invoice process and payment review - laccd - home · invoice process and payment review -...
TRANSCRIPT
Invoice Process and Payment Review for BuildLACCD Briefing No. 3
May 25, 2016
Status Update On February 26, 2016, LACCD’s Board and AECOM requested Deloitte to assess the invoice and payment process at BuildLACCD
All tasks completed on May 25, 2016 which included analyses of following invoice/contract types:
• MATOC Staff-Augmentation
• MATOC Professional Services
• General Contractor (GC)
• Professional Services (non-MATOC)
• Furniture, Fixture and Equipment (FF&E)
To perform these tasks, we:
1. Interviewed CPTs at 9 colleges and PMO
2. Interviewed MATOC Prime-Vendors (Staff-Augmentation)
3. Performed data analytics
4. Performed Contractual Lifecycle Analysis
5. Performed Actual Lifecycle Analysis
6. Performed Variance Analysis
7. Developed Primary Observations and Opportunities for Improvement (see Slides 16 to 18)
BuildLACCD Organization Chart (for invoice and payment process)
Board of Trustees
District
Deloitte Gafcon, Inc.
PMO
CPT City
Primes
Subs
CPT East
Primes
Subs
CPT Harbor
Primes
Subs
CPT Mission
Primes
Subs
CPT Pierce
Primes
Subs
CPT Southwest
Primes
Subs
CPT Trade-Tech
Primes
Subs
CPT Valley
Primes
Subs
CPT West
Primes
Subs
Pacifica Services, Inc.
*Central Services include: College Project Central Services (e.g.: legal and insurance), Satellites (Southgate and VDK), and District Wide Initiatives (e.g.: IT, Energy, Transportation & Accessibility).
Central Services*
PMO Partners PMO Partners
Four Types of BuildLACCD Contracts and Invoices
1. Multi-Award Task Order Contracts (MATOC), which include:
staff augmentation and professional services
2. General Contractor (GC) contracts
Invoices for MATOC and GC contracts require the most effort to process by the BuildLACCD team. For this reason, our analysis and observations focused primarily on these types of contracts.
3. Furniture, Fixture and Equipment (FF&E) contracts, which include:
furniture procurement and Move Managers
4. Professional Services, which includes master agreements for:
Architect/Engineer, Inspector of Record and Laboratory of Record
Invoices for FF&E and Professional Services contracts appeared to require lower level of effort to process by the BuildLACCD team. For this reason, our report entails an ‘overview’ analysis on these types of contracts.
Invoice Process and Payment Review - Contractual Lifecycle (All MATOC Vendors)
Sub-vendors
CPT
Prime Vendors
Prime Vendors
Cut Check/
Prime Receives Payment
Invoice Receipt and Process by PMO
B1
Sub-vendors
Element within PMO’s contractual purview
Element outside of PMO’s contractual purview
Invoice Receipt and process by CPT
District Review, Drawdown and
Wire Funds
(If applicable) (If applicable)
Element outside of PMO’s functional purview
District PMO PMO
Element Contractual Duration
A Beyond PMO’s Contractual Purview
B1 or B2 15th of each Month after POP
C
30 Calendar Days
D
E
F
G Beyond PMO’s Functional Purview
H Paid when Prime paid
(Varies from 7 to 15 Calendar Days for MATOC Staff-Augmentation Vendors)
B2
D
G
E
A H
C F
Invoice Process and Payment Review - Contractual Lifecycle (All Other Vendors)
Sub-vendors
CPT
Prime Vendors
Prime Vendors
Cut Check/
Prime Receives Payment
Invoice Receipt and Process by PMO
B1
Sub-vendors
Element within PMO’s contractual purview
Element outside of PMO’s contractual purview
Invoice Receipt and process by CPT
District Review, Drawdown and
Wire Funds
(If applicable) (If applicable)
Element outside of PMO’s functional purview
District PMO PMO
Element Contractual Duration
A Beyond PMO’s Contractual Purview
B1 or B2 Varies per Contract
C
30 Calendar Days
D
E
F
G Beyond PMO’s Functional Purview
H Varies per Contract
B2
D
G
E
A H
C F
Invoice Process and Payment Review
Multi-Award Task Order Contracts (MATOC): Staff-Augmentation Contracts
Slides 8 to 18
Invoice Process and Payment Review - Actual Lifecycle (Apr 2014 to Mar 2015) MATOC Staff Augmentation Prime-Vendors
Notes: 1. Based on available data within PMO’s information systems (as of our data cut-off date of March 5, 2016), each element is calculated from a distinctive number of invoices. 2. Data was not available for Elements G and H, since they were not within the PMO’s Functional or Contractual purview. 3. “% of Total Invoice Amounts” represents the ratio of each vendor’s total invoiced amount versus the aggregate invoiced amounts by all vendors for this period. 4. Hill International Inc. and Jacobs Project Management did not have invoices within this period.
Process Description Avg. Durations
(Calendar Days)
Arcadis US,
Inc.
Cordoba
Corporation
Cumming
Construction
Management
Hill
International,
Inc.
Jacobs
Engineering
Group
Jacobs
Project
Management
STV/AVA
Vanir
Construction
Management
Yang
Management,
Inc.
Period of Performance (POP) End to Receipt by CPT/PMO
A and B 35 22 28 NA 32 NA 47 37 13
CPT to Prime C - - 5 NA - NA - - -
PMO Analysis D 16 15 14 NA 16 NA 20 14 12
District Review / Drawdown E 6 7 6 NA 7 NA 5 6 6
Cut check / Mail F 3 3 2 NA 2 NA 2 1 2
Integrated Cycle 60 46 52 NA 54 NA 77 60 33
Median 54 34 45 NA 54 NA 72 58 30
Mode 41 34 60 NA 34 NA 72 41 27
Invoice Count 98 15 109 NA 67 NA 12 77 40
Total Invoice Amounts
$1.9 M $313 K $2.1 M NA $1.3 M NA $139 K $1.5 M $641 K
% of Total Invoice Amounts
24% 4% 27% NA 16% NA 2% 19% 8%
Invoice Process and Payment Review - Actual Lifecycle (Apr 2015 to Nov 2015) MATOC Staff Augmentation Prime-Vendors
Notes: 1. Based on available data within PMO’s information systems (as of our data cut-off date of March 5, 2016), each element is calculated from a distinctive number of invoices. 2. Data was not available for Elements G and H, since they were not within the PMO’s Functional or Contractual purview. 3. “% of Total Invoice Amounts” represents the ratio of each vendor’s total invoiced amount versus the aggregate invoiced amounts by all vendors for this period. 4. In mid-April 2015, Jacobs Engineering Group was substituted by Jacobs Project Management to provide Staff Augmentation Services for BuildLACCD. We observed invoices from both entities for a short period in April 2015.
Process Description Avg. Durations
(Calendar Days)
Arcadis US,
Inc.
Cordoba
Corporation
Cumming
Construction
Management
Hill
International,
Inc.
Jacobs
Engineering
Group
Jacobs
Project
Management
STV/AVA
Vanir
Construction
Management
Yang
Management,
Inc.
Period of Performance (POP) End to Receipt by CPT/PMO
A and B 20 29 22 41 16 15 29 21 12
CPT to Prime C 11 - 7 - - - 3 - -
PMO Analysis D 15 11 17 12 26 16 16 11 12
District Review / Drawdown E 6 6 6 6 6 6 6 6 6
Cut check / Mail F 3 3 3 2 3 3 3 3 3
Integrated Cycle 45 50 47 71 51 40 53 42 32
Median 41 37 42 50 43 37 42 41 30
Mode 37 37 41 41 43 31 35 41 24
Invoice Count 380 73 370 28 8 230 143 214 85
Total Invoice Amounts
$6.2 M $1.3 M $6.2 M $376 K $142 K $4.1 M $1.9 M $3.7 M $1.3 M
% of Total Invoice Amounts
25% 5% 25% 2% 1% 17% 8% 15% 5%
Invoice Process and Payment Review - Actual Lifecycle (Dec 2015 to Feb 2016) MATOC Staff Augmentation Prime-Vendors
Notes: 1. This table represents only those invoices that were provided by Primes and paid. 2. Based on available data within PMO’s information systems (as of our data cut-off date of March 5, 2016), each element is calculated from a distinctive number of invoices. 3. Cumming did not provide dates for invoice process and payment tracking. Thus, only Elements C to F were populated (based on data from the PMO’s information systems). 4. Hill International does not carry sub-consultants. 5. “% of Total Invoice Amounts” represents the ratio of each vendor’s total invoiced amount versus the aggregate invoiced amounts by all vendors for this period. 6. All Primes except Cordoba furnished Sub-Consultant agreement templates for our review with respect to their subs.
Process Description Ave. Durations
(Calendar Days)
Contractual Requirement
(Days)
Arcadis US,
Inc.
Cordoba
Corporation
Cumming
Construction
Management
Hill
International,
Inc.
Jacobs
Project
Management
STV/AVA
Vanir
Construction
Management
Yang
Management,
Inc.
