Internal Pile Cutting and Jacket Removal

Upload: others

Post on 29-May-2020

13 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Internal Pile Cutting and Jacket Removal - ProservInternal Cutting Tool Description and Methodology In order to complete the internal cutting scope, Proserv proposes to utilise our

Internal Pile Cutting and Jacket Removal

Page 2: Internal Pile Cutting and Jacket Removal - ProservInternal Cutting Tool Description and Methodology In order to complete the internal cutting scope, Proserv proposes to utilise our

Internal Cutting Tool Description and Methodology

In order to complete the internal cutting scope, Proserv proposes to utilise our internal pile cutter (IPC) in conjunction with the Jetcut system. The IPC is a robust, reliable and field proven manipulator consisting of a fixed cylindrical upper body, a rotating lower nozzle assembly and two sets of hydraulically driven centralising arms. During deployment, the centralising arms and nozzle assembly are retracted into the body of the tool protecting them and allowing the IPC to slide down the internals of the pile unhindered if angled. A circumferential encoder gives real time readout in degrees of progress through the cutting operation.

As the centralising arms do not clamp the IPC in place, only hold in centrally, the manipulator can be easily recovered by deployment crane in the event of hydraulic failure. The cutting head is extended by a pre-charged accumulator, allowing it to ride over seam-welds or non-conformities without any risk of damage to the manipulator assembly. The IPC is deployed by vessel crane or independent winch system into the open top of the pile. Once lowered to agreed cut elevation, the integral centralising arms are extended to adjust the manipulators position within the pile. Next, the nozzle assembly is extended out by a preset accumulator until the guide wheel contacts with the inner wall off the pile. A complete pass is then carried out using only HP water to verify that the manipulator is fully functional and that the nozzle is contact the pile wall rather than mud or scale deposits. Once this cleaning / test pass is completed, abrasive is introduced to the HP water stream and a full cutting pass completed, including a 10 degree over cut ensuring complete severance.

The circumferential movement of the cutting head is controlled using hydraulics, with the cutting process monitored by a radial encoder which gives the operator accurate real time readings of the nozzle position within the pile. With the information supplied please be advised the work scope may be subject to change upon further details being received. Subject to the contract Proserv will provide a project specific operation manual that will include; full work scope, procedure, safety risk assessment and all relevant documentation.

Rev 001

Page 3: Internal Pile Cutting and Jacket Removal - ProservInternal Cutting Tool Description and Methodology In order to complete the internal cutting scope, Proserv proposes to utilise our

TRACK RECORD

ingenious simplicity

[email protected] Rev 001

Proserv has an established track record with internal pile cutting and jacket removal. Below is a sample summary of recent projects completed to demonstrate our capabilities and expertise in this field.

IPC AND JACKET REMOVAL

Year Client Work Scope Location

2017 PCPP 36” od x 2” wt platform jacket (3 locations )

Dana Platform (3 Legged )SK305 Block, Sarawak, Malaysia

2017 PCPP36” od x 2” wt platform jacket (3 locations) 30” od x 1” wt pin piles (4 locations)

D30 Platform (4 Legged with 4 Pin Piles)SK305 Block, Sarawak, Malaysia

2017 Chevron (1) single string conductor 9-5/8”TAWE Platform, Thailand

2017 Perenco3 jackets on Thames. (2) 4 legged jackets and (1) 6 legged jacket, in addition to conductor cutting

North Sea

2017 PerencoWelland platform (3) topside external cuts on 54” piles and (3) subsea internal cuts at 37m

North Sea

2017 TullowHorne & Wren platform removal piles OD 54” at 41 m

North Sea

2017 TechnipFMCCutting of anchor piles. 72”, wt 80 mm at 120 m

North Sea

2017 Jab 4x 30” x 1” wt pin piles at 4 locations Gulf of Mexico

2017 Ranger Pile cuts. (7) 42” (4) 48” Gulf of Mexico

2017 Laredo Pile cuts. (4) 42”, (1) 60”, (1) 72” Gulf of Mexico

2017 Couvillion

Over 60 pile cuts - removal of 17 offshore structures. Cutting requirements included 53 piles and 3 caissons. The cutting of 17 different structures was completed in 19 days

Gulf of Mexico

2017 Tetra Pile cuts (2) 48” (1) 72” Gulf of Mexico

2017 Couvillion (8) 30” piles Gulf of Mexico

2017 Shore Offshore 10 pile cuts - 30-72” Gulf of Mexico

2017 Fieldwood (1) 60” caisson Gulf of Mexico

Page 4: Internal Pile Cutting and Jacket Removal - ProservInternal Cutting Tool Description and Methodology In order to complete the internal cutting scope, Proserv proposes to utilise our

TRACK RECORD

ingenious simplicity

[email protected] Rev 001

TRACK RECORD

ingenious simplicity

[email protected]

Year Client Work Scope Location

2017 Bisso (2) 36” pile cuts and (1) 72” caisson Gulf of Mexico

2016 Maersk Ledon pile cutting North Sea

2016 Island OffshoreCutting of (4) piles for template ca. 52”, 2” wt at 270 m

North Sea

2016 MPI(4) 3 m OD met mast wt 70 mm at Ijmuiden met mast

North Sea

2016 Montco 10 pile cuts (30-42”) Gulf of Mexico

2016 Fieldwood (4) 48”, (2) 42” Gulf of Mexico

2016 Bumac (2) 24/30”, (2) 42” Gulf of Mexico

2016 Enven (2) 26” Gulf of Mexico

2016 Topu (3) 36”, (3) 38” Gulf of Mexico

2015 Island offshorePile cutting on Tjalve 30” conductor, 25 mm wt at ca. 82 m

North Sea

2015 Reach Subsea Cutting of 16 piles 52”, 3” wt at 50 m North Sea

2015 E.OnRobbin Rigg met mast decommissioning (2)3 m OD, wt 73 mm at 30 m

North Sea

2015 Chevron (11) 36” pile cuts Gulf of Mexico

2015 OSF (11) 36” pile cuts Gulf of Mexico

2015 Tetra (7) 42” pile cuts Gulf of Mexico

2015 Bisso (26) 30-48” Gulf of Mexico

2015 Epic (6) 24-24” Gulf of Mexico

2015 Fieldwood (32) 24-64” Gulf of Mexico

2015Rooster Petroleum

(4) 72” Gulf of Mexico

2014 Bisso Pile removal 33 cuts 13-42” cuts Gulf of Mexico

2014 Crowley Yard Trial, pile removal 2 cuts 42” Onshore, USA

2014 Triton Pile removal 5 cuts (4) 36" and (1) 26" Gulf of Mexico

2014Stewart Construction

Pile removal. (5) 60"Geismar Plant, USA

2014 Fieldwood Pile removal. (6) 30". (1) 48" Gulf of Mexico

2014 Aqueos Pile removal. (1) 24" Gulf of Mexico

2014 Tetra Pile removal. (4) 60" and (1) 30" Gulf of Mexico

2014 Diamond Services Pile removal. (8) 24" Gulf of Mexico

2014 Tetra Pile removal. (4) 42" and (12) 48" Gulf of Mexico

Page 5: Internal Pile Cutting and Jacket Removal - ProservInternal Cutting Tool Description and Methodology In order to complete the internal cutting scope, Proserv proposes to utilise our

TRACK RECORD

ingenious simplicity

[email protected] Rev 001

TRACK RECORD

ingenious simplicity

[email protected]

Year Client Work Scope Location

2014 EnVen Pile removal. (1) 10 3/4" Gulf of Mexico

2014 Jab Energy Pile removal. (4) 16" Gulf of Mexico

2013 Tetra Pile removal. (2) 29" , (3) 48" Gulf of Mexico

2013 Pisces Divers Pile removal. (1) 16", (1) 20", (2) 24" Gulf of Mexico

2013 Tetra Pile removal. (2) 30", (5) 36", (1) 72" Gulf of Mexico

2013 Linder Oil Pile removal. (1) 10 3/4", (2) 33" Gulf of Mexico

2013 Tetra Pile removal. (4) 48" Gulf of Mexico

2013 Tetra Pile removal. (4) 36", (3) 48" Gulf of Mexico

2013 Jab Energy Caisson removal. (1) 60" Gulf of Mexico

2013 BOMAC Pile removal. (21) 42" , (2) 60"Port Arthur, TX, USA

2013 Tetra Pile removal. (2) 48", (3) 60", (6) 36" Gulf of Mexico

2013 Chevron/TritonPile removal. (18) 24", (8) 20", (6) 26", (2) 36"

Gulf of Mexico

2013Cal Dive International

Pile removal. (2) 36", (1) 42", (3) 30" Gulf of Mexico

2013 Tetra Pile removal. (4) 36", (16) 48", (6) 60" Gulf of Mexico

2013 Sandridge Pile removal. (4) 36", (16) 48", (6) 60" Gulf of Mexico

2013 LLOG Pile removal. (1) 30", (1) 48" , (5) 60" Gulf of Mexico

2013 Energy Ventures Pile removal. (4) 17" Gulf of Mexico

2013 Tetra Pile removal. (1) 20", (2) 30" , (1) 36", (2) 48" Gulf of Mexico

2013 Tetra Pile removal. (4) 48", (4) 60" Gulf of Mexico

2013 Tetra Pile removal. (3) 120" Gulf of Mexico

2013 Tetra Pile removal. (1) 7 5/8", (2) 10 3/4", (2) 30" Gulf of Mexico

2013 Aqueos Pile removal. (1) 28", (2) 36" Gulf of Mexico

2013 Manson Gulf Pile removal. (3) 42" Gulf of Mexico

2013 Versabar Pile removal. (3) 42" Gulf of Mexico

2013 Manson Gulf Pile removal. (4) 36" Gulf of Mexico

2013 Bibby OffshoreCutting/removal of 12 spool/downcomer from 48 closed drains caisson on Montrose Alpha

North Sea, UK

2013 Bibby Offshore16 caisson cutting and hole cutting for removal of caisson in manageable sections Saltire Platform

North Sea, UK

Page 6: Internal Pile Cutting and Jacket Removal - ProservInternal Cutting Tool Description and Methodology In order to complete the internal cutting scope, Proserv proposes to utilise our

