integrated advanced microwave sounding unit-a (amsu-a
TRANSCRIPT
Report 11183
July 1998
Integrated Advanced Microwave Sounding Unit-A(AMSU-A)
Performance Verification Report
Subassembly and Complete Instrument Assembly
EOS AMSU-A1 Antenna Drive Subassembly,
PIN 1356008-1, SIN 202
Contract No. NAS 5-32314
CDRL 208
Submitted to:
National Aeronautics and Space Administration
Goddard Space Flight Center
Greenbelt, Maryland 20771
Submitted by:
Aerojet
1100 West Hollyvale Street
Azusa, California 91702
Report 11183July 1998
AMSU-A VERIFICATION TEST REPORT
TEST ITEM: AMSU- A1 ANTENNA DRIVE SUBSYSTEM
PART OF P/N: 1356008-1
SERIAL NUMBER : 202
LEVEL OF ASSEMBLY: SUBASSEMBLY AND COMPLETE INSTRUMENTASSEMBLY
TYPE HARDWARE: FLIGHT
VERIFICATION:
PROCEDURE NO.
AE-26002/1C
TEST DATE:
SUBSYSTEM: START DATE:
FINISH DATE:
18 December 1997
10 April 1998
Report11183July1998
TABLE OF CONTENTS
1.0
2.0
3.0
4.0
5.0
5.1
5.2
5.3
5.4
5.5
5.5.1
5.5.2
5.5.3
5.5.4
5.5.5
6.0
7.0
ITEM
INTRODUCTION
SUMMARY
TEST CONFIGURATION
TEST SETUP
TEST RESULTS
REFLECTOR DRIVE ASSEMBLIES
CIRCUIT CARD ASSEMBLIES
SIGNAL PROCESSOR
TRANSISTOR ASSEMBLY
ANTENNA DRIVE SUBSYSTEM TESTS
SCAN MOTION AND JITrER
NOISY BUS PEAK CURRENT AND RISE TIME
RESOLVER READING AND POSITION ERROR
GAIN/PHASE MARGIN
OPERATIONAL GAIN MARGIN
CONCLUSIONS AND RECOMMENDATIONS
TEST DATA
Report11183July1998
1.0 INTRODUCTION
An antenna drive subsystem test was performed on the EOS AMSU-AI_ S/N 202
instrument. The objective of the test was to demonstrate compliance with applicable
paragraphs of AMSU-A specifications S-480-80. Tests were conducted at both the
subassembly and instrument level.
2.0 SUMMARY
The antenna drive subsystem of the EOS AMSU-A1, S/N 202, P/N 1356008-1, completed
acceptance testing per AES Test Procedure AE-26002/1C. The test included: Scan
Motion and Jitter, Noisy Bus Peak Current and Rise Time, Resolver Reading and Position
Error, Gain/Phase Margin, and Operational Gain Margin.
The drive motors and electronic circuitry were also tested at the component level. The
drive motor test includes: Starting Torque Test, Motor Commutation Test, Resolver
Operation/No-Load Speed Test, and Random Vibration. The electronic circuitry was
tested at the Circuit Card Assembly (CCA) level of production; each test exercised all
circuit functions. The transistor assembly was tested during the W3 cable assembly
(1356424-1) test. Refer to Figure 1 for test flow.
CIRCUIT CARD ASSEMBLY
TEST
V
Antenna Subsystem and Subsystem Component Test Flow
The antenna drive subsystem satisfactorily passed all of the performance requirements.
There were no failures in any of the antenna drive components during subsystem testing.
Report 11183July 1998
The results of the subsystem and component level testing are discussed in more detail in
the following sections:
Reflector Drive Assembly ...... 5.1
Circuit Card Assemblies ........ 5.2
Signal Processor ..................... 5.3Transistor Assembly .............. 5.4
Antenna Drive Subsystem ...... 5.5
3.0 TEST CONFIGURATION
The Reflector Drive Assembly Tests confirm the operability of the motor under test. The
test configuration includes, the motor, motor shaft, bearings, and a supporting housing.
The Circuit Card Assembly (CCA) Tests confirm the operability of each CCA. Each test
includes the CCA under test, electronic test fixtures, and the necessary loads.
A segment of the Signal Processor Tests ensures the scan drive electronics are
functioning properly prior to it's assembly into the instrument. The test configurationincludes:
• Timing and Control CCA• Scan Control Interface CCA
• Mux/Relay Control CCA• Interface Converter CCA
• Resolver Data Isolator CCA
• R/D Converter CCA
• Motor Driver CCA
• Test fixture and cabling to simulate the 1553 bus interface
• Test fixture and cabling to interrogate and analyze positional data• Test motor and inertia wheel
The Transistor Assembly Test verifies the correct wiring of the transistor assembly and
associated cabling. Test configuration includes the CKT 1000 (continuity and Hi-Pot
tester), and test fixtures.
The Antenna Drive Subsystem Tests:
• Are configured with the same motor control CCA's used in the signal processor
test, interconnecting wiring, the power transistor assembly, and the drive
assembly with reflector.
• The antenna drive subsystem components were all installed in the instrument
when the subsystem test was performed.
• DC power for the motor control circuit cards was provided by a DC/DC converter
simulator P/N: 1359322-1. The simulator operates on 120VAC facility supplied
Report 11183
July 1998
power. The power for the reflector motor drive circuits however was provided
directly by the STE Noisy Bus power supply.
4.0 TEST SETUP
The antenna drive subsystem tests are performed during system integration. During
system integration testing, the instrument is proven electrically safe via ground isolation,
and power distribution checks. Next, the communication link is exercised to ensure
commands are received and interpreted correctly. The Antenna Drive Subsystem Test is
then performed.
5.0 TEST RESULTS
The Antenna Drive Subsystem components designated for use in the EOS AMSU-A1instrument are shown in Table 1.
CCA (AI-1) S/N
Resolver Data Iso lator Assembly (A 1-1) F25
Interface Converter Assembly (A1-1) F19
Motor Driver Assembly (AI-1) F01
R/D Converter/Oscillator Assembly (AI-1) F21
CCA (A1-2) S/N
Resolver Data Isolator Assembly (A 1-2) F26
F20Interface Converter Assembly (A1-2)
Motor Driver Assembly (A 1-2)
R/D Converter/Oscillator Assembly (A 1-2)
F02
F16
OTHER SIN
Reflector Drive Motor (AI-1) F04
Reflector Drive Motor (A1-2) F05
Signal Processor F01
Transistor Assembly (W3 cable) N/A
Table 1.
EOS AMSU-A1 S/N: 202 Antenna
Subsystem Component SfN Designations
During preliminary testing of these components (in preparation for the antenna drive
subsystem test), several component failures occurred. The component failures and system
related dispositions are listed below:
• Reflector Drive Motor (A1-D - during assembly test, it was noted that
the motor was binding. It was determined that excessive bonding
material was used and it flowed onto the shaft. The shaft was cleaning
Report 11183
July 1998
and tests showed a positive resolution. The process planning wasaltered to reduce the risks of recurrence.
Reflector Drive Motor (.41-2) - during vibration testing the resonant
frequency shifted. The motor was disassembled but anomalies were
found. Electronic tests found nothing abnormal either. The motor was
successfully re-vibrated without failure.
All other components designated for use in the EOS AMSU-A1 instrument (pertaining to
the scan drive circuitry) passed on the first time through component testing.
5.1 REFLECTOR DRIVE ASSEMBLIES
The tests performed on this unit are: Starting Torque Test, Motor Commutation Test,
Resolver Operation/No-Load Speed Test, and Random Vibration. The Motor
Commutation and Resolver Operation tests are performed both pre and post-vibration.
Starting Torque
The starting torque test is performed on the rotating segment of the drive assembly to
verify the torque associated with bearing friction. Reflector drive assembly (F04) failed
the starting torque test at ambient temperature. The motor was binding due to a process
error. Bonding material flowed onto the motor shaft preventing it from turning with
voltage applied. The shaft was cleaned and re-tested. The reflector drive assembly (F04)
then passed the starting torque test at ambient temperature as well as at the colder
plateaus.
Reflector drive assembly (F05) passed the starting torque test at ambient temperature as
well as at the colder plateaus first time through testing.
Motor Commutation Test
This test is performed to determine the commutation characteristics of the motor under
test. Both reflector drive assemblies (F04 and F05) passed the motor commutation test
both pre- and post-vibration tests without incident.
Resolver Operation/No-Load Speed Test
This test is performed to verify resolver operation as well as speed characteristics and
back electromotive force of the motor. Both reflector drive assemblies (F04 and F05)
passed the resolver operation/no-load speed test both pre- and post-vibration testswithout incident.
6
Report 11183July 1998
Random Vibration
Reflector drive assembly (F04) passed vibration testing first time through. The motor
assembly also passed the pre- and post-vibration electronic tests as well as the post-
vibration visual inspection without incident.
Reflector drive assembly (F05) experienced a significant change in resonant frequency at
the random vibration, -6db level. The motor was disassembled, but no anomalies were
found. The motor was successfully re-tested and returned to vibration testing. The motor
was re-vibrated without incident. The reflector drive assembly passed the pre- and post-
vibration electronic tests as well as the post-vibration visual inspection without incident.
