    April 16, 2018

  • Meeting Agenda Progress since Mar. 19, 2018

    Civil/Site Update

    Design Development Update

    Construction Phasing

    Schematic Estimate

    Act 34 preview

    Next Steps

  • Project ScheduleTask O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J

    School District Approval

    Schematic Design 3 MonthsDesign Development 3 Months Construction Doc's 4 1/2 MonthsQuality Control 2 weeks

    Advertising for Bidding

    Code Review / Approval 4 Weeks

    Bidding - 5 Weeks

    Board Approval - Bids / Contracts Construction - Add/Upg : 25 Months

    Sketch Plan 1 MonthZoning 2 MonthsLand Development 6 MonthsSewer 3 MonthsE&S / NPDES 6 MonthsPenn DOT 6 Months (pending scope)

    PLANCONAct 34 Hearing

    January 30, 2018

    Regulatory Process Schedule

    2017

    PDE and PLANCON Schedule

    2020 2021

    RLPS ARCHITECTS

    20192018

    Design and Overall Project Schedule

    D/E F G

    PRELIM

    12 Months New Construction + 12 Months Upgrades

    TODAY

  • Project ScheduleTask

    Design and Overall Project Sc

    School Board Approval

    Schematic Design 3 MonthsDesign Development 3 Months

    Update Site Survey

    Geotechnical Report

    Traffic Impact Study

    Sketch Plan - Land Development - 1 Month

    Zoning - 2 Months

    PA Dept. of Education

    Preliminary Building Code Review

    Educaitonal Program Devlopment

    Department Meetings`

    Community Engagement

    Site / Building Design

    Constructability Reviews

    Cost Estimates

    Committee Presentation & Update

    Schematic Approval (Board)

    ACT 34 Hearing

    PlanCon Part D&E Approval (Board)

    JULY

    2018

    Regulatory Process Schedule

    Project Schedule Notable Items

    School Board and Steering Committee - Benchmarks

    SCHEMATIC DESIGN DESIGN DEVELOPMENT

    JANUARY FEBRUARY MARCH APRIL MAY JUNE

    1

    `

    SCHEMATIC APPROVAL

    SCHEMATIC APPROVAL

    PDE CONFEREN

    1

    ACT 34 PUBLIC

    HEARING

    PENNDOTTRAFFIC IMPACT STUDY

    SCOPING MEETING

    1 1

    PLANCON D/E APPROVAL

    REQUEST SCOPING MEETING

    BEGIN TRAFFICIMPACT STUDY

    PLANCON D/E SUBMISSION

    1

    ACT 34 BOOKLET APPROVAL

    TODAY

  • Since March 19th Two days of Faculty Design

    Development Meetings

    Food Service Programing Meeting w/ Chartwells

    Asbestos Abatement coordination

    PennDOT Traffic Impact Study Scoping Meeting

    DASD Municipality Presentations

    Coordination w/ Abacus CM

  • Committee Meetings Design Development Phase

    April 16 – Design Update

    May 17 – ACT 34 Booklet Approval

    June 11 - Act 34 Hearing

    July 19 – PlanCon D&E Approval

    Construction Document Phase

    Aug./Sept. – Progress Update

    Oct./Nov. - PlanCon Part F Approval

    Bidding

    Dec. - PlanCon Part G Approval

  • Civil/Site Design PennDOT Permitting Process

    4/10/2018 – Scoping meeting w/ PennDOT and Loganville Borough Engineer

    Re-submit additional info to PennDOT – 4/20/2018

    Prepare Traffic Impact Study

    Prepare Highway Occupancy Drawings for PennDOT approval

  • Civil/Site Design Zoning Approvals

    Site plan sent to Loganville Borough Zoning Officer

    Discussion of Zoning items w/ Zoning Officer

    Zoning Officer is reviewing items w/ Borough Solicitor

    Special Exception approval is anticipated

    Submission of Special Exception Application by 4/27/2018

  • Civil/Site Design

    April 16, 2018

  • Existing: 56,861 sf

    March 19, 2017

  • Renovation: 56,861 sfNew: 33,839 sfTotal: 90,700 sf

    Demolition: 0 sf

    April 16, 2018

    Additions & Upgrades

  • Exterior Views

  • Exterior Views

  • Exterior Views

  • Exterior Views

  • Exterior Views

  • Exterior Views

  • Exterior Views

  • Additions & Upgrades

    April 16, 2018

  • Educational Program

    GENERAL BUILDING INFORMATION1 K-3 Elementary Building

    2Current Capacity: 552 Students

    3 Current Plan SF: 90,700 SF

    BUILDING AREAS

    21-Dec-17 8-Jan-18 19-Mar-18 16-Apr-18

    District Capacity Name Qty. SF Total SF

    DistrictCap. Qty. SF Total SF

    DistrictCap. Qty. SF Total SF

    DistrictCap. Qty. SF Total SF

    DistrictCap.

