l30: methods of handling project risk

23
www.izmirekonomi.edu .tr L30: Methods of Handling Project Risk ECON 320 Engineering Economics Mahmut Ali GOKCE Industrial Systems Engineering Computer Sciences

Upload: brigid

Post on 12-Jan-2016

38 views

Category:

Documents


0 download

DESCRIPTION

L30: Methods of Handling Project Risk. ECON 320 Engineering Economics Mahmut Ali GOKCE Industrial Systems Engineering Computer Sciences. Probability Concepts for Investment Decisions. Random variable : variable that can have more than one possible value - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: L30: Methods of Handling Project Risk

www.izmirekonomi.edu.tr

L30: Methods of Handling Project Risk

ECON 320 Engineering EconomicsMahmut Ali GOKCEIndustrial Systems EngineeringComputer Sciences

Page 2: L30: Methods of Handling Project Risk

www.izmirekonomi.edu.tr

Probability Concepts for Investment Decisions Random variable: variable that

can have more than one possible value

Discrete random variables: Any random variables that take on only isolated values

Continuous random variables: any random variables can have any value in a certain interval

Probability distribution: the assessment of probability for each random event

Page 3: L30: Methods of Handling Project Risk

www.izmirekonomi.edu.tr

Expected Return/Risk Trade-off

0 10 20 30 40 50-10-20-30

Investment A

Investment B

Return (%)

Probability (%)

Page 4: L30: Methods of Handling Project Risk

www.izmirekonomi.edu.tr

Measure of Expectation

E X p xj jj

j

[ ] ( )

1

(discrete case)

(continuous case) xf(x)dx

Page 5: L30: Methods of Handling Project Risk

www.izmirekonomi.edu.tr

Expected Return Calculation

Event Return (%)

Probability Weighted

1

2

3

6%

9%

18%

0.40

0.30

0.30

2.4%

2.7%

5.4%

Expected Return

10.5%

Page 6: L30: Methods of Handling Project Risk

www.izmirekonomi.edu.tr

Measure of Variation

Var x x px jj

j

j 2 2

1

( ) ( )

x Var X

Var X p x p xj j j j 2 2( )

E X E X2 2( )

Standard Deviation

Page 7: L30: Methods of Handling Project Risk

www.izmirekonomi.edu.tr

Variance Calculation

Event Deviations Weighted Deviations

1 (6% - 10.5%)2 0.40 (6% - 10.5%)2

2 (9% - 10.5%)2 0.30 (9% - 10.5%)2

3 (18% - 10.5%)2 0.30 (18% - 10.5%)2

( 2) = 25.65

Page 8: L30: Methods of Handling Project Risk

www.izmirekonomi.edu.tr

Estimating the amount of Risk involved in an Investment Project

1. Probabilistic Cash Flow Approach

2. Risk-Adjusted Discount Rate Approach

Page 9: L30: Methods of Handling Project Risk

www.izmirekonomi.edu.tr

1. Probabilistic Cash Flow Approach

0

( )[ ( )]

(1 )

Nnn

n

E AE PW r

r

20

( )[ ( )]

(1 )

Nnn

n

V AV PW r

r

where = a risk-free discount rate,

= net cash flow in period ,

E[ ] = expected net cash flow in period

V[ ] = variance of the net cash flow in period

E[PW

n

n

n

r

A n

A n

A n

(r)] = expected net present worth of the project

V[(PW(r)] = variance of the net present worth of the project

Page 10: L30: Methods of Handling Project Risk

www.izmirekonomi.edu.tr

Example

0 2 3- -2-3

= $723-$759 $2,205

= $494

2

2 22

2 4

$1,000 $2,000[ (6%)] $2,000 $723

1.06 1.06

200 500[ (6%)] 100 243,623

1.06 1.06

[ (6%)] 243,623 $493.58

E PW

V PW

PW

Period Expected cash flow

Estimated standard deviation

0 -$2,000 100

1 1,000 200

2 2,000 500

Page 11: L30: Methods of Handling Project Risk

www.izmirekonomi.edu.tr

Present Worth Distribution

If we can assume that PW(i) is a normal distribution with mean E[PW] and variance V[PW], we can make a more precise probabilistic statement of PW for the project.

0 2 3- -2-3

= $723-$759 $2,205

= $494

0 [ ( )][ ( ) 0]

[ ( )]

7231.4648

493.58

0.0728

E PW iP PW i P Z

PW i

P Z P Z

Page 12: L30: Methods of Handling Project Risk

www.izmirekonomi.edu.tr

2. Risk-Adjusted Discount Rate Approach An alternate approach to consider the risk elements

in project evaluation is to adjust the discount rate to reflect the degree of perceived investment risk.

The most common way to do this is to add an increment to the discount rate, that is, discount the expected value of the risky cash flows at a discount rate that includes a premium for risk.

