by DOWA - IBI Group Architects, Inc. | February, 2016
Centennial School District
Long-Range Facilities CommitteePhase I Recommendations — Project Budgets
+
Introduction 1
Project Budget Summary 3
Mechanical Budget Estimate 9
Electrical Budget Estimate 13
Roofi ng Budget Estimate 19
Telecom Budget Estimate 21
Paving Repair Budget Estimate 25
Proposed Multi-Purpose Room Additions 27
Appendix 33
Centennial School District’sLong-Range Facilities Committee Phase One Recommendations
Build a New School
Address space issues and overcrowding at the seven elementary schools and Centennial Middle School by constructing a new middle school on district property at SE 172nd and Foster Road.
Increase Facility Flexibility at Five Schools
Meet physical education requirements, allow for scheduling of more classes and provide increased space for community use by constructing multi-purpose rooms at Meadows, View, Wood, Parklane and Centennial Park.
Safety and Security
Provide safe and secure learning environments in all schools by making upgrades to intercom systems, cameras, vestibule entries and automatic door locks.
Maintain Stewardship of District Facilities
Demonstrate continued stewardship of district facilities to industry standards by providing healthy and comfortable learning environments for students so they can be world-competitive. This would include updated fi re and life safety systems (alarms, smoke detectors, sprinklers, etc.), HVAC and energy effi ciency upgrades, domestic water improvements, and IT network infrastructure upgrades.
Improve and Maintain Athletic Facilities
Provide for safe and adequate athletic facilities for students and community use by improving and maintaining district athletic facilities with upgraded playable fi elds and gyms that encourage students and the community to live active healthy lives, and for student athletes to be competitive.
Additional recommendations include:
• Continue to develop long-term options for Centennial Park School
• In the event of a bond, establish a citizens’ oversight committee to prioritize bond expenditures and report to the school board.
1
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
FEBRUARY, 2016
Introduction
Project Budget OverviewPROJECT BUDGET
Build a New Middle School
Construct a new 800 Student grades 6-8 Middle School, 140,000 SF
Total Budget $72,977,710
Increase Facility Flexibility at Five Schools
Add Multi-Purpose Rooms at Five Schools
Lynch Meadows $2,122,376
Lynch View $2,122,376
Lynch Wood $2,122,376
Parklane $2,122,376
Centennial Park $2,122,376
Total Budget $10,611,878
Safety and Security
Upgrade Intercom Systems, Cameras, Vestibule Entries and Automatic Door Locks.
Total Budget $2,561,456
Maintain Stewardship of District Facilities
MEP Work
Roof and Seismic
Drywells
Data / Telecom
Playground and Parking Lot Paving
Total Budget $25,274,321
Improve and Maintain Athletic Facilities
Turf Field at Centennial High School
Resurface Tennis Courts
Total Budget $2,176,875
TOTAL BOND 2015 BUDGET $113,602,240
3
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
FEBRUARY, 2016
Project Budget Summary
New 800 Student Middle SchoolCOST ITEM BUDGET NOTES
Construction Costs
Construction Budget
Building Construction 140,000 SF @ $235 $32,900,000
On-Site Construction $5,000,000 Earthwork, Utilities, Landscaping, Parking
Off-Site Water $1,426,750
Off-Site Sanitary Sewer $672,500
Off-Site Transportation $2,821,800
Subtotal (Construction Contract Award) $42,821,050
Construction Change Order Contingency 5% $2,141,053 Base upon Construction Cost
Index to Construction Start 2 years @ 5% $4,496,210
Subtotal Construction Budget $49,458,313
Consultant Costs
Architect / Engineer / Special Consultants 10% $4,282,105 Based upon Construction Cost
Subtotal Consultant Budget $4,282,105
Owner Costs
Fees / Permits / Project Management / FFE 7% $3,462,082 Based upon Construction Cost
Payoff Bond to Purchase Land $12,915,085
Subtotal Owner Budget $16,377,167
Total Project Contingency
5% $2,860,125 Based upon Total Project Budget
TOTAL PROJECT BUDGET $72,977,710
Cost / SF $521
Cost / Student $91,222
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
4+
Project Budget Summary
New Multi-Purpose RoomsCOST ITEM BUDGET NOTES
Construction Costs
Construction Budget
Building Construction 5,000 SF @ $225 $1,237,500
On-Site Construction $150,000 Earthwork, Utilities, Landscaping, Parking
Off-Site Construction NIC Streets & Utility Improvements
Subtotal (Construction Contract Award) $1,387,500
Parklane
Construction Change Order Contingency 8% $111,000 Based upon Construction Cost
Index to Construction Start 2 years @ 5% $149,850
