internal pile cutting and jacket removal - proservinternal cutting tool description and methodology...
TRANSCRIPT
Internal Pile Cutting and Jacket Removal
Internal Cutting Tool Description and Methodology
In order to complete the internal cutting scope, Proserv proposes to utilise our internal pile cutter (IPC) in conjunction with the Jetcut system. The IPC is a robust, reliable and field proven manipulator consisting of a fixed cylindrical upper body, a rotating lower nozzle assembly and two sets of hydraulically driven centralising arms. During deployment, the centralising arms and nozzle assembly are retracted into the body of the tool protecting them and allowing the IPC to slide down the internals of the pile unhindered if angled. A circumferential encoder gives real time readout in degrees of progress through the cutting operation.
As the centralising arms do not clamp the IPC in place, only hold in centrally, the manipulator can be easily recovered by deployment crane in the event of hydraulic failure. The cutting head is extended by a pre-charged accumulator, allowing it to ride over seam-welds or non-conformities without any risk of damage to the manipulator assembly. The IPC is deployed by vessel crane or independent winch system into the open top of the pile. Once lowered to agreed cut elevation, the integral centralising arms are extended to adjust the manipulators position within the pile. Next, the nozzle assembly is extended out by a preset accumulator until the guide wheel contacts with the inner wall off the pile. A complete pass is then carried out using only HP water to verify that the manipulator is fully functional and that the nozzle is contact the pile wall rather than mud or scale deposits. Once this cleaning / test pass is completed, abrasive is introduced to the HP water stream and a full cutting pass completed, including a 10 degree over cut ensuring complete severance.
The circumferential movement of the cutting head is controlled using hydraulics, with the cutting process monitored by a radial encoder which gives the operator accurate real time readings of the nozzle position within the pile. With the information supplied please be advised the work scope may be subject to change upon further details being received. Subject to the contract Proserv will provide a project specific operation manual that will include; full work scope, procedure, safety risk assessment and all relevant documentation.
Rev 001
TRACK RECORD
ingenious simplicity
[email protected] Rev 001
Proserv has an established track record with internal pile cutting and jacket removal. Below is a sample summary of recent projects completed to demonstrate our capabilities and expertise in this field.
IPC AND JACKET REMOVAL
Year Client Work Scope Location
2017 PCPP 36” od x 2” wt platform jacket (3 locations )
Dana Platform (3 Legged )SK305 Block, Sarawak, Malaysia
2017 PCPP36” od x 2” wt platform jacket (3 locations) 30” od x 1” wt pin piles (4 locations)
D30 Platform (4 Legged with 4 Pin Piles)SK305 Block, Sarawak, Malaysia
2017 Chevron (1) single string conductor 9-5/8”TAWE Platform, Thailand
2017 Perenco3 jackets on Thames. (2) 4 legged jackets and (1) 6 legged jacket, in addition to conductor cutting
North Sea
2017 PerencoWelland platform (3) topside external cuts on 54” piles and (3) subsea internal cuts at 37m
North Sea
2017 TullowHorne & Wren platform removal piles OD 54” at 41 m
North Sea
2017 TechnipFMCCutting of anchor piles. 72”, wt 80 mm at 120 m
North Sea
2017 Jab 4x 30” x 1” wt pin piles at 4 locations Gulf of Mexico
2017 Ranger Pile cuts. (7) 42” (4) 48” Gulf of Mexico
2017 Laredo Pile cuts. (4) 42”, (1) 60”, (1) 72” Gulf of Mexico
2017 Couvillion
Over 60 pile cuts - removal of 17 offshore structures. Cutting requirements included 53 piles and 3 caissons. The cutting of 17 different structures was completed in 19 days
Gulf of Mexico
2017 Tetra Pile cuts (2) 48” (1) 72” Gulf of Mexico
2017 Couvillion (8) 30” piles Gulf of Mexico
2017 Shore Offshore 10 pile cuts - 30-72” Gulf of Mexico
2017 Fieldwood (1) 60” caisson Gulf of Mexico
TRACK RECORD
ingenious simplicity
[email protected] Rev 001
TRACK RECORD
ingenious simplicity
Year Client Work Scope Location
2017 Bisso (2) 36” pile cuts and (1) 72” caisson Gulf of Mexico
2016 Maersk Ledon pile cutting North Sea
2016 Island OffshoreCutting of (4) piles for template ca. 52”, 2” wt at 270 m
North Sea
2016 MPI(4) 3 m OD met mast wt 70 mm at Ijmuiden met mast
North Sea
2016 Montco 10 pile cuts (30-42”) Gulf of Mexico
2016 Fieldwood (4) 48”, (2) 42” Gulf of Mexico
2016 Bumac (2) 24/30”, (2) 42” Gulf of Mexico
2016 Enven (2) 26” Gulf of Mexico
2016 Topu (3) 36”, (3) 38” Gulf of Mexico
2015 Island offshorePile cutting on Tjalve 30” conductor, 25 mm wt at ca. 82 m
North Sea
2015 Reach Subsea Cutting of 16 piles 52”, 3” wt at 50 m North Sea
2015 E.OnRobbin Rigg met mast decommissioning (2)3 m OD, wt 73 mm at 30 m
North Sea
2015 Chevron (11) 36” pile cuts Gulf of Mexico
2015 OSF (11) 36” pile cuts Gulf of Mexico
2015 Tetra (7) 42” pile cuts Gulf of Mexico
2015 Bisso (26) 30-48” Gulf of Mexico
2015 Epic (6) 24-24” Gulf of Mexico
2015 Fieldwood (32) 24-64” Gulf of Mexico
2015Rooster Petroleum
(4) 72” Gulf of Mexico
2014 Bisso Pile removal 33 cuts 13-42” cuts Gulf of Mexico
2014 Crowley Yard Trial, pile removal 2 cuts 42” Onshore, USA
2014 Triton Pile removal 5 cuts (4) 36" and (1) 26" Gulf of Mexico
2014Stewart Construction
Pile removal. (5) 60"Geismar Plant, USA
2014 Fieldwood Pile removal. (6) 30". (1) 48" Gulf of Mexico
2014 Aqueos Pile removal. (1) 24" Gulf of Mexico
2014 Tetra Pile removal. (4) 60" and (1) 30" Gulf of Mexico
2014 Diamond Services Pile removal. (8) 24" Gulf of Mexico
2014 Tetra Pile removal. (4) 42" and (12) 48" Gulf of Mexico
TRACK RECORD
ingenious simplicity
[email protected] Rev 001
TRACK RECORD
ingenious simplicity
Year Client Work Scope Location
2014 EnVen Pile removal. (1) 10 3/4" Gulf of Mexico
2014 Jab Energy Pile removal. (4) 16" Gulf of Mexico
2013 Tetra Pile removal. (2) 29" , (3) 48" Gulf of Mexico
2013 Pisces Divers Pile removal. (1) 16", (1) 20", (2) 24" Gulf of Mexico
2013 Tetra Pile removal. (2) 30", (5) 36", (1) 72" Gulf of Mexico
2013 Linder Oil Pile removal. (1) 10 3/4", (2) 33" Gulf of Mexico
2013 Tetra Pile removal. (4) 48" Gulf of Mexico
2013 Tetra Pile removal. (4) 36", (3) 48" Gulf of Mexico
2013 Jab Energy Caisson removal. (1) 60" Gulf of Mexico
2013 BOMAC Pile removal. (21) 42" , (2) 60"Port Arthur, TX, USA
2013 Tetra Pile removal. (2) 48", (3) 60", (6) 36" Gulf of Mexico
2013 Chevron/TritonPile removal. (18) 24", (8) 20", (6) 26", (2) 36"
Gulf of Mexico
2013Cal Dive International
Pile removal. (2) 36", (1) 42", (3) 30" Gulf of Mexico
2013 Tetra Pile removal. (4) 36", (16) 48", (6) 60" Gulf of Mexico
2013 Sandridge Pile removal. (4) 36", (16) 48", (6) 60" Gulf of Mexico
2013 LLOG Pile removal. (1) 30", (1) 48" , (5) 60" Gulf of Mexico
2013 Energy Ventures Pile removal. (4) 17" Gulf of Mexico
2013 Tetra Pile removal. (1) 20", (2) 30" , (1) 36", (2) 48" Gulf of Mexico
2013 Tetra Pile removal. (4) 48", (4) 60" Gulf of Mexico
2013 Tetra Pile removal. (3) 120" Gulf of Mexico
2013 Tetra Pile removal. (1) 7 5/8", (2) 10 3/4", (2) 30" Gulf of Mexico
