james m. alderman stephen bedner jeffrey p. phipps, sr ... · 6/2/2020  · delray beach, florida...

134
Board of Supervisors James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr. Harry Raucher John I. Whitworth III Executive Director Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net June 10, 2020 E F JOHNS LTD 132 INTRACOASTAL CIR TEQUESTA FL 33469 2709 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170 Site Address: 205TH ST S, BOCA RATON FL 33434 Dear E F JOHNS LTD : The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right- of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Upload: others

Post on 25-Sep-2020

9 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 E F JOHNS LTD 132 INTRACOASTAL CIR TEQUESTA FL 33469 2709 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 205TH ST S, BOCA RATON FL 33434 Dear E F JOHNS LTD : The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 2: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in early July 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 3: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 PALM BEACH COUNTY C/O PREM DIVISION 2633 VISTA PKWY WEST PALM BEACH FL 33411 5613 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 205TH ST S, BOCA RATON FL 33434 Dear PALM BEACH COUNTY C/O PREM DIVISION: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 4: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 5: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 JOHNS HOUSTON LTD 132 INTRACOASTAL CIR TEQUESTA FL 33469 2709 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 20150 S STATE ROAD 7, BOCA RATON FL 33434 Dear JOHNS HOUSTON LTD : The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 6: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 7: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 E F JOHNS LTD 132 INTRACOASTAL CIR TEQUESTA FL 33469 2709 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: LYONS RD, BOCA RATON FL 33434 Dear E F JOHNS LTD : The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 8: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 9: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 E F JOHN LTD 132 INTRACOASTAL CIR TEQUESTA FL 33469 2709 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: LYONS RD, BOCA RATON FL 33434 Dear E F JOHN LTD : The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 10: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 11: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 JOHN HOUSTON LTD 132 INTRACOASTAL CIR TEQUESTA FL 33469 2709 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: LYONS RD, BOCA RATON FL 33434 Dear JOHN HOUSTON LTD : The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 12: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 13: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 THOMAS A. & DANIELA O. CHEA 8662 EAGLE RUN DR BOCA RATON FL 33434 5407 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8662 EAGLE RUN DR, BOCA RATON FL 33434 5407 Dear THOMAS A. & DANIELA O. CHEA: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 14: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 15: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 MARTIN A. & FRANCES KEROES 8668 EAGLE RUN DR BOCA RATON FL 33434 5407 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8668 EAGLE RUN DR, BOCA RATON FL 33434 5407 Dear MARTIN A. & FRANCES KEROES: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 16: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 17: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 ROBERT D. & MARLA K. CIEPIELA 8674 EAGLE RUN DR BOCA RATON FL 33434 5407 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8674 EAGLE RUN DR, BOCA RATON FL 33434 5407 Dear ROBERT D. & MARLA K. CIEPIELA: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 18: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 19: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 CHRISTINE M. & FRANCIS J. FRANKO 8680 EAGLE RUN DR BOCA RATON FL 33434 5407 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8680 EAGLE RUN DR, BOCA RATON FL 33434 5407 Dear CHRISTINE M. & FRANCIS J. FRANKO: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 20: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 21: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 AFZAL & YASHIM KHAN 67 08 147TH ST FLUSHING NY 11357 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8686 EAGLE RUN DR, BOCA RATON FL 33434 5407 Dear AFZAL & YASHIM KHAN: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 22: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 23: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 MARTIN R. GOLDBERG & CHRISTINA RICCIARDI 8692 EAGLE RUN DR BOCA RATON FL 33434 5407 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8692 EAGLE RUN DR, BOCA RATON FL 33434 5407 Dear MARTIN R. GOLDBERG & CHRISTINA RICCIARDI: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 24: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 25: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 