Context Plan Areas Trip Generation 2031 (Stage 3)
Land Use Morning peak Evening peak
Inbound Outbound Inbound Outbound
Southern Area
Low Density Dwellings 226 903 941 235
Supermarket (internal trips) - - 151 151
Speciality Retail (internal trips) - - 17 17
Commercial (internal trips) - - 5 5
Primary School (internal and external trips) 145 87 - -
Subtotal 371 990 1,113 408
Northern Area
Low Density Dwellings 226 903 941 235
Total 597 1,892 2,054 643
Table 3-11 - Other Context Plan Areas – 2036 (Stage 4)
Land Use Morning peak Evening peak
Inbound Outbound Inbound Outbound
Southern Area
Low Density Dwellings 226 903 941 235
Primary School (internal and external trips) 145 87 - -
High School (internal and external trips) 355 153 30 66
Subtotal 726 1,142 970 301
Northern Area
Low Density Dwellings 226 903 941 235
Supermarket (internal trips) - - 151 151
Speciality Retail (internal trips) - - 22 22
Commercial (internal trips) - - 8 8
Primary School 145 87
Subtotal 371 990 1,122 416
Total 1,097 2,132 2,092 717
GHD | Lowes Creek Maryland Rezoning 2125621 | 34
Table 3-12 - Other Context Plan Areas – 2036 (Stage 5)
Land Use Morning peak Evening peak
Inbound Outbound Inbound Outbound
Low Density Dwellings (north) 226 903 941 235
A summary of the expected trip generation characteristics of the LCM Precinct and Context Plan
areas (per stage of development), is presented in Table 3-13.
Table 3-13 - Trip Generation Summary
Land Use Morning peak Evening peak
Inbound Outbound Inbound Outbound
LCM Precinct 2021 (Stage 1) 641 802 786 383
LCM Precinct 2026 (Stage 2) 262 1,049 1,274 455
LCM Precinct 2031 (Stage 3) 255 1,018 1,079 283
LCM Precinct 2036 (Stage 4) 256 1,025 1,163 373
LCM Precinct 2041 (Stage 5) 261 1,043 1,067 267
Sub-Total 1,675 4,937 5,370 1,760
Other Areas 2026* (Stage 2) 226 903 941 235
Other Areas 2031* (Stage 3) 597 1,892 2,054 643
Other Areas 2036* (Stage 4) 1,097 2,132 2,092 717
Other Areas 2041* (Stage 5) 226 903 941 235
Sub Total 2,145 5,829 6,026 1,831
TOTAL 3,820 10,766 11,396 3,591
* Includes the northern and southern areas.
The data in Table 3-13 indicates that:
The LCM Precinct is expected to generate up to approximately 6,104 – 7,034 trips during
peak periods of road network activity.
The other Context Plan areas (see Figure 3-1) are expected to generate up to
approximately 7,974– 7,857 trips during peak periods of road network activity.
GHD | Lowes Creek Maryland Rezoning 2125621 | 35
3.4 Trip Distribution
The following assumptions were used to distribute the trips generated by the LCM Precinct and
the Context Plan areas (see Figure 3-1) :
Distribution to external zones was calculated based on the distribution of trips included in
the RMS’s Strategic Traffic Forecasting Model.
Internal trips to and from residential zones have been distributed based on the
approximate number of dwellings in each zone (gravity method).
The northern and southern areas of the Context Plan are assumed to generate internal
trips or to generate trips that are external to the Context Plan area. That is, there are no
trips between the northern area / southern area and the LCM Precinct area. This is
because each area provides a range of facilities so that trips to the other areas would not
be required.
The exception to this is the Bringelly Village Area, which is forecast to increase in size in
the future. Provision for trips between the northern area’s residential developments and
this zone has been accounted for.
3.5 Proposed Context Plan Road Network and Access
The proposed road structure / hierarchy for the Context Plan (as detailed in the Lowes Creek
Maryland Context Plan Principles), is as follows:
A north-south sub-arterial road that intersects Greendale Road to the north and Oran
Park Town Centre to the south.
Two east-west sub-arterial roads that connect the north-south sub-arterial road with The
Northern Road.
A collector road network that distributes local traffic throughout the subject site that
provides access to residential lots and directs vehicles to sub-arterial roads at key
intersections on The Northern Road.
Local roads to provide access to residential dwellings.
A shared path network to encourage active transport within the subject site and provide
connectivity to external active transport networks.
For the purpose of analysis, it has been assumed that the sub-arterial road provides two travel
lanes in either direction and the collector road / local road networks a single travel lane in either
direction.
As displayed in Figure 3-3, within the proposed development, the intersections along the sub-
arterial road are predominantly proposed to be signalised.
The intersections on the collector road network are typically proposed to be priority controlled
(at local roads) with roundabouts and traffic signals at key locations i.e. at junctions with the
sub-arterial road network and in proximity to the schools and local centre.
GHD | Lowes Creek Maryland Rezoning 2125621 | 36
Figure 3-3 – LCM Preliminary Intersection Locations/Type
The Context Plan is based on an interconnected, legible, urban-scale grid street pattern that will
provide optimal opportunities and safety for residents and visitors. The road network has been
planned and spatially integrated with the land use planning. This has facilitated a higher order
road network that is appropriate to its role (within the hierarchy) and the expected traffic
demands that will be placed upon it.
Pedestrians will be provided for on all routes with pedestrian paths provided on both sides of the
roads where active land uses are located adjacent to them. Shared pedestrian and bicycle
paths are proposed to be provided along key landform features including creeks and ridge lines
and the arterial road network.
During the next stages of the planning process, pedestrian pathways and shared
cycle/pedestrian pathways will form an essential element in the design of the proposed road
hierarchy.
GHD | Lowes Creek Maryland Rezoning 2125621 | 37
In summary, the key features of the proposed road network are:
Provide a safe and convenient transport, pedestrian and cycleway network.
A road hierarchy that is compatible with the land use and range of roles that each key
road is likely to serve. This incorporates a grid of sub-arterial and collector roads to
distribute traffic within the Context Plan area and promote access to the regional road
network.
A hierarchy of roads that allows clear and direct access to The Northern Road and the
internal sub-arterial road.
An alignment of roads and intersections that support the existing and proposed road
structure and form.
Local roads will intersect collector roads at left in/left out junctions so that motorists can
utilise nearby roundabouts to undertaken U-turn manoeuvres.
Infrastructure that supports active transport utilisation within the subject site, particularly
for short (local) trips.
RMS have provided some preliminary comments with respect to the road network/access
arrangements for the LCM Precinct subject site, as follows
The grade separation of the intersection of The Northern Road and Maryland Link Road
No.3 is not supported.
The grade separation of pedestrian via a pedestrian bridge at this location is not
supported, signalised pedestrian crossings should be provided instead.
The local centre should not be located adjacent to or be accessed from The Northern
Road.
Left in/left out movements on The Northern Road between Maryland Link Roads No. 2
and No. 3 should be restricted to a service centre and a declaration lane should be
provided
The LCM Precinct Indicative Layout Plan has been designed in accordance with these
specifications.
The indicative staging of the proposed road network is displayed in Figure 3-4.
GHD | Lowes Creek Maryland Rezoning 2125621 | 38
Figure 3-4 – LCM Indicative Road Network and Land Use Development
Staging
3.5.1 Road Reserve Requirements
The Camden Growth Centre Precincts: Development Control Plan (DCP) 2016 specifies the
road reserve requirements / layouts applicable to the LCM Precinct.
Not the only consideration, traffic volumes are an important input into the choice of road
reserve, as it frequently dictates the number of lanes and roadside services to be
accommodated, such as parking provisions and pedestrian accommodations. As a requirement,
the road network should also address local traffic management controls and intersection
treatments to regulate vehicle movements efficiently within the LCM Precinct.
GHD | Lowes Creek Maryland Rezoning 2125621 | 39
In addition to the Camden Growth Centres DCP, GHD consulted a number of planning
guidelines and studies from councils located in or around the SWGA to gain a holistic overview
of typical road reserve requirements.
DPE ongoing investigations on integrated transport and land use planning in SWGA.
Mulgoa Road / Castlereagh Road Corridor Upgrade Between Glenmore Parkway,
Glenmore Park and Andrews Road, Penrith: Preferred Option Report (April 2017).
Penrith Development Control Plan 2014 – Volume 1, Part C: City-wide Provisions.
The road reserve elements described in this section should not be interpreted to be a design in
and of themselves; rather, they consider typical elements to be accommodated when
considering an appropriate road reserve.