Sub to Prime A NA 6 12 Not Provided NA 6 8 11 5
Prime to CPT/PMO B 15th of each month after
POP End 17 24 Not Provided 17 15 19 14 5
CPT to Prime C
30
6 4 5 6 5 5 4 5
PMO Analysis D 17 25 14 23 16 10 17 7
District Review / Drawdown
E 8 8 8 9 7 7 8 8
Cut check / Mail F 2 2 1 2 2 2 1 2
Prime Receives Payment G NA 4 4 Not Provided 5 4 2 3 2
Prime Sends Payment to Sub
H Paid when Prime Paid
(varies from 7 to 15 days) 2 8 Not Provided NA 7 40 7 2
Integrated Cycle 54 71 Not Provided 57 49 63 55 30
Median - 54 NA Not Provided 59 49 59 53 28
Mode - 57 NA Not Provided - 57 35 53 26
Shortest - 35 NA Not Provided 44 38 35 43 26
Longest - 88 NA Not Provided 71 66 114 87 39
Invoice Count - 82 3 39 7 73 28 48 11
Total Invoice Amounts
- $1.4 M $26 K $616 K $107 K $1.3 M $320 K $869 K $158 K
% of Total Invoice Amounts
- 28% 1% 13% 2% 28% 7% 18% 3%
Notes: 1. Data was not available for Elements G and H between April 2014 and November 2015, since they were not within PMO’s functional or contractual purview. 2. Cumming did not provide data for the period between Dec 2015 to Feb 2016. 3. MATOC Prime-Vendors are required to submit their invoices within 15 days after the end of Period of Performance.
Invoice Process and Payment Review Actual Lifecycle for ‘MATOC Staff Augmentation Prime-Vendors’: Elements A to F
(Apr 2014 to Feb 2016)
A and B
A and B
A and B
C C
C
D D D
E E E
F F F
0
5
10
15
20
25
30
35
April 2014 to March 2015 April 2015 to November 2015 December 2015 to February 2015
DAYS
POP End to Receipt by CPT/PMO CPT to PMO PMO Analysis District Review, DD Cut Check/Mail Prime Receives Payment Prime Sends Payment to Sub
G
H
All MATOC Staff-Augmentation Vendors except Cumming All MATOC Staff-Augmentation Vendors
Invoice Process and Payment Review - Actual Lifecycle for MATOC Staff Augmentation: ‘AIM Consulting’ as Jacobs’ Sub-Vendor
(Dec 2015 to Feb 2016)
Notes: 1. These percentages are based on data provided by Jacobs to BuildLACCD (as well as available data within BuildLACCD’s information systems): 17 invoices at Elements A-B; 11 invoices at Elements C-G; and 18 invoices for Element H. 2. According to its Sub-Consultant Agreement, Jacobs was required to pay AIM Consulting within 7 days of Jacobs’ receipt of payment from BuildLACCD. 3. MATOC Prime-Vendors are required to submit their invoices within 15 days after the end of Period of Performance. 4. Element E (District Review/Drawdown) is demonstrated via a stand-alone bar graph (and is already accounted for in Elements C-F).
100%
91%
36% 91% 67%
9%
64% 9% 28%
6%
0
5
10
15
20
25
30
35
40
45
50
POP End to Receipt byCPT/PMO
CPT/PMO Receipt to MailCheck
District Review/Drawdown Prime Receives Payment Prime Paid to Send Paymentto Sub
DAYS
$ 279,000
C-F
A-B
G
H
E
Invoice Process and Payment Review - Actual Lifecycle for MATOC Staff Augmentation: ‘Global Design Build’ as Jacobs’ Sub-Vendor
(Dec 2015 to Feb 2016)
Notes: 1. These percentages are based on data provided by Jacobs to BuildLACCD (as well as available data within BuildLACCD’s information systems): 4 invoices at Elements A-B; and 9 invoices for all other elements. 2. According to its Sub-Consultant Agreement, Jacobs was required to pay its subs within 7 days of Jacobs’ receipt of payment from BuildLACCD. 3. MATOC Prime-Vendors are required to submit their invoices within 15 days after the end of Period of Performance. 4. Element E (District Review/Drawdown) is demonstrated via a stand-alone bar graph (and is already accounted for in Elements C-F).
25%
89%
33% 33% 67%
75%
11%
56%
11%
11% 11%
56%
22%
0
5
10
15
20
25
30
35
40
45
POP End to Receipt byCPT/PMO
CPT/PMO Receipt to MailCheck
District Review/Drawdown Prime Receives Payment Prime Paid to Send Paymentto Sub
DAYS
$ 62,000
C-F
A-B
G
H
E
Invoice Process and Payment Review: Observations/Inputs from CPT Interviews 1. Invoices from GCs require wet signatures from Architect/Engineer and IOR/LOR. CPTs
spend a lot of time to obtain these signatures if these individuals/entities are not on site.
2. Invoices for Retention Release from GCs also require wet signatures from Architect/Engineer and IOR/LOR. CPTs report that these signatures had been previously obtained from prior invoices, are therefore redundant, and need not be required.
3. Certain MATOC Prime Vendors do not submit invoices in a timely way. On occasion, these Primes hold onto invoices from prior months and submit them in a ‘bundle’ at a later date.
4. There was not a clear way to determine how long it takes for Prime Vendors to receive Cut Checks once mailed by the PMO.
5. On occasion, Prime Vendors submit invoice packages that are incomplete or inaccurate. This lengthens the time for processing by the CPT, since they must question the Primes for requisite clarifications and missing information. If vendors do not respond promptly, the CPT will reject the entire invoice (including any Sub-Vendors) and return it to the Prime.
6. On occasion, green-bag courier service was delayed or did not deliver invoices to the PMO.
Invoice Process and Payment Review: Observations/Inputs from MATOC Staff-Aug Prime Interviews 1. Agreements between Primes and Subs specified varying payment terms (between 7 and
15 calendar days).
2. Agreements between Primes and Subs often did not specify a timeline for invoice submission.
3. On occasion, Prime’s staff (or their Subs) have had difficulty in acquiring wet signatures from supervisors for labor logs.
4. After a shift in submission procedure was instituted by the PMO in December 2015, some Primes reported a lack of clear communication and a lack of transparent point of contact among PMO/CPTs. Around this time and on occasion, they experienced delays in invoice payments and difficulties in getting responses to inquiries from the PMO.
5. Some Primes indicated recent, improved communication from the PMO in regard to responding to questions and processing some of their back-logged invoices.
6. Some Primes elected to submit only after it had received all invoices from all Subs for a given period of performance. If one Sub did not submit in a timely way, then all Subs became delayed.
Invoice Process and Payment Review: Opportunities for Process Improvement – MATOC Contracts Element Suggested Improvement Savings in Days
A
1) Electronic signatures on ‘labor logs’ eliminates time to obtain on-site approvals and allows faster processing time between Subs and Primes
2) Automated monthly reminders between Primes to Subs will prompt invoices to be generated in a timely way
1 to 5 days
B
1) Automated monthly reminders between CPT/PMO to Primes will prompt invoices to be generated in a timely way
2) Electronic submission of invoices will reduce transit time of invoices among Primes, CPTs, and the PMO
3) Possible implementation of ‘PMIS’ Invoice Loading feature by Primes to expedite processing and to enhance transparency and communication
4) Assign a Point of Contact at the CPTs/PMO for each prime as a “go-to” resource to facilitate communication between PMO and Primes
1 to 3 days
C 1) Electronic signatures will reduce processing time by CPTs 2) Electronic submission of invoices between CPT and PMO will reduce transit time
1 to 3 days
D 1) Staffing and process review at PMO may alleviate backlog and processing time --
Invoice Process and Payment Review: Opportunities for Process Improvement – MATOC Contracts (Cont.) Element Suggested Improvement Savings in Days
E
1) Designate certain days for submission of Invoice and Drawdown Requests to District (i.e., Tuesday and Thursday of every week by 2:00 PM)
2) Designate back-up individual(s) at District for review and approval of Invoice and Drawdown Requests
3) Allocate Reserve Funds to the PMO to allow checks to be cut prior to District’s final approval
4) Streamline communication between District and LA County to release funds in a more accelerated manner
1 to 4 Days
F & G
Electronic Fund Transfers (EFTs) in lieu of paper checks that are wet-signed and mailed could lead to many efficiencies: 1) Automated authorizations eliminates the need for manual signatures and
mailing of individual checks 2) Less reliance on third-party delivery systems 3) Higher assurance that funds are received, and are received in a faster and more
timely way 4) Automated proof of payment
(See next slide)
Invoice Process and Payment Review: Opportunities for Process Improvement – MATOC Contracts (Cont.)
Element Suggested Improvement Savings in Days
F & G (Cont.)
