Agenda
BIM Around the World
1st Singapore BIM Roadmap 2010
2nd Singapore BIM Roadmap 2015
BIM Research and Development (R&D)
Singapore BIM Adoption & Achievements
U.S. GSA
U.S. Army
Corp of
Engineers 2008 :
Mandatory BIM
for government
projects
Statsbygg, Norway 2010: Requires IFC/BIM for new buildings
Norwegian Defence Estates Agency Is running 3 BIM pilots
Senate Properties
(property services
agency), Finland 2007: Requires IFC/BIM
in its projects and intends
to have integrated model-
based operation in future
UK 2016: Mandatory
BIM for
government
projects > £5
million
Korea 2012: Public
Procurement
Service will fully
adopt IFC-based
open BIM
Hong Kong 2014/15: Mandatory
BIM for all new HKHA
projects
MTR remodelled
existing projects for
sustainability & FM
Global Perspective
Singapore BIM Roadmap (2010)
Entrenched current 2D drafting practices
Lack of demand for BIM
Lack of ready pool of skilled BIM manpower
Additional resources needed to build up BIM
capacity and expertise
Promoting success stories
Public sector taking the lead
Removing impediments
Building BIM capability & capacity
Incentivising BIM adopters
Ch
alle
ng
es S
trate
gie
s
Singapore BIM Roadmap
Entrenched current 2D drafting practices
Lack of demand for BIM
Lack of ready pool of skilled BIM manpower
Additional resources needed to build up BIM
capacity and expertise
Promoting success stories
Public sector taking the lead
Removing impediments
Building BIM capability & capacity
Incentivising BIM adopters
Ch
alle
ng
es S
trate
gie
s
Mandatory BIM e-submission
for regulatory approval
Architecture Submissions for all new building projects > 20,000 m2
Engineering Submissions for all new building projects > 20,000 m2
All submissions for all new building projects > 5,000 m2
* Since July 2013, all projects > 20,000 m2 (67 of them) have met architectural
BIM e-submission requirements
BIM e-Submission Handholding
Monthly BIM e-Submission
Briefings for Qualified Persons
(QPs)
Step by Step Audio – Visual
Guide on BIM E-Submission
Adoption Landscape
No of firms who adopted BIM (total no of firms in green)
Panels Architectural C&S M&E Total
1 38 / 38 34 / 35 23 / 23 95 / 96
2 23 / 25 21 / 28 7 / 10 51 / 63
3 19 / 37 12 / 18 9 / 20 40 / 75
100% 97% 100% 99% 91%
76% 70%
81%
50%
68%
44% 53%
0%
25%
50%
75%
100%
Architecture C&S M&E All PSPC
Notes:
- Figures updated as of 8 Oct 2014
- Tendering limits of the above panels range from $14 million (Panel 3) to $90 million (Panel 1)
- From July 2015, consultants’ regulatory submissions in the BIM format is mandatory for new projects > 5,000m2
Public Sector Panel of Consultants
Adoption Landscape
No of firms who adopted BIM (total no of firms in orange)
Grades All Workheads
A1 73 / 89
A2 41 / 58
B1 57 / 130
B2 41 / 159
82% 71%
44%
26%
0%
25%
50%
75%
100%
All Workheads
Notes:
- Figures updated as of 8 Oct 2014
- Tendering limits of the above grades range from $14 million (B2 contractors) to unlimited (A1 contractors)
Grade A1 – B2 Contractors
Singapore BIM Roadmap
Lack of demand for BIM
Lack of ready pool of skilled BIM manpower
Promoting success stories
Public sector taking the lead
Removing impediments
Building BIM capability & capacity
Incentivising BIM adopters
Ch
alle
ng
es S
trate
gie
s
Entrenched current 2D drafting practices
Additional resources needed to build up BIM
capacity and expertise
BIM Shoot Out
Outreach and Success Stories • BIM Awards (Project & Organisation Category)
• IHLs’ Mentorship by BIM Managers • International IHLs BIM Competition • IHLs BIM Shootout • Government BIM Symposium • BIM Conference • Buildsmart Magazine • BIM@SG Website Site Visit & Presentation by
Industry Mentor
International IHLs BIM Competition
Singapore BIM Roadmap
Entrenched current 2D drafting practices
Lack of demand for BIM
Lack of ready pool of skilled BIM manpower
Promoting success stories
Public sector taking the lead
Removing impediments
Building BIM capability & capacity
Incentivising BIM adopters
Ch
alle
ng
es S
trate
gie
s
Additional resources needed to build up BIM
capacity and expertise
• To lead the development of BIM standards and supporting resources to facilitate the collaborative use of BIM;
• To advise on areas that would enable effective implementation of BIM at company, project and industry levels.
