l2 project management1314(scribe)
TRANSCRIPT
-
7/30/2019 L2 Project Management1314(Scribe)
1/48
Project Management
The Project Plan
Lecture 2
1
-
7/30/2019 L2 Project Management1314(Scribe)
2/48
Learning Objectives
Understand the elements that make goodproject scope management important.
Describe the process for developing a
project scope statement using the projectcharter and preliminary scope statement.
Discuss the scope definition process and
work involved in constructing a workbreakdown structure using the analogy, top-
down, bottom-up, and mind-mapping
approaches.2
-
7/30/2019 L2 Project Management1314(Scribe)
3/48
Learning Objectives
Explain the importance of scope verificationand how it relates to scope definition and
control.
Understand the importance of scope controland approaches for preventing scope-
related problems on information technology
projects.
Describe how software can assist in project
scope management.3
-
7/30/2019 L2 Project Management1314(Scribe)
4/48
What is Project Scope management?
Scope refers to allthe work involved in creating
the products of the project and the processes
used to create them.
A deliverable is a product produced as part of a
project, such as hardware or software, planning
documents, or meeting minutes.
Project scope management includes theprocesses involved in defining and controlling
what is or is not included in a project.
4
-
7/30/2019 L2 Project Management1314(Scribe)
5/48
Project Scope Management Processes
Scope planning:Deciding how the scope will
be defined, verified, and controlled. Scope definition: Reviewing the project charter
and preliminary scope statement and adding
more information as requirements are
developed and change requests are approved.
Creating the WBS: Subdividing the major
project deliverables into smaller, more
manageable components. Scope verification: Formalising acceptance of
the project scope.
Scope control: Controlling changes to projectsco e.5
-
7/30/2019 L2 Project Management1314(Scribe)
6/48
Scope Planning and the Scope
Management Plan
The scope management plan is a document
that includes descriptions of how the team will
prepare the project scope statement, create the
WBS, verify completion of the projectdeliverables, and control requests for changes to
the project scope.
Key inputs include the project charter, preliminaryscope statement, and project management plan.
6
-
7/30/2019 L2 Project Management1314(Scribe)
7/48
Sample Project Charter
7
-
7/30/2019 L2 Project Management1314(Scribe)
8/48
Sample Project
Charter (contd)
8
-
7/30/2019 L2 Project Management1314(Scribe)
9/48
Scope Definition and the
Project Scope Statement
The preliminary scope statement, project
charter, organisational process assets,
and approved change requests provide a
basis for creating the project scope
statement.
As time progresses, the scope of aproject should become clearer and more
specific.
9
-
7/30/2019 L2 Project Management1314(Scribe)
10/48
Table 5-2. Further Defining Project
Scope
10
-
7/30/2019 L2 Project Management1314(Scribe)
11/48
Creating the Work Breakdown
Structure (WBS)
A WBS is a deliverable-oriented grouping of the
work involved in a project that defines the total
scope of the project.
A WBS is a foundation document that provides
the basis for planning and managing project
schedules, costs, resources, and changes.
Decomposition is subdividing project
deliverables into smaller pieces.
11
-
7/30/2019 L2 Project Management1314(Scribe)
12/48
Figure 5-1. Sample Intranet
WBS
Organized by Product
12
-
7/30/2019 L2 Project Management1314(Scribe)
13/48
Sample Intranet WBS
Organized by Phase
13
-
7/30/2019 L2 Project Management1314(Scribe)
14/48
Intranet WBS in Tabular Form1.0 Concept
1.1 Evaluate current systems
1.2 Define requirements
1.2.1 Define user requirements
1.2.2 Define content requirements
1.2.3 Define system requirements
1.2.4 Define server owner requirements1.3 Define specific functionality
1.4 Define risks and risk management approach
1.5 Develop project plan
1.6 Brief Web development team2.0 Web Site Design
3.0 Web Site Development
4.0 Roll Out
5.0 Support14
-
7/30/2019 L2 Project Management1314(Scribe)
15/48
Figure 5-3. Intranet WBS and Gantt
Chart in Project 2000
Project 98 file
15
http://localhost/var/www/apps/conversion/3rd%20edition/3eIM/3eslides/myslides/Fig4-7.mpphttp://localhost/var/www/apps/conversion/3rd%20edition/3eIM/3eslides/myslides/Fig4-7.mpphttp://localhost/var/www/apps/conversion/3rd%20edition/3eIM/3eslides/myslides/Fig4-7.mpp -
7/30/2019 L2 Project Management1314(Scribe)
16/48
Figure 5-4. Intranet Gantt Chart Organized
by Project Management Process Groups
16
-
7/30/2019 L2 Project Management1314(Scribe)
17/48
Table 5-4. Executing Tasks for
sample intranet WBS
17
-
7/30/2019 L2 Project Management1314(Scribe)
18/48
Approaches to Developing WBSs
Analogy approach: Review WBSs of similarprojects and tailor to your project.
Top-down approach: Start with the largest items
of the project and break them down.
Bottom-up approach: Start with the specific
tasks and roll them up.