    Classroom20 Pre-K w/ toilet 0 0 0 022 Kindergarten w/ toilet 6 900 5,400 132 6 900 5,400 132 6 888 5,328 132 6 887 5,322 79222 First Grade 6 900 5,400 132 6 900 5,400 132 6 882 5,292 132 6 884 5,304 79224 Second Grade 6 900 5,400 144 6 900 5,400 144 6 880 5,280 144 6 884 5,304 86424 Third Grade 6 900 5,400 144 6 900 5,400 144 6 894 5,364 144 6 896 5,376 864

    Sub-total: 24 21,600 552 24 21,600 552 24 21,264 552 24 21,306 3,312

    Special Education & CollaborationSpecial Education 4 900 3,600 3 900 2,700 3 884 2,652 3 884 2,652

    Reading Support Classroom 900 0 1 900 900 1 876 876 1 876 876

    Collaborative Learning 4 900 3,600 4 900 3,600 3 905 2,715 3 890 2,670

    Occupational Therapist/P.T. 2 450 900 1 450 450 1 333 333 1 333 333

    Gifted Ed. 0 1 450 450 1 458 458 1 466 466

    Speech & Hearing Special 0 0 1 301 301 1 302 302

    Kindergarten Small Group Instruct. 1 450 450 1 450 450 1 354 354 1 354 354

    1 & 2 Grade Small Group Instruct. 2 450 900 2 450 900 2 424 848 2 430 860

    3 Grade Small Group Instuct. (S.G.I) 1 450 450 1 450 450 1 442 442 1 430 43080 Large Group Instruction* 0 1 995 995 1 1,233 1,233 1 1,242 1,242

    * Will double as stageSchool Psycologist 0 0 1 277 277 1 261 261

    I.S.T. 0 0 1 277 277 1 239 239

    Backpack & Pantry 0 0 1 626 626 1 634 634

    Music S.G.I. 0 0 0 1 152 152

    Sub-total: 14 9,900 15 10,895 17 11,392 17 11,471

  • Educational Program

    21-Dec-17 8-Jan-18 19-Mar-18 16-Apr-18

    District Capacity Name Qty. SF Total SF

    DistrictCap. Qty. SF Total SF

    DistrictCap. Qty. SF Total SF

    DistrictCap. Qty. SF Total SF

    DistrictCap.

    Shared AreasSTEAM Classroom 1 900 900 1 900 900 1 901 901 1 899 899

    Learning Commons 1 2,500 2,500 1 2,500 2,500 1 2,534 2,534 1 2,926 2,926Work Room 1 300 300 1 300 300 1 314 314 1 179 179Storage 1 150 150 1 150 150 1 183 183 1 168 168Book Room 0 0 1 230 230 1 237 237

    Art Room 1 1,000 1,000 1 1,000 1,000 1 946 946 1 924 924Art Storage 1 150 150 1 150 150 1 145 145 1 179 179Kiln Room 1 150 150 1 150 150 1 147 147 1 115 115

    Music Classroom 1 1,000 1,000 1 1,000 1,000 1 974 974 1 974 974Storage Room 1 200 200 1 200 200 1 410 410 1 251 251

    Stage 1 995 995 0 0 0200 Gymnasium 1 6,000 6,000 1 6,000 6,000 1 6,000 6,000 1 6,288 6,288

    Gym Office 0 1 200 200 1 127 127 1 175 175Gym Storage 1 500 500 1 900 900 1 518 518 1 175 175Gym Storage 0 0 1 311 311 1 518 518

    260 Cafeteria 1 3,900 3,900 1 3,900 3,900 1 3,860 3,860 1 3,308 3,308Kitchen 1 3,000 3,000 1 3,000 3,000 1 3,036 3,036 1 2,616 2,616Chair/Table Storage 1 500 500 1 500 500 1 540 540 1 658 658

    Sub-total: 15 21,245 15 20,850 17 21,176 17 20,590

  • 21-Dec-17 8-Jan-18 19-Mar-18 16-Apr-18

    District Capacity Name Qty. SF Total SF

    DistrictCap. Qty. SF Total SF

    DistrictCap. Qty. SF Total SF

    DistrictCap. Qty. SF Total SF

    DistrictCap.