TRACK RECORD

ingenious simplicity

[email protected] Rev 001

Year Client Work Scope Location

2013 Shell

Brent Alpha caisson replacement. topside caisson section recovery and hole cutting for insertion of lifting pins on 3 caissons for removal

North Sea, UK

2013 Exxon MobilCutting of 42 conductor internally 6 m below mudline for recovery Manslagt Z1 Platform

North Sea, German Sector

2012 OSFIPile removal. (4) 32" x 1.50" wt piles @ -15 BML (topside internal)

Gulf of Mexico

2012 Cajun Maritime

Braced caisson removal. (2) 42" x 1.50" wt brace piles @ -15 BML (topside internal), (1) 48" x 1.75" wt caisson @ -15 BML (topside internal)

Gulf of Mexico

2012Tetra Technologies

Pile removal. (3) 26" x 1.00" wt piles @ -15 BML (subsea internal), (1) 24" x 0.50" wt Pile @ -15 BML (subsea internal), (1) 30" x 0.50" wt pile @ -15 BML (subsea internal)

Gulf of Mexico

2012Cal Dive International

Pile removal. (4) 36" x 1.50" wt Piles @ -15 BML (topside internal)

Gulf of Mexico

2012Tetra Technologies

Pile removal. (1) 7 5/8" casing (4) 48" piles Gulf of Mexico

2012 Pisces EnergyCaisson removal. (1) 66" caisson @ -18 BML (subsea internal)

Gulf of Mexico

2012Tetra Technologies

Pile removal. (4) 42" x 1.50" wt piles @ -15 BML (topside internal)

Gulf of Mexico

2012Rooster Petroleum

Pile removal. (1) 30" x 1.00" wt pile @ -15 BML (topside internal)

Gulf of Mexico

2012Tetra Technologies

Pile removal. (4) 48" x 1.25" wt piles @ -20 BML (subsea deployment), (2) 37" x 1.25" wt piles @ -20 BML (topside deployment), (12) 36" x 1.00" wt piles @ -20 BML (topside deployment), (1) 42" x 1.50" wt pile @ -15 BML (topside deployment), (1) 42" x 1.50" wt pile @ -15 BML (topside deployment)

Gulf of Mexico

2012 Wild Well ControlPile removal. (4) 48" x 2.00" wt piles @ -15 BML

Gulf of Mexico

Page 7: Internal Pile Cutting and Jacket Removal - ProservInternal Cutting Tool Description and Methodology In order to complete the internal cutting scope, Proserv proposes to utilise our

TRACK RECORD

ingenious simplicity

[email protected] Rev 001

Year Client Work Scope Location

2012 Wild Well Control

Platform removal. (2) 10 3/4" piles @ -15 BML (topside internal), (2) 16" piles @ -15 BML (topside internal), (2) 26" piles @ -15 BML (subsea internal), (2) 30" piles @ -15 BML (topside internal), (1) 60" Piles @ -15 BML (subsea internal), (4) 72" Piles @ -15 BML (subsea internal), (2) 78" Piles @ -15 BML (subsea internal), (1) 96" Piles @ -15 BML (subsea internal), (3) 120" Piles @ -15 BML (subsea internal)

Gulf of Mexico

2012International Construction

Pile removal. (2) 48" x 1.50" wt piles @ -18 BML (subsea deployment), (1) 72" x 1.75" wt piles @ -15 BML (subsea deployment), (1) 30" x 1.00" wt pile @ - 16 BML (subsea deployment)

Gulf of Mexico

2012 Tetra TechPile removal. (5) 42" x 1.50" wt piles @ -20 BML (topside internal), (2) 60" x 1.50" wt piles @ -20 BML (topside internal)

Gulf of Mexico

2012International Construction

Pile removal. (8) 48" x 1.75" wt piles @ -20 BML (topside internal), (6) 24" x 0.50" wt piles @ -20 BML (topside internal)

Gulf of Mexico

2012 Tetra TechPile removal. (16) 36" x 1.00" wt piles @ -15 BML (topside internal)

Gulf of Mexico

2012 Ranger OffshorePile removal. (1) 20" x 0.50" wt pile @ -16 BML (subsea internal)

Gulf of Mexico

2012 Stone EnergyPile removal. (1) 30" x 1.00" wt pile @ -15 BML (topside internal), (1) 48" x 1.00" wt pile @ -15 BML (topside internal)

Gulf of Mexico

2012 TetraPile removal. (1) 30" x 1.00" Wt pile @ -15 bml (topside internal), (1) 48" X 1.00" wt pile @ -15 BML (topside internal)

Gulf of Mexico

2012 Manson GulfPile removal. (3) 36" x 2.00" wt piles @ -15 BML (topside internal)

Gulf of Mexico

2012 Wild Well ControlPile removal. (3) 42" x 1.00" wt piles @ -15 BML

Gulf of Mexico

2012 TetraPile removal. (11) 26" piles (1) 72", (4) 48", (4) 16", (4) 36"

Gulf of Mexico

2012 ICG Pile removal. (4) 54" piles Gulf of Mexico

2012 Wild Well Control Pile removal. (1) 84" x 2.00" wt pile Gulf of Mexico

2012 Wild Well Control Pile removal. (4) 48" x 1.50" wt piles Gulf of Mexico

2012 Tetra Pile removal. (4) 60" x 2.00" wt piles Gulf of Mexico

Page 8: Internal Pile Cutting and Jacket Removal - ProservInternal Cutting Tool Description and Methodology In order to complete the internal cutting scope, Proserv proposes to utilise our

TRACK RECORD

ingenious simplicity

[email protected] Rev 001

Year Client Work Scope Location

2012 Cajun Maritime Pile removal. (3) 20" piles. (2) 30"piles Gulf of Mexico

2012 Wild Well Control Pile removal. (4) 48" x 1.25" wt piles Gulf of Mexico

2012 Tetra Pile removal. (12) 42" x 1.75" wt piles Gulf of Mexico

2012 Walter Oil & Gas Pile removal. (1) 10 3/4", (2) 30" piles Gulf of Mexico

2012 Tetra Pile removal. (6) 36", (1) 30", (1) 48" Gulf of Mexico

2012 Wild Well Control Pile removal. (2) 72", (8) 48", (5) 42" Gulf of Mexico

2012 Tetra Pile removal. (8) 42" Gulf of Mexico

2012Dynamic Offshore Resources

Pile removal. (2) 72" Gulf of Mexico

2012 LL & G Pile removal. (1) 10 3/4", (1) 30", (1) 42" Gulf of Mexico

2012 Tetra Pile removal. (4) 30", (1) 42" Gulf of Mexico

2012Dynamic Offshore Resources

Pile removal. (1) 10 3/4", (1) 16", (1) 24", (2) 26", (4) 42", (2) 72"

Gulf of Mexico

2012 Tetra Pile removal. (2) 30", (4) 48", (2) 60" Gulf of Mexico

2012 Wild Well Control Pile removal. (4) 48" Gulf of Mexico

2012 Tetra Pile removal. (1) 24" Gulf of Mexico

2012 Tetra Stub removal. (3) 84" Gulf of Mexico

2012 Dynamic Offshore Stub removal. DWS (1) 30" stub Gulf of Mexico

2012 Bibby OffshoreCutting services in support of the Hess FFFA decommissioning project

North Sea, UK

2012 Subsea 710,000 psi system to remove temporary riser clamps from platform jacket on Judy and Jasmine Fields

North Sea, UK

2012Smit Subsea Europe

Severance of 30 conductor 6 m below mudline for recovery

North Sea, UK

2011Seaway Heavy Lift

Platform decommissioning. 14 piles od 48”, wall thickness 45-47.7 mm 19 piles od 36”, wall thickness 32 mm

Shell Inde Filed, Southern UK Sector

2011Cal Dive International

Transitional caisson removal. (1) 108" x transitional @ +6 AML (subsea external), (1) 108" x 2.50" wt transitional caisson @ -16 BML (subsea internal)

Gulf of Mexico

2011International Offshore Services

Drive pile removal. (1) 30" x 1.00" wt drive pile @ -15 BML (subsea internal)

Gulf of Mexico

2011Dynamic Offshore Resources

Pile removal. (4) 48" x 1.75" wt main piles @ -15 BML (topside internal)

Gulf of Mexico

Page 9: Internal Pile Cutting and Jacket Removal - ProservInternal Cutting Tool Description and Methodology In order to complete the internal cutting scope, Proserv proposes to utilise our

TRACK RECORD

ingenious simplicity

[email protected] Rev 001

Year Client Work Scope Location

2011 Wild Well ControlTransitional caisson removal. (1) 48" x 1.50" wt transitional caisson @ -15 BML (topside internal)

Gulf of Mexico

2011 Wild Well Control

Caisson, pile, and conductor removal. (1) 30" x 1.00" wt conductor @ -15 BML (subsea internal), (2) 36" x 1.50" wt piles @ -15 bml (subsea internal), (1) 72" x 2.00" wt caisson @ -15 BML (subsea internal)

Gulf of Mexico

2011Tetra Technologies

Pile removal. (1) 30” x 1.25” wt pile @ -20 bml (subsea internal), (2) 30” x 1.25” wt dolphin pile @ -20 bml (topside internal), (1) 30” x 0.75” wt dolphin pile @ -20 BML (topside internal)

Gulf of Mexico

2011Energy Partners, Ltd.