The final cross-section should be confirmed during detailed design and with the approval of
Camden Council. A road reserve width should be carefully chosen to adhere to both the
Council’s requirements, as well as to provide the required cross-sectional elements safely and
be adaptable to future interventions.
Based on the combined results of the traffic modelling, road network master planning best
practice and the requirements of the Camden Growth Centres DCP, the recommend road
reserves are described below.
Sub-arterial roads
Key features of the proposed LCM Precinct sub-arterial road network (as is shown in Figure
3-5) include:
A 29.1 m road reserve width (including a 4.2 m median).
No provision for on-street parking.
Shared paths (for pedestrians and bicycle riders) on both sides of the road.
Figure 3-5 – Road Reserve Requirements for Sub-Arterial Roads
It would be possible to narrow the sub-arterial road width by reducing the median (as a width of
4.2 m is not needed). However, a median of 6.8 m would allow for a centre-running dual-
direction BRT-type service or even a tram if the need arises in the future for a dedicated, high-
medium capacity public transport service.
Accordingly, it is recommend that a 32 m road reserve for all sub-arterial road within LCM
Precinct would provide for the future provision of higher order public transport services, in
accordance with the expected increases in residential densities.
GHD | Lowes Creek Maryland Rezoning 2125621 | 40
Collector roads:
The Camden City Council provides for two typical design for Collector roads, namely Type 1 –
Collector road with off-road cycle paths and Type 2 – Collector road with on-road cycle paths.
Both types provide a 20 m road reserve.
Based upon discussions with the DPE, it is propoed to provide collector roads within the LCM
precinct with 21 m road reserves (see Figure 3-6), that will be bus and heavy vehicle capable. It
will include 2.5 m shared paths to encourage active transport.
Figure 3-6 – Road Reserve Requirements for Collector Roads
Local streets:
Local streets are typically low-volume streets that connect to the higher order network (via the
collector road network) and provide access to residential properties.
Key features of the proposed LCM Precinct local street road network (as shown in Figure 3-7)
include:
A road reserve width of 16 m.
A carriageway width of 9 m.
Footpaths on either side of the road (1.2 m width).
A travel lane and a parking lane in either direction.
Cyclist are typically accommodated on the road, in non-designated infrastructure. This is
consistent with the low traffic volumes expected on the local road network.
GHD | Lowes Creek Maryland Rezoning 2125621 | 41
Figure 3-7 – Road Reserve Requirements for Local Roads
GHD | Lowes Creek Maryland Rezoning 2125621 | 42
4. Traffic and Transport Assessment
4.1 Modelling Methodology
4.1.1 Introduction
In accordance with instructions from RMS (see Appendix A) a three-tiered modelling process
has been adopted for the LCM Precinct Traffic and Transport Assessment, as follows:
Tier 1 – Strategic modelling using the EMME model
provided by RMS.
Tier 2 – Mesoscopic modelling using AIMSUN to
take into account the consideration of time dynamics
of the traffic demand.
Tier 3 – SIDRA intersection modelling using the
traffic volumes identified in the previous modelling
processes, accounting for the existing/proposed
infrastructure on the adjoining road network.
As typical for traffic modelling projects, the scope of this work entails a number of limitations, as
follows.
The road network structure within the mesoscopic model focuses on the higher order
road network only – motorways, arterials and sub-arterials.
Road network coding considers the coarse network developed within the Context Plan
area (i.e. arterial and sub-arterial roads). Further refinement of the local and collector
road network will be required as part of the precinct planning process.
Traffic analysis has been undertaken for the weekday morning and evening peak periods.
Traffic simulation has been limited to mesoscopic simulation of private vehicles only and
excludes public transport operations.
Table 4-1 summarises, the horizon years included in each tier of modelling (in accordance with
the proposed staging of development detailed in Table 3-13). The remainder of this Section
discusses the individual modelling tiers in detail.
Table 4-1 – Transport Modelling: Horizon Years Included
Scenario 2015 2021 2026 2031 2036 2041
Tier 1: Strategic Modelling (EMME)
Tier 2: Mesoscopic Modelling (AIMSUN)
Tier 3: Intersection modelling (SIDRA)
4.2 Strategic Modelling
This section provides an overview of the strategic modelling task, carried out using RMS’s
Strategic Traffic Forecasting Model (STFM), built using the EMME software platform.
The strategic traffic modelling is required to:
GHD | Lowes Creek Maryland Rezoning 2125621 | 43
Distribute the trip ends4 produced in the trip generation analysis in a realistic manner.
Assign the resulting trip matrices, combined with forecast background traffic for the years
and scenarios shown in Table 4-2.
Provide analysis of the strategic impacts of the LCM Precinct and the wider Context Plan
area rezoning.
Produce traversal demand matrices that represent the project as a subarea within the
Greater Sydney Area for all scenarios to assist in the development of the mesoscopic
modelling.
RMS’s strategic model contains the background traffic demand growth derived from Bureau of
Statistical Analytics (BSA) and therefore, is suitable for traffic assignment for the wider road
network. The strategic model includes the years starting from 2015 up to 2041 with increments
of 5 years.
The model coding updated in the strategic modelling to reflect the most up-to-date development
land use and road network assumptions for the Context Plan area, including:
Future road network in the vicinity of development.
Development traffic generation and attraction.
Table 4-2 presents all the scenarios for which the strategic modelling was undertaken.
Table 4-2 – Strategic Modelling Scenarios
Scenario 2015 2021 2026 2031 2036 2041 Notes
Base Year RMS model
Business As Usual RMS model
Lowes Creek Maryland Precinct
Lowes Creek Maryland Precinct
Wider Context Plan Area
All development (including northern and southern areas)
In accordance with the indicative development staging plan for LCM Precinct (Figure 3-4),
Table 4-3 overlays the indicative development stages with the STFM horizon year models.
Table 4-3 – Alignment of LCM Staging with STFM Model Years
Development Stage Development Timelines Included in STFM Model
Year
Stage 1 2017 to 2021 2021
Stage 2 2022 to 2026 2026
Stage 3 2027 to 2031 2031
Stage 4 2032 to 2036 2036
Stage 5 2037 to 2041 2041
Some of the key assumptions that were used for the strategic modelling tasks include the
following:
4 A ‘trip end’ is the number of trips going to or from a travel zone (the ends of the trip). This is
equivalent to the trip generation of the travel zone.
GHD | Lowes Creek Maryland Rezoning 2125621 | 44
The provision of a future train station in proximity to the subject site is excluded from the
transport modelling (in accordance with instruction from RMS).
The Bringelly Village area trip generation is assumed to be additional to the trips included
in the RMS STFM.
Figure 4-1 through Figure 4-5 present the results strategic modelling (2021 – 2041), expressed
as volume-over-capacity (V/C) ratios (accounting for the trips generated within the wider
Context Plan area) for the AM and PM peak periods.
The V/C ratios are informative, as they are indicative of road network operations and provide
high-level indications of where additional travel lanes might be required. V/C ratios greater than
80 percent are indicative of a road network approaching capacity, while V/C ratios of 100
percent (or more) are indicative of road networks experiencing traffic demand in excess of their
capacity.
In summary, the following conclusions are drawn from the strategic modelling outputs:
Prior to 2026 (see Figure 4-1), no links have a V/C ratio greater than 80 percent. In
general terms, this means congestion on the network is minimal.
In 2026 (see Figure 4-2), during both the AM and PM peaks the V/C ratio exceeds 80
percent along The Northern Road between the northernmost access road to the Lowes
Creek Precinct and Bringelly Road. A V/C ratio exceeding 100 percent is shown over a
short section along The Northern Road.
By 2031 (see Figure 4-3), additional north / south road linkages between Lowes Creek
Maryland Precinct and the adjacent context plan areas have been included. These
alleviate congestion along The Northern Road (by providing alternative routes), where the
V/C ratios are less than 100 percent even though the traffic volumes have increased. This
highlights the benefit of providing additional connectivity between the precincts in parallel
to The Northern Road.
By 2036 (see Figure 4-4), V/C ratios of greater than 100 percent are shown over multiple
sections along The Northern Road particularly in proximity to Bringelly Road during both
the AM and PM peak periods. It is noted that without the trips generated by the LCM
Precinct, sections of The Northern Road would likely continue to operate with a V/C ratio
greater than 100 percent.
In 2041 (see Figure 4-5):
– Within the LCM Precinct, all links are shown to have V/C ratios lower than 80 percent.
– Within the larger Context Plan, only one link (located in the southern area) has a V/C
ratio that exceeds 100 percent.
– Nearly the entirety of The Northern Road (northbound) has a V/C ratio that exceeds
80 percent.