5) Less administrative follow-up burden for PMO and District associated with lost checks
6) Automated notifications to Vendors when funds are wired 1 to 5 Days
H 1) EFTs between Primes and Subs will hasten the payment time --
Cumulative Time Savings
5 to 20 Days
Invoice Process and Payment Review
Multi-Award Task Order Contracts (MATOC): Professional Services Contracts
Slides 20 to 22
Invoice Process and Payment Review - Actual Lifecycle (Apr 2014 to Mar 2015) Top 5 MATOC Professional Services Prime-Vendors
Notes: 1. We selected the top five vendors with the highest invoiced amounts in this period, as tabulated above. 2. Based on available data within PMO’s information systems (as of our data cut-off date of March 5, 2016), each element is calculated from a distinctive number of invoices. 3. Data was not available for Elements G and H, since they were not within the PMO’s Functional or Contractual purview. 4. “% of Total Invoice Amounts” represents the ratio of each vendor’s total invoiced amount versus the aggregate invoiced amounts by all tabulated vendors for this period.
Process Description Ave. Durations
(Calendar Days)
California Testing &
Inspections, Inc.
Cannon Design
Group
Gonzalez Goodale
Architects
Hammel, Green &
Abrahamson, Inc.
PBWS Architects,
LLP
Period of Performance (POP) End to Receipt by CPT/PMO
A and B 32 61 15 35 44
CPT to Prime C 7 8 11 5 7
PMO Analysis D 8 2 14 5 6
District Review / Drawdown E 6 6 7 6 5
Cut check / Mail F 1 - 3 1 2
Integrated Cycle 68 77 51 48 60
Median 68 77 46 40 60
Mode - 77 - - 60
Invoice Count 3 2 4 3 9
Total Invoice Amounts $96 K $50 K $137 K $114 K $172 K
% of Total Invoice Amounts 17% 9% 24% 20% 30%
Invoice Process and Payment Review - Actual Lifecycle (Apr 2015 to Feb 2016) Top 5 MATOC Professional Services Prime-Vendors
Notes: 1. We selected the top five vendors with the highest invoiced amounts in this period, as tabulated above. 2. Based on available data within PMO’s information systems (as of our data cut-off date of March 5, 2016), each element is calculated from a distinctive number of invoices. 3. Data was not available for Elements G and H, since they were not within the PMO’s Functional or Contractual purview. 4. “% of Total Invoice Amounts” represents the ratio of each vendor’s total invoiced amount versus the aggregate invoiced amounts by all tabulated vendors for this period.
Process Description Ave. Durations
(Calendar Days)
American Engineering
Labs, Inc.
California Testing &
Inspections, Inc.
Cannon Design
Group
Southwest Inspection
& Testing, Inc.
Tate Snyder Kimsey,
Inc.
Period of Performance (POP) End to Receipt by CPT/PMO
A and B 83 32 40 86 18
CPT to Prime C 6 5 5 8 8
PMO Analysis D 12 12 14 12 10
District Review / Drawdown E 7 8 5 7 7
Cut check / Mail F 2 1 3 3 2
Integrated Cycle 110 57 65 115 42
Median 97 44 64 103 38
Mode 35 54 - 96 29
Invoice Count 43 33 9 34 20
Total Invoice Amounts $842 K $438 K $514 K $526 K $420 K
% of Total Invoice Amounts 31% 16% 19% 19% 15%
Invoice Process and Payment Review Actual Lifecycle for ‘MATOC Professional Services Prime-Vendors’: Elements A to F
(Apr 2014 to Feb 2016)
Notes: 1. MATOC Prime-Vendors are required to submit their invoices within 15 days after the end of Period of Performance. We observed these invoices are often not submitted on time by the Primes. In addition, we noted some late invoices submitted to PMO/CPTs up to a year after rendering services by the vendor. PMO/CPTs should enforce this contractual term to vendors more rigorously. (Refer to our Recommendation for Elements A-B in slide 16 of this report for more detail) 2. In our review of MATOC – Professional Services invoices, we observed similar trends within Elements C to F, when compared to MATOC – Staff Augmentation invoices.
A and B
A and B
C C D
D
E E
F F
-
5
10
15
20
25
30
35
40
45
50
55
April 2014 to March 2015 April 2015 to February 2016
DAYS
POP End to Receipt by CPT/PMO CPT to PMO PMO Analysis District Review, DD Cut Check/Mail
Invoice Process and Payment Review
General Contractor Contracts
Slides 24 to 26
Invoice Process and Payment Review - Actual Lifecycle (Apr 2014 to Mar 2015) Top 10 General Contractors
Notes: 1. We selected the top ten General Contractors with the highest invoiced amounts in this period, as tabulated above. 2. Based on available data within PMO’s information systems (as of our data cut-off date of March 5, 2016), each element is calculated from a distinctive number of invoices. 3. Data was not available for Elements G and H, since they were not within the PMO’s Functional or Contractual purview. 4. “% of Total Invoice Amounts” represents the ratio of each vendor’s total invoiced amount versus the aggregate invoiced amounts by all tabulated vendors for this period.
Process Description Avg. Durations
(Calendar Days)
Charles
Pankow
Builders
Clark
Construction
Group
Edge
Construction,
LLC
Harper
Construction
Co.
Hensel
Phelps
Construction
Masters
Contracting
Corp.
McCarthy
Building Co.
Pankow
Special
Projects
Pinner
Construction
Company
Taisei
Construction
Period of Performance (POP) End to Receipt by CPT/PMO
A and B 36 17 36 27 27 12 10 72 25 12
CPT to Prime C 3 3 10 6 7 8 4 10 11 8
PMO Analysis D 11 9 15 14 19 14 10 15 19 13
District Review / Drawdown
E 6 8 6 6 7 6 7 7 6 6
Cut check / Mail F 2 1 2 2 4 1 2 2 2 3
Integrated Cycle - - - - - - - - - -
Median 47 35 61 52 59 42 30 76 58 53
Mode 30 - 61 44 89 31 30 - 61 -
Invoice Count 25 5 12 44 16 14 13 22 16 11
Total Invoice Amounts
$16.6 M $5.5 M $8.7 M $38.4 M $17 M $6.1 M $14.9 M $7.1 M $18.8 M $5.5 M
% of Total Invoice Amounts
12% 4% 6% 28% 12% 4% 11% 5% 14% 4%
Invoice Process and Payment Review - Actual Lifecycle (Apr 2015 to Feb 2016) Top 10 General Contractors
Process Description Avg. Durations
(Calendar Days)
Balfour Beatty
Construction
Bernards
Bros., Inc.
Charles
Pankow
Builders
Clark
Construction
Group
Edge
Construction
, LLC
Harper
Construction
Co.
Hensel
Phelps
Construction
Masters
Contracting
Corp.
McCarthy
Building Co.
Pinner
Construction
Company
Period of Performance (POP) End to Receipt by CPT/PMO
A and B 37 96 65 18 56 14 77 28 20 18
CPT to Prime C 13 12 4 5 7 5 11 6 4 11
PMO Analysis D 12 15 11 12 16 15 22 18 13 15
District Review / Drawdown E 7 7 7 7 6 7 7 7 6 5
Cut check / Mail F 3 3 2 3 3 3 2 3 3 4
Integrated Cycle - - - - - - - - - -
Median 71 88 52 45 78 45 81 59 29 49
Mode 96 96 35 - 80 35 43 35 43 43
Invoice Count 41 34 18 10 14 44 15 30 16 12
Total Invoice Amounts $5.6 M $16.6 M $9.4 M $17.9 M $9.3 M $30.2 M $7.8 M $6.7 M $17.4 M $10.1 M
% of Total Invoice Amounts
4% 13% 7% 14% 7% 23% 6% 5% 13% 8%
Notes: 1. We selected the top ten General Contractors with the highest invoiced amounts in this period, as tabulated above. 2. Based on available data within PMO’s information systems (as of our data cut-off date of March 5, 2016), each element is calculated from a distinctive number of invoices. 3. Data was not available for Elements G and H, since they were not within the PMO’s Functional or Contractual purview. 4. “% of Total Invoice Amounts” represents the ratio of each vendor’s total invoiced amount versus the aggregate invoiced amounts by all tabulated vendors for this period.
Invoice Process and Payment Review Actual Lifecycle for ‘General Contractors’: Elements A to F
(Apr 2014 to Feb 2016)
A and B
A and B
C C
D D
E E
F F
-
5
10
15
20
25
30
35
40
45
50
April 2014 to March 2015 April 2015 to February 2016
DAYS
POP End to Receipt by CPT/PMO CPT to PMO PMO Analysis District Review, DD Cut Check/Mail
Notes: 1. General Contractors (GCs) are required to submit their invoices on 1st day of the month after the end of Period of Performance. However, GC invoices on occasion involve Stop Notices and similar claims that prolong the invoice approval and payment process until such claims are resolved. 2. In our review of General Contractor invoices, we observed similar trends within Elements C to F, when compared to other contract type invoices (e.g., MATOC contracts invoices).