Casing and brace pile removal. (1) 18” x 3/8” wt casing @ -21 BML (topside internal), (1) 13 3/8” x 1/2” wt casing @ -23 BML (topside internal), (2) 36” x 1.50” wt brace piles @ -3 BML (topside internal), (2) 72” x 1.75” wt casing @ -44 BWL (topside internal), (2) 72” x 1.75” wt casing @ -44 BWL (topside internal)

Gulf of Mexico

2011Tetra Technologies

Tripod removal. (3) 36" x 1.00" wt piles @ -20 BML (topside internal)

Gulf of Mexico

2011Energy Partners, Ltd.

Caisson removal. (1) 72" x 2.00" wt caisson @ -15 BML (subsea internal)

Gulf of Mexico

2011 Manson Gulf

Pile removal. (3) 42" x 1.50" wt piles @ -20 BML (topside internal), (1) 30" x 1.00" wt conductor stub @ -15 BML (subsea internal)

Gulf of Mexico

2011 OSF

Pile and caisson removal. (1) 72" x 1.50" wt caisson @ -18 BML (subsea internal), (3) 36" x 1.00" wt piles @ -18 BML (topside internal)

Gulf of Mexico

2011 Manson GulfPile removal. (3) 48" x 1.50" wt piles @ -18 BML elevation (topside internal)

Gulf of Mexico

2011Laredo Construction

Pile removal. (3) 42" x 1.50" wt piles @ -16 BML (topside internal), (1) 48" x 1.50" wt pile @ -16 BML (topside internal)

Gulf of Mexico

2011International Offshore Services

Pile removal. (4) 60" x 1.50" wt piles @ -16 BML (topside internal)

Gulf of Mexico

2011 Manson GulfPile removal. (8) 42" x 1.50" wt piles @ -20 BML (topside internal)

Gulf of Mexico

2011Cal Dive International

Pile removal. (4) 36" x 1.25" wt piles @ -15 BML (subsea internal)

Gulf of Mexico

Page 10: Internal Pile Cutting and Jacket Removal - ProservInternal Cutting Tool Description and Methodology In order to complete the internal cutting scope, Proserv proposes to utilise our

TRACK RECORD

ingenious simplicity

[email protected] Rev 001

Year Client Work Scope Location

2011Laredo Construction

Pile and transitional caisson removal. (1) 48" x 72" x 1.50" wt transitional caisson @ - 15 BML (topside internal), (4) 48” x 1.50” wt piles @ - 15 BML (topside internal)

Gulf of Mexico

2011 Manson GulfPile removal. (4) 48” x 1.50” wt piles @ -18 BML (topside internal)

Gulf of Mexico

2011Cal Dive International

Pile removal. (4) 48" x 1.50" wt piles @ -18 BML (topside internal)

Gulf of Mexico

2011 Manson Gulf

Pile and jacket leg removal. (3) 42" x 1.75" wt piles @ -19 BML (topside internal), (3) 45" x 0.75" wt jacket @ -113 BWL (topside internal)

Gulf of Mexico

2011 Tetra Technology

Pile removal. (2) 26" x 0.75" wt piles @ -12 BML (topside internal), (1) 26" x 0.75" wt piles @ -21 BML (topside internal), (4) 26" x 0.75" wt piles @ -20 BML (topside internal)

Gulf of Mexico

2011 Cal Dive International

Pile removal, (4) 48" x 1.50" wt piles @ -16 BML (topside internal)

Gulf of Mexico

2011 Dynamic Offshore Resources

Pile removal, (11) 39" jacket legs w/ 36" pile inside @ mid water line (topside internal)

Gulf of Mexico

2011 Cal Dive International

Pile removal, (3) 42" x 1.75" wt piles @ -15 BML (topside internal)

Gulf of Mexico

2011 Diamond Services Pile removal, (2) 24" x 1.00" wt piles @ -15 BML (subsea internal)

Gulf of Mexico

2011 Wild Well Control Pile removal. (6) 42" x 2.00" wt piles @ -15 BML (topside internal)

Gulf of Mexico

2011 Diamond Services Pile removal. (2) 48" x 1.50" wt piles @ -15 BML (topside internal)

Gulf of Mexico

2011 Cal Dive International

Pile removal. (3) 42" x 1.50" wt piles @ -15 BML (topside internal)

Gulf of Mexico

2011 Pisces Energy Pile removal. (3) 72" x 1.00" wt caisson @ -15 BML (topside internal)

Gulf of Mexico

2011 Rooster Petroleum

Pile removal. (1) 72" x 1.75" wt caisson @ +4 AML (subsea external), (1) 72" x 1.75" wt caisson @ -15 BML (subsea internal)

Gulf of Mexico

2011 Cal Dive International

Pile removal. (3) 22" x 1.00" wt piles @ -15 BML (topside internal)

Gulf of Mexico

Page 11: Internal Pile Cutting and Jacket Removal - ProservInternal Cutting Tool Description and Methodology In order to complete the internal cutting scope, Proserv proposes to utilise our

TRACK RECORD

ingenious simplicity

[email protected] Rev 001

Year Client Work Scope Location

2011 Cal Dive International

Pile removal. (4) 42" x 1.375" wt piles @ -15 BML (topside internal)

Gulf of Mexico

2011 Cal Dive International

Pile removal. (4) 42" x 1.50" wt piles @ -15 BML (topside internal)

Gulf of Mexico

2011 Seamar Divers Pile removal. (4) 30" x 1.50" wt piles @ - 15 BML (subsea internal)

Gulf of Mexico

2011 Dynamic Offshore Resources

Pile and jacket removal. (3) 36" x 1.25" wt piles @ -15 BML elevation (topside internal)

Gulf of Mexico

2011 Energy Partners, Ltd.

Pile removal. (1) 48" x 2" wt piles @ -15 BML elevation (toside internal)

Gulf of Mexico

2011 Walter Oil & Gas Caisson & drive pile removal. (1) 36" (1) 30" (1) 16" @ -15 BML elevation (topside internal)

Gulf of Mexico

2011 Dynamic Offshore Resources

Pile removal. (4) 48” x 2” wt piles @ -17 BML elevation (topside internal)

Gulf of Mexico

2011 Laredo Construction

Pile removal. (1) 48” x 1.50” wt pile @ -16 BML (subsea internal), (1) 36” x 1.50” wt pile @ -17 BML (subsea internal), (3) 30” x 1.00” wt stubs @ -18 BML (subsea internal)

Gulf of Mexico

2011 Seamar Divers Pile removal. (1) 48” x 2.00” wt pile @ -16 BML (topside internal). (2) 36” x 1.50” wt pile @ -16 BML (topside internal)

Gulf of Mexico

2011 OSFI Pile removal. (4) 48" x 1.25" wt piles @ -16 BML (topside internal), (4) 60" x 1.75" wt piles @ -16 BML (topside internal)

Gulf of Mexico

2011 IOS Pile removal. (4) 36" x 2.00" wt piles @ -16 BML (topside internal)

Gulf of Mexico

2011 Manson Gulf

Pile and non grouted conductor removal.(1) 9 5/8" to 13 3/8" grouted conductor @ -25 BML (topside internal), (1) 19” conductor @ -23 BML (topside internal) (1) 7 5/8” conductor @ -28 BML (topside internal), (1) 10 3/4” conductor @ -25 BML (topside internal), (2) 36” piles @ -20 BML (topside internal), (4) 24” x 1” skirt pile @ -20 BML (subsea internal)

Gulf of Mexico

Page 12: Internal Pile Cutting and Jacket Removal - ProservInternal Cutting Tool Description and Methodology In order to complete the internal cutting scope, Proserv proposes to utilise our

TRACK RECORD

ingenious simplicity

[email protected] Rev 001

Year Client Work Scope Location

2011 Tetra Technologies

Various pile removals. (6) 30" piles @ -15 BML (subsea internal)(5) 42" piles @ -15 BML (subsea internal) (2) 24" piles @ -15 BML (subsea internal) (3) 28" piles @ -15 BML (subsea internal) (1) 32" pile @ -15 BML (subsea internal) (1) 36" pile @ -15 BML (subsea internal) (1) 18" pile @ -15 BML (subsea internal) (1) 20" pile @ -15 BML (subsea internal) (1) 16" pile @ -15 BML (subsea internal) (1) 14" pile @ -15 BML (subsea internal)

Gulf of Mexico

2011 Wild Well Control Pile removal. (6) 30" x 1.00" wt pile @ -20 BML (topside internal)

Gulf of Mexico

2011 Manson Gulf Pile removal. (12) 36" x 1.45" wt piles @ -20 BML (topside internal)

Gulf of Mexico

2011 Wild Well Control Pile removal. (4) 42" x 1.25" wt pile @ -21 BML (topside internal)

Gulf of Mexico

2011 Tetra Technologies

Pile removal. (2) 36" x 1.75" wt pile @ -16 BML (topside internal)