2013 Aqueos Pile removal. (1) 28", (2) 36" Gulf of Mexico
2013 Manson Gulf Pile removal. (3) 42" Gulf of Mexico
2013 Versabar Pile removal. (3) 42" Gulf of Mexico
2013 Manson Gulf Pile removal. (4) 36" Gulf of Mexico
2013 Bibby OffshoreCutting/removal of 12 spool/downcomer from 48 closed drains caisson on Montrose Alpha
North Sea, UK
2013 Bibby Offshore16 caisson cutting and hole cutting for removal of caisson in manageable sections Saltire Platform
North Sea, UK
TRACK RECORD
ingenious simplicity
[email protected] Rev 001
Year Client Work Scope Location
2013 Shell
Brent Alpha caisson replacement. topside caisson section recovery and hole cutting for insertion of lifting pins on 3 caissons for removal
North Sea, UK
2013 Exxon MobilCutting of 42 conductor internally 6 m below mudline for recovery Manslagt Z1 Platform
North Sea, German Sector
2012 OSFIPile removal. (4) 32" x 1.50" wt piles @ -15 BML (topside internal)
Gulf of Mexico
2012 Cajun Maritime
Braced caisson removal. (2) 42" x 1.50" wt brace piles @ -15 BML (topside internal), (1) 48" x 1.75" wt caisson @ -15 BML (topside internal)
Gulf of Mexico
2012Tetra Technologies
Pile removal. (3) 26" x 1.00" wt piles @ -15 BML (subsea internal), (1) 24" x 0.50" wt Pile @ -15 BML (subsea internal), (1) 30" x 0.50" wt pile @ -15 BML (subsea internal)
Gulf of Mexico
2012Cal Dive International
Pile removal. (4) 36" x 1.50" wt Piles @ -15 BML (topside internal)
Gulf of Mexico
2012Tetra Technologies
Pile removal. (1) 7 5/8" casing (4) 48" piles Gulf of Mexico
2012 Pisces EnergyCaisson removal. (1) 66" caisson @ -18 BML (subsea internal)
Gulf of Mexico
2012Tetra Technologies
Pile removal. (4) 42" x 1.50" wt piles @ -15 BML (topside internal)
Gulf of Mexico
2012Rooster Petroleum
Pile removal. (1) 30" x 1.00" wt pile @ -15 BML (topside internal)
Gulf of Mexico
2012Tetra Technologies
Pile removal. (4) 48" x 1.25" wt piles @ -20 BML (subsea deployment), (2) 37" x 1.25" wt piles @ -20 BML (topside deployment), (12) 36" x 1.00" wt piles @ -20 BML (topside deployment), (1) 42" x 1.50" wt pile @ -15 BML (topside deployment), (1) 42" x 1.50" wt pile @ -15 BML (topside deployment)
Gulf of Mexico
2012 Wild Well ControlPile removal. (4) 48" x 2.00" wt piles @ -15 BML
Gulf of Mexico
TRACK RECORD
ingenious simplicity
[email protected] Rev 001
Year Client Work Scope Location
2012 Wild Well Control
Platform removal. (2) 10 3/4" piles @ -15 BML (topside internal), (2) 16" piles @ -15 BML (topside internal), (2) 26" piles @ -15 BML (subsea internal), (2) 30" piles @ -15 BML (topside internal), (1) 60" Piles @ -15 BML (subsea internal), (4) 72" Piles @ -15 BML (subsea internal), (2) 78" Piles @ -15 BML (subsea internal), (1) 96" Piles @ -15 BML (subsea internal), (3) 120" Piles @ -15 BML (subsea internal)
Gulf of Mexico
2012International Construction
Pile removal. (2) 48" x 1.50" wt piles @ -18 BML (subsea deployment), (1) 72" x 1.75" wt piles @ -15 BML (subsea deployment), (1) 30" x 1.00" wt pile @ - 16 BML (subsea deployment)
Gulf of Mexico
2012 Tetra TechPile removal. (5) 42" x 1.50" wt piles @ -20 BML (topside internal), (2) 60" x 1.50" wt piles @ -20 BML (topside internal)
Gulf of Mexico
2012International Construction
Pile removal. (8) 48" x 1.75" wt piles @ -20 BML (topside internal), (6) 24" x 0.50" wt piles @ -20 BML (topside internal)
Gulf of Mexico
2012 Tetra TechPile removal. (16) 36" x 1.00" wt piles @ -15 BML (topside internal)
Gulf of Mexico
2012 Ranger OffshorePile removal. (1) 20" x 0.50" wt pile @ -16 BML (subsea internal)
Gulf of Mexico
2012 Stone EnergyPile removal. (1) 30" x 1.00" wt pile @ -15 BML (topside internal), (1) 48" x 1.00" wt pile @ -15 BML (topside internal)
Gulf of Mexico
2012 TetraPile removal. (1) 30" x 1.00" Wt pile @ -15 bml (topside internal), (1) 48" X 1.00" wt pile @ -15 BML (topside internal)
Gulf of Mexico
2012 Manson GulfPile removal. (3) 36" x 2.00" wt piles @ -15 BML (topside internal)
Gulf of Mexico
2012 Wild Well ControlPile removal. (3) 42" x 1.00" wt piles @ -15 BML
Gulf of Mexico
2012 TetraPile removal. (11) 26" piles (1) 72", (4) 48", (4) 16", (4) 36"
Gulf of Mexico
2012 ICG Pile removal. (4) 54" piles Gulf of Mexico
2012 Wild Well Control Pile removal. (1) 84" x 2.00" wt pile Gulf of Mexico
2012 Wild Well Control Pile removal. (4) 48" x 1.50" wt piles Gulf of Mexico
2012 Tetra Pile removal. (4) 60" x 2.00" wt piles Gulf of Mexico
TRACK RECORD
ingenious simplicity
[email protected] Rev 001
Year Client Work Scope Location
2012 Cajun Maritime Pile removal. (3) 20" piles. (2) 30"piles Gulf of Mexico
2012 Wild Well Control Pile removal. (4) 48" x 1.25" wt piles Gulf of Mexico
2012 Tetra Pile removal. (12) 42" x 1.75" wt piles Gulf of Mexico
2012 Walter Oil & Gas Pile removal. (1) 10 3/4", (2) 30" piles Gulf of Mexico
2012 Tetra Pile removal. (6) 36", (1) 30", (1) 48" Gulf of Mexico
2012 Wild Well Control Pile removal. (2) 72", (8) 48", (5) 42" Gulf of Mexico
2012 Tetra Pile removal. (8) 42" Gulf of Mexico
2012Dynamic Offshore Resources
Pile removal. (2) 72" Gulf of Mexico
2012 LL & G Pile removal. (1) 10 3/4", (1) 30", (1) 42" Gulf of Mexico
2012 Tetra Pile removal. (4) 30", (1) 42" Gulf of Mexico
2012Dynamic Offshore Resources
Pile removal. (1) 10 3/4", (1) 16", (1) 24", (2) 26", (4) 42", (2) 72"
Gulf of Mexico
2012 Tetra Pile removal. (2) 30", (4) 48", (2) 60" Gulf of Mexico
2012 Wild Well Control Pile removal. (4) 48" Gulf of Mexico
2012 Tetra Pile removal. (1) 24" Gulf of Mexico
2012 Tetra Stub removal. (3) 84" Gulf of Mexico
2012 Dynamic Offshore Stub removal. DWS (1) 30" stub Gulf of Mexico
2012 Bibby OffshoreCutting services in support of the Hess FFFA decommissioning project
North Sea, UK
2012 Subsea 710,000 psi system to remove temporary riser clamps from platform jacket on Judy and Jasmine Fields
North Sea, UK
2012Smit Subsea Europe
Severance of 30 conductor 6 m below mudline for recovery
North Sea, UK
2011Seaway Heavy Lift
Platform decommissioning. 14 piles od 48”, wall thickness 45-47.7 mm 19 piles od 36”, wall thickness 32 mm
Shell Inde Filed, Southern UK Sector
2011Cal Dive International
Transitional caisson removal. (1) 108" x transitional @ +6 AML (subsea external), (1) 108" x 2.50" wt transitional caisson @ -16 BML (subsea internal)
Gulf of Mexico
2011International Offshore Services
Drive pile removal. (1) 30" x 1.00" wt drive pile @ -15 BML (subsea internal)
Gulf of Mexico
2011Dynamic Offshore Resources
Pile removal. (4) 48" x 1.75" wt main piles @ -15 BML (topside internal)
Gulf of Mexico
TRACK RECORD
ingenious simplicity
[email protected] Rev 001
Year Client Work Scope Location
2011 Wild Well ControlTransitional caisson removal. (1) 48" x 1.50" wt transitional caisson @ -15 BML (topside internal)
Gulf of Mexico
2011 Wild Well Control
Caisson, pile, and conductor removal. (1) 30" x 1.00" wt conductor @ -15 BML (subsea internal), (2) 36" x 1.50" wt piles @ -15 bml (subsea internal), (1) 72" x 2.00" wt caisson @ -15 BML (subsea internal)
Gulf of Mexico
2011Tetra Technologies
Pile removal. (1) 30” x 1.25” wt pile @ -20 bml (subsea internal), (2) 30” x 1.25” wt dolphin pile @ -20 bml (topside internal), (1) 30” x 0.75” wt dolphin pile @ -20 BML (topside internal)
Gulf of Mexico
2011Energy Partners, Ltd.