KRISTIN COOKSON FERNANDES 8698 EAGLE RUN DR BOCA RATON FL 33434 5407 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8698 EAGLE RUN DR, BOCA RATON FL 33434 5407 Dear KRISTIN COOKSON FERNANDES : The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 26: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 27: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 MONA CHAMI & NABIL KHAZEM 8704 EAGLE RUN DR BOCA RATON FL 33434 5432 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8704 EAGLE RUN DR, BOCA RATON FL 33434 5432 Dear MONA CHAMI & NABIL KHAZEM: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 28: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 29: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 RITA A. MCKEEGAN & RITA A. MCKEEGAN TR. 8710 EAGLE RUN DR BOCA RATON FL 33434 5432 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8710 EAGLE RUN DR, BOCA RATON FL 33434 5432 Dear RITA A. MCKEEGAN & RITA A. MCKEEGAN TR.: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 30: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 31: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 JULIE CARDOZO 36276 OKEFENOKEE DR FOLKSTON GA 31537 7852 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8716 EAGLE RUN DR, BOCA RATON FL 33434 5432 Dear JULIE CARDOZO : The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 32: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 33: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 CECILIA RESTREPO 15727 CUTTEN RD APT 622 HOUSTON TX 77070 3944 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8722 EAGLE RUN DR, BOCA RATON FL 33434 5432 Dear CECILIA RESTREPO : The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 34: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 35: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 BRIAN T. SESKIN 8728 EAGLE RUN DR BOCA RATON FL 33434 5432 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8728 EAGLE RUN DR, BOCA RATON FL 33434 5432 Dear BRIAN T. SESKIN : The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 36: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 37: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 AFZAL & YASHMIN KHAN 67 08 147TH ST FLUSHING NY 11357 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8734 EAGLE RUN DR, BOCA RATON FL 33434 5432 Dear AFZAL & YASHMIN KHAN: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 38: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 39: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 DEREK & CHERYL A. ALLISON 8740 EAGLE RUN DR BOCA RATON FL 33434 5432 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8740 EAGLE RUN DR, BOCA RATON FL 33434 5432 Dear DEREK & CHERYL A. ALLISON: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 40: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 41: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 RICHARD & ELLEN LAPIN 8650 EAGLE RUN DR BOCA RATON FL 33434 5437 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8650 EAGLE RUN DR 1, BOCA RATON FL 33434 5437 Dear RICHARD & ELLEN LAPIN: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 42: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 43: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 DOMINICA CIRISANO 8650 EAGLE RUN DR APT 2 BOCA RATON FL 33434 5437 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8650 EAGLE RUN DR 2, BOCA RATON FL 33434 5437 Dear DOMINICA CIRISANO : The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 44: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 45: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 ANTONIO COMPARELLI & CARMELA BARBALUNGA 131 ELGIN STREET THORNHILL, ONTARIO L3T1W7 CANADA DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8650 EAGLE RUN DR 3, BOCA RATON FL 33434 5437 Dear ANTONIO COMPARELLI & CARMELA BARBALUNGA: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 46: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 47: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 PAUL & MARIA VELTRI 8650 EAGLE RUN DR # 4 BOCA RATON FL 33434 5437 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8650 EAGLE RUN DR 4, BOCA RATON FL 33434 5437 Dear PAUL & MARIA VELTRI: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 48: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 49: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 WEDGEWOOD HOMEOWNERS ASSN INC C/O RESIDENTIAL MGMT CONCEPTS PO BOX 97-0069 BOCA RATON FL 33497 0069 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8656 EAGLE RUN DR, BOCA RATON FL 33497 0069 Dear WEDGEWOOD HOMEOWNERS ASSN INC C/O RESIDENTIAL MGMT CONCEPTS: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 50: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 51: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 WEDGEWOOD HOMEOWNERS ASSN INC C/O RESIDENTIAL MGMT CONCEPTS PO BOX 97-0069 BOCA RATON FL 33497 0069 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Parcel Control Number: 00424717080070000 Dear WEDGEWOOD HOMEOWNERS ASSN INC C/O RESIDENTIAL MGMT