Gulf of Mexico

2011 OSFI

Pile removal. (4) 42" x 1.00" wt main piles @ -15 BML (topside internal), (4) 48" x 1.25" wt main piles @ -15 BML (topside internal)

Gulf of Mexico

2011 Wild Well Control

Pile removal. (8) 42" x 2.00" wt main pile @ midwater level (topside internal) , (8) 42" x 2.00" wt main pile @ -15 BML (topside internal)

Gulf of Mexico

2011 Pisces Energy Caisson removal. (1) 7 5/8"(2)10 3/4"(5) 16 caissons @ -20 BML elevation (topside internal), (1) 24"(3) 30"(1) 36"

Gulf of Mexico

2011 Cal Dive International

Pile removal. (8) 42" x 1.50" wt piles @ -15 BML (topside internal)

Gulf of Mexico

2011 Veolia Pipeline removal. DWS. (8) cuts on 10" pipe Gulf of Mexico

2011 Technip Canada Contingency cutting of two piles and spools Canada

2011 Perenco leg cuts and (3) 54” internal cuts 2 m below mud line to remove jacket and assist Welland decommissioning project

North Sea, UK

2010 Dynamic Offshore Resources

Tripod removal. (3) 36" x 1.50" wt main piles @ -15 BML (subsea internal)

Gulf of Mexico

2010 Manson Gulf Jacket removal. (4) 42" x 1.50" wt main piles @ -15 BML (subsea internal)

Gulf of Mexico

Page 13: Internal Pile Cutting and Jacket Removal - ProservInternal Cutting Tool Description and Methodology In order to complete the internal cutting scope, Proserv proposes to utilise our

TRACK RECORD

ingenious simplicity

[email protected] Rev 001

Year Client Work Scope Location

2010 Proserv DCE Caisson and conductor removal. (1)48"-60" x 1.50" transitional caisson @ -25 BML (subsea interal)

Gulf of Mexico

2010 Fairwinds International, Inc.

Jacket removal. (3) 36" x 1.00" wt piles @ -18 BML (subsea internal), (3) 30" x 1.00" wt piles @ -20 BML (subsea internal), (4) 48" x 1.50" wt piles @ -20 BML (subsea internal)

Gulf of Mexico

2010 International Offshore Services

Caisson removal. (1) 48"-60" x 1.5" wt @ -15 BML (subsea internal)

Gulf of Mexico

2010 Laredo Construction

Tripod and caisson removal. (1) 10 3/4" x 16" x 36" conductor @ -32,-30,-22 BML (topside internal), (1) 48" well @ -15 BML (topside internal), (1) 48" stub @ -16 BML (topside internal) (ei 47-15)(3) 42" jacket legs @ -18 BML (topside internal)

Gulf of Mexico

2010 International Offshore Services

Jacket removal. (4) 26" x 1.00" wt conductor @ -15 BML (topside internal)

Gulf of Mexico

2010 Diamond Services

Jacket removal. (4) x 30" x 1.00" wt main piles @ +5 AML & -15 BML (topside internal), (8) x 30" x 1.00" wt main piles @ -15 BML (topside internal), (4) 30" x 1.25" wt main piles @ -15 BML (topside internal)

Gulf of Mexico

2010 International Offshore Services

Conductor, caisson, and brace pile removal.(1) 10" x 16" x 24" x 30" well @ -25, -22, -18, -15 BML (subsea internal), (2) 30" x 1.00 wt brace piles @ -15 BML (subsea internal)

Gulf of Mexico

2010 Diamond Services

Pile removal. (1) 48" @ -15 BML (topside internal), (2) 48" @ -15 BML (topside internal), (2) 48" @ -15 BML (topside internal), (2) 48" @ -15 BML (topside internal)

Gulf of Mexico

2010 Manson Gulf Pile removal(3) 48" x 1.50" wt piles @ -15 BML (topside internal)

Gulf of Mexico

2010 Diamond Services Brace pile removal. (4) 48" x 1.25" wt piles @ -15 BML (subsea internal)

Gulf of Mexico

2010 Manson Gulf Jacket removal. (3) 40" x 1.50" wt piles @ -19 BML (topside internal), (3) 48" x 1.50" wt piles @ -21 BML (topside internal)

Gulf of Mexico

Page 14: Internal Pile Cutting and Jacket Removal - ProservInternal Cutting Tool Description and Methodology In order to complete the internal cutting scope, Proserv proposes to utilise our

TRACK RECORD

ingenious simplicity

[email protected] Rev 001

Year Client Work Scope Location

2010 Dynamic Offshore Resources

Pile removal. (4) 30" x 2.00" wt piles @ -24 BML (topside internal)

Gulf of Mexico

2010 Dynamic Offshore Resources

Pile removal. (1) 36" x 1.00" wt stub pile @ -15 BML (subsea internal)

Gulf of Mexico

2010 Cal Dive International

Tripod removal. (3) 42" x 1.75" wt piles @ -20 BML (subsea internal)

Gulf of Mexico

2010 Wild Well Control

Brace pile and conductor removal. (3) 30" conductor @ -20 BML (subsea internal), (2) 72" brace piles @ -20 BML, (1) 60" brace pile @ -20 BML (subsea internal)

Gulf of Mexico

2010 Manson Gulf Pile removal. (4) 30" x 0.75" wt @ -16 BML (topside internal)

Gulf of Mexico

2010 Diamond Services Pile removal. (4) 36" x 3/4" wt @ -15 BML (topside internal)

Gulf of Mexico

2010 Manson Gulf Pile removal. (3) 48" x 1.75" wt piles @ -16 BML (topside internal)

Gulf of Mexico

2010 Manson Gulf Pile removal. (4) 48" x 1.50" wt piles @ -15 BML (topside internal)

Gulf of Mexico

2010 Manson Gulf

Brace pile, caisson, stub removal. (2) 36" piles @ -20 BML (topside internal), (1) 48" x 60" transitional caisson @ -4 BML & -20 BML (topside & subsea internal)

Gulf of Mexico

2010 Manson Gulf Pile removal. (3) 36" x 1.25" wt piles @ -15 BML elevation (subsea internal)

Gulf of Mexico

2010 Manson Gulf

Conductor, caisson, and brace pile removal. (1) 30" conductor @ -22 BML elevation (topside internal), (2) 36” brace piles @ -17 BML elevation (topside internal), (1) 48” main caisson @ -17 BML elevation (topside internal)

Gulf of Mexico

2010 Manson Gulf Pile removal. (3) 36" x 0.50" wt piles @ -18 BML elevation (subsea internal)

Gulf of Mexico

2010 Manson Gulf Main pile removal. (4) 48" x 1.50" wt piles @ -22 BML (topside internal)

Gulf of Mexico

2010 International Offshore Services

Pile and caisson removal. (1) 10" caisson @ -20 BML (topside internal), (1) 7 3/8" x 10 3/4" x 16" x 30" conductor @ -15 BML (topside internal), (2) 48" pile @ -15 BML (topside internal) (4) 26" piles @ -15 BML (topside internal), (1) 10 3/4" to 36" multi string @ -20 BML (topside internal)

Gulf of Mexico

Page 15: Internal Pile Cutting and Jacket Removal - ProservInternal Cutting Tool Description and Methodology In order to complete the internal cutting scope, Proserv proposes to utilise our

TRACK RECORD

ingenious simplicity

[email protected] Rev 001

Year Client Work Scope Location

2010 Cal Dive International

Main pile removal. (4) 42" x 1.50" wt piles @ -16 BML (topside internal)

Gulf of Mexico

2010 Dynamic Offshore Resources

Transitional caisson removal. (1) 72" transitional @ +2 AML (subsea external),(1) 72" transitional @ -15 BML (subsea internal), (1) 30" conductor @ -15 BML (subsea internal)

Gulf of Mexico

2010 Laredo Construction

Main pile removal. (4) 42" x 1.50" wt piles @ -15 BML (subsea internal)

Gulf of Mexico

2010 Global Industries Pile removal. (6) 48" x 1.25" wt piles @ -15 BML (topside internal)

Gulf of Mexico

2010 OSFI Pile Removal. (4) 48" x 1.50" wt piles @ -20 BML (topside internal), (4) 60" x 2.00" wt piles @ -20 BML (topside internal)

Gulf of Mexico

2010 International Offshore Services

Pile removal. (4) 48" x 1.50" wt piles @ -20 BML elevation (subsea internal). (4) 48" x 1.50" wt skirt piles @ -20 BML elevation (subsea internal)

Gulf of Mexico

2010 Perenco Platform removal. (3) 54” topside external and 3 x 54” subsea internal

UK Southern Sector

2010 Subsea 7 Severance of various sizes of caisson clamps and water caissons

North Sea, UK

2009 Sapura Acergy 34 cuts on platform legs, jacket structure and grout and inflation lines in assistance w decommissioning

Japan, Iwaki Platform

2009 Proserv-Offshore UK

Cutting of platform structures Netherlands

2009 OSFI

8 pile platform removal. (4) 60" x 1.50" wt main piles @ -15 BML (topside internal), (4) 48" x 1.75" wt main piles @ -15 BML (topside internal)

Gulf of Mexico

2009 Proserv DCE Well drive pipe removal. 26" x 1.00" wt drive pipe @ -15 BML (topside internal)

Gulf of Mexico

2009 Chet Morrison Well Services

Tapered caisson removal. 72” x 2.00" wt caisson @ +20 AML (topside internal) 72” x 2.00" wt caisson @ -15 BML (subsea internal)