Subtotal Construction Budget $1,648,350
Consultant Costs
Architect / Engineer / Special Consultants 15% $208,125 Based upon Construction Cost
Subtotal Consultant Budget $208,125
Owner Costs
Fees / Permits / Project Management / FFE 10% $164,825 Based upon Construction Cost
Subtotal Owner Budget $164,835
Total Project Contingency
5% $101,066 Based upon Total Project Budget
TOTAL PROJECT BUDGET $2,122,376
Cost / SF $386
Cost / Student NA
5
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
FEBRUARY, 2016
Project Budget Summary
Safety and SecurityCOST ITEM BUDGET NOTES
Safety and Security
Construction Budget
• Intercom Systems $145,648
• Cameras $390,000 200 Cameras / 5 Servers
• Vestibule Entries 7 each @ $150,000 $1,050,000 Oliver, Wood, View, Meadows PV, CMS, Centennial Park
• Automatic Door Locks $715,000
Subtotal Maintenance and Improvements $1,765,000
Owner Costs 35% $617,750
Index to Construction Start 1.5 years @ 5% $178,706
TOTAL SAFETY AND SECURITY $2,561,456
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
6+
Project Budget Summary
Maintain Stewardship of District FacilitiesCOST ITEM BUDGET NOTES
Maintain Stewardship of District Facilities
• Mechanical / Plumbing Work $2,498,571 From SDC Estimate
• Electrical Work $1,214,521 From SDC Estimate
• Roofs $11,932,000 Roofi ng Only, No Seismic
• Replace Drywells $400,000 Budget for 20 Districtwide
• Data / Telecom $526,251 NIC Intercoms & Cameras
• Playground and Parking Lot Paving $1,514,039
Subtotal Maintenance and Improvements $18,085,382
Owner Costs 30% $5,425,615
Index to Construction Start 1.5 years @ 5% $1,763,325
TOTAL MAINTAIN STEWARDSHIP OF DISTRICT FACILITIES $25,274,321
7
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
FEBRUARY, 2016
Project Budget Summary
Improve and Maintain Athletic FacilitiesCOST ITEM BUDGET NOTES
Improve and Maintain Athletic Facilities
• Turf Field at Centennial High School $1,200,000 Includes subdrainage system
• Resurface Tennis Courts 6 each $50,000 $300,000
Subtotal Maintenance and Improvements $1,500,000
Owner Costs 35% $525,000
Index to Construction Start 1.5 years @ 5% $151,875
TOTAL IMPROVE AND MAINTAIN ATHLETIC FACILITIES $2,176,875
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
8+
Project Budget Summary
Mechanical Budget Estimate
ITEM AREA / SYSTEM DESCRIPTIONS QUANTITY / UNIT UNIT COST COSTWITH SUB
O & P
QTY. Type Cost / Unit Total Cost With Sub O&P 15%
Centennial High School
Basic Materials and Methods 1 ls $2,000 $2,000
Replace Reduced Press Backfl ow Preventer (6”) 1 unit $16,500 $16,500
Replace Obsolete Gordon Piatt Boiler Burners (9000 MBH) 2 unit $19,000 $38,000
Boiler Kill Switches 1 unit $800 $800
IDF Cooling Systems 8 unit $2,250 $18,000
EEM-1: Expand DDC and Upgrade HVAC in Voc. Wing 1 unit $325,000 $325,000
EEM-2: Add Roof Insulation 1 unit $13,130 $13,130
EEM-3: Install Auto Pool Blanket 1 unit $71,223 $71,223
EEM-4: Upgrade Lighting 1 unit $82,330 $82,330
EEM-5: Replace Domestic Water Heaters with Condensing 1 unit $53,280 $53,280
Permit fees 8.4% (not included in sub O&P) 1 unit $52,102 $52,102
Total w/o Permits $620,263 $713,302
Lynch Wood Elementary School
Basic Materials and Methods 1 ls $2,000 $2,000
Replace Backfl ow Preventer 1 unit $1,900 $1,900
Replace Obsolete Gordon Piatt Boiler Burners (7000 MBH) 1 unit $19,000 $19,000
Boiler Kill Switches 1 unit $800 $800
Replace RTU’s (4 ton, 5 ton) 2 unit $7,000 $14,000
New Tunnel Fan Motors and VFD’s (7.5 HP) 1 unit $3,200 $3,200
IDF-MDF Cooling Systems 2 unit $2,250 $4,500
EEM-1: Repair or Replace Steam Traps 1 unit $6,720 $6,720
EEM-2: Install DDC System with CO2 DCV 1 unit $71,000 $71,000
EEM-3: Replace Leaking Vent Fan Preheat Coil 1 unit $11,500 $11,500
EEM-4: Frame in 1/3 of Windows and Upgrade Windows 1 unit $73,137 $73,137
Permit fees 8.4% (not included in sub O&P) 1 unit $17,452 $17,452
Total w/o Permits $207,757 $238,921
9
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
FEBRUARY, 2016
Mechanical Budget Estimate
ITEM AREA / SYSTEM DESCRIPTIONS QUANTITY / UNIT UNIT COST COSTWITH SUB
O & P
QTY. Type Cost / Unit Total Cost With Sub O&P 15%
Lynch View Elementary School
Basic Materials and Methods 1 ls $3,000 $3,000
Replace Obsolete Gordon Piatt Boiler Burners 1 unit $19,000 $19,000
Boiler Kill Switches 1 unit $800 $800
Replace RTU’s (3 ton, 6 ton) 2 unit $7,000 $14,000
DDC Upgrade 1 unit $50,000 $50,000
Finned Pipe Branch Steam Leaks 8 unit $500 $4,000
New Tunnel Fan Motors and VFD’s (5HP) 2 unit $3,000 $6,000
New Steam Pressure Switch 1 unit $500 $500
IDF-MDF Cooling Systems 2 unit $2,250 $4,500
EEM-1: Retro Commission HVAC Controls 1 unit $16,683 $16,683