Invoice Process and Payment Review
Professional Services Contracts (non-MATOC)
Slides 28 to 30
Invoice Process and Payment Review - Actual Lifecycle (Apr 2014 to Mar 2015) Professional Services Prime-Vendors (non-MATOC)
Professional Services (non-MATOC) Analysis is underway as of May 13 and will be completed by May 25 for the next FMPOC Meeting
Invoice Process and Payment Review - Actual Lifecycle (Apr 2015 to Feb 2016) Professional Services Prime-Vendors (non-MATOC)
Professional Services (non-MATOC) Analysis is underway as of May 13 and will be completed by May 25 for the next FMPOC Meeting
Invoice Process and Payment Review Actual Lifecycle for ‘Professional Services Prime-Vendors (non-MATOC)’: Elements A to F
(Apr 2014 to Feb 2016)
Professional Services (non-MATOC) Analysis is underway as of May 13 and will be completed by May 25 for the next FMPOC Meeting
Invoice Process and Payment Review
Furniture, Fixture and Equipment (FF&E) Contracts
Slides 32 to 34
Invoice Process and Payment Review - Actual Lifecycle (Apr 2014 to Mar 2015) FF&E Vendors
FF&E Analysis is underway as of May 13 and will be completed by May 25 for the next FMPOC Meeting
Invoice Process and Payment Review - Actual Lifecycle (Apr 2015 to Feb 2016) FF&E Vendors
FF&E Analysis is underway as of May 13 and will be completed by May 25 for the next FMPOC Meeting
Invoice Process and Payment Review Actual Lifecycle for ‘Professional Services Prime-Vendors (non-MATOC)’: Elements A to F
FF&E Vendors
FF&E Analysis is underway as of May 13 and will be completed by May 25 for the next FMPOC Meeting
Building for tomorrow’s leaders 1
Los Angeles Community College District
PROGRAM MANAGEMENT SERVICES
Active Construction Summary
Facilities Master Planning and Oversight Committee
May 25, 2016
Building for tomorrow’s leaders 2
Active Construction: City College
NOTE: Does not include projects in programming, in procurement, in
design, at DSA, in closeout, or completed. *-Date does not reflect revised date approved via change order.
**-Inclusive of FF&E, retention, close-out and all soft costs.
(All data and dates are current through March 2016) NTP = Notice to Proceed. EAC = Estimate at completion.
Project # Projects Under
Construction
NTP
construction
/ design-build
*Contract
substantial
completion
Forecast
substantial
completion
**Budget **Expended **EAC
01C-110 Holmes Hall
Modernization 02/10/14 01/09/15 05/31/16 $13,009,791 $8,566,759 $13,009,791
01C-134 Student Service Center 02/10/14 08/09/15 06/30/16 $38,105,141 $25,074,218 $38,105,141
01C-173.03 RWGPL - Traffic
Mitigation (Red Line) 12/15/14 01/14/16 09/30/16 $8,471,879 $3,926,760 $8,471,879
Building for tomorrow’s leaders 3
Active Construction: East L.A. College
Project # Projects Under
Construction
NTP
construction
/ design-build
*Contract
substantial
completion
Forecast
substantial
completion
**Budget **Expended **EAC
02E-222.03
Science Career & Math
Bldg G5
(Classrooms/Labs)
04/23/14 06/21/16 08/20/16 $57,801,981 $29,731,540 $57,449,900
02E-222.04 Science Career & Math
Bldg G7 (Lecture Bldg.) 04/23/14 06/21/16 08/20/16 $3,623,162 $1,330,784 $3,770,911
NOTE: Does not include projects in programming, in procurement, in
design, at DSA, in closeout, or completed. *-Date does not reflect revised date approved via change order.
**-Inclusive of FF&E, retention, close-out and all soft costs.
(All data and dates are current through March 2016) NTP = Notice to Proceed. EAC = Estimate at completion.
Building for tomorrow’s leaders 4
Active Construction: Harbor College
Project # Projects Under
Construction
NTP
construction
/ design-build
*Contract
substantial
completion
Forecast
substantial
completion
**Budget **Expended **EAC
03H-307 Theater Drama Speech
Building 09/02/10 09/08/15 08/19/16 $17,200,876 $15,860,418 $16,773,250
03H-350.01 SAILS Student Union 09/07/10 04/05/14 07/31/18 $52,981,751 $15,599,159 $63,731,497
(All data and dates are current through March 2016) NTP = Notice to Proceed. EAC = Estimate at completion.
NOTE: Does not include projects in programming, in procurement, in
design, at DSA, in closeout, or completed. *-Date does not reflect revised date approved via change order.
**-Inclusive of FF&E, retention, close-out and all soft costs.
Building for tomorrow’s leaders 5
Active Construction: Mission College
Project # Projects Under
Construction
NTP
construction
/ design-build
*Contract
substantial
completion
Forecast
substantial
completion
**Budget **Expended **EAC
04M-405 Media Arts Center 11/12/09 10/03/11 03/31/17 $46,378,970 $26,448,543 $46,378,969
04M-419 Campus Modernization
Phase 1 08/07/09 02/29/16 05/31/16 $21,898,351 $20,334,270 $21,859,092
(All data and dates are current through March 2016) NTP = Notice to Proceed. EAC = Estimate at completion.
NOTE: Does not include projects in programming, in procurement, in
design, at DSA, in closeout, or completed. *-Date does not reflect revised date approved via change order.
**-Inclusive of FF&E, retention, close-out and all soft costs.
Building for tomorrow’s leaders 6
Active Construction: Pierce College
Project # Projects Under
Construction
NTP
construction
/ design-build
*Contract
substantial
completion
Forecast
substantial
completion
**Budget **Expended **EAC
05P-502 Life Science, Chemistry,
Physics Building 08/14/15 05/12/16 09/16/16 $22,006,996 $13,577,222 $22,006,996
05P-505.02
Phase II Renovations -
Administration Building -
Interior and Exterior
08/14/15 05/12/16 09/16/16 $11,390,485 $7,909,660 $11,390,485
05P-507
Phase II Renovations -
Computer Science and
Computer Learning
Phase 2 component
finishing at a later date
08/14/15 08/17/16 09/16/16 $10,398,954 $3,772,838 $10,398,954
(All data and dates are current through March 2016) NTP = Notice to Proceed. EAC = Estimate at completion.
NOTE: Does not include projects in programming, in procurement, in
design, at DSA, in closeout, or completed. *-Date does not reflect revised date approved via change order.
**-Inclusive of FF&E, retention, close-out and all soft costs.
Building for tomorrow’s leaders 7
Active Construction: Pierce College (cont.)
Project # Projects Under
Construction
NTP
construction
/ design-build
*Contract
substantial
completion
Forecast
substantial
completion
**Budget **Expended **EAC
05P-510
Phase II Renovations -
Behavioral Science,
Social science,
Mathematics, and English
Buildings
Phase 2 component
finishing at a later date
08/14/15 08/17/16 09/16/16 $17,147,992 $4,525,299 $17,147,993
05P-530.01 Campus Center (Existing)
- General 08/14/15 05/12/16 09/16/16 $2,577,379 $2,540,689 $2,577,379
05P-535.07 SLE Faculty
Center/Campus Center 08/14/15 05/12/16 09/16/16 $3,935,969 $2,071,011 $3,935,969
(All data and dates are current through March 2016) NTP = Notice to Proceed. EAC = Estimate at completion.
NOTE: Does not include projects in programming, in procurement, in
design, at DSA, in closeout, or completed. *-Date does not reflect revised date approved via change order.
**-Inclusive of FF&E, retention, close-out and all soft costs.
Building for tomorrow’s leaders 8
Active Construction: Pierce College (cont.)
Project # Projects Under
Construction
NTP
construction
/ design-build
*Contract
substantial
completion
Forecast
substantial
completion
**Budget **Expended **EAC
05P-535.02
SLE - North of Mall -
Classroom
Modernization/Technology
/Low Voltage
Phase 2 component
finishing at a later date
08/14/15 08/17/16 09/16/16 $9,268,054 $4,262,728 $9,268,054
05P-542.06
SLE - North of Mall -
ADA/Landscaping
Phase 2 component
finishing at a later date
08/14/15 08/17/16 09/16/16 $7,673,426 $3,072,761 $7,673,426
(All data and dates are current through March 2016) NTP = Notice to Proceed. EAC = Estimate at completion.
NOTE: Does not include projects in programming, in procurement, in
design, at DSA, in closeout, or completed. *-Date does not reflect revised date approved via change order.
**-Inclusive of FF&E, retention, close-out and all soft costs.
Building for tomorrow’s leaders 9
Active Construction: Trade-Tech College
Project # Projects Under
Construction
NTP
construction
/ design-build
*Contract
substantial
completion
Forecast
substantial
completion
**Budget **Expended **EAC
07T-720.01 East Parking Structure 07/06/15 07/26/16 08/10/16 $40,803,429 $22,225,851 $40,782,310
07T-772.06
East Campus Substation
and Electrical Distribution
System
07/06/15 07/26/16 11/09/16 $7,036,866 $2,935,319 $7,015,598
07T-720.03 East Campus Ground
Improvements 07/06/15 07/26/16 08/10/16 $1,581,881 $11,803 $1,581,881
(All data and dates are current through March 2016) NTP = Notice to Proceed. EAC = Estimate at completion.