5.2 CIRCUIT CARD ASSEMBLIES
Test procedures were prepared for each motor control circuit card; document revision
status is controlled by reference in the shop order. The cards were individually tested to
the procedures and results were recorded on data sheets found in Appendix A. The
following list indexes the CCA Test Data Sheets:
• Appendix A1 ............. Resolver Data Isolator Assembly (AI-1)
• Appendix A2 ............. Resolver Data Isolator Assembly (A1-2)
• Appendix A3 ............. Interface Converter Assembly (AI-1)
• Appendix A4 ............. Interface Converter Assembly (A 1-2)
• Appendix A5 ............. Motor Driver Assembly (AI-1)
• Appendix A6 ............. Motor Driver Assembly (A1-2)
Appendix A 7 ............. R/D Converter/Oscillator Assembly (A 1-1)
Appendix A8 ............. R/D Converter/Oscillator Assembly (A1-2)
All circuit card assemblies passed testing the first time through. The assembly build shop
orders contain the part number and accept tag record the of test and select resistors.
5.3 SIGNAL PROCESSOR
For the first time, the entire antenna drive motor electronics is mated together. The test
instrumentation commands and interrogates the electronics during this segment of testing.
The instrumentation sends position commands to the Interface Converter CCA. The
Interface Converter D/A's the command and provides inputs to the Motor Driver CCA.
The test motor (instrumentation) responds to the drive signal and feeds back positional
data via resolver outputs. The instrumentation then interrogates the Resolver Data
Isolator CCA for position data. A comparison is made in the instrumentation between the
Report 11183July 1998
position command sent and the actual position received. The pass/fail indication is
presented to the operator for test data sheet recording.
The signal processor assembly (F01) passed all scan drive tests.
5.4 TRANSISTOR ASSEMBLY
All transistor assemblies are tested along with their respective W3 cable. The cable is
continuity, then hi-pot tested prior to attaching the transistor circuitry. Each transistor
pair is exercised validating the turn on voltage, current drawn, and cable wiring as well.
The W3 cable assembly was placed on an Inspection Report (IR# 101780) for cracks in a
connector. The connector was subsequently repair by applying .003 inch minimum 2216
epoxy over the cracks. This action precludes the separation of any connector moldingmaterial.
The W3 cable and transistor assembly underwent component testing and passed without
incident.
5.5 ANTENNA SUBSYSTEM DRIVE TESTS
The antenna drive motor electronics mates with the instrument microprocessor for the
first time during this segment of testing. The microprocessor sends position commands
from the memory CCA to the Interface Converter CCA. The Interface Converter D/A's
the command and provides inputs to the Motor Driver CCA. The Reflector Drive Motor
responds to the drive signals and feeds back positional data via the resolver outputs. The
microprocessor then interrogates the Resolver Data Isolator CCA for position data.. The
microprocessor in turn communicates with the 1553 interface which subsequently relays
positional data to the STE.
During other segments of the test, positional data is monitored via a potentiometer
attached to the shaft of each reflector drive assembly. This provides scan characteristic
information in regard to overshoot, jitter, and beam position transition timing for each
motor assembly.
The remaining paragraphs in this section discuss tests that ensures the instrument
complies with specific operating parameters. Prior to conducting these tests there is a
series of preliminary checks that are run to select component values that customize the
operating parameters of each motor. These checks perform the following functions:
Report11183July1998
• Program"onboard"memorywith BeamPositionPointingAnglesfor eachreflectordriveassembly
• Adjustfor peakMotor CurrentLimits onbothAI-1 andA1-2motor drive circuits• ObservePreliminaryScanDynamicsonbothAI-1 andA1-2motor drive circuits• IdentifyMechanicalResonantFrequenciesof eachreflectordrive assembly
Beam Position Pointing Angles are calculated from Nadir pointing direction which is
determined on the antenna range. The instrument's EPROMs (EPROMs for testing;
PROMs for final configuration) are programmed to reflect the position commands. The
initial programming may require fine tuning; fine tuning is determined during the
remaining segments of the test procedure.
Motor Current Limits were adjusted, via selecting "test and select" resistors, to comply
with the specification requirement; less than 1 amp peak current.
Preliminary Scan Dynamics looked good; transition times, overshoot and jitter were all
acceptable at the sampled pointing directions (5).
The Mechanical Resonant Frequencies were identified; notch filters were calculated and
installed to compensate for these resonant frequencies.
5.5.1 SCAN MOTION AND JITTER
In this test, the antenna position was measured in a series of five 8-sec full scans. The
measurement was made with a 1-turn test potentiometer temporarily affixed to the rear
end of the motor shaft. A Dynamic Signal Analyzer (DSA) was connected to the pot
wiper to record the antenna position data. Five scans of each AI-1 and A1-2 were
captured and stored on the AMSU-A1 Test Data File disc. One representative waveform
from each subassembly is presented in Appendix B1 (AI-1) and Appendix B34 (A1-2).
Each 3.33 degrees scene step was expanded and checked for both a 35 msec max step
time, and a 165 msec integration period. Expanded waveforms were plotted and are
presented in Appendix B2 thru B31 for the AI-1 subassembly and Appendix B35 thru
B64 for the A1-2 subassembly. All of the scene steps meet the step response requirement
for transition time, overshoot, and jitter.
Slew periods to the cold and warm calibration stations were measured and met
requirements. A time of 0.21 sec is allocated for the 35.0 degree slew to cold cal, and
0.40 sec for the 96.67 degree slew to warm cal. Calibration station jitter was less than the
+ 5 % maximum permitted. Expanded waveforms for each subassembly were plotted and
are presented in Appendix B32 and B33 (AI-1) and Appendix B65 and B66 (A1-2). Thewaveforms are also stored on the AMSU-A1 Test Data File disc. The test data sheets are
presented in Appendix B67 (AI-1) and B68 (A1-2).
Report 11183
July 1998
5.5.2 NOISY BUS PEAK CURRENT AND RISE TIME
The Noisy pulse load bus peak current and the rate of change of current were measured.
The peak cu_ent must be less than 1A at any beam position along the scan. Peak current
along the scan is .940A. The current rate of change while transitioning from one beam
position to the next (including the transition to the cold calibration and warm calibration
targets) should be greater than 35 microseconds. A random 3.33 ° step was selected; the
transition to the next step was 1.6 ms. The transition to the warm cal position start and
stop was significantly longer than the required 35 ms; 1.95 and 1.56 ms respectively.
The peak bus current was measured across the entire scan and met the requirement. The
full scan waveform was plotted and is presented in Appendix C 1. The waveform is also
stored on the AMSU-A1 Test Data File disc. The test data sheet is presented in Appendix
C2.
5.5.3 RESOLVER READING AND POSITION ERROR
The 14-bit command position word is stored in the "on-board" memory and is read to the
motor drive circuitry under microprocessor program control. The microprocessor also
reads the resolver output at each of the thirty scene stations, and at the cold and warm
calibration positions. The readings are made at the start of integration (LOOK 1), and
halfway into the integration period (LOOK 2). The resolver data is sent to the 1553 bus
interface for subsequent transmission to the STE.
The purpose of this portion of the test is to demonstrate that the antenna is meeting beam
pointing requirements.
If the antenna is out of the pointing tolerance of> + 10 counts at LOOK 1 or > + 5 counts
at LOOK 2, the EPROM is reprogrammed to bring the pointing direction to within the
prescribe tolerances. A copy of the STE computer print out showing the pointing
direction is shown in Figure 2 for the AI-1 subassembly and Figure 3 for the A1-2
subassembly.
10
BP
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
Report 11183July 1998
Actual Diffe_nce* Actual Difference"
Command Look 1 Look,?. Look1 Look2 BP Commanc Look 1 Look2 Look 1 Look2
14520 14522 14522 -2 -2 17 563 571 563 -8 0
14672 14677 14671 -5 1 18 715 720 714 -5 1
14824 14830 14823 -6 1 t9 866 874 865 -8 1
1497S 14985 14974 -10 1 20 1018 1023 1017 -5 1
15127 15134 15127 -7 0 21 1170 1176 1169 -6 1
15279 15286 15279 -7 0 22 1321 1331 1321 -10 0
15430 15439 15429 -9 1 23 1473 1479 1473 -6 0
15582 15590 15582 -8 0 24 1625 1631 1625 -6 0
15734 15739 15733 -5 1 25 1776 1784 1775 -8 1
15885 15893 15884 -8 1 26 1928 1936 1928 -8 0
16037 16043 16036 -6 1 27 2080 2085 2079 -5 1
16189 16196 16188 -7 1 28 2231 2238 2230 -7 1
16340 16349 16339 -9 1 29 2383 2388 2382 -5 1
108 116 108 -8 0 30 2535 2541 2534 -6 1
260 265 260 -5 0 CC 1 4129 4132 4132 -3 -3
411 421 410 -10 1 WC 8528 8527 8527 1 1
• Difference between Command and Actual
Figure 2. Beam Position Pointing Directions and Error Calculation for AI-1
BP
I
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
Actual Diffemnce* Actual Difference*
Command Look 1 Look2 Look1 Look2 BP Command Look 1 Look2 Look 1 Look2
14168 14169 14169 -1 -1 17 211 212 210 -1 1
14320 14324 14319 .4 1 18 363 366 361 -3 2
14472 14473 14469 -1 3 19 514 518 513 -4 1
14623 14625 14622 -2 1 20 666 670 664 -4 2
14775 14775 14773 0 2 21 818 819 816 -1 2
14927 14930 14926 -3 1 22 969 971 967 -2 2
15078 15082 15078 -4 0 23 1121 1121 1119 0 2
15230 15234 15233 -4 -3 24 1273 1276 1272 -3 1
15382 15385 15381 -3 1 25 1424 1427 1422 -3 2
15533 15538 15533 -5 0 26 1576 1578 1575 -2 1
15685 15687 15684 -2 1 27 1728 1731 1726 -3 2
15837 15841 15835 -4 2 28 1879 1883 1878 .4 1
15988 15990 15986 -2 2 29 2031 2035 2029 .4 2
16140 16141 16138 -1 2 30 2183 2184 2181 -1 2
16292 16295 16290 -3 2 CC1 3777 3779 3779 -2 -2
59 62 57 -3 2 WC 8176 8178 8178 -2 -2
Difference between Command and Actual
Figure 3. Beam Position Pointing Directions and Error Calculation for A1-2
5.5.4 GAIN/PHASE MARGIN
11
Report 11183July 1998
A gain/phase margin test was performed on the antenna drive subsystem. The test was
performed by obtaining a Bode plot of the control loop and measuring the gain at 180 °
phase differential and the phase margin at the 0db crossover point.