    AdministrationInstructional Planning Center (IPC) 2 450 900 2 450 900 1 437 437 1 437 437Instrutional Planning Center (IPC) 1 569 569 1 569 569Teacher Dining Room 1 450 450 1 450 450 1 812 812 1 812 812P.T.O. Room 0 1 500 500 1 412 412 1 412 412In-School Suspension 1 450 450 1 100 100 See Administration 1 124 124Administration 1 3,222 3,222

    Waiting 1 200 200 1 200 200 1 299 299Receptionist 1 150 150 1 150 150 1 150 150Secretary 1 150 150 1 150 150 1 174 174Principal 1 200 200 1 200 200 1 274 274Assistant Principal 1 150 150 1 150 150 1 190 190Conference 2 300 600 2 300 600 2 255 510Work Room 1 150 150 1 150 150 1 129 129Toilet Room 2 50 100 2 50 100 2 58 116

    Guidance 1 882 882Activity Area / Waiting 1 150 150 1 150 150 1 169 169Counselor Offices 2 150 300 2 150 300 2 291 582Storage/Conference Room 1 50 50 1 50 50 1 154 154

    Nurse See AdministrationWaiting/Treatment 1 100 100 1 100 100 1 240 240Office 1 100 100 2 100 200 1 100 100Exam/Treatment Room 1 150 150 2 150 300 2 129 258Cot Room (4 cots) 1 200 200 1 200 200 1 168 168Toilet Room 1 70 70 1 50 50 1 74 74Storage Closet 1 150 150 1 100 100 1 42 42Para Professional Work Station 0 0 1 75 75

    Sub-total: 24 4,770 27 5,100 6 6,334 27 6,058

    Scheduled Area Total 57,515 58,445 60,166 59,425Grossing Factor 1.58 1.58 1.53 1.53

    Gross Square Foot 90,874 552 92,343 552 92,087 552 90,700 552Capacity Capacity Capacity* Capacity*

    Schematic Plan - Grossing Factor 1.56 1.55 1.53 1.53Schematic Plan - GROSS SF 90,000 90,400 92,087 90,700

    Educational Program

  • Educational Program - Evolution 80

    ,000

    SF

    110,

    000

    SF

    100,

    000

    SF

    90,0

    00 S

    F

    101,000 SF10-23-2017

    81,955 SFNov./Dec. 2017

    90,840 SF11-6-2017

    90,700 SF 100,000 SFPlanCon A&B

  • Educational Program - CHECK

    Dallastown Area School District - Elementary Schools

    Existing

    BUILDING BUILDING SF 10-2-17 ENROLLMENT SF PER STUDENT

    ELEMENTARY BUILDINGSDallastown ES 43,790 175 250Leader Heights ES 33,857 160 212Loganville-Springfield ES 56,561 462 122Ore Valley ES 90,057 530 170York Township 101,495 459 221

    PROPOSED PROPOSED

    NEW Loganville-Springfield ES 90,700 550 165

  • Process for Projects Seeking Reimbursement

    Act 34 of 1973

    Public Hearing

    Max. Building Construction Cost

    Design Development

    Exclusions

    1.08% Statutory Limit

    PlanCon

  • Act 34 of 1973

    Act 34 Max. Building Construction Cost

    (Adopted By Board)

    x 1.08%(Statutory Limit)

    Structure CostArch Fee

    FF&E

    Definition

  • Next Steps Design Development Phase

    May 17 – ACT 34 Booklet Approval

    June 11 - Act 34 Hearing

    July 19 – PlanCon D&E Approval

    Construction Document Phase

    Aug./Sept. – Progress Update

    Oct./Nov. - PlanCon Part F Approval

    Bidding

    Dec. - PlanCon Part G Approval

  • Project ScheduleTask O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J

    School District Approval

    Schematic Design 3 MonthsDesign Development 3 Months Construction Doc's 4 1/2 MonthsQuality Control 2 weeks

    Advertising for Bidding

    Code Review / Approval 4 Weeks

    Bidding - 5 Weeks

    Board Approval - Bids / Contracts Construction - Add/Upg : 25 Months

    Sketch Plan 1 MonthZoning 2 MonthsLand Development 6 MonthsSewer 3 MonthsE&S / NPDES 6 MonthsPenn DOT 6 Months (pending scope)

    PLANCONAct 34 Hearing

    January 30, 2018

    Regulatory Process Schedule

    2017

    PDE and PLANCON Schedule

    2020 2021

    RLPS ARCHITECTS

    20192018

    Design and Overall Project Schedule

    D/E F G

    PRELIM

    12 Months New Construction + 12 Months Upgrades

    TODAY PlanCon Part ‘G’ Limit

    Slide Number 1Slide Number 2Slide Number 3Slide Number 4Slide Number 5Slide Number 6Slide Number 7Slide Number 8Slide Number 9Slide Number 10Slide Number 11Slide Number 12Slide Number 13Slide Number 14Slide Number 15Slide Number 16Slide Number 17Slide Number 18Slide Number 19Slide Number 20Slide Number 21Slide Number 22Slide Number 23Slide Number 24Slide Number 25Slide Number 26Slide Number 27Slide Number 28