john taylor - cogeneration framework for south africa...why cogeneration –the bigger picture...
TRANSCRIPT
May 2007FIELDSTONEAFRICA (PTY) LIMITED
Cogeneration Guidelines and
Framework for South Africa
Introduction to FieldstoneIntroduction to Fieldstone
CLIENTS
SERVICES INDUSTRY FOCUS
New York
London
Johannesburg
HyderabadM&APrivatisations
Capital raising Project finance
Debt restructuringStrategic financial advice
RenewablesInfrastructure Merchant plantUtility networksEmission creditsContracted plantEnergy retailing
DevelopersCorporates
GovernmentsFinancial investorsManagement teams
Independent directors/boards
Berlin
CLIENTS
SERVICES INDUSTRY FOCUS
New York
London
Johannesburg
HyderabadM&APrivatisations
Capital raising Project finance
Debt restructuringStrategic financial advice
RenewablesInfrastructure Merchant plantUtility networksEmission creditsContracted plantEnergy retailing
DevelopersCorporates
GovernmentsFinancial investorsManagement teams
Independent directors/boards
Berlin
IELDSTONE IS AN
INTERNATIONAL
INVESTMENT BANKING
FIRM
FOCUSED ON
ENERGY AND
INFRASTRUCTURE
Background Background to Cogeneration Framework and Guidelinesto Cogeneration Framework and Guidelines
Key driver:
need for energy savings
and new capacity
Key driver:
need for energy savings
and new capacity
Identified possible
contribution from
industrial electricity
consumers
Identified possible
contribution from
industrial electricity
consumers
LimitationsLimitations
Regulatory responseRegulatory response
• Looming capacity shortages - understood need from Nersa to
support measures which encourage energy saving or efficient
development of new capacity
• Looming capacity shortages - understood need from Nersa to
support measures which encourage energy saving or efficient
development of new capacity
• Unsolicited approaches from industry to Nersa and Eskom to
develop onsite, decentralized generation
• Unsolicited approaches from industry to Nersa and Eskom to
develop onsite, decentralized generation
• Need for clearly defined process to create enabling environment
– licensing and contracts
• Need for rational pricing of electrical output
• Need for clearly defined process to create enabling environment
– licensing and contracts
• Need for rational pricing of electrical output
• Nersa decision to develop guidelines and regulatory framework
to encourage development of the cogeneration sector
• Fieldstone engaged to assist in development of guidelines –
production of report following extensive consultation with
• Nersa decision to develop guidelines and regulatory framework
to encourage development of the cogeneration sector
• Fieldstone engaged to assist in development of guidelines –
production of report following extensive consultation with
industry, Nersa and Eskom
Cogeneration Guidelines Cogeneration Guidelines –– WhatWhat’’s Covered?s Covered?
Why cogeneration: benefits / need for support
What should be done to support Co-gen?
Long-term vs short-term objectives
Why Cogeneration Why Cogeneration –– DefinitionDefinition
What do we mean by cogeneration
Literature provide numerous sometimes contradictory definitions
Principle driven definition (rather than technology) chosen for Guidelines
Decentralized, non-
centrally dispatched
generation
2. and at least one of
Waste or certain
renewables based fuel
source for generation
Use of heat from
generation in industrial
process (CHP)
or
1. Primary definition
Why Cogeneration Why Cogeneration -- Principal ApplicationsPrincipal Applications
Industrial sites
District Heating/Cooling
Energy Efficient Building
Agri-industry
Why Cogeneration Why Cogeneration –– Possible BenefitsPossible Benefits
Use less fuel per unit of utilised energy product increased productivity
Decentralisation of energy production -Ease transmission grid congestionDefer transmission investment Avoid electrical lossesImproved reliability given location close to source of demand and ability to tailor output
Energy Efficiency
• Reduced Greenhouse gas emissions per unit of utilised energy product
• Potentially produce less environmentally damaging waste and effluent per unit of utilisedenergy product
• Reduction and mitigation of liabilities in carbon constrained future
• Ability to optimise EIA process
Environmental Benefits
Localised inside the fence generation –mitigating demand
Modular, small scale units – capacity added in step rather than in large “lumps”
Bring capacity online in reduced time frame versus large utility-scale power plants
Broaden scope of fuels used to produce electricity
Security of Supply
• Cogeneration project development as possible means of mitigating the countrywide development and engineering skills shortage
• Ideal BEE opportunity
• Ideal entry-point for the mobilization of private sector resources into the electricity sector
Social Benefits
Cogeneration
Why Cogeneration Why Cogeneration –– The Bigger PictureThe Bigger Picture
Central power station
Commercial
building
Local CHP plant
Storage
Storage
Power
quality
device
Flow
Control
Transmission Network
Distribution Network
Tomorrow: distributed/on- site generation with fully integrated
network management
Storage
Photovoltaics
power plant
Wind
power
plant House with domestic CHP
Power
quality
device
Storage
Commercial
building
Local CHP plant
Storage
Storage
Power
quality
device
Flow
Control
Yesterday
Why Cogeneration Why Cogeneration –– Need for Regulatory SupportNeed for Regulatory Support
Why given the above benefits hasn’t the sector seen significant investment as yet?