The Dynamic Signal Analyzer (DSA) was used to make the measurement operating in the
swept sine mode. Three separate Bode plots were made on the antenna and the gain and
phase margins were determined from each plot. The gain margin measured was 9.55 db
(average of three) for the AI-1 subsystem and 9.26 db (average of three) for the A1-2
subsystem. The phase margin measured was 71.1 ° (average of three) for the AI-1
subsystem and 70.0 ° (average of three) for the A1-2 subsystem. These margins exceed
the specification requirements of 9.2 db and 25 degrees and therefore are acceptable. The
three Bode waveforms were plotted and are presented in Appendix D 1 thru D3 for the
AI-1 subsystem and Appendix D4 thru D6 for the A1-2 subsystem. The waveforms are
also stored on the AMSU-A1 Test Data File disc. The test data sheets are presented in
Appendix D7and D8 for AI-1 and A1-2 respectively.
5.5.5 OPERATIONAL GAIN MARGIN
An operational gain margin test was performed on the instrument three times. This test
consists of increasing the gain of the control loop until oscillation occurs. The gain
increase and frequency of oscillation are measured. An increase in gain greater than 8 db
is required; the frequency of oscillation is an observation.
A 50K pot was connected in series with the R58 feedback resistor on amplifier AR8. The
resistance of the test pot was slowly added to the feedback resistor while observing thereflector for oscillations.
The reflector begins to produce an audible sound as gain is increased. The followingadded resistance values are calculated to have the following gain margins for the A1-1
and A1-2 subsystems:
Resistance
(ohms)36.94 K
Gain
8.6 db
36.01 K 8.4 db
36.03 K 8.4 db
AI-1
Resistance
(ohms)34.16 K
Gain
8.1 db
37.67 K 8.7 db
34.32 K 8.2 db
A1-2
12
Report 11183
July 1998
The first mode mechanical resonance of the shaft and reflector is about 171 Hz for the A1-1
subsystem. The power spectrum waveform was plotted and is presented in Appendix E 1. The
first mode mechanical resonance of the shaft and reflector is about 181 Hz for the A1-2
subsystem. The power spectrum waveform was plotted and is presented in Appendix E2. Thesewaveforms are also stored on the AMSU-A1 Test Data File disc. The test data sheets are
presented in Appendix E3 and E4 for the AI-1 and A1-2 subsystems respectively.
6.0 CONCLUSION
Based on the test results, it can be concluded that the EOS AMSU-A1 S/N 202 antenna
drive subsystem meets the AMSU-A specification requirements
7.0 TEST DATA
Test data for the EOS AMSU-A1 S/N 202 obtained in the antenna drive subsystem test is
attached. Data sheet number and type of test is shown in the following Appendix Index.
13
Report 11183July 1998
APPENDIX INDEX
Appendix A 1 ........................
Appendix A2 ........................
Appendix A3 ........................
Appendix A4 ........................
Appendix A5 ........................
Appendix A 6 ........................
Resolver Data Isolator CCA TDS (AI-1)
Resolver Data Isolator CCA TDS (A1-2)
Interface Converter CCA TDS (A l-l)
Interface Converter CCA TDS (A1-2)
Motor Driver CCA TDS (AI-1)
Motor Driver CCA TDS (A1-2)
Appendix A 7 ......................... PUD Converter/Oscillator CCA TDS (A 1-1)
Appendix A8 ......................... R/D Converter/Oscillator CCA TDS (A 1-2)
Appendix B1 ......................... Full Scan Step Response (AI-1)
Appendix B2 thru B31 .......... Single Step Responses (AI-1)
Appendix B32 ....................... Cold Calibration Step Response (AI-1)
Appendix B33 ....................... Warm Calibration Step Response (AI-1)
Appendix B34 ....................... Full Scan Step Response (t41-2)
Appendix B35 thru B64 ........ Single Step Responses (A1-2)
Appendix B65 ....................... Cold Calibration Step Response (A1-2)
Appendix B66 ....................... Warm Calibration Step Response (A1-2)
Appendix B67 ....................... Scan Motion Jitter Test TDS (AI-1)
Appendix B68 ....................... Scan Motion Jitter Test TDS (A1-2)
14
Report11183July1998
Appendix C1 ......................... Peak Pulse Load Bus Current Waveform
Appendix C2 ......................... Pulse Load Bus Current TDS
Appendix D1 thru D3 ....... Gain�Phase Margin Bode Plots (AI-1)
Appendix D4 thru D6 ....... Gain�Phase Margin Bode Plots (A1-2)
Appendix D7 ..................... Gain�Phase Margin TDS (A I-1)
Appendix D8 ..................... Gain/Phase Margin TDS (A1-2)
Appendix E1 ..................... Operational Gain Margin Power Spectrum (A I-1)
Appendix E2 ..................... Operational Gain Margin Power Spectrum (A 1-2)
Appendix E3 ..................... Operational Gain Margin TDS (A 1-1)
Appendix E4 ..................... Operational Gain Margin TDS (A 1-2)
15
....... At
AE-26693A10 Feb 97
TEST DATA SHEET B-6 (SheetIof2)
ILESOLVER DATA ISOLATOR CCA (PfN 1334972) (Paragraph 6.6.7 )
Date:S/N:
6.6.7.1 Supply Voltages
Supply*
+5 V fl)
Measured Value CV)
.O'O
+5 v (u) 5. e I
6.6.7.2 Supply Currents
Steps I and 2:
Supply*+5 V 5)
+5 V (U)
Steps 3 and 4:
Measured Value (mA)
_L
Limits (Vdc)
+0.25
+_0.25
Limits (re.A)
100 max
400 max
+5 V (I)
+5 V (U)
Supply*
* I = Isolated, U = Unisolated
6.6.7.3 Resolver Data
Bit No.
API 0 - AP Bit 0
API1-APBitl
API 2 - AP Bit 2API 3 - AP Bit 3 f'
API 4 - AP Bit 4
API 5 - AP Bit 5
API 6 - AP Bit 6
API 7 - AP Bit 7
API 8 - AP Bit 8
API 9 - AP Bit 9
API 10- APBit 10
API 11 - APBit 11
Measured Value (mA)
_t -_7ll. oq
Pass/Fail
f,¢f
6.6.7.4
fff
API 12 - AP Bit 12
API 13 - AP Bit 13
ConverterBusy Pulse
Limits (mA)
150 max
30 max
Converter Busy Pulse15.0
Measured Value (_ec)
I'¢-'1
Pass/Fail
f
Pass/Fail
t"
Pass/Fail
i"?
B-14
TESTDATASHEETB-6 (Sheet 2 of 2)
RESOLVER DATA ISOLATOR CCA (P/N 1334972) (Paragraph 6.6.7 )
AE-26693A10 Feb 97
Comments:.
Conducted by:
Verified by:
Approved by:
_F_st En_neer .
DC_
Date
Date
Da£e
B-15
AE-26693A10Feb97
TESTDATASHEETB-6(Sheet1of2)
RESOLVERD.ATAISOLATORCCA(P/'N1334972)(Para_aph6.6.7)
Date: q'[19' [ q7
S/N: _ - 7_q q _1
6.6.7.1 Supply Voltages
Supply*+5 v Cl)
+5 v (u)
6.6.7.2 Supply Currents
Steps 1 and 2:
Measured Value ('V)_;,,_ 0
Limits (Vdc)
_+0.9_5
__.0.25
Pass/Fail
P
Supply*
+5 v fl)
+5 V (U)
Measured Value (mA)
55._1
57.2.ce
Limits (mA)I00 max
400 max
Steps 3 and 4:
P_s/Fail
¢¢
Supply*+5 v (I)
Measured Value (mA)9,3 ._7
Limits (mA)150 max
+5 v (U) | _ • I I 30 max
Pass/Fail
t'
* I = Isolated, U = Unisolated
6.6.7.3 Resolver Data
Bit No. Pass/Fail
API 0 - AP Bit 0
API 1-APBitl
API 2 - APBit 2
API 3 - AP Bit 3
API 4 - AP Bit 4
API 5 - AP Bit 5
API 6 - AP Bit 6
API 7- APBit 7
API 8- AP Bit 8
fI'f,t'¢,
API 9- APBit 9 fAPI 10- AP Bit 10 (
API 11 - APBit 11
API 12- APBit 12 ffAPI 13- APBit 13
6.6.7.4 Converter Busy Pulse
L _:272.
