june 10, 2008 tptf early delivery systems status daryl cote, steve white, & ken mcintyre
TRANSCRIPT
June 10, 2008
TPTF
Early Delivery SystemsStatus
Daryl Cote, Steve White, & Ken McIntyre
2TPTF6/10/2008 2
Agenda
• EDS SLA• EDS 2
– Release 3: Telemetry & State Estimator– Release 4: NOMCR
• EDS 3– Release 5: SCED– Release 6: LFC– Release 7: CRR
• EDS 4– Release 8: COMS– Release 9: DAM / RUC / SASM
3TPTF6/10/2008 3
EDS SLA Metrics (April ‘08)
SCED availability increase 10% from the previous month, ongoing issues with MMS 3
4TPTF6/10/2008 4
EDS SLA Metrics (May ‘08)
SCED availability decreased 5% from the previous month due to combined cycle configuration number issue
5TPTF6/10/2008 5
Significant Environment Outage – Month of May ‘08
• Market Information System (MIS) / Market Manager– Total Outage Time – 10 hours– Primary Issues
• Application process hung, Out of memory fault, Deployment (release) issues• Market Management System (MMS)
– Total Outage Time – 3.5 hours– Primary Issues
• Application server process hung (JBOSS)– Outage time significantly reduced from monitoring– MMS 4 should resolve this issue
• Database table locking from clean-up / purge jobs• LMP’s
– Total “Outage” Time – 20 hours– Note: LMP “Outage” includes time where LMP’s were compromised due to ERCOT system
issues. This does not include LMP issues due to MP’s input data (e.g. ICCP, Energy Offer Curves, etc) unless that data caused an unhandled fault in SCED.
– Primary Issues• LMP’s not updating to MIS / Public Reports• Bad telemetry data from MP causes SCED to fail
– HSL < LSL while EOC does cover the full sustainable capacity of resource causes SCED to fail
– To be resolved in MMS4• Transformer constraint causes SCED to fail
– EMS MMS view required update after EMS release– Resolved after occurrence
6TPTF6/10/2008 6
ICCP Servers Update
• Austin ICCP Servers– Production Servers Upgraded
• Taylor Production Servers – ICCP Associations In Progress– 15 of 23 QSE Associations Completed– 6 of 25 TSP Associations Completed
• ICCP High Availability
7TPTF6/10/2008 7
Wind Telemetry
Wind Telemetry• 54 Wind Units• ICCP Telemetry Available for all Units
• Direction, Speed, Barometric Pressure, Temperature
• Telemetry Accuracy• Incorrect Values
• Telemetry Data Quality• Good, Remote Replaced
• Good, Remote Suspect
Contacting QSE’s
8TPTF6/10/2008 8
Wind Telemetry
• MMS UI Feedback– Concerned about the amount of work needed to view/update
COPs, etc. for multiple resources. Current UI allows user to view multiple days for one unit, not multiple units for one day
– Concerned about the way error and confirmation messages display (not implemented yet)
– Concerned about raw .xml displaying on the Awards tab (not implemented yet)
9TPTF6/10/2008 9
Wind Telemetry
10TPTF6/10/2008 10
QSE Telemetry
11TPTF6/10/2008 11
TSP Telemetry
12TPTF6/10/2008 12
TSP Dashboard
Observability Status Dashboard
Initi
al N
umber
of U
nobserv
able
buse
s
with lo
ad a
s of N
ovem
ber 2
007
Remai
ning N
umber
of U