– Similar to the observations for 2036, all approaches at The Northern Road at the
Bringelly Road intersection have V/C ratios that exceed 100 percent.
In summary, the outputs of the strategic modelling indicates that even without the trips
generated by the Context Plan area, The Northern Road should be widened to three lanes in
either direction between 2031 and 2036, to facilitate capacity that can accommodate the
expected travel demand.
More details of the strategic modelling outputs are included in Appendix D.
GHD | Lowes Creek Maryland Rezoning 2125621 | 45
Figure 4-1 – LCM Strategic Modelling Results for 2021 – V/C Ratios
AM Peak Period (07:00 – 09:00)
PM Peak Period (16:00 – 18:00)
GHD | Lowes Creek Maryland Rezoning 2125621 | 46
Figure 4-2 – LCM Strategic Modelling Results for 2026 – V/C Ratios
AM Peak Period (07:00 – 09:00)
PM Peak Period (16:00 – 18:00)
GHD | Lowes Creek Maryland Rezoning 2125621 | 47
Figure 4-3 – LCM Strategic Modelling Results for 2031 – V/C Ratios
AM Peak Period (07:00 – 09:00)
PM Peak Period (16:00 – 18:00)
GHD | Lowes Creek Maryland Rezoning 2125621 | 48
Figure 4-4 – LCM Strategic Modelling Results for 2036– V/C Ratios
AM Peak Period (07:00 – 09:00)
PM Peak Period (16:00 – 18:00)
GHD | Lowes Creek Maryland Rezoning 2125621 | 49
Figure 4-5 – LCM Strategic Modelling Results for 2041 – V/C Ratios
AM Peak Period (07:00 – 09:00)
PM Peak Period (16:00 – 18:00)
GHD | Lowes Creek Maryland Rezoning 2125621 | 50
4.3 Mesoscopic Modelling
Mesoscopic modelling takes account of the time dynamics of traffic. It is useful for determining
optimum vehicle routes between all origins and destinations in the network based on congestion
and travel times throughout the modelled period. Mesoscopic modelling provides a greater level
of understanding of network operations than strategic modelling can provide.
4.3.1 Base Year Traffic Modelling
GHD developed a base model using AIMSUN (version 8.1.3 R40314) for the traffic analyses
undertaken in 2016 that was based on the Context Plan. The base AIMSUN model has been
calibrated using traffic data collected during its development in 2016, as well as validated
against surveyed travel times in the same year. Appendix E contains a short report detailing
the development, calibration and validation of the Base 2016 AIMSUN model.
In summary, the Base 2016 AIMSUN was developed for the four periods displayed in Table 4-4.
Table 4-4 – Mesoscopic Modelled Periods
Modelling period Peak period Warm up period Cool down period
Weekday AM 05:15 – 09:15 1 hour 1 hour
Weekday PM 15:15 – 19:15 1 hour 1 hour
Upon commencement of the mesoscopic modelling stage, GHD confirmed with the DPE that for
the current Context Plan, the Base 2016 model was suitable for use without re-basing, re-
calibrating or re-validating it. SIDRA modelling stage (see Section 4.4).
Figure 4-6 shows the wider study area with the roads and intersections included in the
mesoscopic modelling. The intersection treatments shown, represent initials assumptions with
respect to the precinct’s functionality, the ultimate treatments are discussed in more detail in the
SIDRA modelling stage (see Section 4.4).
GHD | Lowes Creek Maryland Rezoning 2125621 | 51
Figure 4-6 – LCM Mesoscopic Modelling Study Area and Long Term Road Network
GHD | Lowes Creek Maryland Rezoning 2125621 | 52
The key assumptions that have been made with respect to the Context Plan area’s road
network (in accordance with the proposed hierarchy) are detailed in Table 4-5.
Table 4-5 – Mesoscopic Modelling Lane Types and Assumed Capacities
Road Type Speed Lanes Capacity
Arterial 80 km/h 2 or 3 per direction 1,700 veh/hr/lane
Sub-arterial 60 km/h 2 per direction 1,200 veh/hr/lane
Collector 40 km/h 1 per direction 900 veh/hr/lane
Local 37 km/h 1 per direction 600 veh/hr/lane
4.3.2 Future Year Traffic Modelling
AIMSUN models have been developed for the horizon years of 2021, 2026 and 2031. The 2036
and 2041 horizons were excluded from the mesoscopic stage due to the uncertainty of the long-
term forecasts and the coarse assumptions built into the STFM model (as discussed later in this
section). This approach was discussed and agreed with RMS and DPE.
Committed (External) Road Network upgrades
Within the project study area, both The Northern Road and Bringelly Road (east of The Northern
Road) will be upgraded prior to the commencement of operation Western Sydney Airport (which
is projected to open in 2026) and the majority of the expected population and job growth in the
South West Growth Area.
As described previously, key features of the upgraded The Northern Road are:
Two lanes in each direction with a four metre wide shoulder and wide central median
allowing for widening to six lanes when required in the future.
A grade separated interchange at Bringelly Road to the east of Bringelly Village shops
and the existing intersection with Bringelly Road/Greendale Road.
Nine intersection upgrades with new traffic lights (seven of which are located within the
Context Plan area).
Unless otherwise noted, intersection upgrades along The Northern Road generally entail the
upgrade to a four-way, signalised intersections with the following characteristics (see Figure
4-21:
Two through lanes.
Separate short left-turn lanes left, right turning lanes and departure lanes.
In accordance with the current construction activity on The Northern Road and information
provided by RMS, it has assumed that all upgrades would be operational by 2021, which aligns
with the first horizon year for analysis for the LCM Precinct.
A Roads and Maritime Services Circular (RMS 17.039 from July 2017) provides detailed layouts
at each upgraded intersection on The Northern Road. These have been used as the basis of
the geometric layout of all upgrades in horizon year AIMSUN models. Table 4-6 illustrates the
upgraded intersection layouts from the RMS Circular next to the corresponding layout coded in
the 2021 AIMSUN model. The locations of each of the intersections within the context of Lowes
Creek Maryland is displayed in Figure 4-6.
GHD | Lowes Creek Maryland Rezoning 2125621 | 53
Table 4-6 – Intersection Upgrades along The Northern Road
Upgraded Design (as of July 2017) Representation in 2021 AIMSUN model
Site 2 – Marylands Link Road 1 Intersection
Site 3 -- Marylands Link Road 2 Intersection (i.e. southern access road to Lowes Creek Maryland
Precinct)
GHD | Lowes Creek Maryland Rezoning 2125621 | 54
Upgraded Design (as of July 2017) Representation in 2021 AIMSUN model
Site 4 -- Marylands Link Road 3 Intersection (i.e. central access road to Lowes Creek Maryland
Precinct)
Site 5 – Lowes Creek Link Road Intersection (i.e. northernmost access to Lowes Creek Maryland
Precinct)
GHD | Lowes Creek Maryland Rezoning 2125621 | 55
Upgraded Design (as of July 2017) Representation in 2021 AIMSUN model
Site 6 – Belmore Road Intersection
Site 7 – The Northern Road and Bringelly Road Interchange
Prior to receiving the layouts shown in Table 4-6, GHD obtained a concept design layout of The
Northern Road’s committed design5, overlaid on an aerial photo. The design did not specifically
indicate bus lanes at the intersections, and GHD mistakenly interpreted the bus lanes
downstream of each intersection to be acceleration lanes for vehicles entering from the side (i.e.
minor) roads.
5 http://www.rms.nsw.gov.au/documents/projects/sydney-west/the-northern-road/northern-road-ref-appendix-a.pdf
GHD | Lowes Creek Maryland Rezoning 2125621 | 56
Consequently, when translating the layouts into AIMSUN (shown in the right-hand column in
Table 4-6), GHD coded all left-turn movements onto The Northern Road as being continuous
(i.e. unsignalised) movements with short acceleration lanes, rather than the intended treatment
as signalised turns.
This treatment offers the advantage of minimising turn delays, particularly during peak periods
of operations. However, the disadvantage is that continuous left-turn lanes require larger radii
and additional road reserve area (i.e. sellable land) to implement. The precise impact of this can
be determined at a later (detailed design) stage.
All AIMSUN models incorporated continuous left-turns (i.e. a separate lane for turning vehicles
is provided on The Northern Road, see Figure 4-21). In the SIDRA assessments (see Section
4.4), a sensitivity analysis has been undertaken based on both implementing the continuous
left-turns and the signalised left-turns for all horizon years up to 2031.