Reasons cited include:
� Market structure:� Single offtaker: no automatic route to market
� Lack of ability to wheel power
� Current pricing
� Pricing of backup power
� Lack of transparency – uncertainty over process to be followed
� Current process too bureaucratic
� Variations in cost of capital
� Payback horizon for industrial companies
� Development costs
Key barrier: current pricing of potential new capacity versus retail pricing against Eskom’s depreciated asset base � required essential feature of any support mechanism:
Pricing of output to be based on avoided cost of new generation rather than current wholesale power price
Why Cogeneration Why Cogeneration –– Need for Support Need for Support -- ExampleExample
Project funding
Economic benefit versus next best
Avoided cost of next best baseload plant – Line C
Cost of wholesale power – SA system – Line A
Cogeneration project avoided costs – Line B
Required Timescale for support
c/kWh
Time
Guidelines and Framework Guidelines and Framework –– ObjectivesObjectives
Given preceding points the guidelines and framework have two key objectives:
1. Define, and ideally simplify the process for developing, evaluating and implementing
cogen projects
2. Ensure rational pricing for qualifying cogeneration projects
Guidelines Guidelines –– Recommended Support Recommended Support -- OutlineOutline
Overarching Regulatory FrameworkOverarching Regulatory Framework
Determination of qualifying projectsDetermination of qualifying projects
Determination of rational priceDetermination of rational price
Suggested implementation mechanismSuggested implementation mechanism
Key Elements of Regulatory Support for Cogeneration
Provide overall sector
sustainability and bankability
Provide overall sector
sustainability and bankability
Provide specificityProvide specificity
Overcome current pricing
limitations
Overcome current pricing
limitations
Provide project bankabilityProvide project bankability
Guidelines Guidelines –– Overarching Regulatory FrameworkOverarching Regulatory Framework
Suggested long-term
approach
As part of Eskom’s licensing conditions oblige certain percentage of supply to come from cogenerated sources
Consistent with international regulatory best practice
Sector enabler: National Cogeneration
Standard
Nersa determined and approved avoided cost for price settingNersa approved long-term mechanism to allow and incentivise Eskom to recover cost of contracting with cogeneration plant
Project enabler: cost recovery mechanism for
Eskom
Long-term proposals are consistent with
international regulatory practice but are time
consuming and resource intensive
Need for an interim approach – Eskom
Pilot Programme
Guidelines Guidelines –– Determination of Qualifying ProjectsDetermination of Qualifying Projects
How to determine
which projects are
covered?
Expand on earlier definition:
3 Types of basic project covered by Framework
Projects utilizing process energy which would otherwise be underutilized or wasted
Examples:Waste Heat Recovery SystemsGeneration from waste gas Waste or discard solid fuel
Type I
• Primary fuel based generation projects which produce, as part of their core design, other usable energy in addition to electricity
• Examples:� Combined Heat and Power (“CHP”)
Type II
• Renewable fuel based projects, where the renewable fuel source is both a primary source of energy used for generation and a co-product of an industrial process
• Examples:� Sugar industry bagasse based generation
� Generation from forestry waste
�Wastewater based generation� Solid renewable waste
Type III
Guidelines Guidelines –– Determination of Rational PriceDetermination of Rational Price
Determining
“Rational” Price • Initially captures only those plant which are cost efficient versus alternative new capacity options
• As a result no effective subsidy provided to cogeneration plant
• This prioritizes low-cost capacity addition →may require additional incentives in future if
‘pure’ energy efficiency becomes a priority
Starting point – system avoided cost of new
generation as benchmark to be bettered
Capture maximum societal economic benefit (yellow square from earlier)
understood market mechanism
Requires capacity setting targets - difficult to specify amount and timing
Who runs and adjudicates auction?
Auction Capacity
Pros:• No limit on capacity• Reduce development risk - price a known factor
Cons
• How to determine “right” price• Risk of oversupply
• Some loss of societal benefit
Set price at percentage of avoided costs
First
Then either:
Current Preferred
Option is to use
auction to
determine prices –
Eskom Pilot
Programme as test
case
Or
Guidelines Guidelines –– ImplementationImplementation
Implementation
mechanism
Bankable, long-term PPA with Eskom encapsulating supported price
ESKOM ability to lock in long term power below its avoided costs
Eskom credit-passthrough – optimise cost of capital
Application of two-way metering for projects consuming power on-site i.e. paid for all power generated not only that dispatched onto the grid
Power Purchase Agreement with Eskom
Automatic project enabler
Draft PPA already in development for
Eskom Pilot Programme
Guidelines Guidelines –– LongLong--term Objectives term Objectives vsvs ShortShort--term Needsterm Needs
Trade off between long term objectives and short term constraints
Long term objective: ongoing supported program promoting cogeneration
development
� Fully developed and implemented regulatory framework: National Cogeneration
Standard
� Requires dedicated capacity & resource within NERSA: specific cogeneration function
Short term: urgent need to expedite development of new generation capacity.� Increased need to engage ESKOM
� Interim approach NERSA sanctioned tender for PPA’s with ESKOM
Eskom Pilot Programme
ENDEND