EEM-2: Lighting Upgrades 1 unit $54,910 $54,910
EEM-3: Steam Valve Replacement 1 unit $12,567 $12,567
EEM-4: Floating Head Control 1 unit $5,000 $5,000
EEM-5: Steam Trap Replacement 1 unit $32,676 $32,676
EEM-6: Roof Insulation to R-30 1 unit $179,502 $179,502
Permit fees 8.4% (not included in sub O&P) 1 unit $33,864 $33,864
Total w/o Permits $403,138 $463,609
Lynch Meadows Elementary School
Basic Materials and Methods 1 ls $2,000 $2,000
New Gate with Ball Valves at AHU’s 12 unit $150 $1,800
New Boiler 3000 MBH 1 unit $45,000 $45,000
Boiler Kill Switches 1 unit $800 $800
Replace Victulic Piping and Add Expansion Loops 1 unit $18,000 $18,000
IDF-MDF Cooling Systems 2 unit $2,250 $4,500
EEM-2: Recommission Annex HVAC System 1 unit $104,436 $104,436
EEM-3: Replace single Pane Window Assemblies 1 unit $108,383 $108,383
Permit fees 8.4% (not included in sub O&P) 1 unit $23,933 $23,933
Total w/o Permits $284,919 $327,657
Mechanical Budget Estimate (continued)
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
10+
Mechanical Budget Estimate
ITEM AREA / SYSTEM DESCRIPTIONS QUANTITY / UNIT UNIT COST COSTWITH SUB
O & P
QTY. Type Cost / Unit Total Cost With Sub O&P 15%
Pleasant Valley Elementary School
Basic Materials and Methods 1 ls $1,000 $1,000
Replace obsolete Gordon Piatt Boiler Burners (1800 MBH) 2 unit $15,000 $30,000
Boiler Kill Switches 1 unit $800 $800
IDF-MDF Cooling Systems 2 unit $2,250 $4,500
EEM-2
EEM-3
Permit fees 8.4% (not included in sub O&P) 1 unit $3,049 $3,049
Total w/o Permits $36,300 $41,745
Oliver Elementary School
Basic Materials and Methods 1 ls $2,000 $2,000
Replace obsolete Gordon Piatt Boiler Burners 1 unit $19,000 $19,000
Boiler Kill Switches 1 unit $800 $800
Rebuild Drywells 4 unit $6,500 $26,000
DDC Upgrade 1 unit $20,000 $20,000
IDF-MDF Cooling Systems 2 unit $2,250 $4,500
Permit fees 8.4% (not included in sub O&P) 1 unit $6,073 $6,073
Total w/o Permits $72,300 $83,145
Parklane Elementary School
Basic Materials and Methods 1 ls $3,000 $3,000
Repair Roof Drains and Clamps 2 unit $1,000 $2,000
Replace obsolete Gordon Piatt Boiler Burners 1 unit $19,000 $19,000
Boiler Kill Switches 1 unit $800 $800
Replace RTU’s (3 ton, 5 ton) 2 unit $6,500 $13,000
DDC Upgrade 1 unit $20,000 $20,000
Tunnel Fan Motor and VFD 2 unit $3,000 $6,000
IDF-MDF Cooling Systems 2 unit $2,250 $4,500
EEM-2: Install Digital Controls System 1 unit $99,063 $99,063
EEM-3: Frame in 1/3 Windows and Upgrade Windows 1 unit $119,754 $119,754
EEM-4: Replace RTU’s and Add DCV 1 unit $29,250 $29,250
Permit fees 8.4% (not included in sub O&P) 1 unit $26,585 $26,585
Total w/o Permits $316,367 $363,822
Mechanical Budget Estimate (continued)
11
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
FEBRUARY, 2016
Mechanical Budget Estimate
ITEM AREA / SYSTEM DESCRIPTIONS QUANTITY / UNIT UNIT COST COSTWITH SUB
O & P
QTY. Type Cost / Unit Total Cost With Sub O&P 15%
Centennial Middle School
Basic Materials and Methods 1 ls $3,000 $3,000
Replace 80 feet of 2” Copper Domestic Water Pipe 80 lf $50 $4,000
80 feet of Pipe Insulation 80 lf $6 $480
Replace Obsolete Gordon Piatt Boiler Burners 2 unit $19,000 $38,000
Boiler Kill Switches 1 unit $800 $800
IDF-MDF Cooling Systems 3 unit $2,250 $6,750
Permit fees 8.4% (not included in sub O&P) 1 unit $4,455 $4,455
Total w/o Permits $53,030 $60,985
Centennial Park School
Basic Materials and Methods 1 ls $1,000 $1,000
New Split System Heat Pumps in Attics 2 unit $8,000 $16,000
IDF-MDF Cooling Systems 1 unit $2,250 $2,250
Permit fees 8.4% (not included in sub O&P) 1 unit $1,617 $1,617
Total w/o Permits $19,250 $22,138
Butler Creek Elementary School
Basic Materials and Methods 1 ls $500 $500
EEM-1: Optimize AHU-1 Run Time 1 unit $1,600 $1,600
EEM-2: Optimize OSA Controls for AHU-4 1 unit $1,600 $1,600
IDF-MDF Cooling Systems 1 unit $2,250 $2,250
Permit fees 8.4% (not included in sub O&P) 1 unit $500 $500
Total w/o Permits $5,950 $6,843
District Offi ce
Basic Materials and Methods 1 ls $500 $500
IDF-MDF Cooling Systems 1 unit $2,250 $2,250
Permit fees 8.4% (not included in sub O&P) 1 unit $231 $231
Total w/o Permits $2,750 $3,163
Service Center
Basic Materials and Methods 1 ls $500 $500
IDF-MDF Cooling Systems 1 unit $2,250 $2,250
Permit fees 8.4% (not included in sub O&P) 1 unit $231 $231
Total w/o Permits $2,750 $3,163
GRAND TOTAL $2,498,571
Mechanical Budget Estimate (continued)
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
12+
Mechanical Budget Estimate
Electrical Budget Estimate
ITEM AREA / SYSTEM DESCRIPTIONS QUANTITY / UNIT UNIT COST COSTWITH SUB
O & P
QTY. Type Cost / Unit Total Cost With Sub O&P 15%