Internal Road Network: Access Management Principles
Three overarching principles were prepared by GHD for representing access to/from
development areas specifically along the sub-arterial roads with two lanes per direction, namely:
Access Principle 1: Full access (i.e. across the median – see Figure 4-7).
Access Principle 2: Partial access via left-in/left-outs (see Figure 4-8).
Access Principle 3: Combination of Principles 1 and 2 (see Figure 4-9).
Access Principle 1
Figure 4-7 – Access Principle 1: Full Access across the Median
Advantages:
Provides the most direct access to and from development areas.
Vehicles entering the development via a right-turn (i.e. across the median) can “wait” in
dedicated right-turn bays within the median without impeding through traffic along the
main road (if the median is wide enough).
If a median of adequate width is provided (typically more than 6 m), vehicles exiting via a
right-turn can wait safely in the median area for a safe gap in oncoming traffic.
GHD | Lowes Creek Maryland Rezoning 2125621 | 57
Disadvantages:
Vehicles exiting the development via a right-turn have to:
– Cross two oncoming lanes (from their right) plus the median width.
– Often use a two-stage crossing and “wait” in the median if (as expected) the main road
volumes are high.
Might require safe “waiting” space in the median (i.e. a wider median).
High volumes along the main road could create dangerous right-turns.
Higher speed along the main road because of enhanced right-of-way.
High volumes along the main road could necessitate additional intersection control (i.e.
signals) which could impact the perceived mobility function of the road.
Access Principle 2
Figure 4-8 – Access Principle 2: Partial Access via Left-In/Left-Outs
Advantages:
Improved safety, as vehicles exiting the side road only have to merge with traffic coming
from one direction.
The mobility function of the main road is maintained i.e. through movements are not
opposed by right turns.
Disadvantages:
Vehicles are required to take longer routes, to find median openings / intersections /
roundabouts to turn right or turn around.
Limited access / egress opportunities can result in drivers making U-turns at the first
available intersection (often at signalised junctions), resulting in potentially unsafe
behaviour.
Access Principle 3
Figure 4-9 – Access Principle 3: Combination of Principles 1 and 2
GHD | Lowes Creek Maryland Rezoning 2125621 | 58
Advantages:
Left-in/left-out access is provided as a general rule, but supplemented by roundabouts to
facilitate U-turns and access between signalised junctions.
Aims to build on the perceived strengths of aforementioned Principles 1, while reducing
their perceived shortcomings.
Rational balance between maintaining mobility the function of the main road while
providing safe access to the Context Plan area.
Disadvantages:
Mobility function of the main road can be compromised due to frequent roundabouts.
Access to/from certain development clusters will still be more indirect/circuitous than in
the case full access.
GHD presented access principles to the DPE on the 21st May 2018 and highlighted the key
advantages and disadvantages. It was agreed that the mesoscopic modelling would proceed in
accordance with Access Principle 3, i.e. a combination approach.
The intersection treatments within the LCM Precinct used in the mesoscopic modelling (in
accordance with Access Principal 3) are displayed in Figure 4-10. All other accesses between
these intersections (many of them visible in the background in Figure 4-10) were assumed to
be left-in / left-out only.
Figure 4-10 – Mesoscopic Modelling Intersection Treatments
GHD | Lowes Creek Maryland Rezoning 2125621 | 59
Future Year Traffic Volumes
The strategic modelling stage provided the future travel demand for the study area, for each
horizon year up to 2041. The study area travel demand was extracted as traversal (i.e. subarea)
matrices from the EMME model, and incorporated into the 2016 Base AIMSUN model together
with the road network applicable to the particular horizon year of analysis. Appendix F details
the methodology employed to superimpose the strategic (EMME) demands onto the
mesoscopic (AIMSUN) models.
Figure 4-11 presents the AM peak hour travel demands within the subarea for all horizon years,
as extracted from the EMME models.
Figure 4-11 – Future Travel Demand within the Study Area
Figure 4-11 highlights the following:
The total subarea travel demand (blue) shows a sustained increase in all horizon years.
This aligns with the envisaged growth within the South West Growth Centre.
Lowes Creek Maryland Precinct’s travel demand (orange) represents approximately 20
percent of the totals demand within the subarea by 2021. Between 2026 and 2041 its
share of the subarea travel demand is relatively constant, between 33 percent and 36
percent.
Over the period between 2021 and 2041, the total traffic volumes generated by LCM
Precinct will increase by approximately 5,500 vehicles per hour (i.e. from 700 to 6,200
vehicles per hour), while the absolute increase within the Context Plan area was
approximately 13,400 vehicles per hour (i.e. from 3,600 to 17,000 vehicles per hour).
On 5th July 2018 GHD presented the three-tiered preliminary modelling results to
representatives of the RMS and DPE and highlighted the large increase in traffic volumes within
the Context Plan area as displayed in Figure 4-11.
GHD | Lowes Creek Maryland Rezoning 2125621 | 60
During the presentation and the ensuing discussions, it was agreed that:
Mesoscopic modelling would be undertaken for all horizon years up to and including 2031
but not for 2036 and 2041. RMS agreed that the uncertainties underlying future STFM
predictions beyond 2031 are too coarse to include in the mesoscopic modelling stage and
that predictions are car-centric with minimal consideration given to mass public transport
services that may occur at a later time.
RMS instructed GHD that the transport modelling should include the full development
without the provision of the future station, as the train station is not in the forward works
programs and there is uncertainty on the timing. This assumption also contributed to high
car-centric traffic growth in the area.
The agreed timing of the proposed upgrades of The Northern Road and Bringelly Road /
Greendale Road are as follows:
The Northern Road – two travel lanes per direction up 2031 and three travel lanes per
direction subsequent to this.
Bringelly Road / Greendale Road – one travel lanes per direction up 2031 and two travel
lanes per direction subsequent to this.
Network Operations Optimisation
For the mesoscopic modelling of the 2021, 2026 and 2031 horizon years, all signalised
intersections were optimised in terms of layout and signal phasing with the aim of minimising
intersection delays.
Optimisation involved an iterative interaction process between AIMSUN and SIDRA, as
illustrated by Figure 4-12, generally involving the following steps:
Step 1: Extract turn volumes and vehicle compositions at each intersection from
AIMSUN for the network AM and PM peak hour.
Step 2: In SIDRA, develop intersection layouts that are consistent with the AIMSUN
layouts and import the turn volumes from Step 1.
Step 3: In SIDRA, develop signal phasing and cycle times using the method of “Minimum
Intersection Delay” and a LOS D target at worst. Required intersection upgrades (i.e.
additional lanes or layout changes) are identified in this step.
Step 4: In AIMSUN, update the signal phasing plans, signal offsets and/or layouts using
the results of Step 3 and repeat the traffic assignment.
Step 5: Repeat Steps 1 to 4 until the traffic volumes are generally stable between
successive AIMSUN assignments.
GHD | Lowes Creek Maryland Rezoning 2125621 | 61
Figure 4-12 – Intersection Optimisation Process
The STFM forecasts highlight The Northern Road as an important high-order arterial road within
the SWGA and suggests that future traffic volumes could exceed 3,000 vehicles in the peak
direction during the weekday peak hour.
For network optimisation, SIDRA’s Network Analysis feature was utilised to simultaneously
minimise overall delays along The Northern Road and improve traffic progression through the
intersections of interest. Figure 4-13 shows the routes where signal progression was prioritised
in the AM and PM peak hours.
GHD | Lowes Creek Maryland Rezoning 2125621 | 62
Figure 4-13 – Optimised Traffic Progression along The Northern Road
AM Peak Hour (Northbound) PM Peak Hour (Southbound)
This approach of basing optimising on the “Minimum Intersection Delay” has the following
perceived advantages and disadvantages:
Advantages:
Traffic signals are synchronised to improve overall north-south travel, in accordance with
the major traffic flows.
In reality, the north-south movement will likely be prioritised given The Northern Road’s
intended function as a “movement” corridor, and the large volumes of vehicles it is
expected to accommodate.
Disadvantages:
North-south movements are prioritised at the expense of the side-road traffic volumes,
which typically experience longer delays.
SIDRA finds a balance between the green-time requirements of all the intersections.
Depending on the traffic volumes at each intersection (and the ratio between main and
side road volumes), it is possible that a few intersections can be allocated more green-
time than they require along the prioritised route, while others are allocated less.
When the SIDRA optimisations are transferred to AIMSUN, it often involves small manual
adjustments to counteract the imbalances highlighted at the preceding two points.
GHD | Lowes Creek Maryland Rezoning 2125621 | 63
4.3.3 Mesoscopic Modelling Results
This section presents the results of mesoscopic modelling (AM and PM peak hours) completed
to support the LCM Precinct (traffic volumes, V/C and average delays), as described in Table
4-7.
