lesson learnt from transportation and lifting operation of nautica muar heavy structure
TRANSCRIPT
-
7/25/2019 Lesson Learnt From Transportation and Lifting Operation of Nautica Muar Heavy Structure
1/32
This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..
This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..
Prepared by
Muhammad Shafif bin Mohd Saleh
-
7/25/2019 Lesson Learnt From Transportation and Lifting Operation of Nautica Muar Heavy Structure
2/32
This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..
Introduction Transportation and lifting study is essential element to ensure safe
handling of properties throughout the operation
Critical lesson learnt during KMSE transportation and lifting campaignare transportation of EWT and lifting of the flare tower.
Lesson learnt will highlight the processes involved during theengineering stage and the load out/lifting operation.
-
7/25/2019 Lesson Learnt From Transportation and Lifting Operation of Nautica Muar Heavy Structure
3/32
This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..
Scope of work
Transportation of EWT module
Lifting and installation of f lare tower
-
7/25/2019 Lesson Learnt From Transportation and Lifting Operation of Nautica Muar Heavy Structure
4/32
This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..
EWT transportation The EWT transportation commence from Westport
Fabrication Yard and transported to West Port Jetty byMulti Axle Trailer.
At the West Port wharf/jetty 2 units mobile crane wasused for lifting complete with lifting gears according tolifting plans
The transport route leads from Port Klang through theStreet of Malacca towards MMHE jetty at Pasir
Gudang.
-
7/25/2019 Lesson Learnt From Transportation and Lifting Operation of Nautica Muar Heavy Structure
5/32
This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..
Cargo description
PRINCIPAL
DIMENSION
LENGTH = 9.105 MBREADTH = 8.307 MHEIGHT = 9.948 MWEIGHT = 100 TON
-
7/25/2019 Lesson Learnt From Transportation and Lifting Operation of Nautica Muar Heavy Structure
6/32
This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..
Vessel and Barge Detail Barge : MUHIBBAH B29
Year Built : 2007
Length Overall : 54.869m (180ft)
Breadth (Moulded) : 15.24m (50ft)
Depth (Moulded) : 3.048m (10ft)
Design draught : 2.86m
Deadweight : 1634.952 t
Lightship : 330.10 tons
Deck loading : 15 t/m
Tug Boat : TROPICAL EAGLE Year Built : 1987
Length Overall : 25.5m
Breadth (Moulded) : 8.1m
Depth (Moulded) : 4m
GRT : 209
NRT : 63
Flag : Singapore Class : BV
BHP : 2 x 962 KW
-
7/25/2019 Lesson Learnt From Transportation and Lifting Operation of Nautica Muar Heavy Structure
7/32
This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..
COG (option 1)
-
7/25/2019 Lesson Learnt From Transportation and Lifting Operation of Nautica Muar Heavy Structure
8/32
This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..
Barge Muhibbah B29: Arrangement
-
7/25/2019 Lesson Learnt From Transportation and Lifting Operation of Nautica Muar Heavy Structure
9/32
This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..
Advantages
1. Less piping work at MMHE
2. Transport EWT in its complete form
Disadvantages
1. High COG will reduce stability of the barge
2. Fabricate foundation for transportation not economic
-
7/25/2019 Lesson Learnt From Transportation and Lifting Operation of Nautica Muar Heavy Structure
10/32
This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..
COG (option2)
-
7/25/2019 Lesson Learnt From Transportation and Lifting Operation of Nautica Muar Heavy Structure
11/32
This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..
Barge Muhibbah B29: Arrangement
-
7/25/2019 Lesson Learnt From Transportation and Lifting Operation of Nautica Muar Heavy Structure
12/32
This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..
Advantages
1. Easy and safe handling
2. Low COG result on better stability of the barge
Disadvantages
1. Extra piping work at MMHE
-
7/25/2019 Lesson Learnt From Transportation and Lifting Operation of Nautica Muar Heavy Structure
13/32
This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..
Transportation EWTWhat was supposed to happen?
Transportation of EWT module from fabrication yard to Westportshall take 1 hour
-
7/25/2019 Lesson Learnt From Transportation and Lifting Operation of Nautica Muar Heavy Structure
14/32
This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..
What actually happen?
Transport to Westport delayed for 2 days
Cometto breakdown due to hydraulic failure
EWT width wrongly measured by transporter.