[ Converter Busy Pulse I Measured Value (_ec) I15.o ,_34-_ _.q _LLimits (_ec)
4- 3.0 Pass/Failt"
B-14
t47..
TEST DATA SHEET B-6 (Sheet 2 of 2)
RESOLVER DATA ISOLATOR CCA (P/N 1334972) (Paragraph 6.6.7 )
AE-26693A
10 Feb 97
Comments:
Conducted by:
Verified by:
Approved by:
_':_e _4E"n_,zine er ..... Date
K)_ Date .--,_ /
B-15
AE-26693A
• I0 Feb 97
Date:
CCA S/N:
6.13.7.1
TEST DATA SHEET B-13 (Sheet 1 of 3)
INTERFACE/CONVERTER CCA (P/N 1331697) (Paragaph 6.13.7)
I-',>I_qT- 1
Supply Voltages
Supply+5V (U)
+15v (I)-15V (I)
+5v G)
Measured Value (Vdc)
5;.0o¢Limits (Vdc)
+5V_ 0.05
15". O_V +I5V+ 0.15
- 13". cc_/ -15V+0.15
Pass/Fail
t'ff
+5v_0.05 /'
Az.
6.13.7.2 Supply Currents
Step I (CP and API Low):
Supply
+5V (U)
+5V (I)
+15V (I)
- 15V (I)
Measured Value (mA)
17.7 )7-0.37
Limits (mA) Pass/Fail
70- 110 f1.5- 5.5 f'15- 23 P
18 - 26 _'
Step 2 (CP and API High):
Supply Measured Value (m A) Limits (mA) Pass/Fail
+5V (U) _4 -'1...0 40 - 70 ('
+5v 0) z3. g.3+15v a) 1 l. "7 o
-]5v (1) _ o. "_z4
18 - 30 f
15 - 23 f
18 -26 f
6.13.7.3 Amplifier Offsets
AmplifierARI
AR2
Measured Value (mY)
- O. Ol
O-7.0
Limits (mY) Pass/Fail
o.o_+o.15 po.o _zo p
B-26
TEST DATA SHEET B-13 (Sheet 2 of 3)
INTEKFACE/CONVERTER CCA (P/'N 1331697) (Paragraph 6.13.7)
AE-26693A10 Feb 97
6.13.7.4 Subtraction and D-A Conversion
Step 1:
Actual Position (API)
MSB LSB
00000000000000
00000000000001
00000000000010
Command Position (CP)MSB LSB
00000000000000
00000000000000
00000000000000
ARI Output*
Voha_e Required (Vdc)0.00000
-0.00061
-0.00122
00000000000011 00000000000000 -0.00184
00000000000100 00000000000000 -0.00245
00000000001000 00000000000000 -0,00490
00000000010000 00000000000000 -0.00979
00000000100000 00000000000000 -0.01958
00000001000000 00000000000000 -0.03917
00000010000000 00000000(300000 -0.07834
00000100000000 00000000000000 -0.15667
00000000000(0X)00001000000000 -0.31334
01000000(X)0000
00010000000000 00000000000000 -0.62669
00100000000000 00000000000000 -1.25338
00000000000000 -2.50675
I0000000000000 O000000000OO00
* Tolerance on output voltage is + 10%
-5.01350
Test Result
(Vdc)
- 0. ete&l
- o. e,c.,..q,{- _. OQocqq
-n.e!ooc
-o. 1&¢5)
-O.Sa.I _ 3
l_ 0. (Q/..i.,'_/..t-0
- :z._(,qq
-5. i5¢I_
Pass/Fail
P.pf,4'
I"e
I'
ef,
Step 2:
Actual Position (API)
MSB LSB
00000000000000
o0o00o0o000o00
Command Position (CP)MSB LSB
00000000000000
o00000o0o00001
AR 1 Output"
Volta_e Required (Vdc)0.00000
0.00061
00000000000000 000000000000 i0 0.00122
00000000000000 0000000000001 i 0.00184
0000000000(O_ 00000000000100 0.00245
00000000000000 00000000001000 0.00490
00000000000000 00000000010000
00000000100000
0.00979
00000000000000 0.01958
00000000000000 00000001000000 0.03917
00000000000000 00000010000000 0.07834
00000000000000 00000100000000 0.15667
00001000000000 0.31334
0001000000(O_ 0.62669
00000000000000
10000000000000
00000000000000
00000000000000 00100000000000 1.25338 _C'_r_#l
00000000000000 01000000000000 2.50675
-5.0135000000000000000
voltage is + 10%* Tolerance on output
Test Result
(Vdc)
•_o. 0o0oI
4-0.cOc.T:_'_''
Pass/Fail
fI'ff,fI"fffeff
B-27
AE-26693A10Feb97
TESTDATASHEETB-13 (Sheet 3 of 3)
INTERFACE/CONVERTER CCA (P/N 1331697) (Para_aph 6.13.7)
6.13.7.5 Strobe Function
Step I: Strobe Low
No E11 Change
with Input CP Changes
Pass/Fail
f
Step2: Strobe High
El I Change
with Input CP Changes
Pass/Fail
6.13.7.6 Amplifier Gain
Ell
El0
E 10 Voltage
E! 1 Voltage
Measured Value (Vdc)o.2 zlzS
Limits (Vdc)
10.7 - 11.3
Pass/Fail
____L_
___L_
6.13.7.7 Ground Isolation
Pin 91 to Pin 7
DC Resistance
Measured Value.(Mfh Limits (Mr2)
0:_ >20
Pass/Fail
f,
C°mments_k.}O _.
Conducted by:
Verified by:
Approved by:
_,_est Engineer I Date
DCMC -- /
B-28
AE-26693A• I0 Feb 97
Date:CCA S/N:
6.13.7.1
TEST DATA SHEET B-13 (Sheet 1 of 3)
INTERFACE/CONVERTER CCA (P/N 1331697) (Paragraph 6.13.7)
Supply Voltages
Supply+5v (U)
+15V (I)
-15v (D+5v (I)
Measured Value (Vdc)_..,;.ol v'
Limits (Vdc)
-t %.o( v'
+5V± 0.05
q-l_, c3 V +15v+0.15
-15V± 0.15
-f S. ooV +5V± 0.05
Pass/Fail
ei'PI:'
6.13.7.2 Supply Currents
Step 1 (CP and API Low):
Supply+5V (U)
+SV fI)
+15V (I)
-15V (I)
Step 2 (CP and API High):
Measured Value (mA) Limits (mA)
IL¢,. 17 .^ 70- 11o5,37 _ 1.5-5.5
_7. q[ _1_ 15-2318 - 26
Pass/Fail
99g
Supply+5V (U)
+sv (1)+I5V (I)
-15V fl)
Measured Value (mA)
l.. _ .z,q_,_tLimits (mA)
40 - 70
18 - 30
15 - 23
18 - 26
Pass/Fail
t't'¢?