Table 4-7 – Summary of Mesoscopic Modelling Results
Year Traffic Vol (veh/h). and V/C Average Delays (sec)
2021 Figure 4-14 Figure 4-15
2026 Figure 4-16 Figure 4-17
2031 Figure 4-18 Figure 4-19
The links are shades to show the estimated V/C ratios as well as the modelled traffic volumes,
as follows:
The expected traffic volumes are located next to each link.
Low V/C ratios (less than 0.75) are coloured green, yellow and orange, while high V/C
ratios (greater than 0.75) are coloured orange and red.
Delays associated with a LOS E or worse a coloured red, while delays associated with
LOS D or better are coloured green, yellow and orange.
In addition to these figures, high-level delay calculations, extracted from AIMSUN, are included
in Appendix G.
GHD | Lowes Creek Maryland Rezoning 2125621 | 64
Figure 4-14 – Mesoscopic Modelling Results for 2021 (Stage 1) – Traffic Volumes and V/C Ratios
AM Peak Hour (07:15 – 08:15)
PM Peak Hour (17:15 – 18:15)
GHD | Lowes Creek Maryland Rezoning 2125621 | 65
Figure 4-15 – Mesoscopic Modelling Results for 2021 (Stage 1) – Average Delay
AM Peak Hour (07:15 – 08:15)
PM Peak Hour (17:15 – 18:15)
GHD | Lowes Creek Maryland Rezoning 2125621 | 66
Figure 4-16 – Mesoscopic Modelling Results for 2026 (Stages 2 & 3) – Traffic Volumes and V/C Ratios
AM Peak Hour (07:15 – 08:15)
PM Peak Hour (17:15 – 18:15)
GHD | Lowes Creek Maryland Rezoning 2125621 | 67
Figure 4-17 – Mesoscopic Modelling Results for 2026 (Stages 2 & 3) – Average Delay
AM Peak Hour (07:15 – 08:15)
PM Peak Hour (17:15 – 18:15)
GHD | Lowes Creek Maryland Rezoning 2125621 | 68
Figure 4-18 – Mesoscopic Modelling Results for 2031 (Stages 3 & 4) – Traffic Volumes and V/C Ratios
AM Peak Hour (07:15 – 08:15)
PM Peak Hour (17:15 – 18:15)
GHD | Lowes Creek Maryland Rezoning 2125621 | 69
Figure 4-19 – Mesoscopic Modelling Results for 2031 (Stages 3 & 4) – Average Delay
AM Peak Hour (07:15 – 08:15)
PM Peak Hour (17:15 – 18:15)
GHD | Lowes Creek Maryland Rezoning 2125621 | 70
The intersection treatments shown in Figure 4-10, represent the assumptions that were
included in the mesoscopic model. The final treatments are summarised in Section 4.4 (SIDRA
modelling). It is noted that mesoscopic modelling was completed up to the 2031 horizon year, in
accordance with the approach agreed with RMS and DPE on 5th July 2018.
In summary, the following conclusions are drawn from the mesoscopic modelling stage:
By 2021 (see Figure 4-14 and Figure 4-15):
– The V/C ratios on the internal road network are generally less than 25 percent.
– The average delays are generally within acceptable LOS limits.
By 2026 (see Figure 4-16 and Figure 4-17):
– The V/C ratios within the LCM Precinct is generally less than 50 percent, while the V/C
ratios along The Northern Road are approaching 75 percent.
– The average link delays on the internal road network are generally within acceptable
limits (typically LOS C).
By 2031 (see Figure 4-18 and Figure 4-19):
– The V/C ratios on the internal road network is generally in the 50 percent range, which
suggest that the internal road network and hierarchy is sufficient to cater to the
expected trip generation.
– V/C ratios exceed 75 percent in the northbound direction along nearly all sections of
The Northern Road during the AM peak hour. This result indicates that the two lanes
per direction along The Northern Road should be required to be widened to three
lanes in each direction after 2031 to facilitate an acceptable V/C ratio.
– During the PM peak hour the southbound movement is the largest, with V/C ratios
approaching 75 percent along most sections.
– Average delays at intersections (internal and external) are within the acceptable LOS
D range. This suggests that the modelled intersection controls (i.e. traffic signals or
roundabouts) provide sufficient capacity to accommodate the expected demand
without causing unacceptable levels of congestion on the proposed road network.
The following observations are made regarding additional future connectivity to the LCM
Precinct (i.e. to the northern and southern precincts) that were assumed in this study:
Consider additional connectivity to/from the west of LCM Precinct i.e. potentially links to
the Outer Sydney Orbital. Although these linkages were not considered (as agreed with
RMS), it is likely (if they become available) that these will contribute positively to the wider
context plan and reduce traffic volumes at the intersections along The Northern Road.
The long-term potential Outer Sydney Orbital (shown in blue in Figure 4-20) provides the
opportunity for a western access to / from the larger context plan area. However, the best
available information at the time of writing indicated that the Outer Sydney Orbital is
considered a very long-term investment, and would likely only be realised by a 2056
planning horizon.
GHD | Lowes Creek Maryland Rezoning 2125621 | 71
Figure 4-20 – Potential Sydney Outer Orbital
GHD | Lowes Creek Maryland Rezoning 2125621 | 72
4.4 SIDRA Modelling
SIDRA analysis has been undertaken for the external and internal intersections of interest within
and adjacent to the LCM Precinct utilising the turning volumes extracted from AIMSUN and the
proposed road geometry for each horizon year scenario.
The detailed design drawings for the intersection upgrades on The Northern Road (see
Appendix B) have been used to inform the road geometry inputs to the SIDRA models.
The following naming convention has been used to identify the scenarios tested in SIDRA:
Scenario A – separate left turns set as signalised for the east and west approaches to The
Northern Road.
Scenario B – left turn slip lanes set as continuous for the east and west approaches to The
Northern Road.
It is noted that the figures in RMS Circular (RMS 17.039 from July 2017 (as displayed in Table
4-6) have provided the basis of the geometric layouts used in the SIDRA analysis.
The Scenario B layout, as indicated in Figure 4-21 below, will reduce the delays for vehicles
seeking to turn left onto The Northern Road as they can merge downstream with through traffic.
The trigger points for upgrading The Northern Road from two lanes per direction to six lanes per
direction have also been investigated in this analysis.
Generally, intersection geometry used on The Northern Road resemble layouts displayed in
Figure 4-21. The general phasing used for each intersection type were taken from standard
RMS signal phasing arrangements.
Figure 4-21 – Indicative Road geometry on The Northern Road
Scenario A – Signalised left turn slips (E-
W)
Scenario B –Continuous left turn slips (E-W)
The typical phasing used in the SIDRA analysis is displayed in Figure 4-22.
GHD | Lowes Creek Maryland Rezoning 2125621 | 73
Figure 4-22 – Indicative Signal Phasing
Typically, single diamond overlap phasing was applied to intersections along The Northern
Road, with the exception of double diamond overlap phasing used where dual right turns lanes
were proposed on both the north / south approach and east / west approaches (Site 5).
Where dual right turns lanes were proposed, dedicated right turn signals (i.e. arrows) were
provided.
Legend:
GHD | Lowes Creek Maryland Rezoning 2125621 | 74
4.4.1 Assessment Criteria
The intersections of interest have been assessed based on overall average delay per vehicles
(sec/veh). The performance of a road network is largely dependent on the operating
performance of key intersections of interest, which are critical capacity control points. SIDRA 7
intersection modelling software was used to assess the proposed peak hour operating
performance of intersections of interest on the surrounding road network. The criteria for
evaluating the operational performance of intersections is provided by the RMS Guide to Traffic
Generating Developments (2002) as displayed in Table 2-2.
The criteria for evaluating the operational performance of the intersections of interest have been
based on a qualitative measure (i.e. Level of Service), which is applied to each band of overall
average vehicle delay. Typically, an overall LOS D or better is considered acceptable. Delays
greater than this, particularly for the future planning of road networks is considered
unsatisfactory.
4.4.2 Assumptions and parameter settings
The following parameter settings and assumptions have been used in SIDRA:
The internal and external road network was modelled for three horizon years (2021, 2026
and 2031) to coincide with each stage of the development.
The Northern Road was modelled as a co-ordinated route and the intersections were
offset in the SIDRA program to account for this.
A cycle time of 140 seconds was assumed for the intersections on The Northern Road.
A cycle time of 60 – 140 seconds was assumed for signalised junctions on the internal
road network.