-
7/25/2019 Lesson Learnt From Transportation and Lifting Operation of Nautica Muar Heavy Structure
15/32
This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..
-
7/25/2019 Lesson Learnt From Transportation and Lifting Operation of Nautica Muar Heavy Structure
16/32
This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..
-
7/25/2019 Lesson Learnt From Transportation and Lifting Operation of Nautica Muar Heavy Structure
17/32
This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..
-
7/25/2019 Lesson Learnt From Transportation and Lifting Operation of Nautica Muar Heavy Structure
18/32
This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..
-
7/25/2019 Lesson Learnt From Transportation and Lifting Operation of Nautica Muar Heavy Structure
19/32
This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..
What can we learn from this?
1. Route survey shall be done as per actual dimension
2. Ensure transporter prepare spare parts for theirequipment along the operation.
3. Selection of fabrication yard must consider thelocation of the fabrication yard to the means oftransportation
-
7/25/2019 Lesson Learnt From Transportation and Lifting Operation of Nautica Muar Heavy Structure
20/32
This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..
Lifting flare tower
The lifting of flare tower had been executed at in frontof DD1 and DD2 area with 1 no. of Floating Crane and 1supporting crane (by MMHE).
The installation of flare tower had been executed at
quay8 with 1 no. of Floating Crane Engineering of Lift Concepts to its final installation
location.
-
7/25/2019 Lesson Learnt From Transportation and Lifting Operation of Nautica Muar Heavy Structure
21/32
This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..
Cargo description
PRINCIPAL
DIMENSION
LENGTH = 55.00 MBREADTH = 10.156MHEIGHT = 8.4M
WEIGHT = 83.32 TON
-
7/25/2019 Lesson Learnt From Transportation and Lifting Operation of Nautica Muar Heavy Structure
22/32
This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..
Crane
Crane 1 : POE Giant 6 Offshore Floating Crane, 500MTwith 70.104 m. boom length (Aux. hook).
Crane 2 : Supporting Crane (MMHE proposed use LLC
No 3 for supporting Crane)
-
7/25/2019 Lesson Learnt From Transportation and Lifting Operation of Nautica Muar Heavy Structure
23/32
This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..
-
7/25/2019 Lesson Learnt From Transportation and Lifting Operation of Nautica Muar Heavy Structure
24/32
This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..
Lifting sequence
-
7/25/2019 Lesson Learnt From Transportation and Lifting Operation of Nautica Muar Heavy Structure
25/32
This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..
-
7/25/2019 Lesson Learnt From Transportation and Lifting Operation of Nautica Muar Heavy Structure
26/32
This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..
-
7/25/2019 Lesson Learnt From Transportation and Lifting Operation of Nautica Muar Heavy Structure
27/32
This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..
-
7/25/2019 Lesson Learnt From Transportation and Lifting Operation of Nautica Muar Heavy Structure
28/32
This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..
-
7/25/2019 Lesson Learnt From Transportation and Lifting Operation of Nautica Muar Heavy Structure
29/32
This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..
Lifting of f lare towerWhat was supposed to happen?
Flare tip installed before lifting operation Flare tower padeye supposed to be install at fabrication yard Lifting from transporter barge supposed to be done in front of DD1 and
DD2 Lifting commence once flare tower arrive at MMHE
What actually happen?
Flare tip installed after lifting operation
Lifting padeye fabricated at MMHE
Initial lifting had been execute inside DD2
Lifting campaign delay for 2 weeks
-
7/25/2019 Lesson Learnt From Transportation and Lifting Operation of Nautica Muar Heavy Structure
30/32
This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..
-
7/25/2019 Lesson Learnt From Transportation and Lifting Operation of Nautica Muar Heavy Structure
31/32
This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..
What can we learn from this?
1. Install f lare tip after completion of installation of f laretower to ease lifting operation
2. Use crane that able to turn 360 to avoid space limit
3. Reduce crane radius as much as possible to maximize
crane capacity4. Ensure no additional steel work on the module after load
out from fabrication yard
5. Load out from fabrication yard shall synchronize withlifting campaign perfectly
-
7/25/2019 Lesson Learnt From Transportation and Lifting Operation of Nautica Muar Heavy Structure
32/32
This document is the property of MTC Engineering Sdn. Bhd. and shall not be either reproduced or copied in whole or in part or
communicated to any third party without the prior written consent of MTC Engineering Sdn. Bhd..
THANK YOU