6.13.7.3 Amplifier Offsets
AmplifierAR1
AR2
Measured Value (mV) Limits (mY) Pass/Fail
PP
B-26
Aq
TEST DATA SHEET B-I3 (Sheet 2 of 3)
INTERFACE/CONVERTER CCA (P/N 1331697) (Para_aph 6.13.7)
AE-26693A
10 Feb 97
6.13.7.4 Subiraction and D-A Conversion
Step 1 :
Actual Position (API) Command Position (CP)MSB LSB MSB LSB
00000000000000 00000000000000
00000000000001 00000000000000
00000000000010 00000000000000
00000000000011 00000000000000
00000000000100 00000000000000
ARI Output*
Voltage Required (Vdc)0.00000
-0.00061
-0.00122
-0.00184
-0.00245
00000000001000 00000000000000 -0.00490
00000000010000 0000000(0300000 -0.00979
Test Result
(Vdc)
tO. ¢0oo 5'
-O. Q0i?-_-0. ec,IQ,_
-0. f.31_,I'0
Pass/Fail
fff
00000000100000 0000000(X)00000 -0.01958 - 0. c 2.t Z (,00000001000000 000000013000000 -0.03917 f
00000010000000 00000000000(300 -0.07834
00000100000000 00000000000000 -0.15667
-0.3133400001000000000 00000000000000
00010000000000 00000000000000 -0.62669
00100000000000 00000000000000 -1.25338
01000000000000 00000000000000 -2.50675
0000000000000010000000000000
-0.o_cSq-0.eoaiz-7'
- o. 3z_57,7
-O._s)eo_).._Dz3-z. (.oq7
-5.'zc']q--S.01350
P
ff,
Tolerance on output voltage is + 10%
e-e
Ft'
ff
Step 2:
Actual Position (API)
/vISB LS B
Command Position (CP)
MSB LSB
00000000000000 00000000000000
00000000000000 00000000000_ 1 0.00061
00000000000000 00000000000010 0. 00122
00000000000000 00000000000011 0.00184
00000000000000
00000000000000
AR 1Output*
Voltage Required (Vdc)0.00000
00000000000100 0.00245
00000000001000 0.00490
00000000000000 00000000010000 0.00979
00000000000000 00000000100000 0.01958
00000001000000 0.03917
00000010000000 0.07834
00000100000000 0.15667
00000000000000
0000000OO00000
00000000000000
00000000000000 00001000000000 0.31334
00000000000000 00010000000000 0.62669
1.2533800000000000000
(NDO00000000000
00000000000000
0010{_}000000(03
0100000O(0)0O00
10000000000000
voltage is + 10%* Tolerance on output
2.50675
-5.01350
Test Result
(Vdc) Pass/Fail
i'I'
f
ft'fe
fef
P
f,
f
B-27
AE-26693AI0Feb97
TEST DATA SHEET B-13 (Sheet 3 of 3)
INTERFACE/CONVERTER CCA (P/N 1331697) (Parag'raph 6. I3.7)
6.13.7.5 S.trobe Funciion
step i: Strobe Low
No E11 Change
with Input CP Changes
Pass/Fail
Step 2: Strobe High
E11 Change
with Input CP Changes
Pas s/Fa iI
__£___
6.13.7.6 Amplifier Gain
Ell
El0
E 10 Voltage
El I Voltage
Measured Value (Vdc)O.-3z_._, 1
3.5 135,
Limits (Vdc)
10.7 - 11.3
Pa___.ss/Fail
__f_____
__L_
__f,
6.13.7.7 Ground Isolation
Pin 91 to Pin 7
DC Resistance
Measured Value (Mr2)
cP
Limits (Mf_)
>20
Comments:
Conducted by:
Verified by:
Approved by:
est Engineer t Date
uality ICon_ro¶ InspeCt\
B-28
_5
.pi.
%,
TEST DATA SHEET B-4 (Sheet 1 of 2)
MOTOR DRIVER 3-HALL SENSOR CCA (P/N 1331694) (Para_aph 6.4.3)
AE-26693A
I 0 Fel_ 97
S/N:
Date:
6.4.3.2
#l_qql
Input Si_n.al Offset
Step No. Test Results Limits
4 e, 7_; b_/ 0.0 +I mVdc
6 i'Ig _,q 0.0 + I mVdc
0.0 + I mVdc
Step No. Test Resistor Resistance Measured13 E7-E8 (R25)
E9-E 10 (R52)
El 1-El2 (R33)
EI3-EI4(R53)
EIS-EI6 (R42)
EI7-EI8 (R54)
q. zg
3 ,)_h
_-76 I_,.z,,.._k
.zt. 7-zk
Step No. Resisiors Selected Trim Resistors
14 R25
R52
R33
R53
R42
R54
g¢c. 5..gJe.tTr_F-._g _,'c.s.s-.1-:__' !F.S-
Step No. E Point Test Results Limits Pass/Fail19 El9 0.0 _+1 mVdc
E20
E21
q.: t_q_
- O.¢2hV 0.0 +_1 mVdc
0.0 _+I mVdc
PPP
6.4.3.3
Clockwise Rotation:
Motor Driver Operation
Step No. Test Results Limits Pass/Fail2 +5V-+0.05Vdc
3
4
5
_,q_,v
I_,-e7qi. _,_,v,A
- _ff, 1,t vI_ •7"" _,
._._.IoV
70mAde max
+15V+0.15Vdc3.0mAde max
-15V_+0.15Vdc
25mAde max
+28V+0.SVdc
8mAde max
400mVdc max
50mAdc max
50mAdc max
i't'?
F'¢,
B-9
A5
AE-26693A
':" l0 Feb 97%,
TEST DATA SHEET B-4 (Sheet 2 of 2)
MOTOR DRIVER 3-HALL SENSOR CCA (P/N 1331694) (Para_aph 6.4.3)
Counter Clockwise Rotation:
Step No. Test Resuhs Limits
3 '7- _ _ h g 400mVdc max
5 _ O. 2-_ A 50mAdc max
Pass�Fail
f
f
6.4.3.4 .Current Limit Test
Pass/Fail
Comments:
Conducted by:
Verified by:
Approved by:
estEngineer I " _
( Qjla_;t:_._ospoc4rl"-7.,n,.//h/,_ ."'
DCMC
Date
Date
Date
B-10
4"t
S/N:
TEST DATA SHEET B-4 (Sheet I of 2)
MOTOR DRIVER 3-HALL SENSOR CCA (P/N 1331694) (Paragraph 6.4.3)
AE-26693AI0 Feb"97
Date:
6.4.3.2
a.ho/ q7
Input Signal Offset
Step No. Test Results Limits
4 I-'Z'_" I_'_/ 0.0 _.+1 mVdc
6 ],'_C _"V 0.0 +_.ImVdc
8 0.0 • 1 mVdc
I I
Step No. Test Resistor Resistance Measured13 E7-E8 (R25)
E9-E10 (R52)
E11-El2 (R33) ">, 1( K
EI3-EI4 (R53)
EI5-E16 (R42)
EI7-E18 (R54)
Step No.14
Resistors
R25
R52
R33
R53
R42
R54
Selected Trim Resistors
g_c _;5.173"zt FS"
_ h] C 9 5 S q "zZ I F ._
Step No. E Point Tesi Results19 El9
E20
E21
Limits Pass/Fail
0.0 -+1 mVdc p0.0 + 1 mVdc
0.0 + I mVdc 1_
6.4.3.3
Clockwise Rotation:
Motor Driver Operation
Step No.2
3
4
5
Test Results
_. #7V
__. ,/&v
_._
Limits
+5V:t0.05Vdc
70mAdc max
+15V_+0.15Vdc
3.0mAdc max
-15V+0.15Vdc
25mAdc max
+28V_+0.5Vdc
8mAde max
400mVdc max
50mAdc max
50mAde max
Pass/Fail
fffffffff
f
B-9
AE-26693A
:_ l0 Feb 97%,
TEST DATA SHEET B4 (Sheet 2 of 2)
MOTOR DRIVER 3-HALL SENSOR CCA (P/N I331694) (Paragraph 6.4.3)
Counter Clockwise Rotation:
Step No. Test Results Limits Pass/1::ail3 400mVdc max
4
55_,q_A 50mAdc max
50mAdc max
ei'f,
6.4.3.4Current Limit Test
I StepNo. I Test Results I Limits..2-'" _ # 7 t11_ 350-500mAdc I Pass/Failf,
Comments:
Conducted by:
Verified by:
Approved by:
Date("'NTest Engineer
( Quality C_nt_ol Inspec_b'r \ Date
DCMC Date
B-10
TEST DATA SHEET B-5 (Sheeti of3)
R-D CONVERTERJOSCILLATOR CCA (P/N 1337739) (Para_aph 6.5.7)
A_
AE-26693B
19 Jun 97
Date
CCA S/N
6.5.7.1
Step 2:
F .I13377_q- I-U'I/F Pre-Test
Supply Currents C,Vithout UUT)
Step 6:
Supply ('Vdc) (Baseline) Measured Value (mA) Limits (mA) Pass/Fail
(Without UUT)+15 O. 06 0-I
-15
+5
--o.zg0.06
-I-0
0-I
ff
Supply Voltages _Vithout UUT)
Supply+15V (I)
Measured Value (V)
l$.o 2_-15V(I) - L_, O (
+5V fl) _;.Ob
Limits (V) Pass/Fail
± 0.50
± 0.50
_-+0.25 O
Supply Currents (UUT Installed)
Supply (Vdc) Measured Value (mA) Difference (mA) 'Limits (mA)('UU-I"Installed) (Measured - Baseline)
+ 15 20-40
-15 -. j_. _+5 )4- / 0
-30 - -50
30-70
Pass/Fail
Fr
6.5.7.2 Supply Voltages (LrLFF Installed)
Suppl_,
+15V fl) ..