nobserv
able
buses
with lo
ad a
s of J
une 20
08
Number
of u
nobserv
able
buse
s with
a
PUN invo
lved
as
of June
2008
ONCOR 132 9 1
AEP/CPL 105 49 2
TNMP 20 0 0
STEC 15 0 0
RCEC-Rayburn Country Electric 13 12 0
LCRA 14 0 0
PUB 11 0 0
CNP 11 7 7
BEPC 10 0 0
AEN 0 0 0
COD-City of Denton 0 0 0
COG-City of Garland 0 0 0
CPS 0 0 0
MVEC 0 0 0
BTU 0 0 0
CSTX City of College Station 0 0 0
GEUS-Greenville 0 0 0
MEC 0 0 0
TMPA 0 0 0
Total Points 331 77 10
13TPTF6/10/2008 13
Convergence Rate April 08
SE Statistics April 08
0.0
20.0
40.0
60.0
80.0
100.0
120.0
1-Apr
2-Apr
3-Apr
4-Apr
5-Apr
6-Apr
7-Apr
8-Apr
9-Apr
10-A
pr
11-A
pr
12-A
pr
13-A
pr
14-A
pr
15-A
pr
16-A
pr
17-A
pr
18-A
pr
19-A
pr
20-A
pr
21-A
pr
22-A
pr
23-A
pr
24-A
pr
25-A
pr
26-A
pr
27-A
pr
28-A
pr
29-A
pr
30-A
pr
Date
Co
nve
rgen
ce
14TPTF6/10/2008 14
Convergence Rate May 08
SE Statistics May 08
0.0
20.0
40.0
60.0
80.0
100.0
120.0
1-M
ay
2-M
ay
3-M
ay
4-M
ay
5-M
ay
6-M
ay
7-M
ay
8-M
ay
9-M
ay
10-M
ay
11-M
ay
12-M
ay
13-M
ay
14-M
ay
15-M
ay
16-M
ay
17-M
ay
18-M
ay
19-M
ay
20-M
ay
21-M
ay
22-M
ay
23-M
ay
24-M
ay
25-M
ay
26-M
ay
27-M
ay
28-M
ay
29-M
ay
30-M
ay
31-M
ay
Date
Co
nve
rgen
ce
15TPTF6/10/2008 15
Convergence Rate – June (to date)
SE Statistics June 08
0.0
20.0
40.0
60.0
80.0
100.0
120.0
Date
Co
nve
rgen
ce
16TPTF6/10/2008 16
Convergence Rate – June (to date)
SE Mismatch Statistics April- May- 6th June 08
0.0
10.0
20.0
30.0
40.0
50.0
60.0
1-Apr
6-Apr
11-A
pr
16-A
pr
21-A
pr
26-A
pr
1-M
ay
6-M
ay
11-M
ay
16-M
ay
21-M
ay
26-M
ay
31-M
ay5-
Jun
10-J
un
15-J
un
20-J
un
25-J
un
30-J
un
Date
MW
/ M
var
Mis
mat
ch
Daily MW average
Daily MW deviation
Daily Mvar average
Daily Mvar deviation
17TPTF6/10/2008 17
Follow-up from last TPTF: Status of EDW Reports to Support SE and Telemetry Standards
• Expect delivery by end of June:– EDW - State Estimator Convergence Rate DRAFT v0.01
• Working to validate a month of data for:– EDW - MW Residuals vs. Telemetry for Congested Transmission
Elements DRAFT v0.01 & – EDW - MW Residuals vs. Telemetry for Major Transmission Elements
DRAFT v0.01 – EDW - MW Residuals vs. RTCA Base Case Congested Transmission
Elements DRAFT v0.01 – EDW - Voltage Residuals vs. Telemetry for Critical Buses DRAFT v0.01
• Defining validation Approach for:– EDW - electrical buses Not Meeting Telemetry Standards DRAFT v0.01
• EDW environment was down last week for infrastructure maintenance
• Developed real-time ICCP link display to monitor status• Developed real-time reports to identify data issues
18TPTF6/10/2008 18
Release 4 – NMMS / NOMCR
2007 2008Sep Oct Nov Dec Jan Feb
R4: NOMCR / Network Model verificationE2 R4NOMCR Checkout Network Model Verification
Onsite NMMS training and scripted scenario execution completed by all Market Participants on May 21, 08
Single Entry Point Go-Live Procedures communicated last week NDSWG comments gathered by 6/9/08 Present results to ROS on 6/12/08 TPTF comments 6/13/08 Comments closed 6/20/08 TPTF vote 7/7 – 7/8