The layout of the road networks used in the SIDRA analysis to assess the intersections of
interest (for each horizon year of analysis) are included in Appendix H.
4.4.3 Signalised Junctions
2021 SIDRA Results
Figure 4-23 shows the road network and intersections analysed in SIDRA for the 2021 horizon
year.
GHD | Lowes Creek Maryland Rezoning 2125621 | 75
Figure 4-23 – LCM 2021 SIDRA Network
The SIDRA results of the 2021 horizon year are displayed in Table 4-8.
Table 4-8 - 2021 LOS Summary
Site Scenario A* Scenario B*
AM PM AM PM
1 D E D E
2 A A A A
3 B B A A
4 A A A A
5 B B B B
6 A A A A
7 A A A A
8 A A A A
*LOS is based on overall average delay (sec) of the signalised intersection
GHD | Lowes Creek Maryland Rezoning 2125621 | 76
The SIDRA results in Table 4-8 indicate that for 2021:
All intersections except Site 1 perform satisfactorily with spare capacity.
Site 1 (the grade separated intersection of The Northern Road and Bringelly Road)
operates at capacity in the PM peak (for both scenarios). The north and south
approaches of Site 1 are prioritised over the east and west approaches due to the
coordinated route on The Northern Road. This increases the average delay at the east
and west approaches and the overall intersection.
Overall, in 2021 the road network performs satisfactorily, with no trigger points for further
upgrades of The Northern Road, which is consistent with the outputs of the mesoscopic
and strategic modelling.
2026 SIDRA results
In 2026, the road network expands to include sites 12, 15, 18 and 19 (on the proposed collector
road) as shown in Figure 4-24.
Figure 4-24 – LCM 2026 SIDRA Network
The SIDRA results of the 2026 horizon year are displayed in Table 4-9.
GHD | Lowes Creek Maryland Rezoning 2125621 | 77
Table 4-9 – 2026 LOS Summary
Site Scenario A* Scenario B*
AM PM AM PM
1 D D D D
2 A A A A
3 F C B B
4 C B A B
5 E B C B
6 C B C B
7 A B A B
8 A A A A
12 B A B A
15 B A B A
18 B B B B
19 B A B
The SIDRA results in Table 4-9 indicate that for 2026:
The majority of intersections perform satisfactorily with spare capacity.
Site 1 is expected to perform satisfactorily at LOS D. This improvement may be explained
by automatic adjustments to signal timing by the SIDRA program, which can cause slight
improvements in performance and LOS due to increases in traffic volumes from side
roads.
Site 3 (Scenario A) is expected to operate with a poor LOS during AM peak periods,
without continuous left turn lanes.
Overall, in 2026 the road network performs satisfactorily, with limited trigger points (i.e.
poor operation of only at sites 3 and 5 in the AM peak) for the further upgrade of The
Northern Road identified, which is consistent with the outputs of the mesoscopic and
strategic modelling.
Accordingly, to minimise delays, the continuous left turn lanes (Scenario B) are the preferred
intersection layouts along The Northern Road.
In accordance with the 2026 SIDRA outputs for Scenario A (which indicates that some
intersections on The Northern Road are expected to operate with a poor LOS), the 2031 horizon
year analysis has been undertaken with:
Two travel lanes in either direction on The Northern Road.
Three travel lanes in either direction on The Northern Road.
2031 SIDRA results (two travel lanes in either direction on The Northern Road)
The signalised intersections included in the 2031 SIDRA analysis are displayed in Figure 4-25.
It includes the proposed internal north / south sub-arterial road network. It assumes that The
Northern Road will provide two travel lanes in either direction.
GHD | Lowes Creek Maryland Rezoning 2125621 | 78
Figure 4-25 – LCM 2031 Road Network (two travel lanes in either direction on
The Northern Road)
The SIDRA results of the 2031 horizon year with two travel lanes per direction on The Northern
Road are displayed in Table 4-10.
GHD | Lowes Creek Maryland Rezoning 2125621 | 79
Table 4-10 - 2031 SIDRA Results Summary (two travel lanes in either
direction on The Northern Road)
Site
Scenario A Scenario B
AM PM AM PM
1 D D D D
2 F B B B
3 F C B B
4 C C B C
5 F C B C
6 D B D B
7 B A B A
8 B B B B
9 B A B A
11 B A B A
12 B B B B
13 A A A A
14 A B A B
15 C A C A
18 A B A B
19 A A A A
The SIDRA results in Table 4-10 indicate that for 2031:
Unsatisfactory levels of service occur at sites 2, 3, and 5 for Scenario A in the AM peak.
The majority of intersections (including all the internal signalised junctions) perform
satisfactorily with spare capacity.
Site 1 is expected to perform satisfactorily (LOS D). This is consistent with the provision
of additional capacity on the proposed north / south sub-arterial road network providing
an alternative route parallel to and west of The Northern Road that connects to Bringelly
Road
For Scenario B (continuous left turn lanes), all intersections operate at satisfactory
conditions with spare capacity.
The poor LOS at sites 2, 3 and 5 are predominantly associated with vehicles on the east and
west approaches, as priority is allocated to northbound and southbound movements along The
Northern Road.
The outputs from the mesoscopic model indicate that in AM peak periods, large volumes of
vehicles originating within the LCM Precinct will seek to travel northbound on The Northern
Road. Accordingly, continuous left turn lanes from the west approaches onto The Northern
Road (Scenario B) improve overall intersection performance considerably and are the preferred
intersection layouts.
2031 SIDRA results (three travel lanes in either direction on The Northern Road)
The SIDRA in Table 4-10 indicate that without continuous left turn lanes (as detailed in the
Scenario B analysis), some intersections on The Northern Road are expected to operate with a
poor LOS.
The road network was modelled with three-lanes each way on The Northern Road (see Figure
4-26), to increase capacity due to the trigger points identified in the previous analysis.
GHD | Lowes Creek Maryland Rezoning 2125621 | 80
Figure 4-26 – LCM 2031 Road Network (three travel lanes in either direction
on The Northern Road)
The SIDRA results of the 2031 horizon year with three travel lanes per direction on The
Northern Road are displayed in Table 4-11.
GHD | Lowes Creek Maryland Rezoning 2125621 | 81
Table 4-11 - 2031 LOS Summary (three travel lanes in either direction on The
Northern Road)
Site Scenario A Scenario B
AM PM AM PM
1 D D D D
2 F B B B
3 F B A B
4 B C B B
5 D B C C
6 D B D B
7 B A B A
8 B B B B
9 B A B A
11 B A B A
12 B B B B
13 A A A A
14 A B A B
15 C A C A
18 A B A B
19 A A A A
The SIDRA results in Table 4-12 indicate that for 2031 with The Northern Road widened to
three travel lanes in either direction:
In Scenario A, sites 2 and 3 will continue to operate with a poor LOS in the AM peak even
with the additional road capacity. Again, these delays are predominantly associated with
vehicles on the east and west approaches.
With the provision of additional capacity on The Northern Road site 4 improves from LOS
C to LOS B and site 5 improves from LOS F to LOS D during the AM peak. Site 3 and site
5 also improves from LOS C to LOS B in the PM peak.
In Scenario B, site 3 improves from LOS B to LOS A in the AM peak, and from LOS C to
LOS B in the PM peak.
Overall, Scenario B improves the road network such that it is operating at satisfactorily.
This is consistent with the previous analysis for 2031 (two travel lanes in either direction)
and indicates that the provsion of continuous lanes may delay the requirement to upgrade
The Northern Road to three lanes in either direction.
Signalised Intersection Summary
In summary:
The signalised intersections of interest are expected to predominantly operate with a
good LOS in the 2021 and 2026 horizon year.
All the internal signalised intersection are expected to operate with a good LOS through
to and including the 2031 horizon year.
For Scenario A, even with the additional capacity associated with three travel lanes in
either direction on The Northern Road, intersections 2 and 3 are expected to operate with
a poor LOS by 2031.
GHD | Lowes Creek Maryland Rezoning 2125621 | 82
The delays at intersection on The Northern Road with poor LOS (in Scenario A) are
predominantly associated with vehicles on the east and west approaches, as priority is
allocated to north and south through movements.
Accordingly, continuous left turn lanes from the approaches onto The Northern Road
(Scenario B) improve overall intersection performance considerably and may delay the
requirement to upgrade The Northern Road to three lanes in either direction..
4.4.4 Roundabout SIDRA analysis
An assessment of key roundabout locations within the internal road network has been based on
criteria outlined in the RMS Guide to Traffic Generating Developments.
The indicative locations of the roundabouts within the LCM Precinct is displayed in Figure 4-27.
