ISS Commercial Resupply Services
Kathryn Lueders
NASA ISS Program Office
FAA\AST Conference
February 16, 2012
Current Status
2
● Assembly of the ISS vehicle is now complete. The priority is now on fully utilizing this science asset. That requires safe and reliable transportation.
● Post Shuttle retirement, commercial cargo services becomes a key aspect of ISS upmass/return capability. Current ISS transportation strategy through 2015.
• ISS has procured crew rotation services from Roscosmos.
• ESA is providing Automated Transfer Vehicles (ATVs).
• JAXA is providing H-II Transfer Vehicles (HTVs).
• NASA provides the ISS Commercial Resupply Services (CRS) - SpaceX and Orbital.
● Two ISS CRS contracts in work:
● SpaceX - Twelve pressurized and unpressurized upmass and return missions.
● KSC Launch Site
● Orbital – Eight pressurized and disposal missions.
● Wallops/MARs Launch Site
● Reliable commercial cargo transportation will be critical for the continued support of the ISS through 2020.
● Scheduling and planning for these multiple vehicles is an additional challenge for the program.
Q3Q2Q1Q4Q3Q2Q1Q4Q3Q2Q1Q4Q3Q2Q1
CY2014CY2013CY2012CY2011
01/31/12 SpaceX IMS
SpX-1 Launch (8/9/12)
PSR - Dragon
FRR SORRCIR PFR
Engine Prod./Test
Engines installed
1st Stage
@ Cape
2nd Stage
@ Cape Mate
Dragon
Dragon
Ship
SORR
SpX-2 Launch (12/8/12)
EIR CIR
PSR - Dragon
PFR
Engine
Prod./Test
Engines
installed
1st Stage
@ Cape2nd Stage
@ Cape
Mate
Dragon
Dragon
Ship
SpX-3 Launch (7/18/13)
SORRMIR EIR CIR
PSR - Dragon
PFR
SpX-4 Launch (11/3/13)
SORR
VBR MIR CIR
PSR - Dragon
PFR
SpX-5 Launch (4/1/14)
SORRATP VBR MIR CIR
PSR - Dragon
PFR
Vehicle Milestones
Milestones
Launch Date
Hardware schedule in work
for Falcon 9 version 1.1
Hardware schedule in work
for Falcon 9 version 1.1
Hardware schedule in work
for Falcon 9 version 1.1
SpaceX CRS Mission Schedule Overview
4
Q4Q3Q2Q1Q4Q3Q2Q1Q4Q3Q2Q1Q4Q3
CY2014CY2013CY2012CY2011
01/10/12 Orbital L1 Board
Orb-1 Launch (10/2/12)
SORR
FRR PFRCIRPQR
1st
Stg
Core2nd
Stg
FairingPCM SM Cygnus
Mate
Orb-2 Launch (4/8/13)
SORR PFR
MIR CIRPQR
Core1st
Stg
2nd
Stg
Fairing PCM SM Cygnus
Mate
Orb-3 Launch (10/1/13)
SORR PFRMIR CIRPQR
VBR
1st
Stg
Core 2nd
Stg
Fairing PCM SM Cygnus
Mate
Orb-4 Launch (6/1/14)
SORR PFRMIR CIRPQRVBR
Core1st
Stg 2nd
Stg
Fairing PCMSM Cygnus
MateVehicle Milestones
Milestones
Launch Date
Orbital CRS Mission Schedule Overview
5
Multiple support vehicles require complex manifest planning.
Reliable performance will be key to making this work.
6
Conclusion
● We are continuing to make progress towards operational missions. but still
have considerable work ahead.
● Finalizing integrated products and activities with NASA and International
Partners
● Successful demonstration is critical for CRS missions.
● Stability of launch windows is key.
● Important to begin flying in CY 2012.
● This cargo capability is important to the ongoing sustainment of the ISS
vehicle.