Model On Demand & Mod Web training for Planners is targeted for mid July On going support & on line training including reference materials and users guide on how to
use the system, create and maintain projects, and change requests were distributed to the market participants and posted on line at http://nodal.ercot.com/readiness/eds2/documents/index.html
A narrated web-based version of the NMMS course and training material are now available on
line at: http://nodal.ercot.com/training/courses/nc09.html#materials
19TPTF6/10/2008 19
Release 5 - SCED
2007 2008
SCED R5.1 SCED R5.3: RT ICCP SCED R5.4: LMP Post
Sep Oct Nov Dec Jan Feb
SCED R5.2E3 R56-month LMP PostingRT ICCP
EDS 3 Release 5 Exit Criteria % Complete
Comments
Daily submissions of COP, TPO, and OS ~90% •Expect large payload support in August•Daily submission for may provided on following slides
SCED Inputs verified: HRL, LRL, SURAMP, SDRAMP, HDL, LDL; GTBD, ICCP
100%(90%)
Results from first three pre-6.3 test provided to QSEsResults for June 5th to be provided to QSEs
SCED Outputs verified: QSE’s ability to receive Resource Base Points and LMPs via ICCP
100%(90%)
Base Point and LMP calculation verified for Resources with Offer Curves or Output Schedules
100%(100%)
Reports 100%(100%)
LMPs verified for Reasonability and posted to MIS for Market Participant review 100%
(100%)
Legend: % in parentheses are from the 5/7 TPTF update
20TPTF6/10/2008 20
Submission Metrics – Month of May ‘08
COPTPOIDO OS COP
TPOIDO OS COP
TPOIDO OS COP
TPOIDO OS COP
TPOIDO OS
76% 75% 8 78% 85% 10 84% 81% 8 84% 84% 8 89% 89% 13
100% 86% 10 89% 100% 17 89% 88% 11 86% 85% 5 85% 83% 10
67% 63% 10 88% 84% 15 89% 83% 10 88% 88% 12 89% 88% 16
91% 87% 16 83% 78% 13 83% 80% 15 86% 80% 20 90% 86% 19
95% 90% 18 90% 90% 18 94% 92% 17 83% 86% 17 89% 86% 6
81% 78% 12 81% 80% 17 85% 83% 13 90% 89% 5 85% 82% 18
87% 83% 18
5/28/2008
5/23/2008
5/18/2008
5/13/2008
5/21/2008
5/20/20085/19/2008
5/31/2008
5/30/2008
5/8/2008
5/29/20085/26/2008 5/27/2008
5/22/2008 5/24/2008 5/25/2008
5/17/2008
5/14/2008 5/15/2008
5/16/2008
5/10/2008
5/11/2008 5/12/2008
5/5/2008
5/6/2008 5/7/2008 5/9/2008
5/1/2008 5/2/2008 5/3/2008 5/4/2008
21TPTF6/10/2008 21
Release 6 - LFC
2008Jan Feb Mar Apr May Jun
E3 R6 R6.1: RLC & ACE
EDS 3 Release 6.2 Criteria % Complete
Comments
Pre-Test & Test Times Scheduled 100%(100%)
Submit Units for Testing 100%(74%)
Provide Ramp Rate Curves and 5 Minute BPS 100%(28%)
Prove ability to receive Nodal Instructions 100%(28%)
Ability to receive Nodal & Zonal instruction Simultaneously 100%(28%)
Pre-Test Complete 100%(28%)
R6.2: QSE Testing R6.3: TST
Legend: % in parentheses are from the 5/7 TPTF update
Over 40 units participated in testing 22 test sessions had to be rescheduled due to failed test attempts or other delays 14 additional test sessions were conducted to handle additional tests (JOUs, re-tests) The test team averaged over 11 test sessions a week for the last 3 weeks of May to meet the test
completion milestone (original plan had 6 scheduled).