Figure 4-27 – LCM 2031 internal Roundabout Locations
An example of the intersection geometry used in the analysis of the roundabouts is displayed in
Figure 4-28, with two travel lanes on the sub-arterial road network and a single travel lane on
the collector and local road network.
GHD | Lowes Creek Maryland Rezoning 2125621 | 83
Figure 4-28 – Indicative Roundabout Geometry
Table 4-12 provides a summary of the SIDRA results for the 2031 traffic volumes at identified roundabouts within the study area.
Table 4-12 - 2031 SIDRA Roundabout Summary
Notes:
The level of service for priority-controlled intersections is based on the highest average delay per vehicle for the
most critical movement.
The degree of saturation is defined as the ratio of the arrival flow (demand) to the capacity of each approach.
Table 4-12 indicates that for the 2031 scenario all roundabout intersections of interest would
have an acceptable Level of Service based on overall average delay (i.e. better than Level of
Service D).
Site number
AM Peak PM Peak
LOS Degree of saturation
LOS Degree of saturation
30 A 0.239 B 0.162
31 B 0.460 B 0.363
32 A 0.196 B 0.242
34 B 0.087 A 0.073
35 B 0.195 B 0.245
36 B 0.330 B 0.236
37 A 0.075 A 0.080
38 A 0.073 A 0.120
39 B 0.193 B 0.186
40 B 0.457 B 0.508
GHD | Lowes Creek Maryland Rezoning 2125621 | 84
All SIDRA outputs for the signalised intersections and roundabouts are included in Appendix I.
4.5 Road Network Master Plan
4.5.1 Master Plan Summary
Based on the results of the three levels of modelling presented in this study, we recommend the
following road network hierarchy for the LCM Precinct (up to 2031) as displayed in Figure 4-29:
Four-lane sub-arterial roads (60 km/h) bounding the northern, southern and western
perimeter of the precinct area that connects directly to The Northern Road and the
adjacent precincts. In accordance with its movement function, parking will not be
permitted on the sub-arterial road network. Separated shared paths will be provided on
the sub-arterial road network.
Two-lane collector roads (50 km) that provide access to the interior of the precinct and
key land uses (such as the school and local centre) and connect to the sub-arterial roads
and local roads (in accordance with the proposed road hierarchy). Access density is
higher along these roads and on-street parking is permitted.
Both the sub-arterial and collector road networks will be designed to accommodate bus
routes (3.5 m travel lanes required).
Key intersections along the collector and sub-arterial road networks are signalised with
roundabouts to provide additional access and U-turn opportunities (as detailed in “access
principal 3” - Figure 4-9).
Additional access along sub-arterial roads and collector roads should only be provided
through left in / left out (LILO) priority controlled intersections.
Local streets (50 km/h) that provide access to individual properties.
GHD | Lowes Creek Maryland Rezoning 2125621 | 85
Figure 4-29 – Lowes Creek Maryland Proposed Road Hierarchy
4.5.2 Road Network Staging
The road network staging is closely related to the staging of the development of the LCM
Precinct. Figure 4-30 presents the proposed staged implementation of the road network and
intersection control for the LCM Precinct as it is sequentially developed.
GHD | Lowes Creek Maryland Rezoning 2125621 | 86
Figure 4-30 – LCM Staged Implementation of the Road Network
Stage 1 Stage 2 Stage 3 and 4
GHD | Lowes Creek Maryland Rezoning 2125621 | 87
4.6 Travel Demand Management
In accordance with the projected levels of growth within the Context Plan and the wider SWGA,
it is expected that increased traffic volumes will increase delays at key intersections, particularly
on The Northern Road.
Travel demand management (TDM) is a term for strategies that encourage a shift from single
occupant private vehicles trips. TDM improve transport efficiencies while reducing the negative
impacts associated with the use of private motor vehicles. Given the projected congestion at key
intersections on The Northern Road (particularly during peak periods of road network activity),
the implementation of TDM has the potential to provide significant utility to residents and visitors
to the LCM Precinct. TDMs also provide the utility to enhance the operation of the precinct’s
internal road.
The most effective TDM strategies focus on both incentives for non-car use (e.g.: provision of
high quality bicycle riding routes) and disincentives for car use (e.g.: parking fees). The following
sub-sections discuss commonly used approaches which could be adopted. They are based on
either employer based schemes or area-wide schemes.
A transport efficient environment is characterised by land uses that provide opportunities for
active transport and public transport trips. Mixing housing and employment with other services
and retail opportunities allows residents to undertake some of their necessary trips i.e. journey
to works and shops without using a car.
Accordingly, TDMs should be applied to LCM Precinct to discourage single occupancy private
vehicle trips, this could potentially include:
Prioritising on-road public transport through enhanced signal and road space priority.
Designing compact communities with sufficient density to support high-service standards
of public transport (frequency, span of services and better stop and road space priority
infrastructure standards).
Providing employment opportunities within the precinct, to discourage external trips
during peak periods of road network operations.
Supporting “car-lite” and “car-free” developments, tied with time controlled and permit
parking and untying car parking supply from residential and commercial development
where active and public transport services and infrastructure are good.
Provide direct and separated walking and bicycle riding routes to public facilities, public
transport nodes and stations and shopping areas.
GHD | Lowes Creek Maryland Rezoning 2125621 | 88
5. Summary and Conclusion
The summary and conclusions to the Lowes Creek Maryland Precinct Traffic and Transport
Assessment are described below.
5.1 Introduction
GHD has been commissioned to undertake a Traffic Assessment for the Lowes Creek Maryland
Precinct.
Macarthur Developments entered into a Voluntary Planning Agreement (VPA – 1) with the
Minister for Planning and Environment on 25 September 2015. The VPA requires planning to be
undertaken for two areas:
1. Preparation of a context plan for the broader LCM and South Creek West land release
area.
2. Preparation of an Indicative Layout Plan for LCM Precinct to deliver housing and service
infrastructure necessary to accelerate the Precinct.
5.2 Future Transport
The Northern Road is currently being upgraded by RMS from two lanes to a four lane divided
road, with the provision of a median allowing for 6 lanes to be provided in the future. The
upgrade includes the provision of 4 m shoulders, which if required at a later date can be
converted into bus lanes.
The Northern Road upgrade includes the provision of bus lanes in either direction. Currently, no
bus services operate on The Northern Road. However, as the SWGA is developed, increased
population densities may encourage the introduction of new bus routes in the region. Sydney’s
Bus Future (2013) specifies that rapid service routes will be provided for Western Sydney.
5.3 Proposed Land Uses
5.3.1 Residential
It is proposed to provide a variety of different dwelling types within the LCM Precinct, as follows:
A relatively small number of apartment buildings of up to five stories (high density) with
approximately 40 – 60 dwellings per hectare.
Medium density with approximately 25 – 35 dwellings per hectare.
Low density residential dwelling with approximately 15 – 25 dwellings per hectare.
Preliminary estimates (provided by the DPE) indicate that the:
LCM Precinct could accommodate approximately 7,060 dwellings
The Context Plan areas could accommodate 9,950 dwellings.
GHD | Lowes Creek Maryland Rezoning 2125621 | 89
5.3.2 Retail and Commercial Uses
The Draft Lowes Creek Maryland Part Precincts Rezoning Economic (Retail and Employment)
Analysis 2016 provides a preliminary estimate of retail/commercial land uses that are proposed
to be developed within the Context Plan
Within the LCM Precinct, the following retail/commercial facilities are proposed:
A “local centre” with a concentration of retail and commercial facilities. The local centre is
expected to be anchored by a supermarket and includes a number of speciality stores
and discount department stores.
A “mixed use precinct” adjacent to the town centre - primarily expected to serve residents
of the high density developments.
A small “convenience centre” located at the north east corner of the subject site
The following has been assumed with respect to the timing of the development of the retail
facilities:
Local Centre:
– In Stage 1 (2018 to 2021), 70 percent of the supermarket and a third of the speciality
retail/commercial will be developed
– In Stage 2 (2022 to 2026), the remaining 30 percent of the supermarket, two-thirds of
the speciality retail/commercial and the discount department store will be developed.
Mixed use development will be developed in Stage 3 (2027 to 2031).
Convenience centre will be developed in Stage 4 (2032 to 2036).
Maryland South Village will be developed in Stage 3 (2027 to 2031).
Bringelly Village will be developed in Stage 4 (2032 to 2036).
Highway services/employment area 50 percent will be developed in Stage 3 (2027 to
2031) and 50 percent in Stage 4 (2032 to 2036).