NOTE: Does not include projects in programming, in procurement, in
design, at DSA, in closeout, or completed. *-Date does not reflect revised date approved via change order.
**-Inclusive of FF&E, retention, close-out and all soft costs.
Building for tomorrow’s leaders 10
Active Construction: Valley College
Project # Projects Under
Construction
NTP
construction
/ design-build
*Contract
substantial
completion
Forecast
substantial
completion
**Budget **Expended **EAC
08V-836
Community Workforce
Development Center/New
Administration a.k.a.
Valley Glen Gateway
(VGG)
01/28/14 09/11/15 12/30/16 $43,318,309 $27,788,621 $46,678,335
08V-839 Multi-Purpose Community
Services Center 04/15/13 08/20/16 09/26/16 $24,926,523 $21,870,441 $24,926,524
08V-842 Monarch Center (Student
Union Annex) 01/28/14 04/18/14 05/02/16 $37,832,079 $35,023,862 $37,832,079
(All data and dates are current through March 2016) NTP = Notice to Proceed. EAC = Estimate at completion.
NOTE: Does not include projects in programming, in procurement, in
design, at DSA, in closeout, or completed. *-Date does not reflect revised date approved via change order.
**-Inclusive of FF&E, retention, close-out and all soft costs.
Building for Tomorrow’s Leaders
LACCD Program Management 515 S. Flower Street, Suite 900 Los Angeles, California 90071 www.build-laccd.org 213.593 8000 tel 866.817.1051 fax
*--Date does not reflect revised date approved via change order. **-Inclusive of FF&E, retention, close-out and all soft costs.
ACTIVE CONSTRUCTION SUMMARY (All data and dates are current through March 2016)
Does not include projects in programming, in procurement, in design, at DSA, in closeout, or completed. NTP = Notice to Proceed. EAC = Estimate at completion.
No. Project # Projects Under Construction NTP
construction / design-build
*Contract substantial completion
Forecast substantial completion
**Budget **Expended **EAC
Los Angeles City College
1 01C-110 Holmes Hall Modernization 02/10/14 01/09/15 05/31/16 $ 13,009,791 $ 8,566,759 $ 13,009,791
2 01C-134 Student Service Center 02/10/14 08/09/15 06/30/16 $ 38,105,141 $ 25,074,218 $ 38,105,141
3 01C-173.03 RWGPL - Traffic Mitigation (Red Line) 12/15/14 01/14/16 09/30/16 $ 8,471,879 $ 3,926,760 $ 8,471,879
East Los Angeles College
4 02E-222.03 Science Career & Math Bldg G5 (Classrooms/Labs)
04/23/14 06/21/16 08/20/16 $ 57,801,981 $ 29,731,540 $ 57,449,900
5 02E-222.04 Science Career & Math Bldg G7 (Lecture Bldg.) 04/23/14 06/21/16 08/20/16 $ 3,623,162 $ 1,330,784 $ 3,770,911
Los Angeles Harbor College
6 03H-307 Theater Drama Speech Building 09/02/10 09/08/15 08/19/16 $ 17,200,876 $ 15,860,418 $ 16,773,250
7 03H-350.01 SAILS Student Union 09/07/10 04/05/14 07/31/18 $ 52,981,751 $ 15,599,159 $ 63,731,497
Los Angeles Mission College
8 04M-405 Media Arts Center 11/12/09 10/03/11 03/31/17 $ 46,378,970 $ 26,448,543 $ 46,378,969
9 04M-419 Campus Modernization Phase 1 08/07/09 02/29/16 05/31/16 $ 21,898,351 $ 20,334,270 $ 21,859,092
Los Angeles Pierce College
10 05P-502 Life Science, Chemistry, Physics Building 08/14/15 05/12/16 09/16/16 $ 22,006,996 $ 13,577,222 $ 22,006,996
11 05P-505.02 Phase II Renovations - Administration Building - Interior and Exterior
08/14/15 05/12/16 09/16/16 $ 11,390,485 $ 7,909,660 $ 11,390,485
12 05P-507 Phase II Renovations - Computer Science and Computer Learning Phase 2 component finishing at a later date
08/14/15 08/17/16 09/16/16 $ 10,398,954 $ 3,772,838 $ 10,398,954
Building for Tomorrow’s Leaders
*--Date does not reflect revised date approved via change order. **-Inclusive of FF&E, retention, close-out and all soft costs.
Active Construction Summary – March 2016 Page 2
No. Project # Projects Under Construction NTP construction / design-build
*Contract substantial completion
Forecast substantial completion
**Budget **Expended **EAC
13 05P-510 Phase II Renovations - Behavioral Science, Social science, Mathematics, and English Buildings Phase 2 component finishing at a later date
08/14/15 08/17/16 09/16/16 $ 17,147,992 $ 4,525,299 $ 17,147,993
14 05P-530.01 Campus Center (Existing) - General 08/14/15 05/12/16 09/16/16 $ 2,577,379 $ 2,540,689 $ 2,577,379
15 05P-535.07 SLE Faculty Center/Campus Center 08/14/15 05/12/16 09/16/16 $ 3,935,969 $ 2,071,011 $ 3,935,969
16 05P-535.02 SLE - North of Mall - Classroom Modernization/Technology/Low Voltage Phase 2 component finishing at a later date
08/14/15 08/17/16 09/16/16 $ 9,268,054 $ 4,262,728 $ 9,268,054
17 05P-542.06 SLE - North of Mall - ADA/Landscaping Phase 2 component finishing at a later date
08/14/15 08/17/16 09/16/16 $ 7,673,426 $ 3,072,761 $ 7,673,426
Los Angeles Trade Tech College
18 07T-720.01 East Parking Structure 07/06/15 07/26/16 08/10/16 $ 40,803,429 $ 22,225,851 $ 40,782,310
19 07T-772.06 East Campus Substation and Electrical Distribution System
07/06/15 07/26/16 11/09/16 $ 7,036,866 $ 2,935,319 $ 7,015,598
20 07T-720.03 East Campus Ground Improvements 07/06/15 07/26/16 08/10/16 $ 1,581,881 $ 11,803 $ 1,581,881
Los Angeles Valley College
21 08V-836 Community Workforce Development Center/New Administration a.k.a. Valley Glen Gateway (VGG)
01/28/14 09/11/15 12/30/16 $ 43,318,309 $ 27,788,621 $ 46,678,335
22 08V-839 Multi-Purpose Community Services Center 04/15/13 08/20/16 09/26/16 $ 24,926,523 $ 21,870,441 $ 24,926,524
23 08V-842 Monarch Center (Student Union Annex) 01/28/14 04/18/14 05/02/16 $ 37,832,079 $ 35,023,862 $ 37,832,079
TOTAL $499,370,244 $298,460,556 $512,766,413
Building for tomorrow’s leaders
Invoice & Payment Process Improvements
• PMO’s action plan to improve BuildLACCD’s invoice process & payment procedures:
• Recommended actions under review by PMO prior to potential implementation:
Action Benefit
Forecasted
Completion
• Use of e-signature platform • Reduction in processing time (timesheets, invoices) July 2016
• Automated email reminders
• Electronic invoice submission via email
• Reduction in delayed submissions
• Reduction in transit time June 2016
• Point of Contact assignment at the CPTs/PMO for
each Prime
• Serves as a “go-to” resource to facilitate
communication & efficiency June 2016
• Designate days for invoice submission & drawdown
requests to District • Consistency, efficiency Complete
• Back-up District personnel for review/approval of
invoice/drawdown requests • Efficiency Complete
• District to allocate Reserve Funds to PMO • Reduction in release of checks timing Complete
• Streamline District & LA County communications • Accelerate release of funds Complete
• Electronic Funds Transfer (PMO to Prime) • Efficiency (in lieu of wet-signed and mailed) TBD*
Action Benefit
• PMIS Invoice Loading feature • Expedite processing
• Enhance transparency and communication
• PMO staffing and process review • Alleviate backlog and processing time
• Electronic Funds Transfers (Prime to Sub)
Contingent upon EFT of PMO to Prime resolution
• Accelerate payment time
*PMO to coordinate with the District to obtain District approval for PMO to communicate with the Bank and set up the process.
Building for tomorrow’s leaders 1
Los Angeles Community College District
PROGRAM MANAGEMENT SERVICES
PMO Annual Update
Facilities Master Planning and Oversight Committee
May 25, 2016
Building for tomorrow’s leaders 2
BuildLACCD Financial Summary
A B C D E F=B-E
Variance Explanation(s) Funding June 2015
Current Funding Dec 2015
Contracted Dec 2015
Expended Dec 2015
EAC Dec 2015
Variance Funding - EAC
Colleges $4.75 B $4.75 B $4.16 B $3.86 B $4.76 B $(11.21 M)
EAC adjustment ($11.2M) not captured by Dashboard data run due to timing issue. Resolved in January 2016 Dashboard to show zero variance.
Satellites $330.37 M $330.37 M $216.44 M $209.91 M $335.99 M $(5.62 M) Funding adjustment pending District resolution.