Centennial High School
Basic Materials and Methods 1 ls $6,500 $6,500
CHS3 ATS Repair or Replacement 1 ls $5,000 $5,000
CHS4 MDF or IDF Exhaust Fans 10 unit $750 $7,500
Replace Reduced Press Backfl ow Preventer (3”) 1 unit $250 $250
Replace Obsolete Gordon Piatt Boiler Burners 2 unit $500 $1,000
Additional Power & Data Drops Per Classroom 1 ls $98,437 $98,437
MDF - IDF Cooling Systems 8 unit $1,250 $10,000
Total $128,687 $147,990
Centennial Middle School
Basic Materials and Methods 1 ls $1,500 $1,500
CMS2 MDF or IDF Exhaust Fans 4 unit $750 $3,000
Replace Obsolete Gordon Piatt Boiler Burners 2 unit $850 $1,700
Additional Power & Data Drops Per Classroom 1 ls $60,375 $60,375
MDF - IDF Cooling Systems 3 unit $1,250 $3,750
Total $69,775 $80,241
Centennial Park School
Basic Materials and Methods 1 ls $1,500 $1,500
CPS3 LV Demolition 15,308 sf $0.25 $3,827
CPS4 FA System 15,308 sf $1.50 $22,962
CPS6 MDF or IDF Exhaust Fans 1 unit $750 $750
Replace Obsolete Gordon Piatt Boiler Burners 1 unit $500 $500
CPS8 New Service Entrance - 800 amps 1 ls $11,250 $11,250
Additional Power & Data Drops Per Classroom 1 ls $8,750 $8,750
MDF - IDF Cooling Systems 1 unit $1,250 $1,250
Split System Heat Pumps 2 unit $850 $1,700
Total $52,489 $60,362
Butler Creek Elementary School
MDF - IDF Cooling Systems 1 unit $1,250 $1,250
Total $1,250 $1,438
13
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
FEBRUARY, 2016
Electrical Budget Estimate
ITEM AREA / SYSTEM DESCRIPTIONS QUANTITY / UNIT UNIT COST COSTWITH SUB
O & P
QTY. Type Cost / Unit Total Cost With Sub O&P 15%
Lynch Meadows Elementary School
Basic Materials and Methods 1 ls $6,800 $6,800
LM1d New Service Entrance - 800 amps 1 ls $9,800 $9,800
LM2 75 Kva Transformer 1 unit $4,000 $4,000
LM3 Panelboard 1 unit $6,000 $6,000
LM3 45 Kva Transformer 1 unit $3,500 $3,500
LM3 Panelboard 1 unit $4,500 $4,500
LM3 Xfrmr Feeder 70 lf $15 $1,050
LM4 MDF or IDF Exhaust Fans 2 unit $750 $1,500
Replace Obsolete Gordon Piatt Boiler Burners 2 unit $850 $1,700
Additional Power & Data Drops Per Classroom 1 ls $18,900 $18,900
MDF - IDF Cooling Systems 2 unit $1,250 $2,500
Total $60,250 $69,288
Lynch View Elementary School
Basic Materials and Methods 1 ls $9,580 $9,580
LV2a Panelboard 1 unit $4,500 $4,500
LV2b Panelboard 5 unit $5,000 $25,000
LV2c Panelboard 1 unit $4,500 $4,500
LV2d Panelboard 1 unit $6,000 $6,000
LV2e Kitchen Neutral 150 lf $6.50 $975
LV3 MDF or IDF Exhaust Fans 2 unit $750 $1,500
LV4 Inverter Batteries 1 unit $4,500 $4,500
Replace Obsolete Gordon Piatt Boiler Burners 2 unit $850 $1,700
Replace RTU’s (3 & 6 ton) 2 unit $1,500 $3,000
Replace Water Heaters 1 unit $500 $500
New Tunnel Fan Motors and VFD’s 2 unit $1,100 $2,200
Additional Power & Data Drops Per Classroom 1 ls $25,200 $25,200
MDF - IDF Cooling Systems 2 unit $1,250 $2,500
Total $91,655 $105,403
Electrical Budget Estimate (continued)
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
14+
Electrical Budget Estimate
Electrical Budget Estimate (continued)
ITEM AREA / SYSTEM DESCRIPTIONS QUANTITY / UNIT UNIT COST COSTWITH SUB
O & P
QTY. Type Cost / Unit Total Cost With Sub O&P 15%
Lynch Wood Elementary School
Basic Materials and Methods 1 ls $3,200 $3,200
LW2a New MDP - 800 amps 1 ls $9,800 $9,800
LW2b New Service Entrance - 1,200 amps 1 ls $14,800 - Excluded
LW3a Panelboard 1 unit $4,500 $4,500
LW3b Panelboard 5 unit $5,000 $25,000
LW3c Panelboard 1 unit $4,500 $4,500
LW3d Panelboard 1 unit $6,000 $6,000
LW3e Kitchen Neutral 150 lf $6.50 $975
LW4 MDF or IDF Exhaust Fans 2 unit $750 $1,500
LW5 Inverter Batteries 1 unit $4,500 $4,500
Replace Obsolete Gordon Piatt Boiler Burners 1 unit $850 $850
Replace RTU’s (5 ton) 2 unit $1,500 $3,000
New Tunnel Fan Motors and VFD’s 1 unit $1,100 $1,100
Additional Power & Data Drops Per Classroom 1 ls $29,400 $29,400
MDF - IDF Cooling Systems 2 unit $1,250 $2,500
Total $96,825 $111,349
Oliver Elementary School
Basic Materials and Methods 1 ls $6,500 $6,500
OE2a New MDP - 1,000 amps 1 ls $11,500 $11,500
OE2b New Service Entrance - 1,200 amps 1 ls $16,800 - Excluded
OE3a Panelboard 2 unit $4,500 $9,000
OE3b Panelboard 2 unit $4,500 $9,000
OE3c Panelboard 1 unit $5,000 $5,000
OE3d Panelboard 1 unit $6,000 $6,000
OE3e Kitchen Neutral 95 lf $6.50 $618
OE4 Panelboard 10 unit $4,500 $45,000
OE5a LV Demolition 83,458 ls $0.25 $20,865
OE6 FA System 83,458 ls $1.50 $125,187
OE8 MDF or IDF Exhaust Fans 2 unit $750 $1,500
Replace Obsolete Gordon Piatt Boiler Burners 2 unit $850 $1,700
Additional Power & Data Drops Per Classroom 1 ls $68,250 $68,250
MDF - IDF Cooling Systems 2 unit $1,250 $2,500
Total $312,619 $359,512
15