Mind-mapping approach: Write tasks in a non-
linear, branching format and then create the WBSstructure.
18
-
7/30/2019 L2 Project Management1314(Scribe)
19/48
Figure 5-5. Sample Mind-Mapping
Approach
19
-
7/30/2019 L2 Project Management1314(Scribe)
20/48
Figure 5-6. Resulting WBS in Chart
Form
20
-
7/30/2019 L2 Project Management1314(Scribe)
21/48
The WBS Dictionary and Scope Baseline
Many WBS tasks are vague and must beexplained in more detail so people know what to
do and can estimate how long the work will take
and what it will cost.
A WBS dictionary is a document that describesdetailed information about each WBS item.
The approved project scope statement and its
WBS and WBS dictionary form the scopebaseline, which is used to measure performance
in meeting project scope goals.
21
-
7/30/2019 L2 Project Management1314(Scribe)
22/48
Scope Verification It is very difficult to create a good scope statement
and WBS for a project.
It is even more difficult to verify project scope and
minimise scope changes.
Many IT projects suffer from scope creep and poorscope verification (see What Went Wrong?).
FoxMeyer Drug filed for bankruptcy after scope creep on a
robotic warehouse.
Engineers at Grumman called a system Naziware and
refused to use it.
21st Century Insurance Group wasted a lot of time and
money on a project that could have used off-the-shelf
components. 22
-
7/30/2019 L2 Project Management1314(Scribe)
23/48
Importance of Project
Schedules Managers often cite delivering projects on time as one of
their biggest challenges.
Fifty percent of IT projects were challenged in the 2003
CHAOS study, and their average time overrun increased to
82 percent from a low of 63 percent in 2000.*
Schedule issues are the main reason for conflicts on projects,
especially during the second half of projects.
Time has the least amount of flexibility; it passes no matter
what happens on a project.
*The Standish Group, Latest Standish Group CHAOS Report Shows Project Success Rates
Have Improved by 50%, (www.standishgroup.com) (March 25, 2003).
23
-
7/30/2019 L2 Project Management1314(Scribe)
24/48
Figure 6-1. Conflict Intensity Over the
Life of a Project
0.00
0.05
0.10
0.15
0.20
0.25
0.30
0.35
0.40
Project
Formation
Early Phases Middle Phases End Phases
ConflictInten
sity
Schedules
Priorities
Manpower
Technical opinions
Procedures
Cost
Personality conflicts
Average
Total Conflict
24
-
7/30/2019 L2 Project Management1314(Scribe)
25/48
Project Time Management Processes
Activity definition:Identifying the specific activities thatthe project team members and stakeholders mustperform to produce the project deliverables.
Activity sequencing: Identifying and documenting therelationships between project activities.
Activity resource estimating:Estimating how many
resourcesa project team should use to perform projectactivities.
Activity duration estimating:Estimating the number ofwork periods that are needed to complete individualactivities. (hours, days, weeks)
Schedule development:Analyzing activity sequences,activity resource estimates, and activity durationestimates to create the project schedule.
Schedule control: Controlling and managing changes to
the project schedule. 25
-
7/30/2019 L2 Project Management1314(Scribe)
26/48
Activity Definition An activity ortask is an element of work normally found
on the WBS that has an expected duration, a cost, and
resource requirements.
Project schedules grow out of the basic documents that
initiate a project.
The project charter includes start and end dates and
budget information.
The scope statement and WBS help define what will
be done.
Activity definition involves developing a more detailed
WBS and supporting explanations to understand all the
work to be done, so you can develop realistic cost and
duration estimates.26
-
7/30/2019 L2 Project Management1314(Scribe)
27/48
Activity Lists and Attributes An activity list is a tabulation of activities to
be included on a project schedule. The listshould include:
The activity name
An activity identifier or numberA brief description of the activity
Activity attributes provide more information
about each activity, such as predecessors,successors, logical relationships, leads and
lags, resource requirements, constraints,
imposed dates, and assumptions related to
the activity. 27
-
7/30/2019 L2 Project Management1314(Scribe)
28/48
Milestones A milestone is a significant event that normally
has no duration.
It often takes several activities and a lot of work to
complete a milestone.
Milestones are useful tools for setting schedule
goals and monitoring progress.
Examples include completion and customer sign-
off on key documents and completion of specific
products. (project presentation dates etc)
28
-
7/30/2019 L2 Project Management1314(Scribe)
29/48
Activity Sequencing
Involves reviewing activities anddetermining dependencies.
A dependency orrelationship relates tothe sequencing of project activities ortasks.
You mustdetermine dependencies in orderto use critical path analysis. (Refer tonetwork diagrams for more information)
29
-
7/30/2019 L2 Project Management1314(Scribe)
30/48
Network Diagrams
Network diagrams are the preferred
technique for showing activity sequencing.
A network diagram is a schematic displayof the logical relationships among, or
sequencing of, project activities.
Two main formats are the arrow and
precedence diagramming methods.