Casing and brace pile removal. (1) 18” x 3/8” wt casing @ -21 BML (topside internal), (1) 13 3/8” x 1/2” wt casing @ -23 BML (topside internal), (2) 36” x 1.50” wt brace piles @ -3 BML (topside internal), (2) 72” x 1.75” wt casing @ -44 BWL (topside internal), (2) 72” x 1.75” wt casing @ -44 BWL (topside internal)
Gulf of Mexico
2011Tetra Technologies
Tripod removal. (3) 36" x 1.00" wt piles @ -20 BML (topside internal)
Gulf of Mexico
2011Energy Partners, Ltd.
Caisson removal. (1) 72" x 2.00" wt caisson @ -15 BML (subsea internal)
Gulf of Mexico
2011 Manson Gulf
Pile removal. (3) 42" x 1.50" wt piles @ -20 BML (topside internal), (1) 30" x 1.00" wt conductor stub @ -15 BML (subsea internal)
Gulf of Mexico
2011 OSF
Pile and caisson removal. (1) 72" x 1.50" wt caisson @ -18 BML (subsea internal), (3) 36" x 1.00" wt piles @ -18 BML (topside internal)
Gulf of Mexico
2011 Manson GulfPile removal. (3) 48" x 1.50" wt piles @ -18 BML elevation (topside internal)
Gulf of Mexico
2011Laredo Construction
Pile removal. (3) 42" x 1.50" wt piles @ -16 BML (topside internal), (1) 48" x 1.50" wt pile @ -16 BML (topside internal)
Gulf of Mexico
2011International Offshore Services
Pile removal. (4) 60" x 1.50" wt piles @ -16 BML (topside internal)
Gulf of Mexico
2011 Manson GulfPile removal. (8) 42" x 1.50" wt piles @ -20 BML (topside internal)
Gulf of Mexico
2011Cal Dive International
Pile removal. (4) 36" x 1.25" wt piles @ -15 BML (subsea internal)
Gulf of Mexico
TRACK RECORD
ingenious simplicity
[email protected] Rev 001
Year Client Work Scope Location
2011Laredo Construction
Pile and transitional caisson removal. (1) 48" x 72" x 1.50" wt transitional caisson @ - 15 BML (topside internal), (4) 48” x 1.50” wt piles @ - 15 BML (topside internal)
Gulf of Mexico
2011 Manson GulfPile removal. (4) 48” x 1.50” wt piles @ -18 BML (topside internal)
Gulf of Mexico
2011Cal Dive International
Pile removal. (4) 48" x 1.50" wt piles @ -18 BML (topside internal)
Gulf of Mexico
2011 Manson Gulf
Pile and jacket leg removal. (3) 42" x 1.75" wt piles @ -19 BML (topside internal), (3) 45" x 0.75" wt jacket @ -113 BWL (topside internal)
Gulf of Mexico
2011 Tetra Technology
Pile removal. (2) 26" x 0.75" wt piles @ -12 BML (topside internal), (1) 26" x 0.75" wt piles @ -21 BML (topside internal), (4) 26" x 0.75" wt piles @ -20 BML (topside internal)
Gulf of Mexico
2011 Cal Dive International
Pile removal, (4) 48" x 1.50" wt piles @ -16 BML (topside internal)
Gulf of Mexico
2011 Dynamic Offshore Resources
Pile removal, (11) 39" jacket legs w/ 36" pile inside @ mid water line (topside internal)
Gulf of Mexico
2011 Cal Dive International
Pile removal, (3) 42" x 1.75" wt piles @ -15 BML (topside internal)
Gulf of Mexico
2011 Diamond Services Pile removal, (2) 24" x 1.00" wt piles @ -15 BML (subsea internal)
Gulf of Mexico
2011 Wild Well Control Pile removal. (6) 42" x 2.00" wt piles @ -15 BML (topside internal)
Gulf of Mexico
2011 Diamond Services Pile removal. (2) 48" x 1.50" wt piles @ -15 BML (topside internal)
Gulf of Mexico
2011 Cal Dive International
Pile removal. (3) 42" x 1.50" wt piles @ -15 BML (topside internal)
Gulf of Mexico
2011 Pisces Energy Pile removal. (3) 72" x 1.00" wt caisson @ -15 BML (topside internal)
Gulf of Mexico
2011 Rooster Petroleum
Pile removal. (1) 72" x 1.75" wt caisson @ +4 AML (subsea external), (1) 72" x 1.75" wt caisson @ -15 BML (subsea internal)
Gulf of Mexico
2011 Cal Dive International
Pile removal. (3) 22" x 1.00" wt piles @ -15 BML (topside internal)
Gulf of Mexico
TRACK RECORD
ingenious simplicity
[email protected] Rev 001
Year Client Work Scope Location
2011 Cal Dive International
Pile removal. (4) 42" x 1.375" wt piles @ -15 BML (topside internal)
Gulf of Mexico
2011 Cal Dive International
Pile removal. (4) 42" x 1.50" wt piles @ -15 BML (topside internal)
Gulf of Mexico
2011 Seamar Divers Pile removal. (4) 30" x 1.50" wt piles @ - 15 BML (subsea internal)
Gulf of Mexico
2011 Dynamic Offshore Resources
Pile and jacket removal. (3) 36" x 1.25" wt piles @ -15 BML elevation (topside internal)
Gulf of Mexico
2011 Energy Partners, Ltd.
Pile removal. (1) 48" x 2" wt piles @ -15 BML elevation (toside internal)
Gulf of Mexico
2011 Walter Oil & Gas Caisson & drive pile removal. (1) 36" (1) 30" (1) 16" @ -15 BML elevation (topside internal)
Gulf of Mexico
2011 Dynamic Offshore Resources
Pile removal. (4) 48” x 2” wt piles @ -17 BML elevation (topside internal)
Gulf of Mexico
2011 Laredo Construction
Pile removal. (1) 48” x 1.50” wt pile @ -16 BML (subsea internal), (1) 36” x 1.50” wt pile @ -17 BML (subsea internal), (3) 30” x 1.00” wt stubs @ -18 BML (subsea internal)
Gulf of Mexico
2011 Seamar Divers Pile removal. (1) 48” x 2.00” wt pile @ -16 BML (topside internal). (2) 36” x 1.50” wt pile @ -16 BML (topside internal)
Gulf of Mexico
2011 OSFI Pile removal. (4) 48" x 1.25" wt piles @ -16 BML (topside internal), (4) 60" x 1.75" wt piles @ -16 BML (topside internal)
Gulf of Mexico
2011 IOS Pile removal. (4) 36" x 2.00" wt piles @ -16 BML (topside internal)
Gulf of Mexico
2011 Manson Gulf
Pile and non grouted conductor removal.(1) 9 5/8" to 13 3/8" grouted conductor @ -25 BML (topside internal), (1) 19” conductor @ -23 BML (topside internal) (1) 7 5/8” conductor @ -28 BML (topside internal), (1) 10 3/4” conductor @ -25 BML (topside internal), (2) 36” piles @ -20 BML (topside internal), (4) 24” x 1” skirt pile @ -20 BML (subsea internal)
Gulf of Mexico
TRACK RECORD
ingenious simplicity
[email protected] Rev 001
Year Client Work Scope Location
2011 Tetra Technologies
Various pile removals. (6) 30" piles @ -15 BML (subsea internal)(5) 42" piles @ -15 BML (subsea internal) (2) 24" piles @ -15 BML (subsea internal) (3) 28" piles @ -15 BML (subsea internal) (1) 32" pile @ -15 BML (subsea internal) (1) 36" pile @ -15 BML (subsea internal) (1) 18" pile @ -15 BML (subsea internal) (1) 20" pile @ -15 BML (subsea internal) (1) 16" pile @ -15 BML (subsea internal) (1) 14" pile @ -15 BML (subsea internal)
Gulf of Mexico
2011 Wild Well Control Pile removal. (6) 30" x 1.00" wt pile @ -20 BML (topside internal)
Gulf of Mexico
2011 Manson Gulf Pile removal. (12) 36" x 1.45" wt piles @ -20 BML (topside internal)
Gulf of Mexico
2011 Wild Well Control Pile removal. (4) 42" x 1.25" wt pile @ -21 BML (topside internal)
Gulf of Mexico
2011 Tetra Technologies
Pile removal. (2) 36" x 1.75" wt pile @ -16 BML (topside internal)
Gulf of Mexico
2011 OSFI
Pile removal. (4) 42" x 1.00" wt main piles @ -15 BML (topside internal), (4) 48" x 1.25" wt main piles @ -15 BML (topside internal)
Gulf of Mexico
2011 Wild Well Control
Pile removal. (8) 42" x 2.00" wt main pile @ midwater level (topside internal) , (8) 42" x 2.00" wt main pile @ -15 BML (topside internal)
Gulf of Mexico
2011 Pisces Energy Caisson removal. (1) 7 5/8"(2)10 3/4"(5) 16 caissons @ -20 BML elevation (topside internal), (1) 24"(3) 30"(1) 36"
Gulf of Mexico
2011 Cal Dive International
Pile removal. (8) 42" x 1.50" wt piles @ -15 BML (topside internal)
Gulf of Mexico
2011 Veolia Pipeline removal. DWS. (8) cuts on 10" pipe Gulf of Mexico
2011 Technip Canada Contingency cutting of two piles and spools Canada
2011 Perenco leg cuts and (3) 54” internal cuts 2 m below mud line to remove jacket and assist Welland decommissioning project
North Sea, UK
2010 Dynamic Offshore Resources
Tripod removal. (3) 36" x 1.50" wt main piles @ -15 BML (subsea internal)