Measured Value (V) Limits CV,)I5. o_ _.0.50
-15v (D - t_. ¢7 _+0.50
+5V (1) _. o 7. _+0.25
Oscillator Frequency..Dutv Cycle, and ..Output Voltage
Parameter Measured Value Limits
1550-1650 Hz
Pass/Fail
t"t'F
6.5.7.3
Frequency
Du D, Cycle
Output Voltage 7.'/'t V
45'55 %
7.6-8.4 Vrms
Pass/Fail
P
B-II
AE -26693B
19 Jun 97
TEST DATA SHEET B-5 (Sheet 2 of 3)
R-D CONVERTER/OSCILLATOR CCA (P/N 1337739) (Parauaph 6.5.7)
At/
6.5.7.4 R-.D Converter Operation
Step 1:
Bit Number/ CW CCW
Test Fixture Label Pass/Fail Pass/Fail
API 0/1 . , /bAPI I/2
API 2/3
API 3/4
API 4/5
API 5/6
API 6i7
API 7/8
API 8/9
API 9/10
API 10111
API 11/12
API 12/13
API 13114
Converter Busy
rr
I,t
P
i;)
,fStep 2:
RS I Measured Value Calculated Value (Vdc) * Calculated Value (Vde) * Pass/Fail
(El0) I (Vdc) CCA - I Assy CCA -2 AssyCW Rotation** t. #_fTq (+) I" "/'_G V (+) ld[_ -
CCW Rotation** - l- _'2. i (-,) 1"7 _ G' _ (-) _[&
• Signal level function of te{.t and calibration gain resistors. Record calculated value and measured value. Measuredvalue shall be within +_I.0"percent of calculated value. The equation is as follows:
Amplifier Gain
" ' PES-I_S
6.5.7.5
PES = +0.300 Vdc
PES = -0.300 Vdc I-l (_
Measured Value Limits (Vdc)
(Vdc)
i • i 1.ootol.3O '1.00 to 1.30
6.5.7.6 Direction Control Si_=nal
DIR CNTR.L Measured Value Limits (V'dc) Pass/Fail
(Vdc)
CW Rotation _-. e 0 I 4:5 to 5.5 f
CCW Rotation O. I 3 ._ 0.0 to 0.4 -p
¢
B-12
TEST DATA SHEET B-5 (Sheet 3 of 3)
R-D CONVERTER/OSCILLATOR CCA (P/N 1337739) (Paragraph 6.5.7)
,4ri
AE-26693B
19 Jun 97
6.5.7.7 . N.otch Filter Frequency Response
Frequency Measured Value (Hz) Calculated Value (Hz) * Calculated Value (Hz) * Pass/Fail
CCA - I Assy CC.A -2 Ass),
_3 Notch _ t_ wi_r _ fPr dl/_
AR4 Notch _ - IARS Notch _ " [ | I
• Notch frequencies shall be within +_.3percent of values determined by test and calibration resistors. Record calculatedand measured values.
C°mmen_:g0_'_.
Conducted by:
Verified by:
Approved by:
- - D te/ /
DCIvlC Date
B-13
A_
°.:
TEST DATA SHEET B-5 (Sheet 1 of 3)
Date
R-D CONVERTER/OSCILLATOR CCA (P/N 1337739) (Paragraph 6.5.7)
CCA S/N
6.5.7.1I")_ 77_9-- I
UUT Pre-Test
Step 2:
Supply Currents O,Vithout UUT)
Supply (Vdc) (Baseline) Measured Value (mA) Limits (mA) Pass/Fail
(Without UUT)
+15 0-1-15
+5
-I -0
0-I
f?P
Supply Voltages (Without UUT)
Supply+15V (I)
-15V (I)+5V (I)
Measured Value (V)
15. 97.v
!;. o3V
Limits (V)
± 0.50
z 0.50
_+0.25
Pass/Fail
PP
Step 6:
Supply Currents (UUT Installed)
P
Supply (Vdc) Measured Value (mA) Difference (mA) Limits (mA) Pass/Fail
(UUT Installed) (Measured - Baseline)
+ 15 20-40
-15", I. 7.._-
90.51[_t_
-3o - -5o
PP
+5 30-70 p
Limits (V) Pass/Fail
*_0.50 I_
AE-26693A
10 Feb 97
6.5.7.2 Supply Voltages (UUT Installed)
SupPlY
+lSV (I)
Measured Value (V)15;.o IV
-luc. q_V-15V (I) *_0.50
+5V (I) '3- _ 2.,,4 --,20.25
6.5.7.3 Oscillator Frequency, Duty Cycle. and Output Voltage
Parameter Limits Pass/Fail
Frequency
Duty Cycle
Output Voltage
Measured Value
I& 15 _'l'Z 1550-1650 Hz
_9., .'_'o 45-55 %
]1. o._gb '_ 7.6-8.4 Vrms
t'fi=,
aP
B-I1
AE-26693A.: 10 Feb 97
TEST DATA SHEET B-5 (Sheet 2 of 3)
R-D CONVERTER/OSCILLATOR CCA (P/N 1337739) (Paragraph 6.5.7)
6.5.7.4
Step l:
Step 2:
R-D Converter Operation
Bit Number/ CW CCW
Test Fixture Label Pass/Fail Pass/Fail
API 0/1
API 1/2
API 2/3
API 3/4
API 4/5
AP[ 5/6
API 6/7
API 7/8
API 8/9
API 9/10
API 10/l I
API 11/12
API 12/13
API 13/14
Converter Busy
f
f,
¢,t_
fI'
fff,f,f1>
t'fe
f
Measured Value Calculated Value (Vdc) * Calculated Value (Vdc) * Pass/Fail
la._ ('_ so_ fVdc) CCA-1 Ass>, CCA -2 AssyCW Rotation** _. S _ V 1-74 V _///_
CCW Rotation** - I, 19 _' -- [_7_IV ' k//h t7
• Signal level function of test and calibration gam resistors. Record calculated value and measured value. Measured
value shall be within +10 percent of calculated value.'Y'_ _./£_-- cx._-,_...._,_'_:
-- _ _ - Fx__ox v _ RTx _;lh
6.5.7.5 Amplifier Gain _ _. t_, ,9,_
PES-RS Measured Value Limits (Vdc) Pass/Fail '
(Vdc) /PES = +0.300 Vdc _ • i 0 V 1.00 tol.30
PES = -0.300 Vdc _, I "2.- V 1.00 to 1.30
6.5.7.6 Direction Control Signal
DIR CNTRL Measured Value Lim'its (Vd¢) Pass/Fail
(Vdc)
; J_'CW Rotation _, o o V 4.5 to 5.5 _'CCW Rotation _ , I "_I/' 0.0 to 0.4
_'- t 9-9"/
B-12
,4g
TEST DATA SHEET B-5 (Sheet 3 of 3)
R-D CON'VERTERJOSCILLATOR CCA (P/N 1337739) (Paragraph 6.5.7)
AE-26693A
10 Feb 97
6.5.7.7 Notch Filter Frequency Response
Frequency
AR3 Notch
AR4 Notch
AR5 Notch
Measured Value (Hz)
)J
Calculated Value (Hz) *
CCA - 1 Assy
-I
Calculated Value {Hz) * Pass/Fail
CCA -2 Assv
* Notch frequencies shall be within +3 percent of values determined by test and calibration resistors. Record cland measured values.
Comments:
Conducted by:
Verified by:
Approved by:
f"'_Test Engineer , Date ,
B-13
EH
H0
E.<©UM
_r
L.. _ L b
_]|
>
L
d
0|
E
b.
I
n\
0@
>
0
i I
X i• ° • °
b_
>Ext(0
II
il>-<]
GOLfl
©
U>-
>fOEEO©.
,h
UOX>-
LL
(I}m,lOxtECO E0)_ H
, C)]
hiS) CL(O
UOU_
, i
\
xfE>O] .H
Q\
N
"L _ •
r'-
_J
I"7
h-
E ,.
E > LL
B?.
>E
if)CO
LO01II
>..<!
©O0MO0
II>-
>_EE©E),r.i(_ "'"
,QIn1"
ilOX>-<1<I
Ii_
(]om
ELF}Z[',,[',, H,1"t--
Od, ©b,l.13fl_ ,MII <©llgO
X>-
OE>0 "_
OJ 0\
r-i
0@fY >
0@
y--
XLL
Bq
>E©M
©(I]II
>-
U]
0N
I
©II>-
>01E
©,
.0
01nUOX>-
m
Em
D,h3bll
X>-
LLDm
EH
HlO
rl ,
<lOU
OE>0
\
D
r-i
0grF
i
>X
11
t",0
II
(0COII>..<1
OdO]¢31.13
II
II>-
>mEE_iF),l.f)_
,03IJ3m0Olllid
×)-<I<I
CO
EO_[,,,_
,N
b,(.D[',,_no
×>-
i
it
I
2
i! o
/--' ,i .......
lef-
i
%
>E
hD
|
©
II>-
(0
@_JO)
|
(0II>-
>fOEE_¢(0.
l_fll
IIgX>- -<I<]
11.D
©m_M
01(I).I/II--
O, (Xl(I)©n ,O)H <hHO(J
X>-
QE>| °r4
O DG0 \
iI
i
i
q
I
i
r-4
U0r/ >
I
kD
,hh,
© X_ i
lO XLL
iw_w
|©
II>-<_
©©mm
ii>-
>mEE[D
©,
.0
m ii
x>-<_<_
b_]m
H
b_n_.
U_
OD_mODOI
t
,(0II
noX>-
i'I
(
UIE>
\0
n_
LO
>
I
!
I
X
[0 XIi
>E(0
I
mIi
<1
_3o
©|
I1
>_E
(0,
110X>-
Ii
_m
.b,t].,_II <DOIIO0X>-
OE>
0\
,-I
g@O_
B_
Ol X _-_
X> __
©
|
O]II>.<I
(I]#O0
I
II>-
>
E_]©,
,h_]00OOHngX>-
LLD
©m
0_
00©ILl, Li].1%13.,
_R <GO_gUX>-
_]E>
\0
FF
I
"iE
q
c_
0
I
>
F--
U3 x _
LL
13q
!
>E
MII>-
_J
0
II>-
>fOEE_©.