CONCEPTS: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 52: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 53: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 WEDGEWOOD HOMEOWNERS ASSN INC C/O RESIDENTIAL MGMT CONCEPTS PO BOX 97-0069 BOCA RATON FL 33497 0069 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Parcel Control Number: 00424717080120000 Dear WEDGEWOOD HOMEOWNERS ASSN INC C/O RESIDENTIAL MGMT CONCEPTS: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 54: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 55: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 GLADES MEDICAL CENTER CONDOMINIUM ASSOCIATION, INC. C/O FAIRMAN & ASSOCIATES, INC 1651 NW 1ST COURT BOCA RATON FL 33432 3730 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 9325 GLADES RD, BOCA RATON FL 33434 Dear GLADES MEDICAL CENTER CONDOMINIUM ASSOCIATION, INC. : The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 56: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 57: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 COMMERCIAL BANK OF FLORIDA 1550 SW 57TH AVE MIAMI FL 33144 5722 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 205TH PL S, BOCA RATON FL 33434 Dear COMMERCIAL BANK OF FLORIDA : The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 58: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 59: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 BOCA GLADES MASTER ASSN INC 8489 BOCA GLADES BLVD E BOCA RATON FL 33434 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8518 BOCA GLADES BLVD W, BOCA RATON FL 33434 Dear BOCA GLADES MASTER ASSN INC : The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 60: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 61: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 MORDECHAI BARAZANI 8983 SONOMA LAKE BLVD BOCA RATON FL 33434 4062 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8983 SONOMA LAKE BLVD, BOCA RATON FL 33434 4062 Dear MORDECHAI BARAZANI : The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 62: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 63: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 JAMES E. MCGINNIS 7651 ESTRELLA CIR BOCA RATON FL 33433 1649 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8975 SONOMA LAKE BLVD, BOCA RATON FL 33433 1649 Dear JAMES E. MCGINNIS : The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 64: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 65: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 MARIA FABIANI & DANA FOX 8967 SONOMA LAKE BLVD BOCA RATON FL 33434 4062 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8967 SONOMA LAKE BLVD, BOCA RATON FL 33434 4062 Dear MARIA FABIANI & DANA FOX: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 66: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 67: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 QIN LI YONG & HELEN CHEN 8959 SONOMA LAKE BLVD BOCA RATON FL 33434 4062 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8959 SONOMA LAKE BLVD, BOCA RATON FL 33434 4062 Dear QIN LI YONG & HELEN CHEN: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 68: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 69: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 RONALD CHAZAN 8951 SONOMA LAKES BLVD BOCA RATON FL 33434 4062 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8951 SONOMA LAKE BLVD, BOCA RATON FL 33434 4062 Dear RONALD CHAZAN : The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 70: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 71: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 BEHZAD HADAEGH & PARISA GHELICHKANI 4625 CHERRY VALLEY DR ROCKVILLE MD 20853 1110 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8943 SONOMA LAKE BLVD, BOCA RATON FL 33434 4062 Dear BEHZAD HADAEGH & PARISA GHELICHKANI: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 72: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 73: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 STEVEN HIRSCH & JENNY JACOME 8935 SONOMA LAKE BLVD BOCA RATON FL 33434 4062 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8935 SONOMA LAKE BLVD, BOCA RATON FL 33434 4062 Dear STEVEN HIRSCH & JENNY JACOME: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 74: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 75: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 HARRY LERNER 2799 BATCHELDER ST BROOKLYN NY 11235 1701 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8927 SONOMA LAKE BLVD, BOCA RATON FL 33434 4062 Dear HARRY LERNER : The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 76: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 77: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 ROBERT POLIZZI & KAREN B. LEWIS 8919 SONOMA LAKE BLVD BOCA RATON FL 33434 4062 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8919 SONOMA LAKE BLVD, BOCA RATON FL 33434 4062 Dear ROBERT POLIZZI & KAREN B. LEWIS: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 78: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 