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
FEBRUARY, 2016
Electrical Budget Estimate
Electrical Budget Estimate (continued)
ITEM AREA / SYSTEM DESCRIPTIONS QUANTITY / UNIT UNIT COST COSTWITH SUB
O & P
QTY. Type Cost / Unit Total Cost With Sub O&P 15%
Parklane Elementary School
Basic Materials and Methods 1 ls $6,500 $6,500
PE2a New MDP - 800 amps 1 ls $9,800 $9,800
PE2b New Service Entrance - 1,200 amps 1 ls $14,800 - Excluded
PE3a Panelboard 1 unit $4,500 $4,500
PE3b Panelboard 5 unit $5,000 $25,000
PE3c Panelboard 1 unit $4,500 $4,500
PE3d Panelboard 1 unit $6,000 $6,000
PE3e Kitchen Neutral 150 lf $6.50 $975
PE4 MDF or IDF Exhaust Fans 2 unit $750 $1,500
PE5 Inverter Batteries 1 unit $4,500 $4,500
Replace Obsolete Gordon Piatt Boiler Burners 2 unit $850 $1,700
Replace RTU’s (5 ton) 2 unit $1,500 $3,000
Tunnel Fan Motors and VFD’s 2 unit $1,100 $2,200
Additional Power & Data Drops Per Classroom 1 ls $8,750 $8,750
MDF - IDF Cooling Systems 2 unit $1,250 $2,500
Total $81,425 $93,639
Pleasant Valley Elementary School
Basic Materials and Methods 1 ls $10,980 $10,980
PV2a New MDP - 800 amps 1 ls $9,800 $9,800
PV2b New Service Entrance 1 ls $6,500 $6,500
PV3a Panelboard 1 unit $5,000 $5,000
PV3b Panelboard 1 unit $5,000 $5,000
PV3c Panelboard 1 unit $4,500 $4,500
PV3d Panelboard 1 unit $4,500 $4,500
PV3e Panelboard 1 unit $5,000 $5,000
PV4 Rewire Old School 25,000 sf $3.15 $78,750
PV5 Demolition 25,000 sf $0.25 $6,150
PV6 MDF or IDF Exhaust Fans 2 unit $750 $1,500
Replace Obsolete Gordon Piatt Boiler Burners 2 unit $850 $1,700
MDF - IDF Cooling Systems 2 unit $1,250 $2,500
Total $141,980 $163,277
Administration Building
Basic Materials and Methods 1 ls $4,500 $4,500
AB4 New MDP - 400 amps, NEMA 3R 1 ls $11,650 $11,650
MDF - IDF Cooling Systems 1 unit $1,250 $1,250
Total $17,400 $20,010
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
16+
Electrical Budget Estimate
Electrical Budget Estimate (continued)
ITEM AREA / SYSTEM DESCRIPTIONS QUANTITY / UNIT UNIT COST COSTWITH SUB
O & P
QTY. Type Cost / Unit Total Cost With Sub O&P 15%
Service Center
Basic Materials and Methods 1 ls $500 $500
MDF - IDF Cooling Systems 1 unit $1,250 $1,250
Total $1,750 $2,013
17
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
FEBRUARY, 2016
Electrical Budget Estimate
Roofi ng Budget Estimate
SCHOOL / FACILITY AREA ROOF & INSULATION* TOTAL
Elementary Schools
Lynch View 60,000 SF @ $19.00 $1,140,000
Lynch Wood 60,000 SF @ $19.00 $1,140,000
Parklane 60,000 SF @ $19.00 $1,140,000
Pleasant Valley 60,000 SF @ $19.00 $1,140,000
Oliver Elementary 60,000 SF @ $19.00 $1,140,000
Centennial Middle School 81,000 SF @ $19.00 $1,539,000
Centennial High School 247,000 SF @ $19.00 $4.693,000
TOTAL $11,932,000
*Does not include seismic upgrades.
19
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
FEBRUARY, 2016
Roofi ng Budget Estimate
Telecom Budget Estimate
ITEM AREA / SYSTEM DESCRIPTIONS QUANTITY / UNIT UNIT COST COSTWITH SUB
O & P
QTY. Type Cost / Unit Total Cost With Sub O&P 15%
Centennial High School
Basic Materials and Methods 1 ls $2,500 $2,500
MDF Cleanup 1 ls $1,200 $1,200
IDF Cleanup 8 ls $800 $6,400
Fiber Backbone to IDF’s 8 ls $1,200 $9,600
Fiber Backbone to Maintenance 1 ls $3,000 $3,000
Fiber Backbone to Stadium 1 ls $2,200 $2,200
Fiber Backbone to Transportation 1 ls $4,000 40,000
Add 4 Cat 6 per Classroom 69 ea $510 $$35,190
Trenching (1,000’) 1,000 ft $35 $0
300 sq/ft Data Center Upgrade infrastructure only at the new MS. Excludes power, hvac, network hardware
300 sq/ft $220 $66,000
FFE - Wireless 69 ea $500 $.0.00
Total $614,590 $189,379
Centennial Middle School
Basic Material and Methods 1 ls $1,500 $1,500
CMS2 MDF Cleanup 13 ls $1,200 $1,200
IDF Cleanup 3 ea $400 $1,200
Fiber backbone to IDF 3 ea $2,200 $6,600
Fiber backbone to DO 1 ls $3,000 $3,000
Fiber backbone to LW 1 ls $2,000 $2,000
Intercom Headed Replacement 1 ea $17,000 $17,000
Add 4 Cat 6 per classroom 42 ea $510 $21,420
FFE - Wireless 42 ea $500 $21,000
Total $74,920 $86,158
Centennial Park School
Basic Material and Methods 1 ls $1,500 $1,500
MDF Cleanup 1 ls $300 $300
IDF Cleanup 0 ea $0 $0
Fiber Replacement 0 ea $0 $0
Intercom Headend Replacement 0 la $0 $0
Add 4 Cat 6 per Classroom 4 la $510 $2,040
Add Ceiling Mount Projector and Cabling 0 ea $700 $0
FFE - Projector 0 ea $700 $0
FFE - Wireless 4 ea $500 $2,000
Total $5,840 $6,716
21
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
FEBRUARY, 2016
Telecom Budget Estimate
ITEM AREA / SYSTEM DESCRIPTIONS QUANTITY / UNIT UNIT COST COSTWITH SUB
O & P
QTY. Type Cost / Unit Total Cost With Sub O&P 15%
Butler Creek Elementary School