Gulf of Mexico
2010 Manson Gulf Jacket removal. (4) 42" x 1.50" wt main piles @ -15 BML (subsea internal)
Gulf of Mexico
TRACK RECORD
ingenious simplicity
[email protected] Rev 001
Year Client Work Scope Location
2010 Proserv DCE Caisson and conductor removal. (1)48"-60" x 1.50" transitional caisson @ -25 BML (subsea interal)
Gulf of Mexico
2010 Fairwinds International, Inc.
Jacket removal. (3) 36" x 1.00" wt piles @ -18 BML (subsea internal), (3) 30" x 1.00" wt piles @ -20 BML (subsea internal), (4) 48" x 1.50" wt piles @ -20 BML (subsea internal)
Gulf of Mexico
2010 International Offshore Services
Caisson removal. (1) 48"-60" x 1.5" wt @ -15 BML (subsea internal)
Gulf of Mexico
2010 Laredo Construction
Tripod and caisson removal. (1) 10 3/4" x 16" x 36" conductor @ -32,-30,-22 BML (topside internal), (1) 48" well @ -15 BML (topside internal), (1) 48" stub @ -16 BML (topside internal) (ei 47-15)(3) 42" jacket legs @ -18 BML (topside internal)
Gulf of Mexico
2010 International Offshore Services
Jacket removal. (4) 26" x 1.00" wt conductor @ -15 BML (topside internal)
Gulf of Mexico
2010 Diamond Services
Jacket removal. (4) x 30" x 1.00" wt main piles @ +5 AML & -15 BML (topside internal), (8) x 30" x 1.00" wt main piles @ -15 BML (topside internal), (4) 30" x 1.25" wt main piles @ -15 BML (topside internal)
Gulf of Mexico
2010 International Offshore Services
Conductor, caisson, and brace pile removal.(1) 10" x 16" x 24" x 30" well @ -25, -22, -18, -15 BML (subsea internal), (2) 30" x 1.00 wt brace piles @ -15 BML (subsea internal)
Gulf of Mexico
2010 Diamond Services
Pile removal. (1) 48" @ -15 BML (topside internal), (2) 48" @ -15 BML (topside internal), (2) 48" @ -15 BML (topside internal), (2) 48" @ -15 BML (topside internal)
Gulf of Mexico
2010 Manson Gulf Pile removal(3) 48" x 1.50" wt piles @ -15 BML (topside internal)
Gulf of Mexico
2010 Diamond Services Brace pile removal. (4) 48" x 1.25" wt piles @ -15 BML (subsea internal)
Gulf of Mexico
2010 Manson Gulf Jacket removal. (3) 40" x 1.50" wt piles @ -19 BML (topside internal), (3) 48" x 1.50" wt piles @ -21 BML (topside internal)
Gulf of Mexico
TRACK RECORD
ingenious simplicity
[email protected] Rev 001
Year Client Work Scope Location
2010 Dynamic Offshore Resources
Pile removal. (4) 30" x 2.00" wt piles @ -24 BML (topside internal)
Gulf of Mexico
2010 Dynamic Offshore Resources
Pile removal. (1) 36" x 1.00" wt stub pile @ -15 BML (subsea internal)
Gulf of Mexico
2010 Cal Dive International
Tripod removal. (3) 42" x 1.75" wt piles @ -20 BML (subsea internal)
Gulf of Mexico
2010 Wild Well Control
Brace pile and conductor removal. (3) 30" conductor @ -20 BML (subsea internal), (2) 72" brace piles @ -20 BML, (1) 60" brace pile @ -20 BML (subsea internal)
Gulf of Mexico
2010 Manson Gulf Pile removal. (4) 30" x 0.75" wt @ -16 BML (topside internal)
Gulf of Mexico
2010 Diamond Services Pile removal. (4) 36" x 3/4" wt @ -15 BML (topside internal)
Gulf of Mexico
2010 Manson Gulf Pile removal. (3) 48" x 1.75" wt piles @ -16 BML (topside internal)
Gulf of Mexico
2010 Manson Gulf Pile removal. (4) 48" x 1.50" wt piles @ -15 BML (topside internal)
Gulf of Mexico
2010 Manson Gulf
Brace pile, caisson, stub removal. (2) 36" piles @ -20 BML (topside internal), (1) 48" x 60" transitional caisson @ -4 BML & -20 BML (topside & subsea internal)
Gulf of Mexico
2010 Manson Gulf Pile removal. (3) 36" x 1.25" wt piles @ -15 BML elevation (subsea internal)
Gulf of Mexico
2010 Manson Gulf
Conductor, caisson, and brace pile removal. (1) 30" conductor @ -22 BML elevation (topside internal), (2) 36” brace piles @ -17 BML elevation (topside internal), (1) 48” main caisson @ -17 BML elevation (topside internal)
Gulf of Mexico
2010 Manson Gulf Pile removal. (3) 36" x 0.50" wt piles @ -18 BML elevation (subsea internal)
Gulf of Mexico
2010 Manson Gulf Main pile removal. (4) 48" x 1.50" wt piles @ -22 BML (topside internal)
Gulf of Mexico
2010 International Offshore Services
Pile and caisson removal. (1) 10" caisson @ -20 BML (topside internal), (1) 7 3/8" x 10 3/4" x 16" x 30" conductor @ -15 BML (topside internal), (2) 48" pile @ -15 BML (topside internal) (4) 26" piles @ -15 BML (topside internal), (1) 10 3/4" to 36" multi string @ -20 BML (topside internal)
Gulf of Mexico
TRACK RECORD
ingenious simplicity
[email protected] Rev 001
Year Client Work Scope Location
2010 Cal Dive International
Main pile removal. (4) 42" x 1.50" wt piles @ -16 BML (topside internal)
Gulf of Mexico
2010 Dynamic Offshore Resources
Transitional caisson removal. (1) 72" transitional @ +2 AML (subsea external),(1) 72" transitional @ -15 BML (subsea internal), (1) 30" conductor @ -15 BML (subsea internal)
Gulf of Mexico
2010 Laredo Construction
Main pile removal. (4) 42" x 1.50" wt piles @ -15 BML (subsea internal)
Gulf of Mexico
2010 Global Industries Pile removal. (6) 48" x 1.25" wt piles @ -15 BML (topside internal)
Gulf of Mexico
2010 OSFI Pile Removal. (4) 48" x 1.50" wt piles @ -20 BML (topside internal), (4) 60" x 2.00" wt piles @ -20 BML (topside internal)
Gulf of Mexico
2010 International Offshore Services
Pile removal. (4) 48" x 1.50" wt piles @ -20 BML elevation (subsea internal). (4) 48" x 1.50" wt skirt piles @ -20 BML elevation (subsea internal)
Gulf of Mexico
2010 Perenco Platform removal. (3) 54” topside external and 3 x 54” subsea internal
UK Southern Sector
2010 Subsea 7 Severance of various sizes of caisson clamps and water caissons
North Sea, UK
2009 Sapura Acergy 34 cuts on platform legs, jacket structure and grout and inflation lines in assistance w decommissioning
Japan, Iwaki Platform
2009 Proserv-Offshore UK
Cutting of platform structures Netherlands
2009 OSFI
8 pile platform removal. (4) 60" x 1.50" wt main piles @ -15 BML (topside internal), (4) 48" x 1.75" wt main piles @ -15 BML (topside internal)
Gulf of Mexico
2009 Proserv DCE Well drive pipe removal. 26" x 1.00" wt drive pipe @ -15 BML (topside internal)
Gulf of Mexico
2009 Chet Morrison Well Services
Tapered caisson removal. 72” x 2.00" wt caisson @ +20 AML (topside internal) 72” x 2.00" wt caisson @ -15 BML (subsea internal)
Gulf of Mexico
2009 Manson Gulf, LLC Pile removal. 48 cuts Gulf of Mexico
2009 Energy Partners,
Braced caisson well protector removal. (2) 30" x 1.00" wt battered piles @ -15 BML (topside internal), (1) 60” x 1.50” wt caisson @ +5 AML (topside internal) (1) 60” x 1.750” wt caisson @ -15 BML (subsea internal)
Gulf of Mexico
