KAZAKHSTAN Caspian Sea Uzbekistan Kyrgyzstan THE GIANT KASHAGAN - KASHAGAN, 80 KM SOUTH-EAST OF ATYRAU, IN THE NORTH CASPIAN SEA, IS THE LARGEST OIL FIELD DISCOVERED OVER THE LAST THIRTY YEARS WORLDWIDE AND EXTENDS OVER A SURFACE AREA OF APPROXIMATELY 75 KM BY 45 KM. ITS DEVELOPMENT REPRESENTS ONE OF THE GREATEST CHALLENGES FACED BY THE PETROLEUM INDUSTRY, GIV- EN THE DEEP, HIGH-PRESSURE RESERVOIR, THE HIGH SULFUR CONTENT, THE SHALLOW WATERS THAT FREEZE IN WINTER AND THE MARKED SHIFTS IN TEMPERATURE (FROM -30°C TO +40°C). THE POTENTIAL DAILY AVERAGE PRODUCTION AMOUNTS TO 1.2 MILLION BARRELS, WITH ESTIMATED RESERVES OF 38 BILLION BARRELS. THE KASHAGAN PROJECT CONSISTS OF TWO DEVELOPMENTS: OFFSHORE COMPLEX (ARTIFICIAL ISLANDS IN THE CASPIAN SEA) AND ONSHORE COMPLEX (BOLASHAK ON- SHORE PROCESSING FACILITY). KASHAGAN / KAZAKHSTAN ONSHORE / OFFSHORE END USER: NORTH CASPIAN OPERATING COMPANY (NCOC) / A CONSORTIUM OF: KAZMUNAIGAZ / ENI / SHELL / EXXONMOBIL / TOTAL / CNPC / INPEX

Upload: others

Post on 06-Oct-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: KASHAGAN KAZAKHSTAN ONSHORE / OFFSHORE Uzbekistan … · TEKFEN / ZAFER “The products supplied by Skema were able to meet the strict technical standards of the job. Skema’s project

KAZAKHSTAN

Caspian Sea

Uzbekistan

Kyrgyzstan

THE GIANT KASHAGAN - KASHAGAN, 80 KM SOUTH-EAST OF ATYRAU, IN THE NORTH CASPIAN SEA, IS THE LARGEST OIL FIELD

DISCOVERED OVER THE LAST THIRTY YEARS WORLDWIDE AND EXTENDS OVER A SURFACE AREA OF APPROXIMATELY 75 KM

BY 45 KM. ITS DEVELOPMENT REPRESENTS ONE OF THE GREATEST CHALLENGES FACED BY THE PETROLEUM INDUSTRY, GIV-

EN THE DEEP, HIGH-PRESSURE RESERVOIR, THE HIGH SULFUR CONTENT, THE SHALLOW WATERS THAT FREEZE IN WINTER AND

THE MARKED SHIFTS IN TEMPERATURE (FROM -30°C TO +40°C). THE POTENTIAL DAILY AVERAGE PRODUCTION AMOUNTS TO

1.2 MILLION BARRELS, WITH ESTIMATED RESERVES OF 38 BILLION BARRELS. THE KASHAGAN PROJECT CONSISTS OF TWO

DEVELOPMENTS: OFFSHORE COMPLEX (ARTIFICIAL ISLANDS IN THE CASPIAN SEA) AND ONSHORE COMPLEX (BOLASHAK ON-

SHORE PROCESSING FACILITY).

KASHAGAN / KAZAKHSTAN ONSHORE / OFFSHORE

END USER: NORTH CASPIAN OPERATING COMPANY (NCOC) / A CONSORTIUM OF: KAZMUNAIGAZ / ENI / SHELL / EXXONMOBIL / TOTAL / CNPC / INPEX

Page 2: KASHAGAN KAZAKHSTAN ONSHORE / OFFSHORE Uzbekistan … · TEKFEN / ZAFER “The products supplied by Skema were able to meet the strict technical standards of the job. Skema’s project
Page 3: KASHAGAN KAZAKHSTAN ONSHORE / OFFSHORE Uzbekistan … · TEKFEN / ZAFER “The products supplied by Skema were able to meet the strict technical standards of the job. Skema’s project

