1. CATENARY AND ALIGNMENTS
Aim - to achieve proper alignment ofvarious rotors, Loading of rotor on Brg.
Deviation lead to problem high shaftvibration, high brg. Vibration, high babbittmetal temperature of bearing.
Stages of maintaining catenary- before &after pedestal grouting, during rotoralignment with brg on position.
-
7/31/2019 L-05 Critical Activities Anp-2
3/11
2. ASSEMBLY OF BEARING AT SITE
Measurement of bore dia of brg, journaldia of shaft,
Measurement of contact surfaces- toruswith pedustal, brg bottom with torus,bearing with shaft journal. (0.03 mmtightness)
Check for oil openings, cleaning ofpedustal,
-
7/31/2019 L-05 Critical Activities Anp-2
4/11
3. COUPLINGS AND ALIGNMENTS OFROTORS
Function- to connect two or more shafttogether to form a shaft assembly.
Coupling- measurement of axial run out
of coupling face, geometry of entirecoupling face i.e. concavity/convexity.
Rotor align. follow continuous deflection
curve as per drg of particular machine.Axial & Radial position of two coup. flange
Casing alignment wrt rotor alignmnt.
-
7/31/2019 L-05 Critical Activities Anp-2
5/11
3. COUPLINGS AND ALIGNMENTSOF ROTORS (cont)
Measure before coupling- coup hole dia,coup bolt dia, spigot / recess of coupling,
shaft journal diameter. - axial run out of coupling face.
- radial run out of rotor.
- Axial clearance (slip gauge), radialclearance (dial gauge) 0f two coupling.
-
7/31/2019 L-05 Critical Activities Anp-2
6/11
4. SWING CHECK
- Swing check is a measurement of radialthrow at the free end of the compltd rotor.
Swing caused due to non parallelity ofcoup face.
High swing value causes- high shaftvibration, high brg shell temperature.
Swing depends upon axial run out ofcoup face, Dia of coup, length of rotor.
-
7/31/2019 L-05 Critical Activities Anp-2
7/11
5. AXIAL CLEARANCE TEST (BUMPTEST)
Movement of shaft in +ve or ve dirctionwhile casing is fixed and radially align.
Based on bump test rading, axial positionof shaft wrt casing is to be fixed and NOTTO BE ALTERED. (i.e. Rotor Zero Position)
-
7/31/2019 L-05 Critical Activities Anp-2
8/11
6. ROLL CHECK
Measurement of minimum radial clearanceof HP, IP & LP casing by moving the
casing radially while rotor is rotated byhand.
Positioning of casing depends on top &
bottom radial clearances.
-
7/31/2019 L-05 Critical Activities Anp-2
9/11
7. HORN DROP TEST
To determine the loading of the casing on eachcorner.
Stages of horn drop test- without connecting the
piping, without connection of breach nut ofHPCV, after completion of all piping connectionto turbine casing.
This test indicat the quality of work during
assembly / welding of pipe lines with casings. Problem may cause- high vibration, failure ofbarring gear in hot / cold condition, obstructionduring expansion of machine.
-
7/31/2019 L-05 Critical Activities Anp-2
10/11
WELDING OF STEAM INLET ANDEXHAUST PIPE LINES WITH H P
AND I P CASING
Floating of piping.
Adjustment of piping hangers.
Making free joint at turbine connection.
-