Basic Material and Methods 1 ls $1,500 $1,500
MDF Cleanup 1 ls $600 $600
IDF Cleanup 1 ea $400 $400
Fiber Replacement 1 ea $900 $900
Intercom Headend Replacement 1 la $18,200 $18,200
Add 4 Cat 6 per Classroom 20 la $510 $10,200
FFE - Wireless 20 ea $500 $10,000
Total $41,800 $48,070
Lynch Meadows Elementary School
Basic Material and Methods 1 ls $1,500 $1,500
MDF Cleanup 1 ls $600 $600
IDF Cleanup 1 ea $400 $400
Fiber Replacement 1 ea $1,100 $1,100
Intercom Headend Replacement 1 ls $17,800 $17,800
Add 4 Cat 6 per Classroom 19 ls $510 $9,690
FFE - Wireless 19 ea $500 $9,500
Total $40,590 $46,679
Lynch View Elementary
Basic Material and Methods 1 ls $1,500 $1,500
MDF Cleanup 1 ls $500 $500
IDF Cleanup 1 ea $300 $300
Fiber Replacement 1 ea $1,100 $1,100
Intercom Headend Replacement 1 ls $17,500 $17,500
Add 4 Cat 6 per Classroom 17 ls $510 $8,670
FFE - Wireless 17 ea $500 $8,500
Total $38,070 $43,781
Lynch Wood Elementary
Basic Material and Methods 1 ls $1,500 $1,500
MDF Cleanup 1 ls $300 $300
IDF Cleanup 1 ea $400 $400
Fiber Replacement 1 ea $1,200 $1,200
Intercom Headend Replacement 1 ls $19,300 $19,300
Add 4 Cat 6 per Classroom 20 ls $510 $10,200
FFE - Wireless 20 ea $500 $10,000
Total $42,900 $49,335
Telecom Budget Estimate (continued)
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
22+
Telecom Budget Estimate
ITEM AREA / SYSTEM DESCRIPTIONS QUANTITY / UNIT UNIT COST COSTWITH SUB
O & P
QTY. Type Cost / Unit Total Cost With Sub O&P 15%
Oliver Elementary
Basic Material and Methods 1 ls $1,500 $1,500
MDF Cleanup 1 ls $400 $400
IDF Cleanup 1 ea $400 $400
Fiber Replacement 1 ea $1,300 $1,300
Intercom Headend Replacement 1 ls $14,600 $14,600
Add 4 Cat 6 per Classroom 15 ls $510 $7,650
FFE - Wireless 15 ea $500 $7,500
Total $54,350 $62,503
Parklane Elementary
Basic Material and Methods 1 ls $1,500 $1,500
MDF Cleanup 1 ls $300 $300
IDF Cleanup 1 ea $200 $200
Fiber Replacement 1 ea $1,000 $1,000
Intercom Headend Replacement 1 ls $6,750 $6,750
Add 4 Cat 6 per Classroom 16 ls $510 $8,160
FFE - Wireless 16 ea $500 $8,000
Total $25,910 $29,797
Pleasant Valley Elementary
Basic Material and Methods 1 ls $1,500 $1,500
MDF Cleanup 1 ls $300 $300
IDF Cleanup 1 ea $200 $200
Fiber Replacement 1 ea $1,250 $1,250
Intercom Headend Replacement 1 ls $14,500 $14,500
Add 4 Cat 6 per Classroom 14 ls $510 $7,140
FFE - Wireless 14 ea $500 $7,000
Total $31,890 $36,674
Administration Building
Basic Material and Methods 1 ls $1,500 $1,500
MDF Cleanup 1 ls $300 $300
Fiber Replacement 1 ea $0 $0
Intercom Headend Replacement 1 ls $0 $0
Add Wifi and Cat 6 (16 Offi ces) 20 ls $250 $5,000
FFE - Wireless 4 ea $500 $2,000
Total $8,800 $10,120
Maintenance
Basic Material and Methods 1 ls $300 $300
MDF Cleanup 1 ls $300 $300
Add Wifi and Cat 6 13 ls $350 $4,550
FFE - Wireless 3 ea $500 $1,500
Total $6,650 $7,648
Telecom Budget Estimate (continued)
23
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
FEBRUARY, 2016
Telecom Budget Estimate
ITEM AREA / SYSTEM DESCRIPTIONS QUANTITY / UNIT UNIT COST COSTWITH SUB
O & P
QTY. Type Cost / Unit Total Cost With Sub O&P 15%
Transportation
Basic Material and Methods 1 ls $300 $300
MDF Cleanup 1 ls $300 $300
Add Wifi and Cat 6 12 ls $350 $4,200
FFE - Wireless 2 ea $600 $1,000
Total $5,800 $6,670
Stadium
Basic Material and Methods 1 ls $800 $800
MDF Cleanup 1 ls $300 $300
Add Wifi and Cat 6 12 ls $550 $6,600
FFE - Wireless 6 ea $500 $3,000
Total $10,700 $12,305
SUBTOTAL TELECOM $671,899
Recommended but Not Included
UPS Large 1 ea $16,000 $16,000
UPS Mid 2 ea $7,000 $14,000
Ups Small 31 ea $2,000 $62,000
CCTV System Cabling (200 Cameras) 1 ls $60,000 $60,000
CCTV System (200 Cameras / 5 Servers) 1 ls $330,000 $330,000
Additional Exterior Paging Speakers 1 ea $160 $160
Computer Lab (40 Connections) 17 ea $16,000 $272,000
MDF / IDF AC Units (Split System) 27 ea $11,200 $302,400
TOTAL W/ RECOMMENDED $1,728,459
Materials and Methods includes mobilization, contractor PM, fuel charges, etc.MDF/IDF Cleanup includes patch cord replacement, grounding and documentation.District requests net add of +4 network cables per classroom.District requests net add of +1 network cables per classroom for wireless as noted.District fi ber backbone needs replacement as it is a network bottleneck.FFE costs for wireless access points is estimated based on standard cost model.HVAC cost is average, cost will vary based on lineset length, tonnage and location.Some jurisdictions require seismic and structural calculations for HVAC and Telecom Systems these costs are not included in this estimate.Security is Excluded based on use of Sonitrol for access / security / cctv.
