1 Alto Garda Power Cogeneration Power Plant main tips Client Alto Garda Power (Trento Italy) Location Riva del Garda, situated at the most north side of the Garda Lake in the Trento Province of Italy. The Plant has been built within the premises of the Paper Mill Factory “Cartiere del Garda” Total contract 49 MWe Cogenerative CCPP with: 1 GT (GE LM6000) + 1 HRSG 1 ST Turbomach + 1 Auxiliary boiler Scope of work Plant overall EPC supply up to commissioning and start up from green field including, Turbo-set Generators and relevant auxiliaries, Electro-Mechanical BOP, Boilers, I&C, Control Systems (DCS), Civil Works, link to municipal House Heating System, link to national electrical grid, link to the paper mill system for electrical and steam supply. All main Units including relevant auxiliaries and electrical equipment are enclosed in a Precast Concrete Power House. Contract value 81 M$ Contract period 2007 - 2010

Upload: lythuan

Post on 23-Aug-2019

218 views

Category:

Documents


0 download

TRANSCRIPT

1

Alto Garda Power – Cogeneration Power Plant main tips

Client Alto Garda Power (Trento – Italy)

Location Riva del Garda, situated at the most north side of the Garda Lake in the Trento

Province of Italy.

The Plant has been built within the premises of the Paper Mill Factory “Cartiere del

Garda”

Total contract 49 MWe Cogenerative CCPP with:

1 GT (GE LM6000) + 1 HRSG

1 ST Turbomach + 1 Auxiliary boiler

Scope of work Plant overall EPC supply up to commissioning and start up from green field

including, Turbo-set Generators and relevant auxiliaries, Electro-Mechanical BOP,

Boilers, I&C, Control Systems (DCS), Civil Works, link to municipal House Heating

System, link to national electrical grid, link to the paper mill system for electrical

and steam supply.

All main Units including relevant auxiliaries and electrical equipment are enclosed

in a Precast Concrete Power House.

Contract value 81 M$

Contract period 2007 - 2010

2

Alto Garda Power – Cogeneration Power Plant Location overview

The town “Riva del Garda” and the Paper Mill Factory

3

Alto Garda Power – Cogeneration Power Plant Location overview

The location of the new Cogeneration Power plant within the open area of the Paper Mill Factory

4

Alto Garda Power – Cogeneration Power Plant The Plant Overwiew

The Power House

The Electrical Substation

The Gas Station

5

Alto Garda Power – Cogeneration Power Plant The Power House

6

Alto Garda Power – Cogeneration Power Plant The Power House

7

Alto Garda Power – Cogeneration Power Plant The Power House

8

Alto Garda Power – Cogeneration Power Plant The Power House

9

Alto Garda Power – Cogeneration Power Plant The Construction History

Escavation started

10

Alto Garda Power – Cogeneration Power Plant The Construction History

Cable Tunnel Construction

11

Alto Garda Power – Cogeneration Power Plant The Construction History

Cable Tunnel Construction

12

Alto Garda Power – Cogeneration Power Plant The Construction History

HRSG and Chimney Foundation

13

Alto Garda Power – Cogeneration Power Plant The Construction History

GT Foundation

14

Alto Garda Power – Cogeneration Power Plant The Construction History

Building Foundation

15

Alto Garda Power – Cogeneration Power Plant The Construction History

Building Erection

16

Alto Garda Power – Cogeneration Power Plant The Construction History

Building Erection

17

Alto Garda Power – Cogeneration Power Plant The Construction History

Building Erection

18

Alto Garda Power – Cogeneration Power Plant The Construction History

GT package at Assembly Factory

and ready for delivery to site

19

Alto Garda Power – Cogeneration Power Plant The Construction History

Transportation of GT-Generator

20

Alto Garda Power – Cogeneration Power Plant The Construction History

The GT Generator setting

The Gas Turbine & Air Filter

21

Alto Garda Power – Cogeneration Power Plant The Construction History

The Gas Turbine & Auxiliries

22

Alto Garda Power – Cogeneration Power Plant The Construction History

The HRSG Erection

23

Alto Garda Power – Cogeneration Power Plant The Construction History

The HRSG Erection

24

Alto Garda Power – Cogeneration Power Plant The Construction History

Diverter Damper and GT Stack supporting structure

25

Alto Garda Power – Cogeneration Power Plant The Construction History

HRSG and Chimney GT and HRSG

26

Alto Garda Power – Cogeneration Power Plant The Construction History

Pipe Rack Construction

27

Alto Garda Power – Cogeneration Power Plant The Construction History

Piping and mechanical erection

in the Power House

28

Alto Garda Power – Cogeneration Power Plant The Construction History

Electrical erection

in the Power House

29

Alto Garda Power – Cogeneration Power Plant The Construction History

Electrical Room – Detail of Low Voltage Panels Transformer

30

Alto Garda Power – Cogeneration Power Plant The Construction History

Plant Control and Supervision System

31

Alto Garda Power – Cogeneration Power Plant The Construction History

Gas Station Gas Compressors

32

Alto Garda Power – Cogeneration Power Plant The Construction History The Power House