22TPTF6/10/2008 22
Telemetry Availability vs Mismatch and Convergence
-60
-50
-40
-30
-20
-10
0
10
20
30
40
MW
/Mvar
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
%
Max MW Max MVAR Telem Avail % SE %
6/5 6am-Noon
23TPTF6/10/2008 23
Nodal SE Convergence: 6/5
Solution Convergence %
65.00%
70.00%
75.00%
80.00%
85.00%
90.00%
95.00%
100.00%
6/5 7am: Bad Transformer SCADA at Nueces_B Station 6/5 8am: Lost 4453 Analog measurements & 8144 status measurements & Incorrect
breaker status at station HOC 6/5 9am: Lost 4453 Analog measurements & 8144 status measurements 6/5 10am: loss in data caused N_Sharpe Phase Shifter tap to incorrectly estimate causing
mismatches.
6/5 6am-Noon
24TPTF6/10/2008 24
Limits during test period 6/5, 7am – 11am
GTBD within 500-1000MW of HDL (most units deployed as high as possible)
10000 MW
15000 MW
20000 MW
25000 MW
30000 MW
35000 MW
40000 MW
45000 MW
50000 MW
55000 MW
60000 MW
SUM_HEL
SUM_HSL
SUM_HASL
SUM_HDL
SUM_LDL
SUM_LASL
SUM_LSL
SUM_LEL
GTBD
25TPTF6/10/2008 25
Reference LMPs Vs GTBD (6/5)
Compensating for Resources “invisible” to SCED by 7:20 brought LMPs off cap Flat spots from 8:15-8:50 and 10:30-10:45 due to 300-500MW of flat EOC on marginal units Jumps from 9:30-10:00 due to switching between two groups of marginal units as dispatch limits are
reached. Changes in all Resource HDLs/LDLs and Output Schedules as well as GTBD affect the selection of marginal units
34000 MW
36000 MW
38000 MW
40000 MW
42000 MW
44000 MW
46000 MW
48000 MW
$60.00
$70.00
$80.00
$90.00
$100.00
$110.00
$120.00
GTBD REFERENCE_LMP
26TPTF6/10/2008 26
Reference LMPs Vs MCPE (6/5)
Reference LMP comparable to MCPE LMPs in west zone were lower than reference LMP Nodal LMP indicative of submitted TPOs – very good
-$40.00
-$20.00
$0.00
$20.00
$40.00
$60.00
$80.00
$100.00
$120.00
$140.00
34000 MW
36000 MW
38000 MW
40000 MW
42000 MW
44000 MW
46000 MW
48000 MW
H N S W LMP GTBD
27TPTF6/10/2008 27
Upcoming Events to support the 2-Hour Total System Test
WebEx on June 11th to discuss logistics of test http://www.ercot.com/calendar/2008/06/20080611-EDS3-6
Next RARF load will be on June 17th for RARFs submitted by COB on June 12th Market notice forth coming
Final pre-6.3 LFC test (a.k.a open loop test) will be on June 19th from 9am-1pm central Market notice forth coming
28TPTF6/10/2008 28
EDS 3 Release 7 - CRR
EDS 3 Release 7 Status % Complete Comments
Release 7.1 Connectivity and Submissions 100%(0%)
59 participants successfully completed UI testing (97% participation)
* completion of R7.1 qualifies MP for production cert
Release 7.2 Scripted Monthly Auction 100%(0%)
No Change
Release 7.3 unscripted Monthly Auction 100%(0%)
No Change
Release 7.4 Unscripted Annual Allocation/Auction
83%(0%)
9 participants successfully submitted PCRR nominations (82% participation)
46 participants successfully submitted bids (75% participation)
83% done as of noon 6/9/08. Should be complete by noon 6/10/08
Jan 08 Feb 08 Mar 08 Apr 08 May 08Dec 07
CRR – R7.0 CRR – R7.1 CRR – R7.2 CRR – R7.3 CRR R7.4 CRR – R7.5 (TBD)
Jan 08 Feb 08 Mar 08 Apr 08 May 08Dec 07 Jan 08 Feb 08 Mar 08 Apr 08 May 08Dec 07