.©1.003(_IIII0X>-<I.<I
LL
_rnfOOD(I)_
0)(3b,. (:3,COn .
_H <0]_OlJ×>-
_E>
D\
0@
_0
I
"_×
>
It-"
IT
X
>E
O_(D
I
U]M
>-
_JPJO_D,
II>-
>_EEL",©,
,©_MM_
X)-
LL
CO
,_0O_ .•_n <CD
X>-
I:
_b
i
p
OE>
\
r-I
0@r(
f
_d r!
,_o
,@£so
t_
tn _
>
T
XU_
>E[0O0
|
(0M]I>-
©©
|
O_II>-
>fOEEbl©,_N,0_
_mMxHox>-
(no
©oo
lO0
N_II0X>-
LL
m
EH
H
0.,
U
OE>O -_
D\
_Y
I
I
_r
'o_
I-
Ll
>XlL
6P-
>E
O0(I)
I
{I>-.<I
if)D,_Jg)N
g_II>-
>DIEEGO©,
,GOLOft)_HllOX>-
CO0100
Q0010g_m..0)
_HHOX>
LL
m
t---t
O_0_.
0
DEQ
>
fil\
q
I
!1
I
1
r--!
0Qn" >
IO_
-daJ_.
'i
r_
EL
>E
|
mII>-
©0_0O0
|
O_II>-
iI
q
Ii
>(hEE('r)
(0,
,0)I.F)('0MIIii gX>,-
M
D,,_O0_©,,@
NnnoX>-
hDm
EH
HN
<0U_
OE>0
[]\
/
r-4
@FY
I
P
X
_q
>
_f
, N
O) "13 ....
[1_
>E
CB
hlMII>-<_
D,OdOd
D
II>-
>_EE_(0._xt.O)
_r0mnnox>-
ii
x_mo_D
0_D,H
.@ 12-.Ell <:_11I:] U_X)-
QE>D
D\
r-_
0@FY
!
,8
,1
ca_ A
>
2,"_ X ..
XL
BI5
p
@
MII>-
a)
_0
0
II>-
>_EE_lO,
.D,_mm_
X>-
©NO.O0,i-4
OOU
X>-
I,3m
EH
H@
<0O_
OE>0
D\
I
j!
g@n_ >
|
0
M
,-q
X
X[L
I
_J
8
>E
M
MII>-
©O]@
|
Q
II>-
, Bt_!
II
I
ii
.I
>t_EEN©,
_gMM_llgX>-
LL
_rnlO©
0]© HQ._JQ M
Mll <_IIOU_X>"
DE>
Q\
0@r_
F
>
U')|
0
_°
,-..&
X
"13X
11
I
N
.i
>.E
|
01il>-<I
r4
lO_J01
@
rt
II>-
>OlE
(0._-Irl
.el)_m01UOgX>-
LOb,01
T-I •
n_
mgfig
X>-
llDm
i-4
!-0
Q.. .
U_
OE>0 -H
N 0\
K
O@n, >
,_ '.
r
_ e
I
t--
(I)I
09 _
>E03
mII>-
mO)tO
I
rl
II>-
>InEED(0._O.©
mnIox>-<_<_
m
u]_mrl I
mll
×>-
LL
m
H
@ OE0I-I
.i
.!
!
)
>.rl
(]\
,I
r-i
Q
C
O_ "
J
t-
_ X_ _
LL
eZO
>E
O3|
U]01]I>-
O3
Ol
U>-
>lflE
b,.b, flO
OOn
X>-
LL
_m
_Zb,b,
iT"l N t
0]_ <:(11HOU_X>-
OE>0
\
i,
I'
0
n,
I
>
LO|
rl
I
o_
"4
I
b--
I:L", -
x _ _11
>EODOD
InO0II>-
ODQ
|
r.I
11>-
>ODEE_t(1),_-,OD
bDmOD_IOX>-<I<I
LL
m
QE>
\
Ol(I)
g)Q _r'l f _-,
Q_ b,t v'! (]... e
IID U_XY
4
I
r_
Ogn,
i
I
!f
o
>
I "": L
CD, 0
1
'Xl
%_ °
>E
|
mII>-<I
D,|
N
II>-
>(f) EEO)(.0 I,-40,0)
1.1303mll_OX>-<]<_
D,.10g)
0J
N,NN
xt_II OX>-
IiDm
EI--t
l-i--t
11,<mU,'_
OE>O .,4
,--' t3\
r-.,i
O@n,
8Z2
>
_q
9q
hJz
O] Xt
_ X[I.
BZ._
mliix)-
LD
© m _
IOO,_X)-
OE>0 -H
\
>E
0)|
IS)00II>-
D,C]
m
II>-
>mEEU3©,
,CDu3mmnIOX>-
LL
@menD,b3_
IJ')_ H
0J,F-O03 CO
_'n <(T)_DU_X>-
C]D
E>.rl
D\
,¢
/\
r_
g@rF
!
ii-
IL
C]
O0|
&rch
.i
4 °
0
DO
> LL
>E
I
OQII>-
i
| N
L:
8Z5
(0
I
01i--I
II>-
>O')EE,--,(0,rl_-i
.(I)
UU×>-<1<1
LLD
N . I--.a)_ m
trl N j
_t_ <xtllgU_)<Y
OE>0 -_
\
I/<
r-i
U
E >
tn _
b_
>EGDGD
mIi>-<_
D,©m
|
II>-
>(hEEm©,
,(]Dmmm_Ig
x>-<_<_
b.D
blm
@z
Dm Ul
n g L),_X>-
DE>
D\
It.
I
\
I
d
q
d
q.,1
I
DQn_ >
|
fl )
I "
! "-"---
08Ol
N
-m
_o
Cl)@
I
D- XI
CO -13XEL
8_
i
I
I
_,_
F-
I
]
cO
Y_
>E
G0_0
|
U3
II>-<_
OO__3
|
II>-
>10EED_(0._J,OD
LOf0mlXgX>-<I<I
IfZ:)!
I-,_ O0
l_n <_-iIg L)_X>-
!
!
I
OE>0 -_
,-" [3\
r-i
g
iZ
,[[]
\
° ,._0 I,,.
t--.-
..'-L
@
o xSi
>
>EODCO
@
b3COII>-
D-O©O_
_t
II>-
>_EEM©,
,D,_O0
DOX>-<_<_
LL
mm
_E(BE)m , I---
,,-4 O- •
IDII<U]I10 U,-"X>-
DE>Q .,-t
X0@FY
B/.._
L
,,,}
,,--,'5
,,r..
"-->i
N
> LL
>E
@
II>-<
5J
m@
tO
II>-
>tOEE(Q(D.
.D,,I/Im
II0X>-
D,,(I)01c1r_ m
©N"
tonII0X>-
,.,..,.,
h.
m
V==t
V-\ OE>
D\
!
i
i
,-I
@fY >
; , I
0
, J0 .I
t
I_
._r..
l
O=Zx_
LL
@ X|
>E(I)
@
l.B01II>-
03(.0
E)II
I11
II>-
>(/IEEM©,
,01
MIInOX>-<I<I
01©0')
,._MN'.GOLF)tr-.l
1.1311110X>-.
!.I..
m
I,--!
i--
ri_ ,.<©(_.)_
d
'I
p,
i"
OE>0 .,-I
,'-'CI\
Ir
I
-J.._
r-i
0@rY >
I_b
M XIf
I_ "0 "d
LL
-..d
c_
.',/,Ji
l,q"",..-I
!
_3t
This page has been intentionally left blank
O0|
©©I-4
U>-
If)
|
II>-
>
E@_m.co
o.
x>-
b_D
_rn
OE
i'-'I O- e
_OONX>-
f(
DE>O .H
O0 0\
B_z.
!
@
I
r-i
0@
>
_ X_ _]
>E
OlCO
>-
N
NOl
OlNII>-
>
ECO
00D_
NOX>-
O)
O0
E).
m_--4
O__g
X>,-
LLZ]m
EH
Hbl
<D,UO0
U]I
N
>
D\
/\
O
U]
>
t'- ._
i,5
tu
X ° • • .
"0XLL
E
H
_
00_.
om
u]f
>
[]\
0
rr >
0
0
O. ,.-4_
,t -,._ (_
0 _
X N "---
OO
|
L_(7OII>-
@Od
I
11>-
>_EE_©,
,©
nOX>-
ELD
_m_D
_il <,
X>-
i
ii
i1
i
DE>
(3 DO3 \
El@
,L
• i
c,,.I
!
00
>
(J)
11-
E --_!
M
._ i"_ . .
I!
0@
©
II>-<_
00OO)
T-i
@
COU>-
>
EO(O,
,00
00II_OX>-
LL
©m
EL",00C)_.,00I-
(70, N
0011 < ,110 UCOX_-
b
DE>I "r']
(3 DCO \
CO©
n_ >
|
E:-I
,'7 I_t-,l
0 _
I'
o_ _
I) ox_-_II
<_
i.R
11)...
>U_EEm©,.4Ix,0_
U3mO0_
X>-
0_,-'EO)(9[O
8,[',,(]0i.011UO
X>-
!1-Im
i--I
I-
fib,<,U(]0
QEII
(3
i
d
#D
f
"-,..,...