Telecom Budget Estimate (continued)
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
24+
Telecom Budget Estimate
Paving Repair Budget Estimate
SCHOOL / FACILITY PLAY-GROUND
PLAY-GROUND SF PARKING
LOTPARKING
LOT SF COMMENT UNIT COST
ESTIMATEDCONSTRUCTION
COST
District Offi ce 0 191 67 12,797 Overlay $2.50 $31,993
District Offi ce 0 275 34 9,350 Overlay $2.50 $23,375
District Offi ce 0 34 75 2,550 Overlay $2.50 $6,375
District Offi ce 0 34 75 2,550 Overlay $2.50 $6,375
Subtotal $68,118
Lynch Meadows 0 35 230 8,050 Overlay $2.50 $20,125
Lynch Meadows 0 35 250 8,750 Overlay $2.50 $21,875
Lynch Meadows 0 35 145 5,075 Overlay $2.50 $12,688
Subtotal $54,688
Centennial Middle School 0 35 725 25,375 Overlay $2.50 $63,438
Centennial Middle School 227 322 73,094 Sealcoat $0.25 $18,274
Subtotal $81,711
ITC 0 94 125 11,750 Overlay $2.50 $29,375
ITC 0 35 355 12,425 Overlay $2.50 $31,063
Subtotal $60,438
Lynch View ES 0 95 200 19,000 Overlay $2.50 $47,500
Lynch Vie 0 35 200 7,000 Overlay $2.50 $17,500
Lynch View 0 35 200 7,000 Overlay $2.50 $17,500
Lynch View 0 95 150 14,250 Overlay $2.50 $35,625
Subtotal $118,125
Oliver 0 70 340 23,800 Overlay $2.50 $59,500
Oliver 0 30 120 3,600 Overlay $2.50 $9,000
Oliver 10 182 1,820 95 104 9,880 Overlay $2.50 $24,700
Oliver 12 350 4,200 0 New paving along N. Wall
of Building
$6.00 $25,200
Oliver 10 150 1,500 0 Overlay $2.50 $3,750
Oliver 40 75 3,000 0 Overlay $2.50 $7,500
Oliver 90 144 12,960 0 Overlay $2.50 $32,400
Subtotal $162,050
Parklane 127 225 28,575 0 Overlay $2.50 $71,438
Parklane 168 130 21,840 0 Overlay $2.50 $54,600
Parklane 0 406 43 17,458 Overlay $2.50 $43,645
Parklane 0 100 55 5,500 Overlay $2.50 $13,750
Subtotal $183,433
Lynch Wood 0 145 220 31,900 Overlay $2.50 $79,750
Lynch Wood 0 20 220 4,400 Overlay $2.50 $11,000
Lynch Wood 0 90 20 1,800 Overlay $2.50 $4,500
Lynch Wood 115 225 25,875 0 Overlay $2.50 $64,688
Lynch Wood 180 162 29,160 0 Overlay $2.50 $72,900
Lynch Wood 13 470 6,110 0 Overlay $2.50 $15,275
Subtotal $248,113
25
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
FEBRUARY, 2016
Paving Repair Budget Estimate
SCHOOL / FACILITY PLAY-GROUND
PLAY-GROUND SF PARKING
LOTPARKING
LOT SF COMMENT UNIT COST
ESTIMATEDCONSTRUCTION
COST
Pleasant Valley 0 178 210 37,380 Overlay $2.50 $93,450
Pleasant Valley 0 20 200 4,000 Overlay $2.50 $10,000
Pleasant Valley 0 36 42 1,512 Overlay $2.50 $3,780
Pleasant Valley 0 13 72 936 Overlay $2.50 $2,340
Pleasant Valley 0 27 245 6,615 Overlay $2.50 $16,538
Pleasant Valley 0 130 260 33,800 Overlay $2.50 $84,500
Pleasant Valley 110 125 13,750 0 Sealcoat $0.25 $3,438
Subtotal $214,045
Centennial Park School 27 245 6,615 Remove & Replace
$8.00 $52,920
Centennial Park School 130 260 33,800 Remove & Replace
$8.00 $270,400
$323,320
TOTAL $1,514,039
Paving Repair Budget Estimate (continued)
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
26+
Paving Repair Budget Estimate
AAA B
Drop Off
Centennial School District / Lynch Meadows Elementary School
0 10020Proposed Multi-Purpose Room Addition
SE 182nd Ave.
27
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
FEBRUARY, 2016
Proposed Multi-Purpose Room Additions
Centennial School District / Lynch View Elementary School
0 10020Proposed Multi-Purpose Room Addition
Possible Community Access
SE Market St.
A
B
Dro
p O
ff
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
28+
Proposed Multi-Purpose Room Additions
Possible Community Access
SE 174th Ave.
Centennial School District / Lynch Wood Elementary School
0 10020Proposed Multi-Purpose Room Addition
A
BD
rop
Off
29
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
FEBRUARY, 2016
Proposed Multi-Purpose Room Additions
SE Main St.
Centennial School District / Parklane Elementary School
0 10020Proposed Multi-Purpose Room Addition
A
B
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
30+
Proposed Multi-Purpose Room Additions
SE Main St.
Centennial School District / Centennial Park School
0 10020Proposed Multi-Purpose Room Addition
A
31
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
FEBRUARY, 2016
Proposed Multi-Purpose Room Additions
•
•
•
33
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
FEBRUARY, 2016
Appendix
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
34+
Appendix
•••••
35
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
FEBRUARY, 2016
Appendix
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
36+
Appendix
Meeting Notes Page 1 of 4
111 SW Fifth Avenue, Suite 2500, Portland, OR 97204 503.542.3860 FAX 503.274.4681
Austin, TX Eugene, OR Portland, OR When provided by KPFF, paper copies are printed on 100% Recycled Post-Consumer Fiber (PCF) paper
MEETING DATE: TIME:
June 2, 2015 11:00-12:00 AM
LOCATION: Gresham City Hall 1333 NW Eastmond Parkway
PROJECT: 315074-Centennial Middle School SUBJECT: City Coordination Meeting
ACTION ITEMS: TASK RESPONSIBLE PARTY DEADLINE Provide KPFF/DOWA with SDC credit estimates. Ken Koblitz Work with Comprehensive Planning department to determine existing IGA boundary.
Jim Wheeler
DISCUSSION TOPICS:
SDCs + Reimbursement Districts 1. The utility line extensions necessary to service the site for sanitary and water are significant. The City of
Gresham would apply SDC credits (up to a calculated amount determined by the City) for the offsite extension improvements sized above 8”.
2. These credits would apply be determined based on the entire cost of the utility installation (not just the delta above 8”) to any water or wastewater system greater than 8" in diameter. The credit would reimburse the cost incurred per the SDC methodology. Ken noted that, depending on actual construction costs, the City’s calculated cost to determine credits could likely be less than the actual construction cost.
3. In addition to the SDC’s determined for the proposed new school, additional SDC credits over and
above could be “banked” to connect another nearby school to the utility. This would require council approval, but that approval likely would not be an issue.