TRACK RECORD
ingenious simplicity
[email protected] Rev 001
Year Client Work Scope Location
2009 Hunt Petroleum Caisson removal. (1) 72" x 2.25" wt caisson @ -15 BML (subsea internal)
Gulf of Mexico
2009 OSFI Tripod removal, drive pipe removal. (3) 36" x 1.50" wt main piles @ -15 BML (topside internal)
Gulf of Mexico
2009 OSFI Platform removal. (4) 36" x 1.50" wt main piles @ -15 BML (topside internal)
Gulf of Mexico
2009 OSFI Platform removal. (4) 36" x 1.25" wt main piles @ -15 BML (topside internal)
Gulf of Mexico
2009 OSFI
Platform removal. (3) 48” piles @ the -15 BML elevation 3 x 48” pile @ the elevation above the bend. (1) 7” x 9 5/8” x 30” well @ the elevation below the bend. (1) 7” x 9 5/8” well @ the -19 BML elevation, (1) 30” well drive pipe @ the -16 BML elevation
Gulf of Mexico
2009 OSFI
Platform removal. (3) 36" x 1.50" wt main piles @ -15 BML (topside internal), (1) 60" x 1.750" wt caisson @ -15 BML (subsea internal)
Gulf of Mexico
2009 Laredo Construction
Platform removal. (4) 30" x 1.00" wt main piles @ -16 BML (topside internal)
Gulf of Mexico
2009 OSFI Platform removal. (3) 42" x 1.50" wt main piles @ -16 BML (topside internal)
Gulf of Mexico
2009 Diamond Services Well protector pile removal. (2) 36" x 1.50" wt main piles @ -15 BML (subsea internal)
Gulf of Mexico
2009 Diamond Services Platform removal. 23 cuts. Gulf of Mexico
2009 Energy Resource Technology
Pile removal. (4) 36" x 1.875" wt main piles @ -20 BML (topside internal)
Gulf of Mexico
2009 Energy Resource Technology
Pile removal. 7 cuts Gulf of Mexico
2009 Tetra Technologies
Tripod removal. 8 cuts Gulf of Mexico
2009 Pioneer Natural Resources
Pile stub removal. (7) 42" x 1.75" wt piles @ -15 BML (subsea internal)
Gulf of Mexico
2009 W & T Offshore Caisson removal. (1) 72" x 1.75" wt main piles @ -16 BML (topside internal)
Gulf of Mexico
2009 Manson Gulf Platform removal. 11 cuts Gulf of Mexico
2009 International Offshore Services
Platform removal. (4) 60" x 1.375" wt main piles @ -16 BML (topside internal), (4) 72" x 1.875" wt main piles @ -16 BML (topside internal)
Gulf of Mexico
2009 O.S.F.I Platform removal. (3) 36" x 1.50" wt main piles @ -16 BML (topside internal)
Gulf of Mexico
TRACK RECORD
ingenious simplicity
[email protected] Rev 001
Year Client Work Scope Location
2009 W & T Offshore Caisson removal. (1) 72" x 1.50" wt caisson @ +36 AML (topside internal)
Gulf of Mexico
2009 International Offshore Services
Platform removal. (4) 48" x 1.25" wt main piles @ -16 BML (topside internal), (4) 60" x 1.375" wt main piles @ -16 BML (topside internal)
Gulf of Mexico
2009 Energy Partners, Ltd.
Caisson removal. (1) 48" x 1.00" wt caisson @ +6 AML (topside internal), (1) 48" x 1.00" wt caisson @ +6 AML (topside internal), (1) 48" x 1.00" wt caisson @ -15 BML (subsea internal), (1) 48" x 1.00" wt caisson @ -15 BML (subsea internal)
Gulf of Mexico
2009 Cal Dive International
Pile removal. (3) 48" x 2.00" wt piles @ -15 BML (topside internal)
Gulf of Mexico
2009 Manson Gulf Jacket removal. 5 cuts Gulf of Mexico
2009 OSFI Jacket removal. (4) 48" x 2.00" wt main piles @ -16 BML (topside internal)
Gulf of Mexico
2009 Dynamic Offshore Resources
Platform removal. (1) 7 5/8" x 1.00" wt conductor @ -22 BML (subsea internal), (1) 10 3/4" conductor @ -20 BML (subsea internal), (1) 30” drive pile @ -17 BML (subsea internal), (1) 30” drive pile @ -17’ 3” BML (subsea internal), (1) 60” x 1.75” wt caisson @ +5 AML (subsea external), (1) 60” x 1.75” wt caisson @ -15 BML (subsea internal)
Gulf of Mexico
2009 Tetra Technologies
Jacket removal. (4) 48" x 1.25" wt main piles @ -15 BML (topside internal), (4) 60" x 1.25" wt main piles @ -15 BML (topside internal)
Gulf of Mexico
2009 Tetra Technologies
Jacket removal. (8) 48" x 2.00" wt main piles @ -5 BML (topside internal)
Gulf of Mexico
2009 Global Industries
Platform removal. (2) 30" x 1.00" wt drive piles @ -15 BML (subsea internal), (3) 48" x 2.00" wt main piles @ -15 BML (topside internal)
Gulf of Mexico
2009 Energy Resource Technology
Stub removal and hole cutting. (1) 30" x 1.00" wt well stub @ -15 BML (subsea internal) 4 x 6" holes
Gulf of Mexico
2009 Diamond Services Pile removal. (2) 48" x 1.00" wt piles @ -16 BML (topside internal)
Gulf of Mexico
TRACK RECORD
ingenious simplicity
[email protected] Rev 001
Year Client Work Scope Location
2008 Energy Partners, Ltd.
Platform removal. (3) 36" x 1.50" wt main piles @ -15 BML (topside internal)
Gulf of Mexico
2008 OSFI Platform removal. (8) 48" x 2.00" wt main piles @ -17 BML (topside internal)
Gulf of Mexico
2008 Energy Partners, Ltd.
Platform removal. (3) 36" x 1.50" wt main piles @ -15 BML (topside internal) - project awarded
Gulf of Mexico
2008 Chevron - HRT Downed platform - subsea pile removal. (3) 30" x 1.5" wt piles @ -15' BML (subsea internal)
Gulf of Mexico
2008 Chevron - HRT Downed platform - subsea pile removal. (2) 30" x 1.50" wt piles @ -15 BML (subsea internal)
Gulf of Mexico
2008 OSFI Platform removal. (14) 36" x 1.375" wt main piles @ -15 BML (topside internal)
Gulf of Mexico
2008 Chevron - HRT Downed platform - subsea pile removal. (4) 30" x 1.00"wt piles @ -15 BML (subsea internal)
Gulf of Mexico
2008 OSFI
Tripod removal. (2) 36" x 1.50" wt main piles @ -15 BML (topside internal), (1) 48" x 1.50" wt main pile @ -15 BML (topside internal)
Gulf of Mexico
2008 Energy Partners, Ltd.
Caisson removal. (1) 60" x 2.00" wt caisson @ -15 BML (subsea internal)
Gulf of Mexico
2008 OSFI
Platform removal. (4) 48" x 1.250" wt main piles @ -15 BML (topside internal), (4) 60" x 1.50"wt main piles @ -15 BML (topside internal), (4) 48" x 1.125"wt skirt piles @ -15 BML (subsea internal)
Gulf of Mexico
2008 Power Performance, Inc.
Guyed caisson removal. (1) 84" x 2.00" wt caisson @ -15 BML (subsea internal), (3) 72" x 1.50" wt anchor piles @ -20 BML (subsea internal)
Gulf of Mexico
2008 Tetra Technologies, Inc.
Platform and well removal. (1) 13 3/8" well conductor @ -18 BML (topside internal), (1) 20" well conductor @ -17 BML (topside internal), (4) 36” x 1.250” wt main piles @ -20 BML (topside internal)
Gulf of Mexico
TRACK RECORD
ingenious simplicity
[email protected] Rev 001
Year Client Work Scope Location
2008 OSFI
Platform removal. (8) 48" x 2.00" wt main piles @ -17 BML (topside internal), (4) 48" x 1.50" wt skirt piles @ -17 BML (subsea internal)
Gulf of Mexico
2008 Tetra Technologies, Inc.
Caisson removal. (1) 96" x 2.00" wt caisson removal @ -18 BML (subsea internal)