5.3.3 Recreational and Educational Uses
Recreational facilities including parks, sports ovals and playing fields will be provided to serve
the residents of the LCM Precinct. The sports/ovals and playing fields are proposed to be
concentrated to the north of the local centre
The proposed development will include the following educational facilities:
1 primary schools and 1 high school within the LCM Precinct
An additional 2 primary schools and 1 high school within the remaining Context Plan
area.
Demand for educational facilities will increase as the Context Plan area is developed as the
residential population grows. Accordingly, the following, has been assumed with respect to the
timing of the development of the educational facilities:
A primary school and high school will be constructed within the LCM Precinct in Stage 1
(2017 to 2021).
Within the southern area, a primary school will be constructed in Stage 3 (2027 to 2031)
and a high school in Stage 4 (2032 to 2036).
Within the northern area, a primary school will be constructed in Stage 3 (2027 to 2031).
GHD | Lowes Creek Maryland Rezoning 2125621 | 90
5.4 Road Network and Access
The proposed road structure/hierarchy for the Context Plan is as follows:
A north-south sub-arterial road that intersects Greendale Road to the north and Oran
Park Town Centre to the south.
Two east-west sub-arterial roads that connect the north-south road with The Northern
Road.
A collector road network that distributes local traffic throughout the subject site that
provides access to residential lots and directs vehicles to sub-arterial roads at key
intersections on The Northern Road.
Local roads to provide access to residential dwellings
A shared path network to encourage active transport within the subject site and provide
connectivity to external pedestrian
5.4.1 Trip Generation Assessment
A detailed trip generation assessment indicates that:
The LCM Precinct is expected to generate approximately 6,104 – 7,034 trips during peak
periods of road network activity.
The Context Plan areas are expected to generate approximately 7,974– 7,857 trips
during peak periods of road network activity.
5.5 Modelling Methodology
5.5.1 Introduction
In accordance with instructions from RMS a three-tiered modelling process has been adopted
for the LCM Precinct Traffic Study, as follows:
Tier 1 – Strategic modelling using the EMME model provided by RMS.
Tier 2 – Mesoscopic modelling using AIMSUN to take into account the consideration of
time dynamics of the traffic demand.
Tier 3 – SIDRA intersection modelling using the traffic volumes identified in the previous
modelling processes, accounting for the existing/proposed infrastructure on the adjoining
road network.
5.5.2 Strategic Modelling
The following conclusions are drawn from the strategic modelling outputs:
Prior to 2026 (see Figure 4-1), no links have V/C ratio greater than 80 percent. In general
terms, this means congestion on the network is minimal.
In 2026 (see Figure 4-2), during both the AM and PM peaks the V/C ratio exceeds 80
percent along The Northern Road between the northernmost access road to the Lowes
Creek Maryland Precinct and Bringelly Road.
By 2031 (see Figure 4-3), additional north / south road linkages between LCM Precinct
and the adjacent context areas have been included. These alleviate congestion along
The Northern Road (by providing alternative routes).
GHD | Lowes Creek Maryland Rezoning 2125621 | 91
By 2036 (see Figure 4-4), V/C ratios of greater than 100 percent are shown over multiple
sections along The Northern Road particularly in proximity to Bringelly Road intersection
during both the AM and PM peak periods.
In 2041 (see Figure 4-5):
– Within the LCMs Precinct, all links are shown to have V/C ratios lower than 80
percent.
– Within the larger Context Plan area, only one link (located in the southern area) has a
V/C ratio that exceeds 100 percent.
– Nearly the entirety of The Northern Road (northbound) has a V/C ratio that exceeds
80 percent.
– Similar to the observations for 2036, all approaches at The Northern Road at the
Bringelly Road intersection have V/C ratios that exceed 100 percent.
The Northern Road should be widened to three lanes in either direction between 2031
and 2036, to facilitate capacity that can accommodate the expected travel demand.
GHD | Lowes Creek Maryland Rezoning 2125621 | 92
5.5.3 Mesoscopic Modelling
In summary, the following conclusions are drawn from the mesoscopic modelling stage:
By 2021 (see Figure 4-14 and Figure 4-15):
– The V/C ratios on the internal road network are generally less than 25 percent.
By 2026 (see Figure 4-16 and Figure 4-17):
– The V/C ratios within the LCM Precinct is generally less than 50 percent, while the V/C
ratios along The Northern Road are approaching 75 percent.
By 2031 (see Figure 4-18 and Figure 4-19):
– The V/C ratios on the internal road network is generally in the 50 percent range, which
suggests that the internal road network and hierarchy is sufficient to cater to the
expected trip generation.
– V/C ratios exceed 75 percent in the northbound direction along nearly all sections of
The Northern Road during the AM peak hour. This result indicates that the two lanes
per direction along The Northern Road should be widened to three lanes in each
direction after 2031.
5.5.4 SIDRA Modelling
In summary:
The signalised intersections of interest are expected to predominantly operate with a
good LoS in the 2021 and 2026 horizon years.
All the internal signalised intersection are expected to operate with a good LoS up to and
including the 2031 horizon year.
For Scenario A, even with the additional capacity associated with three travel lanes in
either direction on The Northern Road, intersections 2 and 3 are expected to operate with
a poor LoS by 2031.
The delays at intersection on The Northern Road with poor LOS (in Scenario A) are
predominantly associated with vehicles on the east and west approaches, as priority is
allocated to north and south through movements.
Accordingly, left turn continuous lanes from the approaches onto The Northern Road
(Scenario B) improve overall intersection performance considerably and may delay the
requirement to upgrade The Northern Road to three lanes in either direction.
All the internal roundabouts are expected to operate with a good LOS up to 2031.
5.6 Road Network and Access
5.6.1 Proposed Road Network
In summary
LCM Precinct internal road hierarchy and cross-sections should align with the Road
Network Master Plan indicated in Figure 4-29.
High traffic forecast along The Northern Road in excess of 2,500 vehicles per direction
per hour by 2031 place pressure on maintaining its function as a mobility corridor and
providing access to/from the side roads at acceptable levels of service.
GHD | Lowes Creek Maryland Rezoning 2125621 | 93
5.6.2 Travel Demand Management
In accordance with the projected levels of growth within the Context Plan area and the wider
SWGA, it is expected that increased traffic volumes will increase delays at key intersections,
particularly on The Northern Road.
Travel demand management (TDM) is a term for strategies that encourage a shift from single
occupant private vehicles trips. TDM improve transport efficiencies while reducing the negative
impacts associated with the use of private motor vehicles. Given the projected congestion at key
intersections on The Northern Road (particularly during peak periods of road network activity),
the implementation of TDM has the potential to provide significant utility to residents and visitors
to the LCM Precinct. TDMs also provide the utility to enhance the operation of the precinct’s
internal road
In accordance with the expected peak hour congestion on The Northern Road and to enhance
the operation of the LCM Precinct’s internal road network, TDMs should be applied the precinct
to discourage single occupancy private vehicle trips,
GHD | - Lowes Creek Maryland Part Precinct Rezoning Proposal, 21/25621
Appendices
GHD | Lowes Creek Maryland Rezoning 2125621 | 95
Appendix A – RMS Modelling Method
GHD | Lowes Creek Maryland Rezoning 2125621 | 96
Appendix B – Proposed Intersection Upgrades on The Northern Road
GHD | Lowes Creek Maryland Rezoning 2125621 | 97
Appendix C – Traffic Survey Outputs
GHD | Lowes Creek Maryland Rezoning 2125621 | 98
Appendix D – EMME Model Outputs
GHD | Lowes Creek Maryland Rezoning 2125621 | 99
Appendix E – AIMSUN Calibration and Validation Report
Appendix F – Strategic Modelling Details (EMME to AIMSUN)
Appendix G – AIMSUN Delay Calculations
Appendix H – SIDRA Network Layouts
Appendix I – SIDRA Network Outputs
GHD
133 Castlereagh St Sydney NSW 2000 - T: +61 2 9239 7100 F: +61 2 9239 7199 E: [email protected]
© GHD 2018
This document is and shall remain the property of GHD. The document may only be used for the purpose for which it was commissioned and in accordance with the Terms of Engagement for the commission. Unauthorised use of this document in any form whatsoever is prohibited.
N:\AU\Sydney\Projects\21\0101208\Projects\Lowes Creek\SAM\2125621_REP Rev B.docx
Document Status
Revision Author Reviewer Approved for Issue
Name Signature Name Signature Date
A Stefan Ellis
Mark Lucas On file Bert Prinsloo On file 08/08/18
B Stfan Ellis Mark Lucas On file Bert Prinsloo On file 27/09/18
www.ghd.com