Removing Impediments
- BIM Steering Committee (2011)
Removing Impediments
- BIM Manager Forums
• Develop practical Essential BIM Guides • Address technical issues
- Singapore BIM Guide;
- Particular Conditions of Contract for BIM
Design Object Libraries
for architectural and
engineering
Key Achievements
Singapore BIM Guide and Essential BIM Guides (7)
BIM e-submission Guidelines and Software/Version-specific Template Guidelines (15)
• Revise the current BIM e-submission guides and develop new guides
Code of Practice on
BIM e-submission
BIM Guides for Land Surveying , Building
Performance Analysis, and Construction
Collaboration
Upcoming Guides
Singapore BIM Roadmap
Lack of demand for BIM
Lack of ready pool of skilled BIM manpower
Promoting success stories
Public sector taking the lead
Removing impediments
Building BIM capability & capacity
Incentivising BIM adopters
Ch
alle
ng
es S
trate
gie
s
Entrenched current 2D drafting practices
Additional resources needed to build up BIM
capacity and expertise
Building BIM Capability & Capacity
> 2,000 students trained each year
> 30 programmes from various IHLs offered BIM-related courses & workshops
> 2,000 industry professionals trained > 300 trained to become BIM Managers
> 4,500 industry professionals trained
Singapore BIM Roadmap
Entrenched current 2D drafting practices
Lack of demand for BIM
Lack of ready pool of skilled BIM manpower
Additional resources needed to build up BIM
capacity and expertise
Promoting success stories
Public sector taking the lead
Removing impediments
Building BIM capability & capacity
Incentivising BIM adopters
Ch
alle
ng
es S
trate
gie
s
Architects
Engineers
Contractors
Others
PROFILE OF FIRMS
55%
5% 17%
23%
More than 700 firms have benefited.
More than 8,000 professionals have been trained.
More than 25% average efficiency improvement gained.
Note: As of 31 MAY 15
Copyright © Building and Construction Authority
BIM 1st TRANCHE
Main
Contractor
Various Sub-contractors
Proposal for BIM Collaboration Funding
Tier 1 (Basic) : BIM Fund
Pre-Tender (Consultants only)
Post-Tender (Consultants, Main and Sub-
Contractors)
ARCH C&S M&E QS PM others
Potential
applicants
2 Stages
in a
project
OVERVIEW OF 2ND TRANCHE
ARCH C&S M&E QS PM others
Copyright © Building and Construction Authority
BEP Quality Coordinated BIM Handover BIM
Template available on
Funding website
CONTROL ELEMENTS 1
INTER-DISCIPLINE
2
INTRA-DISCIPLINE 3
2 floor elements
do not overlap
OVERVIEW OF 2ND TRANCHE (DELIVERABLES)
CONTROL ELEMENTS
Copyright © Building and Construction Authority
OVERVIEW OF 2ND TRANCHE (COORDINATED MODELS)
1
INTRA-DISCIPLINE INTER-DISCIPLINE
2 3
53,2%
69,1%
72,7%
73,4%
81,3%
82,0%
84,2%
84,9%
85,6%
12%
11%
18%
15%
21%
14%
16%
19%
22%
Carried out other automations/value-added services
Reduced overall project duration
Improved track changes process
Overall outcomes realised
Reduced errors and omissions in construction documents
Reduced reworks downstream
Improved productivity in construction documents preparation
Identified and resolved design conflict upfront
Improved visualisation/presentation
Ave. Improvements Firms
2013 Survey: Improvements Made
2011 IPE ENDORSEMENT
Entrenched in the current 2D
drafting practices
Lack of demand for BIM
Lack of ready pool of skilled BIM
manpower
Additional resources needed to build up
BIM expertise
Challenges
Promoting success stories
Public sector taking the lead
Removing impediments
Building BIM capability & capacity
Incentivising BIM adopters
Strategies 2013 IPE RECOMMENDATIONS
BIM for Facility & Asset Management
Public sector taking the lead
Accelerating Process Transformation
Building BIM capability & capacity
BIM R&D
Revised Strategies
Building BIM capability
of specialist contractors
B
Developers Consultants Main
contractors Specialist