Gulf of Mexico

2009 Manson Gulf, LLC Pile removal. 48 cuts Gulf of Mexico

2009 Energy Partners,

Braced caisson well protector removal. (2) 30" x 1.00" wt battered piles @ -15 BML (topside internal), (1) 60” x 1.50” wt caisson @ +5 AML (topside internal) (1) 60” x 1.750” wt caisson @ -15 BML (subsea internal)

Gulf of Mexico

Page 16: Internal Pile Cutting and Jacket Removal - ProservInternal Cutting Tool Description and Methodology In order to complete the internal cutting scope, Proserv proposes to utilise our

TRACK RECORD

ingenious simplicity

[email protected] Rev 001

Year Client Work Scope Location

2009 Hunt Petroleum Caisson removal. (1) 72" x 2.25" wt caisson @ -15 BML (subsea internal)

Gulf of Mexico

2009 OSFI Tripod removal, drive pipe removal. (3) 36" x 1.50" wt main piles @ -15 BML (topside internal)

Gulf of Mexico

2009 OSFI Platform removal. (4) 36" x 1.50" wt main piles @ -15 BML (topside internal)

Gulf of Mexico

2009 OSFI Platform removal. (4) 36" x 1.25" wt main piles @ -15 BML (topside internal)

Gulf of Mexico

2009 OSFI

Platform removal. (3) 48” piles @ the -15 BML elevation 3 x 48” pile @ the elevation above the bend. (1) 7” x 9 5/8” x 30” well @ the elevation below the bend. (1) 7” x 9 5/8” well @ the -19 BML elevation, (1) 30” well drive pipe @ the -16 BML elevation

Gulf of Mexico

2009 OSFI

Platform removal. (3) 36" x 1.50" wt main piles @ -15 BML (topside internal), (1) 60" x 1.750" wt caisson @ -15 BML (subsea internal)

Gulf of Mexico

2009 Laredo Construction

Platform removal. (4) 30" x 1.00" wt main piles @ -16 BML (topside internal)

Gulf of Mexico

2009 OSFI Platform removal. (3) 42" x 1.50" wt main piles @ -16 BML (topside internal)

Gulf of Mexico

2009 Diamond Services Well protector pile removal. (2) 36" x 1.50" wt main piles @ -15 BML (subsea internal)

Gulf of Mexico

2009 Diamond Services Platform removal. 23 cuts. Gulf of Mexico

2009 Energy Resource Technology

Pile removal. (4) 36" x 1.875" wt main piles @ -20 BML (topside internal)

Gulf of Mexico

2009 Energy Resource Technology

Pile removal. 7 cuts Gulf of Mexico

2009 Tetra Technologies

Tripod removal. 8 cuts Gulf of Mexico

2009 Pioneer Natural Resources

Pile stub removal. (7) 42" x 1.75" wt piles @ -15 BML (subsea internal)

Gulf of Mexico

2009 W & T Offshore Caisson removal. (1) 72" x 1.75" wt main piles @ -16 BML (topside internal)

Gulf of Mexico

2009 Manson Gulf Platform removal. 11 cuts Gulf of Mexico

2009 International Offshore Services

Platform removal. (4) 60" x 1.375" wt main piles @ -16 BML (topside internal), (4) 72" x 1.875" wt main piles @ -16 BML (topside internal)

Gulf of Mexico

2009 O.S.F.I Platform removal. (3) 36" x 1.50" wt main piles @ -16 BML (topside internal)

Gulf of Mexico

Page 17: Internal Pile Cutting and Jacket Removal - ProservInternal Cutting Tool Description and Methodology In order to complete the internal cutting scope, Proserv proposes to utilise our

TRACK RECORD

ingenious simplicity

[email protected] Rev 001

Year Client Work Scope Location

2009 W & T Offshore Caisson removal. (1) 72" x 1.50" wt caisson @ +36 AML (topside internal)

Gulf of Mexico

2009 International Offshore Services

Platform removal. (4) 48" x 1.25" wt main piles @ -16 BML (topside internal), (4) 60" x 1.375" wt main piles @ -16 BML (topside internal)

Gulf of Mexico

2009 Energy Partners, Ltd.

Caisson removal. (1) 48" x 1.00" wt caisson @ +6 AML (topside internal), (1) 48" x 1.00" wt caisson @ +6 AML (topside internal), (1) 48" x 1.00" wt caisson @ -15 BML (subsea internal), (1) 48" x 1.00" wt caisson @ -15 BML (subsea internal)

Gulf of Mexico

2009 Cal Dive International

Pile removal. (3) 48" x 2.00" wt piles @ -15 BML (topside internal)

Gulf of Mexico

2009 Manson Gulf Jacket removal. 5 cuts Gulf of Mexico

2009 OSFI Jacket removal. (4) 48" x 2.00" wt main piles @ -16 BML (topside internal)

Gulf of Mexico

2009 Dynamic Offshore Resources

Platform removal. (1) 7 5/8" x 1.00" wt conductor @ -22 BML (subsea internal), (1) 10 3/4" conductor @ -20 BML (subsea internal), (1) 30” drive pile @ -17 BML (subsea internal), (1) 30” drive pile @ -17’ 3” BML (subsea internal), (1) 60” x 1.75” wt caisson @ +5 AML (subsea external), (1) 60” x 1.75” wt caisson @ -15 BML (subsea internal)

Gulf of Mexico

2009 Tetra Technologies

Jacket removal. (4) 48" x 1.25" wt main piles @ -15 BML (topside internal), (4) 60" x 1.25" wt main piles @ -15 BML (topside internal)

Gulf of Mexico

2009 Tetra Technologies

Jacket removal. (8) 48" x 2.00" wt main piles @ -5 BML (topside internal)

Gulf of Mexico

2009 Global Industries

Platform removal. (2) 30" x 1.00" wt drive piles @ -15 BML (subsea internal), (3) 48" x 2.00" wt main piles @ -15 BML (topside internal)

Gulf of Mexico

2009 Energy Resource Technology

Stub removal and hole cutting. (1) 30" x 1.00" wt well stub @ -15 BML (subsea internal) 4 x 6" holes

Gulf of Mexico

2009 Diamond Services Pile removal. (2) 48" x 1.00" wt piles @ -16 BML (topside internal)

Gulf of Mexico

Page 18: Internal Pile Cutting and Jacket Removal - ProservInternal Cutting Tool Description and Methodology In order to complete the internal cutting scope, Proserv proposes to utilise our

TRACK RECORD

ingenious simplicity

[email protected] Rev 001

Year Client Work Scope Location

2008 Energy Partners, Ltd.

Platform removal. (3) 36" x 1.50" wt main piles @ -15 BML (topside internal)

Gulf of Mexico

2008 OSFI Platform removal. (8) 48" x 2.00" wt main piles @ -17 BML (topside internal)

Gulf of Mexico

2008 Energy Partners, Ltd.

Platform removal. (3) 36" x 1.50" wt main piles @ -15 BML (topside internal) - project awarded

Gulf of Mexico

2008 Chevron - HRT Downed platform - subsea pile removal. (3) 30" x 1.5" wt piles @ -15' BML (subsea internal)

Gulf of Mexico

2008 Chevron - HRT Downed platform - subsea pile removal. (2) 30" x 1.50" wt piles @ -15 BML (subsea internal)

Gulf of Mexico

2008 OSFI Platform removal. (14) 36" x 1.375" wt main piles @ -15 BML (topside internal)

Gulf of Mexico

2008 Chevron - HRT Downed platform - subsea pile removal. (4) 30" x 1.00"wt piles @ -15 BML (subsea internal)

Gulf of Mexico

2008 OSFI

Tripod removal. (2) 36" x 1.50" wt main piles @ -15 BML (topside internal), (1) 48" x 1.50" wt main pile @ -15 BML (topside internal)

Gulf of Mexico

2008 Energy Partners, Ltd.

Caisson removal. (1) 60" x 2.00" wt caisson @ -15 BML (subsea internal)

Gulf of Mexico

2008 OSFI

Platform removal. (4) 48" x 1.250" wt main piles @ -15 BML (topside internal), (4) 60" x 1.50"wt main piles @ -15 BML (topside internal), (4) 48" x 1.125"wt skirt piles @ -15 BML (subsea internal)

Gulf of Mexico

2008 Power Performance, Inc.

Guyed caisson removal. (1) 84" x 2.00" wt caisson @ -15 BML (subsea internal), (3) 72" x 1.50" wt anchor piles @ -20 BML (subsea internal)

Gulf of Mexico

2008 Tetra Technologies, Inc.

Platform and well removal. (1) 13 3/8" well conductor @ -18 BML (topside internal), (1) 20" well conductor @ -17 BML (topside internal), (4) 36” x 1.250” wt main piles @ -20 BML (topside internal)

Gulf of Mexico

Page 19: Internal Pile Cutting and Jacket Removal - ProservInternal Cutting Tool Description and Methodology In order to complete the internal cutting scope, Proserv proposes to utilise our

TRACK RECORD

ingenious simplicity

[email protected] Rev 001

Year Client Work Scope Location

2008 OSFI

Platform removal. (8) 48" x 2.00" wt main piles @ -17 BML (topside internal), (4) 48" x 1.50" wt skirt piles @ -17 BML (subsea internal)

Gulf of Mexico

2008 Tetra Technologies, Inc.

Caisson removal. (1) 96" x 2.00" wt caisson removal @ -18 BML (subsea internal)