79: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 MARJORIE YAPPOW 8911 SONOMA LAKE BLVD BOCA RATON FL 33434 4062 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8911 SONOMA LAKE BLVD, BOCA RATON FL 33434 4062 Dear MARJORIE YAPPOW : The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 80: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 81: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 JOSEPH DARMETTA 8903 SONOMA LAKE BLVD BOCA RATON FL 33434 4062 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8903 SONOMA LAKE BLVD, BOCA RATON FL 33434 4062 Dear JOSEPH DARMETTA : The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 82: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 83: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 JOHN GALBO 8895 SONOMA LAKE BLVD BOCA RATON FL 33434 4070 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8895 SONOMA LAKE BLVD, BOCA RATON FL 33434 4070 Dear JOHN GALBO : The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 84: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 85: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 RICHARD L. & LOIS SCHOENFELD 8887 SONOMA LAKE BLVD BOCA RATON FL 33434 4070 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8887 SONOMA LAKE BLVD, BOCA RATON FL 33434 4070 Dear RICHARD L. & LOIS SCHOENFELD: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 86: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 87: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 NANCY J. GAMBINO 8879 SONOMA LAKE BLVD BOCA RATON FL 33434 4070 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8879 SONOMA LAKE BLVD, BOCA RATON FL 33434 4070 Dear NANCY J. GAMBINO : The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 88: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 89: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 NEIL L. FRAPART 8871 SONOMA LAKE BLVD BOCA RATON FL 33434 4070 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8871 SONOMA LAKE BLVD, BOCA RATON FL 33434 4070 Dear NEIL L. FRAPART : The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 90: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 91: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 WILLIAM J. SCERBO 8863 SONOMA LAKES BLVD BOCA RATON FL 33434 4070 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8863 SONOMA LAKE BLVD, BOCA RATON FL 33434 4070 Dear WILLIAM J. SCERBO : The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 92: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 93: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 SONOMA LAKE ESTS AT BOCA RATON HOA INC C/O CREST MANAGEMENT GROUP 6413 CONGRESS AVE STE 100 BOCA RATON FL 33487 2848 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 8760 SONOMA LAKE BLVD, BOCA RATON FL 33487 2848 Dear SONOMA LAKE ESTS AT BOCA RATON HOA INC C/O CREST MANAGEMENT GROUP: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 94: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 95: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 FREDDY & ALBA LOPEZ 20525 CAROUSEL CIR W BOCA RATON FL 33434 3930 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 20525 CAROUSEL CIR W, BOCA RATON FL 33434 3930 Dear FREDDY & ALBA LOPEZ: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 96: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 97: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 IH6 PROPERTY FLORIDA LP 600 N PINE ISLAND RD STE 100 FORT LAUDERDALE FL 33324 1324 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 9721 CAROUSEL CIR N, BOCA RATON FL 33434 3930 Dear IH6 PROPERTY FLORIDA LP : The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 98: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 99: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 SHAMUEL & MORIAH AHARON 9713 CAROUSEL CIR N BOCA RATON FL 33434 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 9713 CAROUSEL CIR N, BOCA RATON FL 33434 3930 Dear SHAMUEL & MORIAH AHARON: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 100: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 101: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 LAURENCE & JOAN MILLER 9705 CAROUSEL CIR N BOCA RATON FL 33434 3928 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 9705 CAROUSEL CIR N, BOCA RATON FL 33434 3928 Dear LAURENCE & JOAN MILLER: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 102: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 103: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 MLADEN & DANICA TRIFUNOVIC 9693 CAROUSEL CIR N BOCA RATON FL 33434 3922 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 9693 CAROUSEL CIR N, BOCA RATON FL 33434 3922 Dear MLADEN & DANICA TRIFUNOVIC: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 104: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 105: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 AMINA & AHMED EJAZ 9681 CAROUSEL CIR N BOCA RATON FL 33434 3922 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 9681 CAROUSEL CIR N, BOCA RATON FL 33434 3922 Dear AMINA & AHMED