Central Services $541.02 M $541.02 M $440.41 M $368.38 M $541.02 M $- N/A
Districtwide Initiatives
$371.62 M $374.65 M $205.83 M $160.01 M $374.64 M $0.01 M
June to Dec Funding: Funding transfer from Pierce College to consolidate project IT funds into one financial ID. Current Funding to EAC: EAC adjustment not captured by the Dashboard data run due to timing issue. Resolved in January 2016 Dashboard to show zero variance.
Retire District Debt & Refinance
$117.16 M $117.16 M $109.64 M $109.64 M $117.16 M $- N/A
District Bond Contingency
$14.64 M $14.64 M $- $- $1.53 M $13.12 M N/A
Program Reserve1 $140.00 M $133.17 M $- $- $- $133.17 M Funding transfer to Mission College.
TOTAL $6.26 B $6.26 B $5.13 B $4.70 B $6.13 B $129.47 M
Source: December 2015 Dashboard Report
1 Program Reserve EAC currently under evaluation to account for outstanding Program-wide exposure.
Building for tomorrow’s leaders 3
College-Level Financial Summary
A B C D E F=B-E
Variance Explanation(s)
Funding June 2015
Current Funding Dec 2015
Contracted Dec 2015
Expended Dec 2015
EAC Dec 2015
Variance Funding - EAC
City $568.44 M $568.44 M $482.14 M $452.76 M $568.44 M $- N/A
East $664.82 M $664.82 M $622.67 M $573.94 M $664.82 M $- N/A
Harbor $449.24 M $449.24 M $440.22 M $382.64 M $460.44 M $(11.21 M)
EAC adjustment not captured by Dashboard data run due to timing issue. Resolved in January 2016 Dashboard to show zero variance.
Mission $438.68 M $445.51 M $420.83 M $399.88 M $445.51 M $- Funding variance (June to Dec): Funds transfer from Program Reserve.
Pierce $627.76 M $625.06 M $499.49 M $440.33 M $625.06 M $-
Funding variance (June to Dec): Funds transfer from Pierce to 40J IT to consolidate budget under one financial ID.
Southwest $405.39 M $405.39 M $375.46 M $370.27 M $405.39 M $- N/A
Trade $582.29 M $582.29 M $467.22 M $433.74 M $582.29 M $- N/A
Valley $612.49 M $612.49 M $490.64 M $449.08 M $612.49 M $- N/A
West $400.91 M $400.91 M $360.24 M $354.30 M $400.91 M $- N/A
TOTAL $4.75 B $4.75 B $4.16 B $3.86 B $4.76 B $(11.21 M) See Harbor Variance Explanation above.
Source: December 2015 Dashboard Report
Building for tomorrow’s leaders 4
Risk Exposure Analysis
• Risk cost workshops conducted at the Colleges & PMO (Oct-Dec 2015)
• Monte Carlo analysis run in December 2015 for all active registers
• Analysis determined risk exposure at the 80th percentile
As of December 31, 2015
Potential Commitments $39.30M
College COPs: $12.10M
Aggregate College Risk Exposure $61.34M
Program Risk Exposure $60.78M
Aggregate College Contingency
$100.65M
Aggregate College Reserve $27.39M
40J Risk Exposure $2.10M
District Bond Contingency $14.64M
Program Reserve $133.17M
$-
$50,000,000
$100,000,000
$150,000,000
$200,000,000
$250,000,000
$300,000,000
Aggregate Risk Exposure & Outstanding COPs & Commitments Aggregate Contingencies & Reserves
LACCD Aggregate Risk Exposure as a Function of College and District Contingencies & Reserves
Building for tomorrow’s leaders 5
College Projects Status Summary
Pending Planning Design Construction Completed TOTAL
City 6 3 3 5 52 69 East 3 4 3 3 88 101 Harbor 7 0 1 3 55 66 Mission 1 1 5 4 66 77 Pierce 7 12 4 8 75 106 Southwest 0 2 2 0 71 75 Trade 7 8 0 3 64 82 Valley 6 6 2 5 45 64 West 4 1 9 0 47 61 Satellites 0 2 0 0 10 12
Projects Remaining Breakdown
12% 9%
8%
8%
22%
3%
13%
14%
10% 1%
City East Harbor Mission
Pierce SW Trade Valley
West Satellites
As of December 2015
Chart does not include 40J college projects such as ADA, Stormwater, Technology, Energy, etc.
80 Projects Pending/In Planning
29 Projects in Design/DSA
Review
31 Projects in Construction
41 Projects forecasted to start
Construction in 2016
Building for tomorrow’s leaders 6
$-
$20
$40
$60
$80
Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15
Aw
ard
s (
$M
)
2015 New Contract Awards
Design Construction Other
Procurement Activity Summary
40 39
57
25 26
51
0102030405060
Ju
l-1
5
Aug
-15
Sep
-15
Oct-
15
Nov-1
5
Dec-1
5
No
. o
f T.O
.s
Task Orders Issued
36
18 21
31
20 24
0
10
20
30
40
Ju
l-1
5
Aug
-15
Sep
-15
Oct-
15
Nov-1
5
Dec-1
5
No
. o
f P.O
.s
Purchase Orders Issued
2.4 2.5 2.6
1.3
0.7
2.5
$-
$0.5
$1.0
$1.5
$2.0
$2.5
$3.0
Ju
l-1
5
Aug
-15
Sep
-15
Oct-
15
Nov-1
5
Dec-1
5
Mil
lio
ns
Value of TOs and POs Issued
Construction: $74.20M
Design: $7.71M Contract value only
Building for tomorrow’s leaders 7
Remaining Work by College
$0
$20,000,000
$40,000,000
$60,000,000
$80,000,000
$100,000,000
$120,000,000
$140,000,000
$160,000,000
$180,000,000
$200,000,000
Total Remaining Funds Remaining Construction Funds Only
* Southgate is included within the Satellite category per the Dashboard report. Remaining Work: Current Funding less Expended to-date (data as of 12/31/15).
As of December 2015
Building for tomorrow’s leaders 8
0
5
10
15
20
25
30
35
40
45
50
Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15
No
. of
Pro
ject
s Projects Status Activity
Planning
Design/DSA
Construction
Design & Construction
1
10
1
3 3 2 2
1
0
2
4
6
8
10
12
Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15
No
. of
Pro
ject
s
Construction Activity
Construction NTP Issued Substantial Completion Achieved
Building for tomorrow’s leaders 9
DSA Certification
26 Projects
Closed with Certification
Construction Value: $389M
0
5
10
15
20
25
30
35
40
Jul-15 Dec-15
Nu
mb
er
of
Pro
jec
ts
Closed without Certification Trend
College Projects CWC July - Dec 2015
City 2
East 6
Harbor 4
Mission 1
Pierce 3
Southwest 3
Trade 1
Valley 4
West 2
TOTAL 26
CWC: Closed with Certification
CWOC: Closed without Certification
* Two additional projects closed without certification in September
2015 (City, Pierce) and have since been submitted to DSA for
certification.
Projects
CWOC July 2015
Remaining
CWOC * Dec 2015
6 7
9 7
2 0
2 1
6 5
1 0
5 5
6 3
0 1
37 29
22% Drop in Total Projects
Closed without Certification
Building for tomorrow’s leaders 10
July –December 2015
7 Recordables
2015 NAICS Avg. 3.2
TRIR Goal: 3.2
TRIR Actual: 3.1
NAICS: North American Industry Classification System
TRIR: Total Recordable Injury Rate
Safety Report
1
3
0
1 1 1
0
1
2
3
4
5
Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15
To
tal M
on
thly
In
cid
en
ts
Incidents by Month
79,615 80,705
69,816
84,313
64,717 62,889
-
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
90,000
Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15
To
tal M
an
Ho
urs
Man Hours by Month
Building for tomorrow’s leaders 11
College Key Performance Indicators
• New criteria established and implemented for Risk and Schedule KPIs
• Change Order KPI criteria under development
• 2 New KPIs under development: Commissioning & Closeout
• KPI Comparison Report (June 30, 2015 vs. December 31, 2015):
Jun-15 Dec-15 Jun-15 Dec-15 Jun-15 Dec-15 Jun-15 Dec-15 Jun-15 Dec-15 Jun-15 Dec-15
Compliant
Needs
Improvement
Unsatisfactory
Compliance
Construction
Schedule
Monthly
Risk
Quarterly
Time to Execute
Change Orders
Monthly
Variance 0 to 1%
Variance > 1%
Budget to
EAC Variance
Monthly
Invoice
Timing
Monthly
Safety
Monthly
< 20 days
20 to 30 days
30 + days
RIR < 3.4
RIR w ithin 10% of
3.4
RIR > 3.4
> 90% C.O.s approved
w ithin 90 days
50% - 89% C.O.s
approved w ithin 90 days
Variance < = 0%
City
East
Harbor
Mission
Pierce
Southwest
Trade
Valley
West
< 50% C.O.s approved
w ithin 90 days
All Individual Projects Green
(SC Slippage 0 to 30 days)
Total of All Projects is Yellow
(SC Slippage 31 - 60 days),
or One Project Yellow or Red
(SC Slippage > 60 days)
Total of All Projects is Red
(SC Slippage > 60 days)
Weighted criteria
score 100% - 85%
Weighted criteria
score 84% - 50%
Weighted criteria
score 49% - 0%
New Criteria New Criteria Criteria Under Dev.