4. Ken said he would provide the SDC credit calculation that has been done by the City.
5. An alternate method for the district to be reimbursed the cost of public utility extension would be to
set up a reimbursement district. There are two options for reimbursement districts: Option 1: set up reimbursement district for the entire cost of the utility extension. Option 2: set up reimbursement district for the portion of the costs that aren't covered by SDC
credits.
6. A reimbursement district would collect payment from any "benefiting property" that hooks up. Who this includes would largely be defined by a basin analysis in coordination with the City. The benefiting area would be significantly larger for the sewer extension than the water extension due to required pressure zones in the water system.
37
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
FEBRUARY, 2016
Appendix
Meeting Notes Page 2 of 4 June 2, 2015
7. Existing properties are not required to connect to water until development. Sewer is a bit more stringent, but the requirement is similar (trigger is development or a failing septic system). Rick noted that CSD has had bad experiences with reimbursement districts.
8. Reimbursement district typically last for 10 years, but can be renewed.
Water System 1. Ken presented the City’s proposed alignment for bringing water service to the site (see attached figure).
This alignment has been configured to occur within established rights-of-way.
2. The water line extension presented by the City is determined from the established City of Gresham Master Plan. Point of connection would be SW 41st Street. Total extension is approximately 9,000 linear feet of 8”, 12” and 16” water lines.
3. The proposed alignment does not exactly match the Master Plan alignment is not exactly the same, but
substantially in conformance and would be acceptable to the City. Sanitary Sewer 1. Ken also presented a potential alignment for extending sewer service to the site (see attached figure).
This alignment has also been configured to occur with established rights-of-way.
2. The sewer line extension presented by the City is determined from the established City of Gresham Master Plan. Point of connection would be SE Jenne Road. Total extension is approximately 5,000 linear feet of 8”, 10” and 24” sewer lines.
Stormwater 1. There is a regional stormwater pond facility master-planned to exist on the site (exhibit attached).
Regional facilities would need to treat and detain half of the nuisance storm, which Ken thought was the 10 year event. Real estate would need to be preserved for the eventual build-out of this regional pond.
2. Offsite utility extension would not be required for stormwater, but the project would need to construct a proportional amount of the regional pond. In addition, the project would need to provide its own code-required detention and treatment facilities onsite.
3. SDC credits would also be available for any constructed portion of the regional stormwater pond.
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
38+
Appendix
Meeting Notes Page 3 of 4 June 2, 2015
Transportation 1. Required transportation system improvements would include (exhibit attached):
Traffic signal installations on SE 172nd Av at SE Foster Rd and Crystal Springs Rd. Half street improvements along SE 172nd Av (arterial). Half street improvements along Crystal Springs (standard collector). Half street improvements along Foster Road. Potential full street construction for a proposed extension of Crystal Springs Rd (standard collector).
2. There is a standard collector proposed in the master plan. It is currently shown to angle through the
south portion of the site, but there isn't an immediately obvious reason it couldn't run along the south property line. If street improvements are needed, the school district would likely need to pay for street improvements along half streets bordering the site. The exact alignment of the proposed standard collector would depend on master planning for the site.
Annexation 1. There is some uncertainty on how exactly the site will be annexed between Gresham and Portland. A
portion of the site may not be annexed by Gresham. A portion along the west end near the drainage could be annexed by Portland. The exhibits presented are based on information from 2004. There may be more recent information, Rick remembers seeing something suggesting the City of Portland would like to annex to the creek because it is in the Johnson Creek watershed.
2. Mark asked if a public utility extension could precede annexation. Ken said that properties within the UGB would typically require annexation first. This property is within the UGB.
3. Rick asked if we could annex a noncontiguous parcel. Jim said that the City could annex the parcel, plus
the contiguous right of way to connect the property to the City (“cherry stem”). All annexation would have to be approved by City council. Cherry Stem annexation is the only means available for annexing the property at the current time until the intervening properties are annexed.
4. An “expedited” annexation process can be used. There would be no hearing and no property
notification required. Master Planning 1. The site will require a master plan, which will define the location / impact of transportation planning
elements and the regional stormwater facility. Any site larger than 20 acres requires a master plan to establish these elements.
2. We will also need to eventually coordinate with the City of Portland. We need a better understanding of the IGA between Gresham and Portland to determine where and when the boundary line will be established. Any line change would require a change to the IGA, which would require approval from both councils. It would be preferable for the property to be in one jurisdiction.
3. Jim Wheeler will work with Comprehensive Planning to determine where the boundary line is defined.
39
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
FEBRUARY, 2016
Appendix
Meeting Notes Page 4 of 4 June 2, 2015
Environmental Zoning 1. A significant amount of the site, predominantly along the west and north edges, an Environmentally
Sensitive Restoration Area (ESRA). See the attached figure. The line is based on a combination of factors including wetland setbacks, drip lines, required buffers from stream cooridors, etc. We would not be allowed to do much of any development work in the zone, as it is intended to be dedicated for habitat restoration.
ATTENDEES COMPANY NAME EMAIL ADDRESS Ken Koblitz Public Works Development & Inspection Manager
City of Gresham Kenneth.Koblitz @GreshamOregon.gov
Jim Wheeler Senior Development Planner
City of Gresham Jim.Wheeler @GreshamOregon.gov
Rick Larson Director of Business & Operations
Centennial School District
rick_larson @centennial.k12.or.us
Thea Wayburn Architect
DOWA-IBI Group [email protected]
Mark Wharry Associate / Project Manager
KPFF [email protected]
Peter Craig Civil Engineer
KPFF [email protected]
ADDITIONAL DISTRIBUTION: Steve Olson, DOWA-IBI Group MINUTES PREPARED BY: Peter Craig ATTACHMENTS: water, wastewater, stormwater and transportation / zoning exhibits
These meeting notes represent KPFF’s understanding of key points of discussion. Please provide any additions or corrections within one week.
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
40+
Appendix
41
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
FEBRUARY, 2016
Appendix
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
42+
Appendix
43
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
FEBRUARY, 2016
Appendix
DOWA-IBI GROUP ARCHITECTS + CENTENNIAL SCHOOL DISTRICT LONG RANGE FACILITIES COMMITTEE PHASE I RECOMMENDATIONS - PROJECT BUDGETS
44+
Appendix