Gulf of Mexico

2008 Tetra Technologies, Inc.

Caisson and conductor removal. (1) 72" x 1.75" wt caisson removal @ -15 BML (subsea internal). (1) 36" x 1.25" wt conductor @ -18 BML (topside internal)

Gulf of Mexico

2008 Energy Resource Technology

Guyed caisson removal. (1) 72" x 2.250" wt caisson removal @ +5 AML (external), (1) 72" x 2.250" wt caisson removal @ -15 BML (subsea internal), (3) 84" x 1.50" wt anchor piles @ -22 BML (subsea internal)

Gulf of Mexico

2008 Cal Dive International

Downed platform - subsea jacket leg / main pile external cutting. (7) 40" jacket leg x 36" main pile @ + 30 AML (midwater external)

Gulf of Mexico

2008 Energy Resource Technology

Caisson stub removal. (1) 105" x 1.750"wt caisson removal @ -15 BML (subsea internal)

Gulf of Mexico

2008 W & T Offshore

Transitional caisson removal. (1) 72" x 1.75" wt caisson removal @ + 5 AML (subsea external), (1) 72" x 2.00" wt caisson removal @ -15 BML (subsea internal)

Gulf of Mexico

2008 Tetra Technologies, Inc.

Platform removal. ( 4) 48" x 2.00"wt main piles @ -15 BML (topside internal)

Gulf of Mexico

2008 Manson Gulf

Braced caisson stub removals. (2) 48" x 1.00" wt caisson removal @ -15 BML (topside internal), (1) 48" x 1.00" wt pile removal @ -10 BML (topside internal)

Gulf of Mexico

2008 Tetra Technologies, Inc.

Caison stub removal. (1) 84" x 2.00"wt caisson @ -15 BML (subsea internal)

Gulf of Mexico

2008 Manson Gulf

Tripod and conductor removal. (3) 42" x 1.50"wt main piles @ -15 BML (topside internal), 16" & 24" conductor & -15 BML (3) 36" x 1.50" wt main piles @ -15 BML (topside internal)

Gulf of Mexico

2008 OSFI 10 pile platform removal. (10) 42" x 2.00"wt main piles @ -15 BML (topside internal)

Gulf of Mexico

2008 Chet Morrison Contractors

Platform removal. (4) 40" x 1.00" wt main piles @ -15 BML (topside internal)

Gulf of Mexico

2008 Wild Well Control Caisson stub removal. (4) 40" x 1.00" wt main piles @ -15 BML (topside internal)

Gulf of Mexico

Page 20: Internal Pile Cutting and Jacket Removal - ProservInternal Cutting Tool Description and Methodology In order to complete the internal cutting scope, Proserv proposes to utilise our

TRACK RECORD

ingenious simplicity

[email protected] Rev 001

Year Client Work Scope Location

2008 OSFI Platform removal. (4) 42" x 2.50" wt main piles @ -15 BML (topside internal)

Gulf of Mexico

2008 Chet Morrison Contractors

Braced caisson removal. (1) 48" x 1.50" wt caisson @ -15 BML (topside internal), (2) 36" x 1.00" wt battered piles @ -15 BML (topside internal)

Gulf of Mexico

2008 Energy Parterns, Ltd.

Caisson removal. (1) 72" x 2.00" wt caisson @ +6 AML (topside internal), (1) 72" x 2.00" wt caisson @ -15 BML (subsea internal)

Gulf of Mexico

2007 AMC Pile guide removal Frigg / DP2

2007 OSFI Platform removal. (4) 84' x 2.5" wt skirt piles @ -15 BML (subsea internal)

Gulf of Mexico

2007 OSFI Platform removal. (4) 72" x 2.00" wt skirt piles @ -15 BML (subsea internal)

Gulf of Mexico

2007 Pinnacle Engineering

Braced caisson removal. (2) 48' x 1" wt piles @ -15 BML (topside internal), (1) 60” x 1.75” wt caisson @ -15 BML (topside internal)

Gulf of Mexico

2007 OSFI Single pile removal. (1) 48" x 2.25" wt pile @ -15 BML (topside internal)

Gulf of Mexico

2007 Tetra Technologies, Inc.

Platform removal. (4) 42" x 1.5" wt main piles @ -15 BML (topside internal)

Gulf of Mexico

2007 BP Trinidad & Tobago

Jacket leg repair 15' x 25' windowAtlantic Ocean, Trinidad

2007 OSFI Platform removal. (3) 36" x 1.5"wt main piles @ -15 BML (topside internal)

Gulf of Mexico

2007 Cal Dive International

Platform removal. (8) 46" x 1" jacket legs c/w 42" x 1" main piles

Gulf of Mexico

2007 Tetra Technologies, Inc.

Platform removal. (2) 48" x 1.5" main piles @ -15 BML (topside internal), (2) 60" x 1.0" wt main piles @ -15 BML (topside internal)

Gulf of Mexico

2007 OSFI Caisson removal. (2) 60" x 2" wt caissons @ -15 BML (topside internal)

Gulf of Mexico

2007 OSFI Transitional caisson removal. (1) 60" x 1.75"wt caissons @ -15 BML (topside internal)

Gulf of Mexico

2007 OSFI Platform removal.. (1) 60” x 1.75”wt caissons @ -15 BML (topside internal)

Gulf of Mexico

Page 21: Internal Pile Cutting and Jacket Removal - ProservInternal Cutting Tool Description and Methodology In order to complete the internal cutting scope, Proserv proposes to utilise our

TRACK RECORD

ingenious simplicity

[email protected] Rev 001

Year Client Work Scope Location

2007 Tetra Technologies, Inc.

Production platform removal. (4) 48" x 1.75" wt main piles @ -15 BML (topside internal), (1) 30" x 1.00" wt conductor @ -15 BML (topside internal)

Gulf of Mexico

2007 Global

Platform removal. (4) 48" x 1.0" wt main piles @ -15 BML (topside internal), (1) 48" x 2.00" wt caisson @ -15 BML (topside internal), (2) 30" x 1.00' wt conductors @ -15 BML (topside internal)

Gulf of Mexico

2007 OSFI Platform removal. (4) 42" x 1.625" main piles @ -25 BML (topside internal)

Gulf of Mexico

2007 Premium Energy Services

Caisson removal. (1) 72" x 2.50" caisson @ +30 AML, -15 BML (topside internal & subsea internal)

Gulf of Mexico

2007 Global Industries, Ltd.

Well protector platform removal. (3) 36" x 1.50" main piles @ -15 BML (topside internal) (1) 14 x 18" grouted conductor @ -15 BML (topside internal)

Gulf of Mexico

2007 Hunt Petroleum

Braced caisson structure removal. (2) 30" x 0.625" main piles @ -15 BML (topside internal), (1) transitional caisson 48" to 72" x 1.75" wt @ +50 AML, -15 BML (topside internal / subsea internal)

Gulf of Mexico

2007 Tetra Technologies, Inc.

Platform removal. (4) 42" x 2.00" main piles @ -15 BML (topside internal)

Gulf of Mexico

2007 Knight Well Services

Transitional caisson and conductor removalTransitional caisson. 48" x 1.5" wt to 60" x 2.0" wt @ +45 AML, +5 AML, -15 BML (internal/external/internal) - 1 x 26" x 0.75" wt conductor @ -15 BML (internal)

Gulf of Mexico

2007 OSFI Platform removal. (4) 48" x 1.5" wt main piles @ -18 BML (topside internal)

Gulf of Mexico

2007 Tetra Technologies, Inc.

Hurricane Rita damaged platform removal.(4) 30" x 1.50" wt main piles @ -15 BML (topside internal)

Gulf of Mexico

2007 Horizon Offshore Platform removal. (4) 36" x 1.5"wt main piles @ -15 BML (topside internal)

Gulf of Mexico

2007 OSFI

Platform removal. (8) 36" x 2.00" wt main piles @ -15 BML (topside internal), (8) 48" x 1.75" wt skirt piles @ -15 BML (subsea internal)

Gulf of Mexico

Page 22: Internal Pile Cutting and Jacket Removal - ProservInternal Cutting Tool Description and Methodology In order to complete the internal cutting scope, Proserv proposes to utilise our

TRACK RECORD

ingenious simplicity

[email protected] Rev 001

Year Client Work Scope Location

2007 Cal Dive International

Conductor removal. (3) 30" x 1.00" wt subsea conductors @ -15 BML (subsea internal), (1) 30" x 1.00" wt subsea conductor @ -15 BML (subsea internal)

Gulf of Mexico

2007 OSFI

Platform removal. (3) 42" x 1.75" wt main piles @ -15 BML (topside internal), (1) 30" x 1.00" wt conductor @ -15 BML (topside internal)

Gulf of Mexico

2007 Manson Gulf, LLC

Platform and conductor removal. (3) 36" x 1.5"wt main piles @ -15 BML (topside internal), (1) 30" x 1.00"wt conductor @ -15 BML (subsea internal)

Gulf of Mexico

2007 SeaQuest Diving Caisson and conductor removal. (1) 30" x 1" wt conductor (1) 60" x 1.5" wt caisson

Gulf of Mexico

2007 Tetra Technologies, Inc

Platform removal. (3) 36" x 1.5"wt main piles @ -15 BML (topside internal) 1 x 72” x 2.50” wt caisson @ -15 BML (subsea internal)

Gulf of Mexico

2007 Knight Well Services

Transitional caisson removal. (1) 48" x 60" x 2.250" wt transitional caisson @ +5 AML & -15 BML (subsea external / subsea internal)