30
-
7/30/2019 L2 Project Management1314(Scribe)
31/48
Figure 6-2. Sample Activity-on-Arrow
(AOA) Network Diagram for Project X
Note activities A,B,C can start in parallel. Activity J cant start until H, F & I complete
31
-
7/30/2019 L2 Project Management1314(Scribe)
32/48
Arrow Diagramming Method
(ADM)
Also called activity-on-arrow (AOA)
network diagram.
Activities are represented by arrows.
Nodes or circles are the starting and
ending points of activities.
Can only show finish-to-start
dependencies. 32
-
7/30/2019 L2 Project Management1314(Scribe)
33/48
Process for Creating AOA Diagrams1. Find all of the activities that start at node 1. Draw their
finish nodes and draw arrows between node 1 andthose finish nodes. Put the activity letter or name and
duration estimate on the associated arrow.
2. Continuing drawing the network diagram, working from
left to right. Look for bursts and merges. A burst occurswhen a single node is followed by two or more activities.
A merge occurs when two or more nodes precede a
single node.
3. Continue drawing the project network diagram until allactivities that have dependencies are included in the
diagram.
4. As a rule of thumb, all arrowheads should face toward
the right, and no arrows should cross in an AOA network
diagram. 33
P d Di i M th d
-
7/30/2019 L2 Project Management1314(Scribe)
34/48
Precedence Diagramming Method
(PDM)
Activities are represented by boxes.
Arrows show relationships between
activities.
More popular than ADM method and used
by project management software.
Better at showing different types of
dependencies. 34
-
7/30/2019 L2 Project Management1314(Scribe)
35/48
Figure 6-3. Task Dependency Types
35
-
7/30/2019 L2 Project Management1314(Scribe)
36/48
Sample PDM Network Diagram
Critical path 36
-
7/30/2019 L2 Project Management1314(Scribe)
37/48
Activity Resource Estimating Before estimating activity durations, you must
have a good idea of the quantity and type of
resources that will be assigned to each activity.
Consider important issues in estimating
resources:
How difficult will it be to complete specific
activities on this project?
What is the organisations history in doingsimilar activities?
Are the required resources available?
37
-
7/30/2019 L2 Project Management1314(Scribe)
38/48
Gantt Charts Gantt charts provide a standard format for
displaying project schedule information by listingproject activities and their corresponding start
and finish dates in a calendar format.
Symbols include: Black diamonds: Milestones
Thick black bars: Summary tasks
Lighter horizontal bars: Durations of tasks
Arrows: Dependencies between tasks
38
-
7/30/2019 L2 Project Management1314(Scribe)
39/48
G tt Ch t f S ft L h P j t
-
7/30/2019 L2 Project Management1314(Scribe)
40/48
Gantt Chart for Software Launch Project
40
Addi Mil t t G tt
-
7/30/2019 L2 Project Management1314(Scribe)
41/48
Adding Milestones to Gantt
Charts
Many people like to focus on meeting
milestones, especially for large projects.
Milestones emphasize important events oraccomplishments in projects. E.g. presentations
You typically create a milestone byentering tasks that have a zero duration,
or you can mark any task as a milestone.
41
-
7/30/2019 L2 Project Management1314(Scribe)
42/48
SMART Criteria
Milestones should be:
Specific
Measurable
Assignable
Realistic
Time-framed42
-
7/30/2019 L2 Project Management1314(Scribe)
43/48
Sample Tracking Gantt Chart
43
-
7/30/2019 L2 Project Management1314(Scribe)
44/48
Critical Path Method (CPM) CPM is a network diagramming technique used
to predict total project duration.
A critical path for a project is the series of
activities that determines the earl iest t imeby
which the project can be completed.
The critical path is the longest paththrough the
network diagram and has the least amount of
slack or float. Slack orfloat isthe amount of time an activity
can be delayed without delaying a succeeding
activity or the project finish date.44
-
7/30/2019 L2 Project Management1314(Scribe)
45/48
Calculating the Critical Path
Develop a good network diagram.
Add the duration estimates for all activities on
each path through the network diagram.
The longest path is the critical path.
If one or more of the activities on the critical path
takes longer than planned, the whole projectschedule will slip unless the project manager
takes corrective action.
45
Fi 6 8 D t i i th
-
7/30/2019 L2 Project Management1314(Scribe)
46/48
Figure 6-8. Determining the
Critical Path for Project X
46
-
7/30/2019 L2 Project Management1314(Scribe)
47/48
Summary
Ultimate goal is to create a realistic projectschedule that provides a basis for monitoring
project progress for the time dimension of the
project.
Creating realistic schedules and sticking to
them is a key challenge of project
management.
Important tools and techniques include WBS,Gantt charts, critical path analysis, critical
chain scheduling, and PERT analysis.
Use appropriate project management software47
-
7/30/2019 L2 Project Management1314(Scribe)
48/48
Draft Project Plan
Presentations Next week
Upload documentation by Friday 4pm to
ASM module on X-stream
Use templates on PM X-stream
Ensure MS Project used for WBS & Gantt
chart
Discuss with your ASM tutor if
requirements not clear
48