Building for tomorrow’s leaders 12
LSEDV Contract Award Breakdown
Contract Category Total Firms
LSEDV Firms
LSEDV Firms with
Task Orders
Non-LSEDV Firms with
Task Orders
Staff Augmentation 178 124 34 15
Architecture/Engineering 18 7 5 7
Environmental 12 6 6 4
Inspector of Record 18 13 7 4
Laboratory of Record 9 5 5 4
Whole Bldg. Commissioning
11 3 2 5
Professional Services 246 158 59 39
Construction Companies 51 20 N/A N/A
LSEDV : Local, Small, Emerging, Disabled Veterans
297 Total
Companies
178 LSEDV
Companies
60% Task Orders
awarded to
LSEDV Figures are not totaled under the “Total Companies” and “LSEDV Companies” to avoid
double-counting.
December 2015
Building for tomorrow’s leaders 13
Local Worker Hiring Performance
14,598 Workers performed
work on 28 active projects
4,733 or 32%, are local
(through Dec 2015)
43% 39%
27%
32% 20% 25%
34% 41%
30% 34%
27% 37% 33% 43% 27%
29% 36% 37% 34%
0%5%10%15%20%25%30%35%40%45%50%
0
5,000
10,000
15,000
20,000
25,000
30,000
35,000
Total Craft Workers Local Workers
Contractor Local Worker Hiring Performance
28.00%
29.00%
30.00%
31.00%
32.00%
33.00%
07/15 08/15 09/15 10/15 11/15 12/15Actual Local Hire Participation (By Month)
Building for tomorrow’s leaders 14
College Internship Program Monthly Intern Participation (H1-B Grant Funded On-Campus/PMO Positions)
0
1
2
3
4
5
6
07/2015 08/2015 09/2015 10/2015 11/2015 12/2015
Inte
rn C
ou
nt
by C
om
pan
y
AECOM HARPER PACIFICA SGI
Building for tomorrow’s leaders 15
Small Business Program-Small Contractor Boot Camp
0
10
20
30
40
SBE LBE DVBE EBE
21
38
2 9
Small Contractor Boot Camp Participants Spring 2015
(51 Contractors)
SBE
LBE
DVBE
EBE
*Some firms qualify for more than one business category.
21 Small Business Enterprise (SBE)
38 Local Business Enterprise (LBE)
9 Emerging Business Enterprise (EBE)
2 Disabled Veteran Business Enterprise (DVBE)
*Some firms qualify for more than one business category.
51 Small Contractors attended Small Contractor
Spring 2015
Building for tomorrow’s leaders 16
Small Business Program-Prequalification Workshop
37 small contractors attended the workshop
31, or 84%, responded to the Request for Small Contractor Pre-Qualification
11 of 31, or 35%, who attended the workshop are Prequalified. Five (5) of those contractors attended the Small Contractor Boot Camp
Building for tomorrow’s leaders 17
Energy: PV System Buyouts Summary
Year Type College Project Name Early Buyout Net EBO Price Total Net
EBO Price
1 2007 PPA East NW Parking PV Farm /
Carport Structure
5/1/16 $ 2,972,750 $ 2,972,750
2 2009 SL Harbor Phase 1 – Parking lots 6 &
8
6/30/16 2,050,501
5,993,497
3 2009 SL Harbor Phase 2 – Parking lots 6 &
7
6/30/16 2,126,845
4 2009 SL Pierce Parking lot 6 6/30/16 896,160
5 2009 SL East A1 CC, C1 MG, E9 WG,
G3 Aud, H9 PF, P1 AS
6/30/16 217,542
6 2009 SL SW Parking Lot 3 6/30/16 463,194
7 2009 SL East NW Parking PV System
Expansion
6/30/16 239,255
8 2010 SL Pierce Parking lots 1 & 8 12/30/17 1,377,619
2,905,136 9 2010 SL Valley M&O, C & D Parking Lots 12/30/17 1,140,045
10 2010 SL VDK South Parking Lot 12/30/17 387,471
TOTAL $ 11,871,383
PPA = Power Purchase Agreement with production guarantees
SL = Solar Leases/Master Equipment Leases with production guarantees
Building for tomorrow’s leaders 18
ELAC Buyout Status
• Tasks Underway
– Fair market value assessment (Energy Consultant)
– Buyout contract Good Faith review (Outside Counsel)
• Next Steps (April 2016)
– PMO recommendation to the Board regarding the buyout execution
– PMO recommendation to the Board regarding the post buyout
maintenance & operation
– Obtain Board approval of next steps and proceed
Alternative I No action; Service and maintenance of PV system performed by current owner
under contract.
Alternative II District to hire outside entity to service and maintain existing solar asset.
Alternative III Continue a service and maintenance contract for 1 year (min) with outside entity
to allow college staff to be trained on system service and maintenance.
Alternative I Execute buyout contract immediately,
Alternative II Continue to make annual payments for the remaining 12 years of the contract.
1
2
3
Building for tomorrow’s leaders 19
– Completed FY 2015 KPMG Performance and Financial Audits:
• Audit period covered: July 1, 2014 – June 30, 2015
• Audits reported: at November 18, 2015 Facilities Master Planning and
Oversight Committee meeting
• Audit results: No material or significant weaknesses or findings
– Auditors repeatedly expressed recognition of major/significant
improvements in several areas:
• Budget
• Estimating
• Cost reporting
• Scheduling
• Communication and Expediency
• Standardization across Colleges
• Audit Transparency
External Assessment
Building for tomorrow’s leaders 20
Returning vs. New Visitors Visitor Acquisition Device Type
Website Activity – Jul 1, 2015 – Dec 31, 2016
Building for tomorrow’s leaders 21
Program Awards
October 2015
Green California Schools & Community Colleges
Summit, 2015 Green Building Award for
Community Colleges
Leadership Award https://green-technology.smugmug.com/Events/GCSCS15-
Leadership-Awards/
November 2015
US Green Building Council Los Angeles Chapter,
5th Annual Sustainable Innovation Awards
Energy & Atmosphere Merit: Pierce College
Library Learning Crossroads http://usgbc-la.org/greengala/
Building for tomorrow’s leaders
Revised Baseline & Forecast
Building for tomorrow’s leaders 23
Revised Baseline Financial Summary
A B C D F=A-D
Variance Explanation(s)
Current Funding Mar. 2016
Contracted Mar. 2016
Expended Mar. 2016
EAC Mar/Apr 2016 *
Variance Funding - EAC
Colleges $4.75 B $4.16 B $3.91 B $4.77 B $(16.0 M) See slide 25 for detail.
Satellites $330.37 M $216.44 M $209.99 M $335.99 M $5.44 M
Variance shown is not to offset VDK shortfall as Firestone is currently in programming. To be re-evaluated at the completion of Firestone.
Central Services $542.95 M $444.19 M $375.10 M $543.32 M $(0.37 M)
EAC adjustment not captured by Dashboard data run due to timing issue. Resolved in April 2016 Dashboard to show zero variance. Note: Funding variation from Dec 2015 due to Corporate Center funding transfer.
Districtwide Initiatives
$378.73 M $206.12 M $161.36 M $378.73 M $-
Note: Funding variation from Dec 2015 due to funding transfer from Pierce and West for physical security upgrade projects.
Retire District Debt & Refinance
$117.16 M $109.64 M $109.64 M $117.16 M $- N/A
District Bond Contingency
$12.72 M $- $- $1.53 M $11.19 M Note: Funding variation from Dec 2015 due to Corporate Center funding transfer.
Program Reserve** $130.87 M $- $- $- $130.87 M Note: Funding variation from Dec 2015 due to settlement payment.
TOTAL $6.26 B $5.14 B $4.77 B $6.13 B $131.11 M
Source: March 2016 Dashboard Report
* EAC figures listed under Colleges and Satellites reflect the revised baseline EAC per the analysis completed in
April 2016. EAC figures for the remaining line items listed reflect the March 2016 Dashboard figures. Analysis for
the Central Services and Districtwide Initiatives accounts is commencing in Summer 2016.