contractors Facility
managers The 2nd BIM Roadmap
Drive BIM collaboration throughout value chain
A
New training programmes at all levels
C
BIM for Design for Manufacturing & Assembly (DfMA)
D
Research & Development F
BIM for FM &
Smart Building
E
2nd BIM Roadmap (2015 - 2020)
Focus: Virtual Design and Construction
Drive BIM collaboration throughout value chain
Building BIM capability of specialist contractors
New training programmes at all levels
A
B
C
Drive the adoption
of Virtual Design
and Construction
(VDC)
EXECUTION VIRTUAL
PLANNING CONSTRUCTION
INTENT
Drive the adoption of VDC
Promoting Virtual Design and Construction practices downstream through training, funding, guides and R&D
DESIGN INTENT
Drive the adoption of VDC
Building BIM capability of specialist contractors
Drive the adoption of VDC
• BCA Academy Continuing Education on VDC/BIM:
– BIM Series • BIM Management
• BIM Planning
• BIM Modelling (Architectural, Structural, MEP)
• BIM Parametric Modelling
– Lean Management Series • BIM for Scheduling, workflow and process management
• BIM for Cost management
• Stanford CIFE – BCA Advanced Management Programmes on VDC
Drive the adoption of VDC
FACILITIES FOR VDC TRAININGS BIM STUDIO
Create exciting and
experiential learning
through:
• Big Room Concept for
VDC integrated project
• Showcase of cutting edge
BIM technology for VDC
• Immersive 3D virtual
environment
• AR/VR Room & BIM-to-
Field
Develop BIM for DfMA Guide together with industry
practitioners
Work with local DfMA projects stakeholders to use BIM
for DfMA
BIM for Design for Manufacturing and Assembly D
EXTERNAL CLADDING
GALVANIZED STEEL
WALL ASSEMBLY WITH FIRE RATED BOARD PROTECTION
GALVANIZED STEEL
FLOOR ASSEMBLY
INTERIOR FINISHES FURNITURE FITTING-OUT SERVICES
GALVANIZED STEEL
ROOF ASSEMBLY
FACADE-ASSEMBLY
FAÇADE SCREENING FAÇADE FINISHES
WALL ASSEMBLY
Impressive BIM for DfMA entries in 2015
International Student BIM Competition
BIM for Design for Manufacturing and Assembly D
BIM for FM and Smart Buildings E
FM
GPE FM Requirements
(MOHH, PA, Statecourt, National Gallery)
Buildingsmart Essential Guide
for Owners and Facility Managers
Smart Buildings
BIM for Underground Masterplan
BCA Academy Smart Campus project
Virtual Singapore initiative
BIM R&D
• A steering committee formed to formulate BIM R&D Roadmap to address gaps in
– Firm- and project-based implementation strategy,
– BIM practice and workflow
– BIM technology
• Focus: overall construction productivity improvement
• Centres of Excellence at NTU and NUS
VDC/BIM as part of BCA’s Construction R&D Roadmap
CoE@NUS: VDC/BIM for Safety, Sustainability, and Lean Construction
CoE@NTU: VDC/BIM for Pre-caster and Underground works
Potential VDC/BIM for DfMA and Parametric Design research collaboration with SUTD
RESEARCH & DEVELOPMENT F
2013 IPE Recommendation: BIM R&D
42
NTU COE – HDB Precast Project (3 x 3)
A standard set of parametric precast BIM objects commonly used in HDB projects, associated shop drawings & schedule
Streamlines process for shop drawing production & approval
Increases number of components production with the same mold (repetition)
Reduces conflicts & rejection from site due to connection issues, as the connections can be reviewed in the model first.
NTU COE Project
CD Shelter
Façade Walls Parapet wall
3 Objects 3 Precasters 3 BIM software
NUS COE Project (ongoing) Intelligent System for Determining Productivity & Safety Index
using BIM
Intelligent Review of Design for Safety Using Safety Knowledge-Based Building Information Modelling
Singapore Key Adoption & Achievements
102 GPE projects adopted BIM
8000 professionals trained
$20 million committed to 707 firms with
average of 21.5% efficiency gain
181 projects met mandatory BIM requirements
2000 students trained before graduation