Gulf of Mexico
2008 Tetra Technologies, Inc.
Caisson and conductor removal. (1) 72" x 1.75" wt caisson removal @ -15 BML (subsea internal). (1) 36" x 1.25" wt conductor @ -18 BML (topside internal)
Gulf of Mexico
2008 Energy Resource Technology
Guyed caisson removal. (1) 72" x 2.250" wt caisson removal @ +5 AML (external), (1) 72" x 2.250" wt caisson removal @ -15 BML (subsea internal), (3) 84" x 1.50" wt anchor piles @ -22 BML (subsea internal)
Gulf of Mexico
2008 Cal Dive International
Downed platform - subsea jacket leg / main pile external cutting. (7) 40" jacket leg x 36" main pile @ + 30 AML (midwater external)
Gulf of Mexico
2008 Energy Resource Technology
Caisson stub removal. (1) 105" x 1.750"wt caisson removal @ -15 BML (subsea internal)
Gulf of Mexico
2008 W & T Offshore
Transitional caisson removal. (1) 72" x 1.75" wt caisson removal @ + 5 AML (subsea external), (1) 72" x 2.00" wt caisson removal @ -15 BML (subsea internal)
Gulf of Mexico
2008 Tetra Technologies, Inc.
Platform removal. ( 4) 48" x 2.00"wt main piles @ -15 BML (topside internal)
Gulf of Mexico
2008 Manson Gulf
Braced caisson stub removals. (2) 48" x 1.00" wt caisson removal @ -15 BML (topside internal), (1) 48" x 1.00" wt pile removal @ -10 BML (topside internal)
Gulf of Mexico
2008 Tetra Technologies, Inc.
Caison stub removal. (1) 84" x 2.00"wt caisson @ -15 BML (subsea internal)
Gulf of Mexico
2008 Manson Gulf
Tripod and conductor removal. (3) 42" x 1.50"wt main piles @ -15 BML (topside internal), 16" & 24" conductor & -15 BML (3) 36" x 1.50" wt main piles @ -15 BML (topside internal)
Gulf of Mexico
2008 OSFI 10 pile platform removal. (10) 42" x 2.00"wt main piles @ -15 BML (topside internal)
Gulf of Mexico
2008 Chet Morrison Contractors
Platform removal. (4) 40" x 1.00" wt main piles @ -15 BML (topside internal)
Gulf of Mexico
2008 Wild Well Control Caisson stub removal. (4) 40" x 1.00" wt main piles @ -15 BML (topside internal)
Gulf of Mexico
TRACK RECORD
ingenious simplicity
[email protected] Rev 001
Year Client Work Scope Location
2008 OSFI Platform removal. (4) 42" x 2.50" wt main piles @ -15 BML (topside internal)
Gulf of Mexico
2008 Chet Morrison Contractors
Braced caisson removal. (1) 48" x 1.50" wt caisson @ -15 BML (topside internal), (2) 36" x 1.00" wt battered piles @ -15 BML (topside internal)
Gulf of Mexico
2008 Energy Parterns, Ltd.
Caisson removal. (1) 72" x 2.00" wt caisson @ +6 AML (topside internal), (1) 72" x 2.00" wt caisson @ -15 BML (subsea internal)
Gulf of Mexico
2007 AMC Pile guide removal Frigg / DP2
2007 OSFI Platform removal. (4) 84' x 2.5" wt skirt piles @ -15 BML (subsea internal)
Gulf of Mexico
2007 OSFI Platform removal. (4) 72" x 2.00" wt skirt piles @ -15 BML (subsea internal)
Gulf of Mexico
2007 Pinnacle Engineering
Braced caisson removal. (2) 48' x 1" wt piles @ -15 BML (topside internal), (1) 60” x 1.75” wt caisson @ -15 BML (topside internal)
Gulf of Mexico
2007 OSFI Single pile removal. (1) 48" x 2.25" wt pile @ -15 BML (topside internal)
Gulf of Mexico
2007 Tetra Technologies, Inc.
Platform removal. (4) 42" x 1.5" wt main piles @ -15 BML (topside internal)
Gulf of Mexico
2007 BP Trinidad & Tobago
Jacket leg repair 15' x 25' windowAtlantic Ocean, Trinidad
2007 OSFI Platform removal. (3) 36" x 1.5"wt main piles @ -15 BML (topside internal)
Gulf of Mexico
2007 Cal Dive International
Platform removal. (8) 46" x 1" jacket legs c/w 42" x 1" main piles
Gulf of Mexico
2007 Tetra Technologies, Inc.
Platform removal. (2) 48" x 1.5" main piles @ -15 BML (topside internal), (2) 60" x 1.0" wt main piles @ -15 BML (topside internal)
Gulf of Mexico
2007 OSFI Caisson removal. (2) 60" x 2" wt caissons @ -15 BML (topside internal)
Gulf of Mexico
2007 OSFI Transitional caisson removal. (1) 60" x 1.75"wt caissons @ -15 BML (topside internal)
Gulf of Mexico
2007 OSFI Platform removal.. (1) 60” x 1.75”wt caissons @ -15 BML (topside internal)
Gulf of Mexico
TRACK RECORD
ingenious simplicity
[email protected] Rev 001
Year Client Work Scope Location
2007 Tetra Technologies, Inc.
Production platform removal. (4) 48" x 1.75" wt main piles @ -15 BML (topside internal), (1) 30" x 1.00" wt conductor @ -15 BML (topside internal)
Gulf of Mexico
2007 Global
Platform removal. (4) 48" x 1.0" wt main piles @ -15 BML (topside internal), (1) 48" x 2.00" wt caisson @ -15 BML (topside internal), (2) 30" x 1.00' wt conductors @ -15 BML (topside internal)
Gulf of Mexico
2007 OSFI Platform removal. (4) 42" x 1.625" main piles @ -25 BML (topside internal)
Gulf of Mexico
2007 Premium Energy Services
Caisson removal. (1) 72" x 2.50" caisson @ +30 AML, -15 BML (topside internal & subsea internal)
Gulf of Mexico
2007 Global Industries, Ltd.
Well protector platform removal. (3) 36" x 1.50" main piles @ -15 BML (topside internal) (1) 14 x 18" grouted conductor @ -15 BML (topside internal)
Gulf of Mexico
2007 Hunt Petroleum
Braced caisson structure removal. (2) 30" x 0.625" main piles @ -15 BML (topside internal), (1) transitional caisson 48" to 72" x 1.75" wt @ +50 AML, -15 BML (topside internal / subsea internal)
Gulf of Mexico
2007 Tetra Technologies, Inc.
Platform removal. (4) 42" x 2.00" main piles @ -15 BML (topside internal)
Gulf of Mexico
2007 Knight Well Services
Transitional caisson and conductor removalTransitional caisson. 48" x 1.5" wt to 60" x 2.0" wt @ +45 AML, +5 AML, -15 BML (internal/external/internal) - 1 x 26" x 0.75" wt conductor @ -15 BML (internal)
Gulf of Mexico
2007 OSFI Platform removal. (4) 48" x 1.5" wt main piles @ -18 BML (topside internal)
Gulf of Mexico
2007 Tetra Technologies, Inc.
Hurricane Rita damaged platform removal.(4) 30" x 1.50" wt main piles @ -15 BML (topside internal)
Gulf of Mexico
2007 Horizon Offshore Platform removal. (4) 36" x 1.5"wt main piles @ -15 BML (topside internal)
Gulf of Mexico
2007 OSFI
Platform removal. (8) 36" x 2.00" wt main piles @ -15 BML (topside internal), (8) 48" x 1.75" wt skirt piles @ -15 BML (subsea internal)
Gulf of Mexico
TRACK RECORD
ingenious simplicity
[email protected] Rev 001
Year Client Work Scope Location
2007 Cal Dive International
Conductor removal. (3) 30" x 1.00" wt subsea conductors @ -15 BML (subsea internal), (1) 30" x 1.00" wt subsea conductor @ -15 BML (subsea internal)
Gulf of Mexico
2007 OSFI
Platform removal. (3) 42" x 1.75" wt main piles @ -15 BML (topside internal), (1) 30" x 1.00" wt conductor @ -15 BML (topside internal)
Gulf of Mexico
2007 Manson Gulf, LLC
Platform and conductor removal. (3) 36" x 1.5"wt main piles @ -15 BML (topside internal), (1) 30" x 1.00"wt conductor @ -15 BML (subsea internal)
Gulf of Mexico
2007 SeaQuest Diving Caisson and conductor removal. (1) 30" x 1" wt conductor (1) 60" x 1.5" wt caisson
Gulf of Mexico
2007 Tetra Technologies, Inc
Platform removal. (3) 36" x 1.5"wt main piles @ -15 BML (topside internal) 1 x 72” x 2.50” wt caisson @ -15 BML (subsea internal)
Gulf of Mexico
2007 Knight Well Services
Transitional caisson removal. (1) 48" x 60" x 2.250" wt transitional caisson @ +5 AML & -15 BML (subsea external / subsea internal)
Gulf of Mexico
2007 Horizon Offshore
Platform and conductor removal. (3) 36" x 1.25"wt main piles @ -15 BML (topside internal), (3) 30" x 1.00"wt conductors @ -15 BML (topside internal)
Gulf of Mexico
2007 Knight Well Services
Transitional caisson removal. (1) 60" x 2.25" wt caisson @ +5 AML & -15 BML (subsea external / subsea internal)
Gulf of Mexico
2007 SeaQuest Diving, LLC
Subsea well conductor removal. (1) 26" x 1" wt conductor @ -15 BML (internal)
Gulf of Mexico
2007 OSFI
Platform removal. (4) 30" x 2.00"wt main piles @ -15 BML (topside internal), (4) 30" x 1.50" wt skirt piles @-15 BML (subsea internal)
Gulf of Mexico
2007 Knight Well Services
Well outer drive caisson removal. (2) 48" x 1.00"wt caissons @ -15 BML (topside internal)