** Program Reserve EAC currently under evaluation to account for outstanding Program-wide exposure.
Building for tomorrow’s leaders 24
Revised Baseline & Forecast Basis & Assumptions
• Current College Funding as of March 31, 2016
• Baseline Estimate at Completion (EAC) figures as of April 2016
– Negative variance (EAC to Funding) explanations provided in subsequent
slide
– Positive variances (EAC to Funding) remain at a few colleges and Southgate;
however risks remain, as many projects are in early in design that could
erode those funds as the project progresses
• Remaining Work is the forecasted EAC less incurred costs as of
March 2016
Building for tomorrow’s leaders 25
Revised EAC Baseline & Forecast Summary
COLLEGES A B C D=B+C E F=A-D
Major Negative
Variance Drivers
Potential Negative Variance
Mitigation Measures
Current
Funding
Mar. 2016
Design &
Construction
Contingency
Mar. 2016
Projected
EAC w/o
Contingency
Apr. 2016
Projected EAC
w/ Contingency
Apr. 2016
Remaining
Work
Mar. 2016
Variance
Funding to
EAC+
Contingency
City $568.4 M $15.9 M $549.4 M $565.3 M $106.6 M $3.2 M N/A N/A
East $664.8 M $12.2 M $649.6 M $661.8 M $72.1 M $3.0 M N/A N/A
Harbor $449.2 M $2.9 M $451.7 M $454.6 M $67.2 M ($5.4) M
Student Union cost escalation
and delay due to subsurface
conditions; IT data center
addition to Student Union
Deferral of Central Green; Use of
40J IT funding for IT project;
LAUSD funding transfer to LAHC
Mission $445.5 M $3.6 M $442.8 M $446.5 M $40.7 M ($0.9) M Central Plant & Media Arts
escalation due to current market Central Plant scope reduction
Pierce $625.1 M $24.7 M $599.1 M $623.9 M $172.0 M $1.2 M N/A N/A
Southwest $405.4 M $3.2 M $399.9 M $403.1 M $31.2 M $2.3 M N/A N/A
Trade $582.3 M $12.1 M $572.6 M $584.7 M $139.8 M ($2.4) M
Art & Culinary Arts cost
escalation and schedule delay
due to extended DSA review,
Deferral of Facilities M&O &
Toyon Hall (Pending final
Culinary Arts construction
contract award amount)
Valley $612.7 M $16.6 M $614.5 M $631.1 M $161.2 M ($18.4) M
Media Arts bid exceeds original
estimate; Gym Complex,
Campus Center, Allied Health,
Energy Infrastructure projects:
escalation due to current market;
ATF contract amendment
Litigation settlement funds to
LAVC; Use of 40J IT funding for
IT project; Deferral of
Sustainable Mall, RWGPL
Parking Lots H&J
West $399.1 M $4.3 M $393.4 M $397.7 M $42.7 M $1.5 M N/A N/A
TOTAL $4.75 B $95.6 M $4.67 B $4.77 B $833.4 M ($16.0) M
A: Current funding as documented in the March 2016 Dashboard.
C: EAC (Estimate at Completion) as of Apr 2016; figure not reflected in Dashboard as this is a detailed analysis underway.
E: Remaining work calculated using the forecasted EAC less incurred costs as of March 2016
Note: 40J projects are not included in figures above.
SATELLITES
Southgate $192.1 M $24.7 M $156.4 M $181.1 M $113.0 M $11.1 M N/A N/A
Building for tomorrow’s leaders 26
Revised EAC + Risk Exposure Summary
COLLEGES FUNDING & PROJECTED EAC RISK EXPOSURE ANALYSIS
A B C D=B+C E=A-B F=A-D
Current Funding
Mar. 2016
Projected EAC +
Contingency
Apr. 2016
Risk Exposure
Dec. 2015
Projected EAC+
Contingency+ Risk
Apr. 2016
Variance
Funding to EAC+
Contingency
Variance
Funding to EAC+
Contingency+ Risk
City $568.4 M $565.3 M $6.3 M $571.5 M $3.2 M ($3.1) M
East $664.8 M $661.8 M $5.0 M $666.8 M $3.0 M ($2.0) M
Harbor $449.2 M $454.6 M $2.4 M $457.0 M ($5.4) M ($7.8) M
Mission $445.5 M $446.5 M $2.7 M $449.2 M ($0.9) M ($3.7) M
Pierce $625.1 M $623.9 M $9.3 M $633.2 M $1.2 M ($8.1) M
Southwest $405.4 M $403.1 M $1.5 M $404.6 M $2.3 M $0.8 M
Trade $582.3 M $584.7 M $7.7 M $592.4 M ($2.4) M ($10.1) M
Valley $612.7 M $631.1 M $12.2 M $643.3 M ($18.4) M ($30.6) M
West $399.1 M $397.7 M $3.1 M $400.8 M $1.5 M ($1.7) M
TOTAL $4.75 B $4.77 B $50.3 M $4.82 B ($16.0) M ($66.3) M
SATELLITES
Southgate $192.1 M $181.1 M $11.1 M $192.1 M $11.1 M $0.0 M
• Risk exposure is based upon December 2015 model.
• Fluctuation of risks & risk exposure value since December 2015
• Risks mitigated & closed
• Risks realized as change order proposals
• New risks identified
• Next Risk Model run: Summer 2016
Building for tomorrow’s leaders 27
Project Completions Post April 2018
• See 11x17 Handout
Building for tomorrow’s leaders 28
40J Account Rebaseline & Forecast Next Steps
• Estimate at Completion (EAC) rebaseline and forecast
analysis for each Central Services & Districtwide Initiatives
account to commence in Summer 2016.
– Technology projects analysis underway and scheduled to be
completed in June 2016.
• 40J Account allocations per college may change based on
a variety of reasons such as:
– EAC analysis discovery
– College need
– Project priority
– Project scope refinement
Building for tomorrow’s leaders 29
40J: Central Services Accounts Funding Summary
Account
A B C D E=A-D
Funding
Mar. 2016
Expended
Mar. 2016
% Expended
Mar. 2016
EAC
Mar. 2016
Variance
Mar. 2016
Asset Management $52.4 M $35.4 M 68% $52.4 M $0.0 M
Audit $13.5 M $6.2 M 46% $13.5 M $0.0 M
Corporate Center $1.9 M $0.0 M 0% $1.9 M $0.0 M
FF&E $24.8 M $18.3 M 74% $24.8 M $0.0 M
Legal $49.2 M $31.9 M 65% $49.2 M $0.0 M
Move Management $44.3 M $30.4 M 69% $44.3 M $0.0 M
OCIP $91.0 M $57.2 M 63% $91.0 M $0.0 M
Program
Management $210.8 M $150.0 M 71% $210.8 M $0.0 M
Project
Management $1.4 M $1.4 M 100% $1.4 M $0.0 M
Recycling $7.7 M $7.6 M 99% $7.7 M $0.0 M
Specialty Consulting $45.9 M $36.7 M 80% $45.9 M $0.0 M
TOTAL $542.9 M $375.1 M 69% $542.9 M $0.0 M
A: Funding as reported in the March 2016 Dashboard.
D: EAC is Estimate at Completion.
Note: Central Services often use a single, pooled account or central repository to simplify charges and leverage economies of
scale (e.g. buying bulk insurance). Each Central Service account in the pooled account equals to the amount of funds colleges
have contributed. It is possible for central accounts to change allocations based on current/future needs. Allocation changes
require approval of District CFE.
Building for tomorrow’s leaders 30
40J: Districtwide Initiatives Funding Summary
Account
A B C D E=A-D
Funding
Mar. 2016
Expended
Mar. 2016
% Expended
Mar. 2016
EAC
Mar. 2016
Variance
Mar. 2016
Anti-Graffiti
Program $1.1 M $1.1 M 100% $1.1 M $0.0 M
Energy $128.8 M $64.1 M 50% $128.8 M $0.0 M
Stormwater
Implementation $23.0 M $4.4 M 19% $23.0 M $0.0 M
Technology $134.9 M $58.9 M 44% $134.9 M $0.0 M
Transportation
& Accessibility
Improvements
(ADA)
$68.0 M $16.4 M 24% $68.0 M $0.0 M
Warranty
Program $3.1 M $3.1 M 100% $3.1 M $0.0 M
Whole Building
Commissioning $19.8 M $13.4 M 67% $19.8 M $0.0 M
TOTAL $378.7 M $161.4 M 43% $378.7 M $0.0 M
A: Funding as reported in the March 2016 Dashboard.
D: EAC is Estimate at Completion
Note: Allocations to each account subject to change based on current/future needs. Allocation changes require approval of District
CFE.
Building for tomorrow’s leaders 31
40J: District Bond Contingency Funding Summary
Account
A B C D E=A-D
Funding
Mar. 2016
Expended
Mar. 2016
%
Expended
Mar. 2016
EAC
Mar. 2016
Variance
Mar. 2016
District Bond
Contingency $12.7 M $0.0 M 0% $1.5 M $11.2 M
A: Funding as reported in the March 2016 Dashboard.
• Purpose: Funds reserved for Central Services, Satellite, and
Districtwide Initiatives budgets that may be insufficient due to:
– Unprecedented increases in costs
– Unavoidable but necessary changes in scope
– Additional scope of services
– Protracted delays caused by external forces that result in additional costs
• District assesses level of funding to maintain, when the funding
may be reduced, explores potential uses of these remaining
funds.
Building for tomorrow’s leaders
Thank You
Building for tomorrow’s leaders 1
New Bond Program Overview
• Summary of District Needs 1. Central Services & Districtwide Initiatives
2. Per College
• Bond Measure Ballot Language o Request for approval – June 8, 2016
• Potential Project List o Request for approval – June 22, 2016