EJAZ: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 106: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 107: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 ALON GOLAN 9669 CAROUSEL CIR N BOCA RATON FL 33434 3922 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 9669 CAROUSEL CIR N, BOCA RATON FL 33434 3922 Dear ALON GOLAN : The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 108: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 109: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 GEVORK & AGUNICK SARKSIAN 9657 CAROUSEL CIR N BOCA RATON FL 33434 3922 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 9657 CAROUSEL CIR N, BOCA RATON FL 33434 3922 Dear GEVORK & AGUNICK SARKSIAN: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 110: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 111: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 DONALD BLAZEJEWSKI & CHRISTINE IGNACIUK 9645 CAROUSEL CIR N BOCA RATON FL 33434 3922 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 9645 CAROUSEL CIR N, BOCA RATON FL 33434 3922 Dear DONALD BLAZEJEWSKI & CHRISTINE IGNACIUK: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 112: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 113: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 LOUIS T. PATSALOS 9633 CAROUSEL CIR N BOCA RATON FL 33434 3922 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 9633 CAROUSEL CIR N, BOCA RATON FL 33434 3922 Dear LOUIS T. PATSALOS : The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 114: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 115: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 2017 1 IH BORROWER LP 1717 MAIN ST STE 2000 DALLAS TX 75201 4657 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 9621 CAROUSEL CIR N, BOCA RATON FL 33434 3922 Dear 2017 1 IH BORROWER LP : The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 116: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 117: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 ROXANEE R. MESORACA & ROXANEE R. MESORACA TR. 9609 CAROUSEL CIR N BOCA RATON FL 33434 3922 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 9609 CAROUSEL CIR N, BOCA RATON FL 33434 3922 Dear ROXANEE R. MESORACA & ROXANEE R. MESORACA TR.: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 118: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 119: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 DAVID P. & CALLIE L. SHAFFER 9597 CAROUSEL CIR N BOCA RATON FL 33434 3922 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 9597 CAROUSEL CIR N, BOCA RATON FL 33434 3922 Dear DAVID P. & CALLIE L. SHAFFER: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 120: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 121: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 BRIAN H. & MARIA A. SMITH 9585 CAROUSEL CIR N BOCA RATON FL 33434 3922 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 9585 CAROUSEL CIR N, BOCA RATON FL 33434 3922 Dear BRIAN H. & MARIA A. SMITH: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 122: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 123: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 LILLY SHER 9573 CAROUSEL CIR N BOCA RATON FL 33434 3922 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 9573 CAROUSEL CIR N, BOCA RATON FL 33434 3922 Dear LILLY SHER : The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 124: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 125: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 ANDREW & SABINA SMEJKAL 9561 E CAROUSEL CIR BOCA RATON FL 33434 3965 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 9561 CAROUSEL CIR E, BOCA RATON FL 33434 3965 Dear ANDREW & SABINA SMEJKAL: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 126: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 127: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 JARED D. & SARA A. SHULMAN 9549 CAROUSEL CIR E BOCA RATON FL 33434 3965 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 9549 CAROUSEL CIR E, BOCA RATON FL 33434 3965 Dear JARED D. & SARA A. SHULMAN: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 128: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 129: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 CORAL LAKE AT BOCA RATON HOA INC C/O SWIFT MGMT SOLUTIONS INC 1750 UNIVERSITY DR # 205 CORAL SPRINGS FL 33071 6077 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 9535 BOCA RIVER CIR, BOCA RATON FL 33434 Dear CORAL LAKE AT BOCA RATON HOA INC C/O SWIFT MGMT SOLUTIONS INC: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 130: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 131: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 ZOM BOCA RATON LTD C/O UBS REALTY INVESTORS PO BOX 1368 CARLSBAD CA 92018 1368 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Parcel Control Number: 00424718150020000 Dear ZOM BOCA RATON LTD C/O UBS REALTY INVESTORS: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 132: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District