The size of risk premium naturally increases with the perceived risk of the investment

Page 13: L30: Methods of Handling Project Risk

www.izmirekonomi.edu.tr

Example

You are considering a $1 million investment promising risky cash flows with an expected value of $250,000 annually for 10 years. What is the investment’s NPW when the risk-free interest rate is 8% and management has decided to use a 6% risk premium to compensate for the uncertainty of the cash flows

Page 14: L30: Methods of Handling Project Risk

www.izmirekonomi.edu.tr

Solution

Given: initial investment = $1 million, expected annual cash flow = $250,000, N = 10 years, r = 8%, risk premium = 6%

Find: net present value and is it worth investing? First find the risk adjusted discount rate = 8% + 6%

= 14%. Then, calculate the NPW using this risk-adjusted discount rate:

PW(14%) = -$1 million + $250,000 (P/A, 14%, 10) = $304,028

Because the NPW is positive, the investment is attractive even after adjusting for risk.

Page 15: L30: Methods of Handling Project Risk

www.izmirekonomi.edu.tr

Comparing Risky Investment Projects - Comparison Rule If EA > EB and VA VB,

select A. If EA = EB and VA VB,

select A. If EA < EB and VA VB,

select B. If EA > EB and VA > VB,

Not clear.

Model Type

E (NPW)

Var (NPW)

Model 1 $1,950 747,500

Model 2 2,100 915,000

Model 3 2,100 1,190,000

Model 4 2,000 1,000,000

Model 2 vs. Model 3 Model 2 >>> Model 3Model 2 vs. Model 4 Model 2 >>> Model 4Model 2 vs. Model 1 Can’t decide

Page 16: L30: Methods of Handling Project Risk

www.izmirekonomi.edu.tr

Investment Strategies

Trade-Off between Risk and Reward Cash: the least risky with the lowest returns Debt: moderately risky with moderate returns Equities: the most risky but offering the

greatest payoff Broader diversification reduces risk Broader diversification increase expected return

Page 17: L30: Methods of Handling Project Risk

www.izmirekonomi.edu.tr

Broader Diversification Reduces Risk

Page 18: L30: Methods of Handling Project Risk

www.izmirekonomi.edu.tr

Broader Diversification Increases Return

Amount Investment Expected Return

$2,000 Buying lottery tickets -100% (?)

$2,000 Under the mattress 0%

$2,000 Term deposit (CD) 5%

$2,000 Corporate bond 10%

$2,000 Mutual fund (stocks) 15%

Page 19: L30: Methods of Handling Project Risk

www.izmirekonomi.edu.tr

Option Amount Investment Expected Return

Value in 25 years

1 $10,000 Bond 7% $54,274

$2,000 Lottery tickets -100% $0

$2,000 Mattress 0% $2,000

2 $2,000 Term deposit (CD)

5% $6,773

$2,000 Corporate bond 10% $21.669

$2,000 Mutual fund (stocks)

15% $65,838

$96,280

1

Page 20: L30: Methods of Handling Project Risk

www.izmirekonomi.edu.tr

Summary

Project risk—the possibility that an investment project will not meet our minimum requirements for acceptability and success.

Our real task is not to try to find “risk-free” projects—they don’t exist in real life. The challenge is to decide what level of risk we are willing to assume and then, having decided on your risk tolerance, to understand the implications of that choice.

Page 21: L30: Methods of Handling Project Risk

www.izmirekonomi.edu.tr

•Three of the most basic tools for assessing project risk are as follows:

1. Sensitivity analysis– a means of identifying the project variables which, when varied, have the greatest effect on project acceptability.

2. Break-even analysis– a means of identifying the value of a particular project variable that causes the project to exactly break even.

3. Scenario analysis-- means of comparing a “base –case” or expected project measurement (such as NPW) to one or more additional scenarios, such as best and worst case, to identify the extreme and most likely project outcomes.

Page 22: L30: Methods of Handling Project Risk

www.izmirekonomi.edu.tr

Sensitivity, break-even, and scenario analyses are reasonably simple to apply, but also somewhat simplistic and imprecise in cases where we must deal with multifaceted project uncertainty.

Probability concepts allow us to further refine the analysis of project risk by assigning numerical values to the likelihood that project variables will have certain values.

The end goal of a probabilistic analysis of project variables is to produce a NPW distribution.

Page 23: L30: Methods of Handling Project Risk

www.izmirekonomi.edu.tr

•From the NPW distribution, we can extract such useful information as the expected NPW value, the extent to which other NPW values vary from , or are clustered around, the expected value, (variance), and the best- and worst-case NPWs.

•All other things being equal, if the expected returns are approximately the same, choose the portfolio with the lowest expected risk (variance).