Gulf of Mexico
2007 Tetra Technologies, Inc.
Subsea well conductor removal(1) 26" x 1" wt conductor @ -15 BML (subsea internal)
Gulf of Mexico
TRACK RECORD
ingenious simplicity
[email protected] Rev 001
Year Client Work Scope Location
2007 Energy Partners, Ltd.
Subsea well conductor removal. (1) 26" x 1"wt conductor @ -15 BML (subsea internal)
Gulf of Mexico
2006 OSFI Single pile removal. (1) 48" x 2.00"wt pile @ -15 BML (topside internal)
Gulf of Mexico
2006 Tetra Technologies, Inc.
Jacket removal. (4) 60" x 1.25"wt main piles @ -15 BML (topside internal)
Gulf of Mexico
2006 Horizon Offshore Platform removal. (4) 36” x 1.25”wt main piles @ -15 BML (topside internal)
Gulf of Mexico
2006 OSFI
Platform removal. (2) 36” x 1.5”wt main piles @ -15 BML (topside internal), (1) 48” x 1.5” main pile @ -15 BML (topside internal)
Gulf of Mexico
2006 OSFI Single leg pile removal. (1) 41” x 1.00”wt @ -15 BML (topside internal)
Gulf of Mexico
2006 Callon Petroleum Single conductor removal. -30” x 1.25” @ 22 BML (subsea internal)
Gulf of Mexico
2006 Tetra Technologies, Inc.
Pile and conductor removal. 1-48” x 2.00”wt pile @ -15 BML (topside internal)(1) 24” x 10 3/4” @ -15 BML(topside internal)
Gulf of Mexico
2006 Manson Gulf Platform removal. 1x20x30 conductor @ -15 BML (topside internal) - 4 x 30" x 1.25” wt main piles @ -15 BML (topside internal).
Gulf of Mexico
2006 W & T Offshore Subsea caisson removal. (1) 72” x 1.875"wt caisson @ -15 BML (subsea internal)
Gulf of Mexico
2006 PMI Cement pile removal. (14) 54” x 5”wt concrete piles @ + 5 AWL (topside external)
Gulf of Mexico
2006 Tetra Technologies, Inc.
Platform removal. (3) 48” x 1.5”wt main piles @ -15 BML (topside internal)
Gulf of Mexico
2006 Tetra Technologies, Inc.
Platform removal. (4) 36” x 1.5”wt main piles @ -15 BML (topside internal)
Gulf of Mexico
2006 Tetra Technologies, Inc.
Caisson removal. (1) 72” x 2.00” wt drive pipe@ -15 BML (subsea internal)
Gulf of Mexico
2006 OSFI Platform removal. (8) x 54" x 2.5"wt main piles @ -15 BML (topside internal)
Gulf of Mexico
TRACK RECORD
ingenious simplicity
[email protected] Rev 001
Year Client Work Scope Location
2006 Tetra Technologies, Inc
Braced caisson removal. (1) 30” x 1.0"wt conductor @ -18 BML (topside internal), (1) x 84” x 2.00”wt caisson @ -15 BML (subsea internal), (2) 42” x 1.25”wt batter piles @ -15 BML (subsea internal)
Gulf of Mexico
2006 Tetra Technologies, Inc.
Braced caisson removal. (1) 72” x 2.00”wt caisson @ -15 BML (subsea internal), (2) 42” x 1.00”wt batter piles @ -15 BML (topside internal), (1) 30” x 1.00”wt conductor string @ -18 BML (subsea internal)
Gulf of Mexico
2006 Manson Gulf, LLC Platform removal. (3) 36” x 1.75” wt main piles @ -15 BML(topside internal)
Gulf of Mexico
2006 Apache Corporation
Well conductor removal. 26" x 1.00"wt conductor @ -15 BML (topside internal) - 9 5/8" conductor @ -15 BML (topside internal) - 13 3/8" x 20" @ -18 BML (topside internal)
Gulf of Mexico
2006 Tetra Technologies, Inc.
Platform removal. (4) 48" x 1.5"wt main piles @ -15 BML (topside internal)
Gulf of Mexico
2006 Tetra Technologies, Inc.
Platform removal. (2) 36" x 1.00"wt main piles @ -15 BML (topside internal)
Gulf of Mexico
2006 Maersk Olie og Gas AS
Cutting of support frames Tyra Dan
2006 Maersk Olie og Gas AS
Cutting of platform structures Halfdan
2006 Aker Kværner Pile guide removal Frigg DP2
2005 Mc Dermott Final Pile cutting Sakhalin
2005 Maersk Olie og Gas AS
Cutting of platform structures Halfdan
2005 OSFI Platform removal. (8) 48” x 2.5” Gulf of Mexico
2005 OSFI 108” pile removal Gulf of Mexico
2005 OSFI Tripod. (3) 36” x 1.5”, (1) 16” x 1” Gulf of Mexico
2005 Manson Gulf Tripod. 9 5/8 thru 30” conductor (3) 36” x 1.5 “ piles
Gulf of Mexico
2005 OSFI Tripod. (3) 42” x 1.5 pile Gulf of Mexico
2005 Tetra Technologies, Inc.
Single pile. (1) 120” x 2” Gulf of Mexico
TRACK RECORD
ingenious simplicity
[email protected] Rev 001
Year Client Work Scope Location
2005 Tetra Technologies, Inc.
Single caisson. (1) 72” x 2.5” pile Gulf of Mexico
2005 OSFI Tripod. (3) 42” x 1.5” Gulf of Mexico
2005 Manson Gulf Single caisson. (1) 60” x 1” pile Gulf of Mexico
2005 OSFI 2 platforms. (4) 48” x 1.5” piles, (5) 42” x 1.75” piles
Gulf of Mexico
2005 Manson Gulf Platform removal. (4) 36” x 1.5” (2) 36” x 1.5” (2) 20-`13 3/8”
Gulf of Mexico
2005 OSFI Platform removal. (8) 52.5-48” x 1.5” conductor
Gulf of Mexico
2005 Manson Gulf Platform removal. (4) 48 x 1.5 piles, (2) 36 x 1.5 piles
Gulf of Mexico
2005 Manson Gulf Platform removal 1 conductor. (4) 42 x 2.5 piles, (1) 9 5/8 x 16 x 24” multi (1) 16 x 24 “ multi (1) 24” conductor
Gulf of Mexico
2005 Manson Gulf Tripod and conductor. (3) 30 x 1.25” piles, (1) 10 3/4 x 14” multi
Gulf of Mexico
2005 Horizon Offshore Tripod and (2) conductors. (3) 30 x 1.25” piles, (1) 30 x 1.25” stub. (1) 9 5/8 x 13 3/8 x 18 multi
Gulf of Mexico
2005 Athena Const. (1) conductor (1) 10 x 16 “ multi Gulf of Mexico
2005 Manson Gulf (1) 7 5/8 x 10 3/4 conductors , (1) 7 5/8 to 26” multi x 42” piles
Gulf of Mexico
2005 OSFI Jacket removal. (4) 48 1.5” piles (2 x piles recut)
Gulf of Mexico
2005 Bluewater Caisson removal. (1) 72 external pile, (1) 72” internal pile
Gulf of Mexico
2005 OSFI Platform removal. (4) 42”x 1.5” piles Gulf of Mexico
2005 OSFI Jacket removal. (4) 60 x 2” skirt piles (2 recut)
Gulf of Mexico
2005 Bluewater Single leg platform and 1 conductor. (1) x 72” internal (3) x 42” piles
Gulf of Mexico
2004 Pioneer Natural Resources
Single casing severance. (1) 30” x 1.5” Gulf of Mexico
2004 OSFI Double platform removal. (12) 30” x 1” main piles, (8) 30” x 1” skirt piles and (4) 29.5” x .75” dolphin piles
Gulf of Mexico
2004 OSFI Jacket removal. (4) x 48” x 1.5” drive piles Gulf of Mexico
2004 OSFI Platform removal.. (8) x 42” x 1” drive piles Gulf of Mexico
2004 OSFI Caisson Severance. (1) 108” x 2.5” external cut, (1) 108” x 2.5” internal cut
Gulf of Mexico
TRACK RECORD
ingenious simplicity
[email protected] Rev 001
Year Client Work Scope Location
2004 OSFI Single casing severance and jacket removal. (1) x 30” x 1” sub-sea casing, (4) 48” x 1.25” drive piles
Gulf of Mexico
2004 OSFI Caisson severance. (1) 72” x 1.5” external cut, (1) 72” x 1.5” internal cut
Gulf of Mexico
2004 Horizon Offshore (1) caisson 48” x 1.75”, (1) caisson 60” x 1.75”, (1) well 9 5/8” x 13 3/8” x 18 5/8” x 30”, (1) well 9 5/8” x 13 3/8” x 18 5/8” x 26”
Gulf of Mexico
2004 Global Industries (4) 60” x 1.75” caissons (1) multi-string 7 5/8” x 9 5/8” x 13” x 20” x 30”, (2) multi-string 9 5/8” x 13” x 20” x 30”