Page 133: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Board of Supervisors

James M. Alderman Stephen Bedner

Jeffrey P. Phipps, Sr. Harry Raucher

John I. Whitworth III Executive Director

Tommy B. Strowd, P.E. 13081 MILITARY TRAIL Attorney DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A.

Phone: (561) 498-5363 • Fax: (561) 495-9694 • www.lwdd.net

June 10, 2020 ZOM BOCA RATON LTD C/O REALTY INVESTORS PO BOX 1368 CARLSBAD CA 92018 1368 DELIVERED VIA REGULAR MAIL AND HAND DELIVERY Subject: SECOND NOTIFICATION

Rehabilitation of the L-45 Canal from approximately 1,275 LF east of the E‐1 Canal to Lyons Road Project No. 16‐9974P.01; Job No. 170

Site Address: 20525 S CHARLESTON, BOCA RATON FL 33434 Dear ZOM BOCA RATON LTD C/O REALTY INVESTORS: The Lake Worth Drainage District (District) is planning necessary rehabilitation work on the L-45 Canal adjacent to your property. This work is necessary to facilitate effective flood control for public safety and to provide unobstructed access for emergency flood control response and routine canal maintenance. Rehabilitation efforts may include removal of vegetative encroachments, removal of structural and non-structural encroachments, dredging of the canal channel, and reshaping or reconstruction of the canal bank(s). Encroachments located on the District’s canal right-of-way can create obstructions to water flow during a heavy rainfall event or hinder the District’s ability to properly maintain the canal, both of which can cause serious flooding issues for surrounding neighborhoods. The limits of the project are scheduled to be re-staked by the Florida Licensed Surveyors beginning the week of June 15, 2020 to identify the boundaries of the District’s L-45 Canal right-of-way. Any plantings or vegetation, structures, fences or personal property located and identified within this right-of-way are encroachments and should be removed by the property owner prior to the commencement of this project. Please be advised that any encroachments remaining in the right-of-way at the commencement of the project may be removed and disposed of by the District. If you have any prior written approvals, agreements, permits, or any other written authorization from the District for any existing encroachments, or any other information relative to any existing encroachment within the canal right-of-way, please contact the District as soon as you can so that this information can be reviewed.

Page 134: James M. Alderman Stephen Bedner Jeffrey P. Phipps, Sr ... · 6/2/2020  · DELRAY BEACH, FLORIDA 33484-1105 Mark A. Perry, P.A. Phone: (561) 498-5363 • Fax: (561) 495-9694 •

Project No. 16‐9974P.01; Job No. 170 June 10, 2020 Page 2 Also, if you have constructed or installed any fencing, plantings or vegetation, or any other items within the canal right-of-way of which you are relying on for security purposes, please be advised these are considered encroachments and they may be removed with this rehabilitation project. If any of these existing encroachments have previously been permitted by the District, you may apply for a permit to replace them; however, all current and applicable permit criteria must be met. If you wish to secure your private property, you must do so outside the limits of the canal right-of-way. Based on the District’s current canal rehabilitation schedule, we estimate the project will begin in late June 2020. The project schedule is subject to change at any time due to weather conditions, labor or equipment allocations, project site conditions, etc. To view additional information regarding this canal rehabilitation project including a map of the project boundaries, please visit our website at www.lwdd.net and click on ‘In Your Neighborhood’ or email us at [email protected]. If you would like to speak with a representative regarding this specific project, please contact Steve Sherman, Right-of-Way Compliance Coordinator, at 561-819-5580 or [email protected]. Sincerely,

Brian Tilles, P.E. Right-of-Way Compliance Manager c: Tommy Strowd, P.E., Executive Director, Lake Worth Drainage District