190 km2 total area of onshore operations =

the size of Amsterdam

120,000 tons

total weight of steel items and struc-

tures used = 1.5 times the weight of the

Golden Gate Bridge in San Francisco

510 km total length of pipelines = almost the dis-

tance between New York and Montreal

5,000 km total length of electric and instrumen-

tation cables = about the distance

between Almaty and Rome

50,000 m3

volume of concrete structures used

= the size of the landmark 88-floor

building of Petronas Towers in Kuala

Lumpur, Malaysia

Page 4: KASHAGAN KAZAKHSTAN ONSHORE / OFFSHORE Uzbekistan … · TEKFEN / ZAFER “The products supplied by Skema were able to meet the strict technical standards of the job. Skema’s project

MV/LVPACKAGED SUBSTA-TIONSONSHORE

Skema was in charge of the engineering,

manufacturing, testing and commis-

sioning of 9 MV/LV Packaged Substa-

tions. The Substations feed the infra-

structure utilities for the Kashagan field

and are part of the Early Works of the

Kashagan Experimental Programme.

Each Substation was equipped with:

> 10 kV Switchboards

> PMCC LV Switchgear

> Distribution boards

> Distribution transformers

> AC and DC UPS batteries

> Alarm and communication RTUs

> HVAC system

> Electrical Control System

FRAMEAGREEMENTONSHORE /OFFSHORE

Skema was awarded the frame agree-

ment for the provision of all intelligent

LV Switchgear/Intelligent Power Motor

Control Centers, RTUs, the Integrat-

ed Protection and Control System for

both offshore and onshore facilities

and LMS / DMS (onshore).

5.5 km = the total length of columns

supplied by Skema.

EPC CONTRACTORS:

ABB PS&S / AKER KVAERNER /

BATEMAN / CONSAFE - FORES

GE OIL & GAS NP / GUSTO MSC /

KAZSTROYSERVICE / LITWIN /

MSS / PUNJI LLOYD /

SAIPEM / SBM / SIEMENS

TURBOMACHINERY /

ROSETTI MARINO / RENCO -

TEKFEN / ZAFER

“The products supplied by Skema were able to meet the strict technical standards of the job. Skema’s project team showed competent technical skills and the ability to work and

support us at all stages of the project from engineering to commissioning.”

Project Electrical and Instrumentation Engineer

OFFSHORE BUILDINGS / IN COUNTRYSOLUTIONS DELIVERED

EPC Contract for 13 Offshore Utilities

Buildings for Island D.

KEY SUCCESS FACTORS:

> Maximum local content achieva-

ble for Modular Substations

> Project delivered on time and

without any punch list

> Complete project cycle managed

by internal resources: from fea-

sibility studies to the design of

structures, electrical HVAC and

safety systems, procurement, con-

struction, assembly, pre-commis-

sioning, start-up, commissioning,

load out activities and on site su-

pervision and installation

Page 5: KASHAGAN KAZAKHSTAN ONSHORE / OFFSHORE Uzbekistan … · TEKFEN / ZAFER “The products supplied by Skema were able to meet the strict technical standards of the job. Skema’s project

LOCALEQUIPMENTROOMSOFFSHORE

Skema was awarded the EPC Con-

tract for the provision of 18 Local

Equipment Rooms (LERs).

The scope of work includes the co-

ordination and monitoring of every

aspect of the project, from feasibility

studies and cost/performance opti-

mization to the design of structural,

electrical, HVAC and safety systems,

procurement, construction, assembly,

commissioning, final inspection and

supervision of on-site installation.

The LERs are pre-fabr icated

steel-structure modules, which have

the following systems installed: Me-

dium and Low Voltage Switchboards,

Transformers, Distribution Switch-

boards, UPSs and relevant Batteries,

supervision and control equipment,

HVAC with provisions for explosive/

dangerous gas injections, electrical

networks, fire-detection and fire-fight-

ing systems and telecoms equipment.

Each LER has an average length of

50 m and weight of 1000 t.

The LERs were built in Ravenna,

shipped to the Caspian Sea on barg-

es and located on artificial islands in

the Caspian Sea.

“First of all congratulations at completing barge 3 and 4

pre-commissioning. Your person-nel and the support offered to

them during their stay here was first class. All concerned were

impressed – our subcontractors, our client and all.”