Gulf of Mexico
2004 OSFI Platform removal. (16) 18” x .5 “ piles, (16) 20” x .5” piles, (8) 30” x .625” piles, (10) x 30” x 1.25” piles
Gulf of Mexico
2004 OSFI Jacket removal. (4) 24” x .5” piles Gulf of Mexico
2004 OSFI Tripod removal. (3) 26” x 1.25” piles Gulf of Mexico
2004 Tetra Technologies, Inc.
Cassion removal. (2) 60” x 2” brace piles Gulf of Mexico
2004 W&T Offshore Conductor removal. (15) multiple well strings and casing
Gulf of Mexico
2004 OSFI Caission removal. (1) 96” x 1.5” caission Gulf of Mexico
2004 Manson Gulf Tripod removal. (3) 13 3/8 x >5” conductors, (3) 20” x .5” casing, (3) 36” x 1.25” casing (3) 48” x 1.5” drive pile
Gulf of Mexico
2004 OSFI Tripod and casing removal. (1) 30” x .57 casing stub, (1) 42” x 1.5” vertical pile, (2) 36” x 1.5” brace pile
Gulf of Mexico
2004 OSFI Platform removal. (4) 48” x 1.75”, (2) 48” x 1.75” piles
Gulf of Mexico
2004 Manson Gulf Platform removal. (1) 36” x 1.5”, (2) 48” x 1.5” piles
Gulf of Mexico
2004 OSFI Tripod removal. (1) 48” x 1.75”, (2) 48” x 1.75” brace piles
Gulf of Mexico
2004 OSFI Platform removal. (1) 30” x 1” casing stub (4) 48” x 1.5” piles
Gulf of Mexico
2004 OSFI Platform removal. (1) 60” x1 3/4, (2) 42” x 1 skirt piles
Gulf of Mexico
2004 OSFI Platform removal (2) 42” x 1 3/4 Gulf of Mexico
2004 OSFI Platform removal. (2) 42” x .51 Gulf of Mexico
TRACK RECORD
ingenious simplicity
[email protected] Rev 001
Year Client Work Scope Location
2004 OSFI Platform removal. (3) 42” x 1.25 Gulf of Mexico
2004 UWG Well abandonment, cut inner pipe Total; UK
2004 Aker Kværner Offshorepartner AS
Cutting lids in tank top, internal cutting Ekofisk
2003 Stolt Offshore AS Various cutting, template Valdemar
2003 OSFI Platform abandoment. Bridge support platforms - (12) 48” x 1 3/4”, (4) 48” x 2 1/4”,(4) 60” x 1 7/8” pile cutting
Gulf of Mexico
2003 OSFI Platform abandonment. (2) 48” x 1 3/4”, (2) 48” x 2”, (2) 42” x 1 1/2”, (2) 42” x 1 3/4” pile cutting, (1) 30” x 1/2” conductor cutting
Gulf of Mexico
2003 OSFI Platform abandonment. (1) 72” x 4” (4) 84” x 1 3/4” (4) 72” x 1 3/4”
Gulf of Mexico
2003 OSFI Platform abandonment. (4) 60” x 3 1/4” 3 x 72” x 4”
Gulf of Mexico
2003 Global Platform abandonment. (1) 13 x 1/2” casing , (1) 16 x 1/2” casing, (1) 30” x 1 1/2” conductor cuttings
Gulf of Mexico
2003 Global Platform abandonment. (4) 36” x 1 1/2” Gulf of Mexico
2003 McDermott Pile removal. (3) 30” x 1” Gulf of Mexico
2003 OSFI Platform abandonment. (1) 10” x 1/2” casing, (1) 30” 1 1/4” conductor, (3) 36: x 1 1/4” piles
Gulf of Mexico
2003 Global Platform abandonment. (4) 60” x 1.5” piles Gulf of Mexico
2003 Stolt Platform abandonment. (2) 42” x 1.5” jacket legs
Gulf of Mexico
2003 OSFI Platform abandonment. (4) 60” x 1.5” piles Gulf of Mexico
2003 Bisso Marine Conductor removal. (3) 30” x 3/4” c/w 16” & 10.5” x 3/4’ multi-string conductor, (4) 30” x 3/4” c/w 10.5” x 3/4” multi string conductor
Gulf of Mexico
2003 OSFI Platform abandonment. (2) 36” x 1” 1 x 48” x 1” drive piles
Gulf of Mexico
2003 Tetra Technologies, Inc.
Platform abandonment. (4) 54” x 2 5/8” drive piles
Gulf of Mexico
2003 OSFI Platform abandonment. (8) 48” x 1 1/2” drive piles
Gulf of Mexico
TRACK RECORD
ingenious simplicity
[email protected] Rev 001
Year Client Work Scope Location
2003 Chevron Texaco Pumping station removal. (4) 36” x 6” concrete piles
South Timbalier Bay, USA
2003 OSFI Platform abandonment. (4) 36” x 1 1/2” drive piles
Gulf of Mexico
2003 OSFI Platform removal. (2) 42” x 1.5” and (1) 72” x 2”
Gulf of Mexico
2003 OSFI Platform removal. (2) 8” x 1.5” and (1) 72” x 2”
Gulf of Mexico
2002 OSFI Platform abandonment. (4) 48” x 1 1/4” pile cutting, (1) 16” conductor c/w (1) inner string, 10” x 3/8” grouted
Gulf of Mexico
2002 Horizon Platform abandonment. (4) 60” x 2” pile cutting
Gulf of Mexico
2002 OSFI Platform abandonment. (4) 48” x 1 3/4” pile cutting, (1) 30” x 1” cassion cutting
Gulf of Mexico
2002 OSFI
Platform abandonment. (2) 36” x 1” pile cutting, (1) 30” x 1” drive pile cutting(1) 16” x 1/2” cassion cutting, (1) 10 3/4” x 3/8” cassion cutting, (1) 48 x 1 1/2” cassion cutting
Gulf of Mexico
2002 OSFI Platform abandonment. (4) 48” x 1 1/2” pile cutting. (3) 30” x 1” cassion cutting
Gulf of Mexico
2002 OSFI Platform abandonment. (2) 60” x 1 1/2” pile cutting. (2) 48” x 2” pile cutting
Gulf of Mexico
2002 Global Industries Platform abandonment. (4) 42” x 1 1/4” pile cutting
Gulf of Mexico
2002 OSFI / Chet Morrison
Platform abandonment. (1) 36” x 1 1/2” pile cutting . (2) 36” x 1 1/2” pile cutting
Gulf of Mexico
2002 OSFI Platform abandonment. (4) 48” x 2” pile cutting
Gulf of Mexico
2001 OSFI Platform abandonment. (3) 36” x 1” pile cutting
Gulf of Mexico
2001 OSFI
Platform abandonment. (24) 14” x 1/2” leg pile cutting. (3) 36” x 1” skirt pile cutting(4) 24” conductors c/w (2) inner strings 18 5/8” & 9 5/8” ungrouted
Gulf of Mexico
2001 OSFI
Platform abandonment. (16) 16” x 1/2” leg pile cutting. (4) 36” x 1 1/4” skirt pile cutting. (1) dolphin pile 36” x 1” wall thickness
Gulf of Mexico
TRACK RECORD
ingenious simplicity
[email protected] Rev 001
Year Client Work Scope Location
2001 OSFI Platform abandonment. (3) 36” x 1 1/2” pile cutting
Gulf of Mexico
2001 OSFI Platform abandonment. (8) 48” x 1 1/4” pile cutting. (2) 24” conductor’s c/w (1) inner string 16” x 1/2” grouted
Gulf of Mexico
2001 OSFI Platform abandonment. (4) 48” x 1 1/2” pile cutting. (1) 30” x 1 1/4” cassion cutting
Gulf of Mexico