CRR – R7.0 CRR – R7.1 CRR – R7.2 CRR – R7.3 CRR – R7.5 (TBD)
R7.4 exit delayed by 26 business days (to 6/10/08) due to issues clearing annual auction: Data and system environment / application tuning
Legend: % in parentheses are from the 5/7 TPTF update
29TPTF6/10/2008 29
EDS 4 - Release 8
• Posted Mock RTM Statements and Invoices to Readiness Center (5/29/08)http://nodal.ercot.com/readiness/reports/si/kd/mock_rtm_settlement_examples.zip
• Release 7.4 CRR Auction Invoices posted to MIS Certified Area by 6/13/08 (first 12 months only)
30TPTF6/10/2008 30
EDS 4 Release 9.1
2008Jan Feb Mar Apr May Jun
E4 R9 R9.1: DAM/RUC Submission Testing R9.3: R9.4: DAM/ Adj Period, RT
R9.2: Outage Scheduler
Legend: % in parentheses are from the 5/7 TPTF update
EDS 4 Release 9.1 Exit Criteria % Complete
Comments
Sign-Up Testing Window Scheduled 94%(86%)
The following need to schedule test windows:
Ambridge Energy, Aquila, Citadel Energy Products, Clearview Electric, Glacial Energy , Kansas City Power and Light, National Power Company, Sitara Energy, Texpo Power, Urban Energy Source, WCW
International Working with New QSEs, Resource Movements, etc. as needed
MP8 - QSE Ability to Submit Transactions Via MIS
94%(86%)
MP9 – QSE Ability to Submit Web Service Transactions
100%(100%)
Of those who indicated desire to use Web Services
31TPTF6/10/2008 31
EDS 4 Release 9.2
2008Jan Feb Mar Apr May Jun
E4 R9 R9.1: DAM/RUC Submission Testing R9.3: R9.4: DAM/ Adj Period, RT
R9.2: Outage Scheduler
Legend: % in parentheses are from the 5/7 TPTF update
EDS 4 Release 9.2 Exit Criteria % Complete
Comments
Test Window Scheduled 100%(83%)
Completed Scripted Testing 67%(0%)
12 MPs to complete this week leaving only 3 more
9.2.2 testing extended until 6/30
Group and Opportunity Outages (6/30)
Summary Screen Enhancements (7/14)
Custom Filtering
Enter Actual Start/End
Warnings (7/14)
Copy/Print/Export, Enhanced Validation (7/31)
Participate in Performance testing 0% Start of 9.2.3 testing effort moved to July 1
Participate in Dual Entry days (prior to 168hr test)
0%
32TPTF6/10/2008 32
EDS 4 Release 9.3
2008Jan Feb Mar Apr May Jun
E4 R9 R9.1: DAM/RUC Submission Testing R9.3: R9.4: DAM/ Adj Period, RT
ERCOT has executed during April and May:
13 DAMs (constrained and unconstrained, last two without guardrails/scripting)
2 SASMs, 6 DRUCs, 2 HRUCs
QSE participation level excellent overall
ERCOT is suspending DAM execution in existing software environment; will maintain and support the existing EDS environment to allow for QSE market submissions and testing
Suspension will allow focus on expediting migration to MMS4 for EDS, address missing integration to achieve a more realistic DAM/RUC, QSE/ERCOT to focus on EIP testing and delivery
Exit criteria for release 9.3 have not completed
33TPTF6/10/2008 33
EDS Deliverables
168-Hr Test DST
Post for TPTF Comment
June 3 June 12
Comment Close June 11 June 19
TPTF Vote June 23-25 July 7-8
Texas Nodal Market Go-Live Procedure approved by TAC on June 5th
Nodal Transition Outage Management Plan Rescinded by TAC on June 5th Will revisits the plan when a revised TNMID is published
Legend: indicates completion