itp for batteries, chargers and ups
DESCRIPTION
ITP for Batteries, Chargers and UPSTRANSCRIPT
DOCUMENT REVIEW AND COVER SHEETCompany: Construction Contractor:
Engineering Contractor: Engineering and Technical Services:
Review:
PROJECT Gasprom Neftehim Salavat Acrylic Acid / Acrylates Plant (RSAE) Project Bashkortostan, Russian Federation
CONTRACT NO 88621 - December, 2012
DOCUMENT TITLE Batteries, Battery Chargers & UPS
DOCUMENT NUMBER RSAE - ITP - QA - REV. A1
DOCUMENT DESCRIPTION Inspection and Test Plan (ITP)
Status Status Code Code Description
⃝; 1 APPROVED WITHOUT COMMENT
⃝; 2 REVISE AND RESUBMIT. WORK MAY PROCEED SUBJECT TO INCORPORATON OF CHANGES INDICATED.
⃝; 3 REJECTED. TO BE REVISED B: RESUBMITTED. WORK MAY NOT PROCEED
⃝; 4 INFORMATION ONLY. REVIEW NOT REQUIRED. WORK MAY PROCEED
⃝; 5 CANCELLED/SUPERSEDEDRevieved Engineer:
NAME SIGN DATE
Remarks or Comments:
Document Number: Revision:
RSAE ITP QAA1
PROJECT CODE DEPARTMENT CODE DOCUMENT TYPE DICIPLINE CODE SEQUENCE NUMBER
A1 Issued for Approval
Rev. Amendment Prepared Checked Approved Date
Company: Construction Contractor:
Engineering Contractor: Engineering and Technical Services:
Project Title:
Gasprom Neftehim SalavatAcrylic Acid / Acrylates Plant (RSAE) Project
Bashkortostan, Russian FederationDocument Title:
Inspection and Test Plan
Batteries, Battery Chargers & UPS
Document Number: Revision:
RSAE ITP QAA1
PROJECT CODE DEPARTMENT CODE DOCUMENT TYPE DICIPLINE CODE SEQUENCE NUMBER
REVISION SHEETRevision Description of changes Page
A1 First Issued For approval
Document Number: Revision:
RSAE ITP QAA1
PROJECT CODE DEPARTMENT CODE DOCUMENT TYPE DICIPLINE CODE SEQUENCE NUMBER
Gasprom Neftehim Salavat Acrylic Acid / Acrylates Plant (RSAE) Project
Inspection and Test PlanBATTERIES, BATTERY CHARGERS & UPS
Issue Date: 01/06/2014 Doc. Number: RSAE-ITP-QA- Revision: A1 Page: 1 of 2
No DESCRIPTION OF ACTIVITY CONTROL DOCUMENT ACCEPTANCE CRITERIA VERIFICATION DOCUMENT INVOLVEMENTSRC MHI OWNER
1 General
1.1Check substation/CCR is ready for installation of Batteries, Battery Chargers and UPS
CCR/SS arrangement DWGDWG: 3935 E471-00100 3935 E471-00200 3935 E474-00100 3935 E474-00120Vendor DWGDWG: 3935 E323-00700 3935 E323-00800
(1) Clean condition(2) No water in the the room (3) Panel foundation is available(4) Temperature control as per Vendor's manual
Vendor instruction manualDWG:AC UPS:3935 E423- 00800DC Charger:3935 E423-00700And Good Condition of substation, CCR
W W S
1.2Verify that equipment is properly grounded in accordance with the grounding notes, symbols, and details
DWG: 3935 E463-00100 3935 E463-00200 As per drawing RSAE-FRM-205 W W S
1.3Verify that all power cables and distribution buses have been inspected and tested
DWG: 3935 E461-00100 3935 E461-00200 ITP for cable Inspection Record for the
cable W W S
LEGEND RC: Renaissance Construction, MHI: Mitsubishi Heavy Industries,, OWNER: Gasprom Neftehim Salavat, W: Witness , R: Review , H: Mandatory Hold Point , S: Surveillance (Random Check)
Gasprom Neftehim Salavat Acrylic Acid / Acrylates Plant (RSAE) Project
Inspection and Test PlanBATTERIES, BATTERY CHARGERS & UPS
Issue Date: 01/06/2014 Doc. Number: RSAE-ITP-QA- Revision: A1 Page: 2 of 2
No DESCRIPTION OF ACTIVITY CONTROL DOCUMENT ACCEPTANCE CRITERIA VERIFICATION DOCUMENT INVOLVEMENTSRC MHI OWNER
2 General
2.1 Check Battery Installation
DWG:AC UPS:3935 E323-00600 3935 E423- 00800 DC Charger: 3935 E323-00700 3935 E423-00700
Vendor drawing and vendor's manual instruction RSAE-EFRM-206
W W S
2.2 Check Battery Chargers Installation DWG: 3935 E323-00700 3935 E423-00700
Vendor drawing and vendor's manual instruction
RSAE-EFRM-205 W W S
2.3 Check UPS Installation DWG: 3935 E323-00600 3935 E423-00800
Vendor drawing and vendor's manual instruction
RSAE-EFRM-207 W W S
2,4Vendor's Test(1) Function Test(2) Electrical Test
Vendor's drawing As per Vendor's drawing Vendor's record W W S
Attachment 1: RSAE-FRM-XXX Rev.0 INSPECTION CHECK LIST FOR BATTERY INSTALLATION.xlsxAttachment 2: RSAE-FRM-XXX Rev.0 INSPECTION CHECK LIST FOR BATTERY CHARGER INSTALLATION.xlsxAttachment 3: RSAE-FRM-XXX Rev.0 INSPECTION CHECK LIST FOR UPS INSTALLATION.xlsx
LEGEND RC: Renaissance Construction, MHI: Mitsubishi Heavy Industries,, OWNER: Gasprom Neftehim Salavat, W: Witness , R: Review , H: Mandatory Hold Point , S: Surveillance (Random Check)