LAGLEY HOUSE & DOUGLAS GARDENSBerkhamsted, Hertfordshire
CLIENT: DACORUM BOROUGH COUNCIL
VALUE: £1,750,000
CONTRACT PERIOD: 35 WEEKS
Borras were awarded the contract to carry out alterations and
refurbishments to Lagley House and Douglas Gardens which serve
as sheltered housing for the elderly.
The buildings required considerable alterations to meet new DDA
requirements and building regulations to provide up to date and
suitable accommodation for the elderly. The existing accommodation
had mostly been for single persons, but the new design restructured
the internal layout so that couples could be accommodated.
The works consisted of the strip out of all services, new heating
and plumbing installations and new electrical installations. Each flat
was also provided with a new kitchen and bathroom and a lift was
installed into each of the buildings.
Whilst Lagley House was an unoccupied building, Douglas Gardens
remained in residence throughout the works. This necessitated the
need for additional safety measures and the regular consultation
with the facility manager and client to ensure disruption was kept
to a minimum.
HEALTH