Gulf of Mexico

2007 Horizon Offshore

Platform and conductor removal. (3) 36" x 1.25"wt main piles @ -15 BML (topside internal), (3) 30" x 1.00"wt conductors @ -15 BML (topside internal)

Gulf of Mexico

2007 Knight Well Services

Transitional caisson removal. (1) 60" x 2.25" wt caisson @ +5 AML & -15 BML (subsea external / subsea internal)

Gulf of Mexico

2007 SeaQuest Diving, LLC

Subsea well conductor removal. (1) 26" x 1" wt conductor @ -15 BML (internal)

Gulf of Mexico

2007 OSFI

Platform removal. (4) 30" x 2.00"wt main piles @ -15 BML (topside internal), (4) 30" x 1.50" wt skirt piles @-15 BML (subsea internal)

Gulf of Mexico

2007 Knight Well Services

Well outer drive caisson removal. (2) 48" x 1.00"wt caissons @ -15 BML (topside internal)

Gulf of Mexico

2007 Tetra Technologies, Inc.

Subsea well conductor removal(1) 26" x 1" wt conductor @ -15 BML (subsea internal)

Gulf of Mexico

Page 23: Internal Pile Cutting and Jacket Removal - ProservInternal Cutting Tool Description and Methodology In order to complete the internal cutting scope, Proserv proposes to utilise our

TRACK RECORD

ingenious simplicity

[email protected] Rev 001

Year Client Work Scope Location

2007 Energy Partners, Ltd.

Subsea well conductor removal. (1) 26" x 1"wt conductor @ -15 BML (subsea internal)

Gulf of Mexico

2006 OSFI Single pile removal. (1) 48" x 2.00"wt pile @ -15 BML (topside internal)

Gulf of Mexico

2006 Tetra Technologies, Inc.

Jacket removal. (4) 60" x 1.25"wt main piles @ -15 BML (topside internal)

Gulf of Mexico

2006 Horizon Offshore Platform removal. (4) 36” x 1.25”wt main piles @ -15 BML (topside internal)

Gulf of Mexico

2006 OSFI

Platform removal. (2) 36” x 1.5”wt main piles @ -15 BML (topside internal), (1) 48” x 1.5” main pile @ -15 BML (topside internal)

Gulf of Mexico

2006 OSFI Single leg pile removal. (1) 41” x 1.00”wt @ -15 BML (topside internal)

Gulf of Mexico

2006 Callon Petroleum Single conductor removal. -30” x 1.25” @ 22 BML (subsea internal)

Gulf of Mexico

2006 Tetra Technologies, Inc.

Pile and conductor removal. 1-48” x 2.00”wt pile @ -15 BML (topside internal)(1) 24” x 10 3/4” @ -15 BML(topside internal)

Gulf of Mexico

2006 Manson Gulf Platform removal. 1x20x30 conductor @ -15 BML (topside internal) - 4 x 30" x 1.25” wt main piles @ -15 BML (topside internal).

Gulf of Mexico

2006 W & T Offshore Subsea caisson removal. (1) 72” x 1.875"wt caisson @ -15 BML (subsea internal)

Gulf of Mexico

2006 PMI Cement pile removal. (14) 54” x 5”wt concrete piles @ + 5 AWL (topside external)

Gulf of Mexico

2006 Tetra Technologies, Inc.

Platform removal. (3) 48” x 1.5”wt main piles @ -15 BML (topside internal)

Gulf of Mexico

2006 Tetra Technologies, Inc.

Platform removal. (4) 36” x 1.5”wt main piles @ -15 BML (topside internal)

Gulf of Mexico

2006 Tetra Technologies, Inc.

Caisson removal. (1) 72” x 2.00” wt drive pipe@ -15 BML (subsea internal)

Gulf of Mexico

2006 OSFI Platform removal. (8) x 54" x 2.5"wt main piles @ -15 BML (topside internal)

Gulf of Mexico

Page 24: Internal Pile Cutting and Jacket Removal - ProservInternal Cutting Tool Description and Methodology In order to complete the internal cutting scope, Proserv proposes to utilise our

TRACK RECORD

ingenious simplicity

[email protected] Rev 001

Year Client Work Scope Location

2006 Tetra Technologies, Inc

Braced caisson removal. (1) 30” x 1.0"wt conductor @ -18 BML (topside internal), (1) x 84” x 2.00”wt caisson @ -15 BML (subsea internal), (2) 42” x 1.25”wt batter piles @ -15 BML (subsea internal)

Gulf of Mexico

2006 Tetra Technologies, Inc.

Braced caisson removal. (1) 72” x 2.00”wt caisson @ -15 BML (subsea internal), (2) 42” x 1.00”wt batter piles @ -15 BML (topside internal), (1) 30” x 1.00”wt conductor string @ -18 BML (subsea internal)

Gulf of Mexico

2006 Manson Gulf, LLC Platform removal. (3) 36” x 1.75” wt main piles @ -15 BML(topside internal)

Gulf of Mexico

2006 Apache Corporation

Well conductor removal. 26" x 1.00"wt conductor @ -15 BML (topside internal) - 9 5/8" conductor @ -15 BML (topside internal) - 13 3/8" x 20" @ -18 BML (topside internal)

Gulf of Mexico

2006 Tetra Technologies, Inc.

Platform removal. (4) 48" x 1.5"wt main piles @ -15 BML (topside internal)

Gulf of Mexico

2006 Tetra Technologies, Inc.

Platform removal. (2) 36" x 1.00"wt main piles @ -15 BML (topside internal)

Gulf of Mexico

2006 Maersk Olie og Gas AS

Cutting of support frames Tyra Dan

2006 Maersk Olie og Gas AS

Cutting of platform structures Halfdan

2006 Aker Kværner Pile guide removal Frigg DP2

2005 Mc Dermott Final Pile cutting Sakhalin

2005 Maersk Olie og Gas AS

Cutting of platform structures Halfdan

2005 OSFI Platform removal. (8) 48” x 2.5” Gulf of Mexico

2005 OSFI 108” pile removal Gulf of Mexico

2005 OSFI Tripod. (3) 36” x 1.5”, (1) 16” x 1” Gulf of Mexico

2005 Manson Gulf Tripod. 9 5/8 thru 30” conductor (3) 36” x 1.5 “ piles

Gulf of Mexico

2005 OSFI Tripod. (3) 42” x 1.5 pile Gulf of Mexico

2005 Tetra Technologies, Inc.

Single pile. (1) 120” x 2” Gulf of Mexico

Page 25: Internal Pile Cutting and Jacket Removal - ProservInternal Cutting Tool Description and Methodology In order to complete the internal cutting scope, Proserv proposes to utilise our

TRACK RECORD

ingenious simplicity

[email protected] Rev 001

Year Client Work Scope Location

2005 Tetra Technologies, Inc.

Single caisson. (1) 72” x 2.5” pile Gulf of Mexico

2005 OSFI Tripod. (3) 42” x 1.5” Gulf of Mexico

2005 Manson Gulf Single caisson. (1) 60” x 1” pile Gulf of Mexico

2005 OSFI 2 platforms. (4) 48” x 1.5” piles, (5) 42” x 1.75” piles

Gulf of Mexico

2005 Manson Gulf Platform removal. (4) 36” x 1.5” (2) 36” x 1.5” (2) 20-`13 3/8”

Gulf of Mexico

2005 OSFI Platform removal. (8) 52.5-48” x 1.5” conductor

Gulf of Mexico

2005 Manson Gulf Platform removal. (4) 48 x 1.5 piles, (2) 36 x 1.5 piles

Gulf of Mexico

2005 Manson Gulf Platform removal 1 conductor. (4) 42 x 2.5 piles, (1) 9 5/8 x 16 x 24” multi (1) 16 x 24 “ multi (1) 24” conductor

Gulf of Mexico

2005 Manson Gulf Tripod and conductor. (3) 30 x 1.25” piles, (1) 10 3/4 x 14” multi

Gulf of Mexico

2005 Horizon Offshore Tripod and (2) conductors. (3) 30 x 1.25” piles, (1) 30 x 1.25” stub. (1) 9 5/8 x 13 3/8 x 18 multi

Gulf of Mexico

2005 Athena Const. (1) conductor (1) 10 x 16 “ multi Gulf of Mexico

2005 Manson Gulf (1) 7 5/8 x 10 3/4 conductors , (1) 7 5/8 to 26” multi x 42” piles

Gulf of Mexico

2005 OSFI Jacket removal. (4) 48 1.5” piles (2 x piles recut)

Gulf of Mexico

2005 Bluewater Caisson removal. (1) 72 external pile, (1) 72” internal pile

Gulf of Mexico

2005 OSFI Platform removal. (4) 42”x 1.5” piles Gulf of Mexico

2005 OSFI Jacket removal. (4) 60 x 2” skirt piles (2 recut)

Gulf of Mexico

2005 Bluewater Single leg platform and 1 conductor. (1) x 72” internal (3) x 42” piles

Gulf of Mexico

2004 Pioneer Natural Resources

Single casing severance. (1) 30” x 1.5” Gulf of Mexico

2004 OSFI Double platform removal. (12) 30” x 1” main piles, (8) 30” x 1” skirt piles and (4) 29.5” x .75” dolphin piles

Gulf of Mexico

2004 OSFI Jacket removal. (4) x 48” x 1.5” drive piles Gulf of Mexico

2004 OSFI Platform removal.. (8) x 42” x 1” drive piles Gulf of Mexico

2004 OSFI Caisson Severance. (1) 108” x 2.5” external cut, (1) 108” x 2.5” internal cut

Gulf of Mexico

Page 26: Internal Pile Cutting and Jacket Removal - ProservInternal Cutting Tool Description and Methodology In order to complete the internal cutting scope, Proserv proposes to utilise our