Commissioning Superintendent

Page 6: KASHAGAN KAZAKHSTAN ONSHORE / OFFSHORE Uzbekistan … · TEKFEN / ZAFER “The products supplied by Skema were able to meet the strict technical standards of the job. Skema’s project

SIZE OF THE LERs

SCOPE OF WORK DIMENSIONS (m) WEIGHT (t)

COMPLEX A LER 36.3 x 15.3 x 8.3 800

DRILLING ISLAND MAIN LER 55.2 x 15.3 x 8.3 1,050

DRILLING ISLAND HVAC LER 35.9 x 11.3 x 8.3 500

PSA1 MAIN LER 48.6 x 15.3 x 8.3 1,000

PSA1 HVAC LER 42.6 x 15.3 x 8.3 800

RISER ISLAND MAIN LER 48.6 x 15.3 x 8.3 1,000

RISER ISLAND HVAC LER 24.6 x 15.3 x 8.3 500

PSA2 MAIN LER 48.6 x 15.3 x 8.3 1,000

PSA2 HVAC LER 42.6 x 15.3 x 8.3 800

PUA MAIN LER 57.5 x 15.3 x 8.3 1,150

PUA HVAC LER 43.7 x 15.3 x 8.3 850

LSA MAIN LER 42.6 x 15.3 x 8.3 800

LSA HVAC LER 42.6 x 15.3 x 8.3 800

LSA IBEEV LER 33.8 x 17.6 x 11.8 800

DRILLING ISLAND EAST MAIN LER 66.5 x 15.2 x 8.3 1,105

DRILLING ISLAND EAST HVAC LER 48.5 x 15.2 x 8.4 947

PUA EMERGENCY DIESEL GENERATOR LER 35.9 x 15.3 x 8.3 500

COMPLEX A EMERGENCY DIESEL GENERATOR LER 6.0 x 4.0 x 4.0 20

TOTAL 11,484 m2 14,422 tons

Page 7: KASHAGAN KAZAKHSTAN ONSHORE / OFFSHORE Uzbekistan … · TEKFEN / ZAFER “The products supplied by Skema were able to meet the strict technical standards of the job. Skema’s project
Page 8: KASHAGAN KAZAKHSTAN ONSHORE / OFFSHORE Uzbekistan … · TEKFEN / ZAFER “The products supplied by Skema were able to meet the strict technical standards of the job. Skema’s project

18 LERs

Offshore

9 Substations

Early Works / Onshore

10 PUBs Offshore / Built in Italy

13 PUBsOffshore / Built in Country

(Kazakhstan)

All PMCCsFrame Agreement for all LV

Switchgear /

Intelligent Power Motor Control

Centers and RTUs /

Onshore / Offshore

5.5 km The total length of columns

supplied by Skema

IPCS Onshore / Offshore

LMS/DMS Onshore

Page 9: KASHAGAN KAZAKHSTAN ONSHORE / OFFSHORE Uzbekistan … · TEKFEN / ZAFER “The products supplied by Skema were able to meet the strict technical standards of the job. Skema’s project
Page 10: KASHAGAN KAZAKHSTAN ONSHORE / OFFSHORE Uzbekistan … · TEKFEN / ZAFER “The products supplied by Skema were able to meet the strict technical standards of the job. Skema’s project

END USER: NORTH CASPIAN OPERATING COMPANY (NCOC) / A CONSORTIUM OF: KAZMUNAIGAZ / ENI / SHELL / EXXONMOBIL / TOTAL / CNPC / INPEX

“Company congratulates Contractor with the big achieve-ment of meeting the requested delivery date, and thanks

for its good work and cooperation.”

Contract Holder

SOLUTIONS DELIVERED

> 18 Local Equipment Rooms

> 9 Packaged Substations

> 23 Process Utility Buildings

> MV Switchgear (965 columns)

> Intelligent Power Motor Control Centers

(4,874 columns, 7,054 drawers)

> 476 Remote Terminal Units

> Distribution boards (506 columns)

> Integrated Protection and Control System (IPCS)

> LMS/DMS

THE QUALITY OF THE POST-SALES SERVICE AND MAINTENANCE OPERATIONS IS ALSO PROVIDED AND ENSURED BY SKEMA LLP (SKEMA’S IN COUNTRY COMPANY). THROUGH SKEMA LLP, SKEMA CAN PROVIDE LOCAL ASSEMBLY, WAREHOUSE STORAGE, AFTER SALES SERVICES, TECHNICAL CONSULTANCY, TRAINING PROGRAMS AND CUSTOMER SERVICE.