TRACK RECORD

ingenious simplicity

[email protected] Rev 001

Year Client Work Scope Location

2004 OSFI Single casing severance and jacket removal. (1) x 30” x 1” sub-sea casing, (4) 48” x 1.25” drive piles

Gulf of Mexico

2004 OSFI Caisson severance. (1) 72” x 1.5” external cut, (1) 72” x 1.5” internal cut

Gulf of Mexico

2004 Horizon Offshore (1) caisson 48” x 1.75”, (1) caisson 60” x 1.75”, (1) well 9 5/8” x 13 3/8” x 18 5/8” x 30”, (1) well 9 5/8” x 13 3/8” x 18 5/8” x 26”

Gulf of Mexico

2004 Global Industries (4) 60” x 1.75” caissons (1) multi-string 7 5/8” x 9 5/8” x 13” x 20” x 30”, (2) multi-string 9 5/8” x 13” x 20” x 30”

Gulf of Mexico

2004 OSFI Platform removal. (16) 18” x .5 “ piles, (16) 20” x .5” piles, (8) 30” x .625” piles, (10) x 30” x 1.25” piles

Gulf of Mexico

2004 OSFI Jacket removal. (4) 24” x .5” piles Gulf of Mexico

2004 OSFI Tripod removal. (3) 26” x 1.25” piles Gulf of Mexico

2004 Tetra Technologies, Inc.

Cassion removal. (2) 60” x 2” brace piles Gulf of Mexico

2004 W&T Offshore Conductor removal. (15) multiple well strings and casing

Gulf of Mexico

2004 OSFI Caission removal. (1) 96” x 1.5” caission Gulf of Mexico

2004 Manson Gulf Tripod removal. (3) 13 3/8 x >5” conductors, (3) 20” x .5” casing, (3) 36” x 1.25” casing (3) 48” x 1.5” drive pile

Gulf of Mexico

2004 OSFI Tripod and casing removal. (1) 30” x .57 casing stub, (1) 42” x 1.5” vertical pile, (2) 36” x 1.5” brace pile

Gulf of Mexico

2004 OSFI Platform removal. (4) 48” x 1.75”, (2) 48” x 1.75” piles

Gulf of Mexico

2004 Manson Gulf Platform removal. (1) 36” x 1.5”, (2) 48” x 1.5” piles

Gulf of Mexico

2004 OSFI Tripod removal. (1) 48” x 1.75”, (2) 48” x 1.75” brace piles

Gulf of Mexico

2004 OSFI Platform removal. (1) 30” x 1” casing stub (4) 48” x 1.5” piles

Gulf of Mexico

2004 OSFI Platform removal. (1) 60” x1 3/4, (2) 42” x 1 skirt piles

Gulf of Mexico

2004 OSFI Platform removal (2) 42” x 1 3/4 Gulf of Mexico

2004 OSFI Platform removal. (2) 42” x .51 Gulf of Mexico

Page 27: Internal Pile Cutting and Jacket Removal - ProservInternal Cutting Tool Description and Methodology In order to complete the internal cutting scope, Proserv proposes to utilise our

TRACK RECORD

ingenious simplicity

[email protected] Rev 001

Year Client Work Scope Location

2004 OSFI Platform removal. (3) 42” x 1.25 Gulf of Mexico

2004 UWG Well abandonment, cut inner pipe Total; UK

2004 Aker Kværner Offshorepartner AS

Cutting lids in tank top, internal cutting Ekofisk

2003 Stolt Offshore AS Various cutting, template Valdemar

2003 OSFI Platform abandoment. Bridge support platforms - (12) 48” x 1 3/4”, (4) 48” x 2 1/4”,(4) 60” x 1 7/8” pile cutting

Gulf of Mexico

2003 OSFI Platform abandonment. (2) 48” x 1 3/4”, (2) 48” x 2”, (2) 42” x 1 1/2”, (2) 42” x 1 3/4” pile cutting, (1) 30” x 1/2” conductor cutting

Gulf of Mexico

2003 OSFI Platform abandonment. (1) 72” x 4” (4) 84” x 1 3/4” (4) 72” x 1 3/4”

Gulf of Mexico

2003 OSFI Platform abandonment. (4) 60” x 3 1/4” 3 x 72” x 4”

Gulf of Mexico

2003 Global Platform abandonment. (1) 13 x 1/2” casing , (1) 16 x 1/2” casing, (1) 30” x 1 1/2” conductor cuttings

Gulf of Mexico

2003 Global Platform abandonment. (4) 36” x 1 1/2” Gulf of Mexico

2003 McDermott Pile removal. (3) 30” x 1” Gulf of Mexico

2003 OSFI Platform abandonment. (1) 10” x 1/2” casing, (1) 30” 1 1/4” conductor, (3) 36: x 1 1/4” piles

Gulf of Mexico

2003 Global Platform abandonment. (4) 60” x 1.5” piles Gulf of Mexico

2003 Stolt Platform abandonment. (2) 42” x 1.5” jacket legs

Gulf of Mexico

2003 OSFI Platform abandonment. (4) 60” x 1.5” piles Gulf of Mexico

2003 Bisso Marine Conductor removal. (3) 30” x 3/4” c/w 16” & 10.5” x 3/4’ multi-string conductor, (4) 30” x 3/4” c/w 10.5” x 3/4” multi string conductor

Gulf of Mexico

2003 OSFI Platform abandonment. (2) 36” x 1” 1 x 48” x 1” drive piles

Gulf of Mexico

2003 Tetra Technologies, Inc.

Platform abandonment. (4) 54” x 2 5/8” drive piles

Gulf of Mexico

2003 OSFI Platform abandonment. (8) 48” x 1 1/2” drive piles

Gulf of Mexico

Page 28: Internal Pile Cutting and Jacket Removal - ProservInternal Cutting Tool Description and Methodology In order to complete the internal cutting scope, Proserv proposes to utilise our

TRACK RECORD

ingenious simplicity

[email protected] Rev 001

Year Client Work Scope Location

2003 Chevron Texaco Pumping station removal. (4) 36” x 6” concrete piles

South Timbalier Bay, USA

2003 OSFI Platform abandonment. (4) 36” x 1 1/2” drive piles

Gulf of Mexico

2003 OSFI Platform removal. (2) 42” x 1.5” and (1) 72” x 2”

Gulf of Mexico

2003 OSFI Platform removal. (2) 8” x 1.5” and (1) 72” x 2”

Gulf of Mexico

2002 OSFI Platform abandonment. (4) 48” x 1 1/4” pile cutting, (1) 16” conductor c/w (1) inner string, 10” x 3/8” grouted

Gulf of Mexico

2002 Horizon Platform abandonment. (4) 60” x 2” pile cutting

Gulf of Mexico

2002 OSFI Platform abandonment. (4) 48” x 1 3/4” pile cutting, (1) 30” x 1” cassion cutting

Gulf of Mexico

2002 OSFI

Platform abandonment. (2) 36” x 1” pile cutting, (1) 30” x 1” drive pile cutting(1) 16” x 1/2” cassion cutting, (1) 10 3/4” x 3/8” cassion cutting, (1) 48 x 1 1/2” cassion cutting

Gulf of Mexico

2002 OSFI Platform abandonment. (4) 48” x 1 1/2” pile cutting. (3) 30” x 1” cassion cutting

Gulf of Mexico

2002 OSFI Platform abandonment. (2) 60” x 1 1/2” pile cutting. (2) 48” x 2” pile cutting

Gulf of Mexico

2002 Global Industries Platform abandonment. (4) 42” x 1 1/4” pile cutting

Gulf of Mexico

2002 OSFI / Chet Morrison

Platform abandonment. (1) 36” x 1 1/2” pile cutting . (2) 36” x 1 1/2” pile cutting

Gulf of Mexico

2002 OSFI Platform abandonment. (4) 48” x 2” pile cutting

Gulf of Mexico

2001 OSFI Platform abandonment. (3) 36” x 1” pile cutting

Gulf of Mexico

2001 OSFI

Platform abandonment. (24) 14” x 1/2” leg pile cutting. (3) 36” x 1” skirt pile cutting(4) 24” conductors c/w (2) inner strings 18 5/8” & 9 5/8” ungrouted

Gulf of Mexico

2001 OSFI

Platform abandonment. (16) 16” x 1/2” leg pile cutting. (4) 36” x 1 1/4” skirt pile cutting. (1) dolphin pile 36” x 1” wall thickness

Gulf of Mexico

Page 29: Internal Pile Cutting and Jacket Removal - ProservInternal Cutting Tool Description and Methodology In order to complete the internal cutting scope, Proserv proposes to utilise our

TRACK RECORD

ingenious simplicity

[email protected] Rev 001

Year Client Work Scope Location

2001 OSFI Platform abandonment. (3) 36” x 1 1/2” pile cutting

Gulf of Mexico

2001 OSFI Platform abandonment. (8) 48” x 1 1/4” pile cutting. (2) 24” conductor’s c/w (1) inner string 16” x 1/2” grouted

Gulf of Mexico

2001 OSFI Platform abandonment. (4) 48” x 1 1/2” pile cutting. (1) 30” x 1 1/4” cassion cutting

Gulf of Mexico