>
E3\
"--L._
A-- __
Bsq
i
!'4
h
f_o
t,.h
I--1
0@n."
EI
'-' !T_
I/)"_JiC)"_ ° °
>
[,,,Q
©110ii>-<I
b,
CDO)O0
flOII
>..
>O_EE_(0.
.(I)[OO3mnuox>-
[,,,0")[',Eml.f')_I"
,LO
[",GOt',, !III 0X>-
m
i-
G.Q<.UO')
!91
I
OE>f "r'l
0 £3GO \
r-i
0@A"
E
O]N
c_
4
Ii] ,
Y
0 _q@
01F-.-q
E -!I:
,_ x _
U.>
b_0
|
©O]II
O_T-I
0O0N
I
OlI>-
>_EE_©._0
m__gX>-
11D
_mo]©Eft) Z
.0_ t-
@ll_._gO0)X>-
'I
/\
OE>• -r'4
O D00 \
B_
4_
• Jt
r_
xg
IS
0@01
00 X
g@n_
_q
>
.Oi o'.,9.<3
XLL
>E _
D,,Q
|
©
U>-<1
If)
g)N"©
II>..
>fOE
10.
.0)
mniioX>--<I<I
D,
xt_0_GO_
,0_,-'11llgX>"
ELDm
H
F
&.El< .UO)
QE
{303
'i
i
>.H
El\
,--i
QIn/
--,,,....
,¢
O_
:>
. ,_I
y
.I
i.
f,.9
g)
b--
"7t
x_
OO(I)
Iii
I.O03I!>.-<I
Ill[,,,,,,I-I
0
0
11>-
>_EEl/)©.•-.40_
.t',,1.13030011I]0
X>-
111_m
O)t",,[0CO©03,
,0),-4 I!II]
X>-
II
I
I
I
III
i
i
J
I
Ii
!I.L I
m
i
!--,1
Jt--Ill DE
11., 1:3<0U,4
\
9
I
I
!
4
4
i1
d
d
1I
i
d
,I
r,,
>
,rl
0\
i--i
Qn" >
.4
I,o
..-2
p-.
m
|
00
U_
IN-I
>EO3O0
|
b3MH>-
m
60M
@
0
II>-
>
ED,lO.,_If).0)
_BllgX>-
b_
b30tl--I
_IIII0X>-
O3n<d0,"4
DE0I--I
>"1-I
D\
\
b.
qD
4
i\
r-I
@n_
0D
N
@--
U_
J
q_
0--.
>
>E00
|
b')
II>-<_
GOtOIF)D,,
I
0
II>-
>IQEE©(D,_h.00
_H_OX>-
LL
NmInhDE
0) ,Hib-O
flgU_X>-
OE>O .,-_
\
r
'x!
i
i
!
4
i
I
I
ii
I
i
i.iq
+.i
i
Ii
J
.I
+i
q
\
>
[DCO
|
bDOOII>-<_
U]OD_J
|
II>-
>OIEECD©,_D,0)
U_COCOMHOX>-
LL
_tmODUI
U3D-
CDO xt
,-'11 <:_llgO_
X>-
DE>C] ._
D\
r_
0QOC >
T
er_
< ]
_Ir,j
0O
l!
a:
h.
O0(I)
|
If)M!I>-<1
(I)
0IF)
I
,r-,l
11>-
>tOEE©
tO,_0,O
I.f')_M ]1DO
X>.-.<1<_
ILD
b,mlO(I)
i.j] ,--4 H0),1-,-4,..4 GO
t_l n ,
_11 ,<,-.4110 (.3_
X>'-
OE>0 .,'-1
•-' 13\
f
pl
/
r-I
0I]iIX
13
i " "
&j, Oi
"
O..
Y
0@01
O_T-I
v_
>
IOo
, Lo ,,..q
e.-'F _"_i
x _; q
I!
>E
(D
II>-
_J
D_
I
II>-
>
E_©,
U]mO] !1II
X>-<1<1
flO010)
r_
i I---I
11111lib
X>-
Ii
m
ZI--I
t-
<OJU,'_
OE>Q -H
n\
JI
gn, >
o_
N
q3 r,_
l
O] : t
_"_ Or).
_- x ."i7i
_ X[1.
OD(D
_3
II
NII
('dr-i
II
>03E
_,.
.00_fO
noX_
_C0
NUII0X_-
Dm
E
U3n.<NU_
\
OE>0
\ QE >
D,|
N
,_ "
I_J
if)
t-T
d_8
x _
>E_)O3
@
MIIY<I
O
©|
OJ
II>-
>mEE'_"©,,-,N"
U')mmgII O
×>-._<I
61©
_tN
m_trl
ed_fig×>-
h.
m
I--4
F-O_
N a
<OdtJ_
:!q
OE>
Q\
i
/
r_
D@
>
<N
. ,1_ _
n
0 _@
X
v_
b_
>E
CO
h901
>-
©D,
N
II>-
>
EO_(0,_b.
,b.UIOlOlUHO
X>-
Lc
_m010
mlD.Q]O,HON N
m_ <01II g U_
X>-
FJr
DE>O "_
D\
r-i
@n, >
_t|
NT-I
M
n<
0OtO
0101
X
"0XIi
I"J
1,.
'L
1_.
!
IJ
>E£000
MII>-
_t10_t03
|
O0
II>-
;>(hEEN
[0 l
,CO
rOl;ltgX>-<1<:1
LL
lO0_
Q,t-
w'r4 _ a
MII <or)U _] 0,-,
X>-
,i
4
,i
d
,I
I
i\
DE>
,..4 0\
r-,i
0@n/ >
GO|
'i_44
0
LL
id
! j
|
tl.
65O
>E0000
|
(7OII>-<I
NN
@
MT-I
II>-
>O_EE©©,_C)
.0
MIflu
X>-
r_
fr-I
mHUOX>-
b_Dm
EH
H0]
<MU_
\
II
OE>0
[]\
O@
rF >
,JO_
EL
0O
7
x_
'7-- _
>
_t
II)-
>_EEm©.,-_D,,.0)
or)_
X>-<_<I
ILD
O) m_)©mE
N'D,,H_.{--
e_'-I0.. J
OOU <_DO(J_X>-
OE>Q ",'_
\
).
i!,,(
iA
\
0
_t
t.,-..-
cL-": ",.b
v" ,_c.,c-
0@
g@
© I
O0 "I].-'"
>
B5Z.
>EO0O0
m
_3O0II>-
b30©
T-I
II>-
>tOEEOlO,
,0)U3MMII
X>--,q<l
tOM0
T-I •
II0X>-
Dm
F-b, OE>
D\
p.
P
,,I
b
r-I
0@
i
J
0
0@tO
°I
I
o_x .j
11.
>E
|
If)(7OI>-<I
_3m_0
|
_t
II>-
>InEEO_©,_O
_mO_H
X>-<I<I
IL
_m
_Z
O_ _Jwl--In .
ngU_X>-
OE>O "_
D\
q
r-i
00rr
q ,
> IL
B_4
00
03
!
G)II
tOmII>-<:1
O0Q_J
B
U3
II>-
>01EE_tO,_0),00
L_O
X>-
O0
(11.
IIOX>-
m
V=4
i.-(.D
t"l •
U,.-.I
OE>
D\
•,L
i
r-i
0@
:>
_ _ 8S5
4
2,0
Ii
>E00O3
II
If)
II>-<_
O3If)
|
b3
II>-
>fOEEU3©.
LOm031I 0X>-<I<I
©LOb,
I--I
N.
,T-I
IIX>-
IL3m
E
H0
<©O_
OEOr-i
>.rl
[]\
r-i
g
n, >
E) I
i
I
I13'Y__'Z_,__
r,%
7Nt_
k.)
0003
7--- c_
0
_5
X
>EO3O3
tO
II>-
5J_J
O)
IO
H>-
>U)EEO(0.
.03U30_
_gX>-
D,bIC0O)
D,b_
(Olne_-4
_nIf
x_-
IT
m _
V-4
N0_,<lOL)_
OE>0
D\
gQrY >
I
I
_t
rc_<Z)
a..J-"
en
m
_ _-" t
0
i •i
© to _, t_ _
t_
_ X
O)m
II
tO0111>..<1
(13
[13m
II
(13
!I>..
©,
,(3)tommllII0
X>-<1<1
(0U_M
tO
N,
_OX)-
EL
m
H
©rl •
.<:f..OU,-4
DE>0 "_
D\
N
00
>
O0
tO
%'I
J
<
@
j,
! r
i
x j
X _-
>E
O0
I
m
>-
I
(DT-I
II>-
>_EE(_(0,
.0)
noX>-
LL
_m_Q
0(0 O_
[on <lo_gu_x>-
I
k
OE>
D\
i
0Qn" >
B_
m_
N
t
<
Co
00
I
|
>ECOO0
MII>-
©0
|
D_
II>-
>InEEGOCO.
.CO_mm__gX>-
EL
D,m
D__D, Hm.H
i£)[ <[",tlBU_X>--
II
ql
1
t
' I41• i
q I
1
It4
I
q
II
II
qI
", I
,i
•I !
'i
4d
4t
ic
\
OE>0
\
A--I
00n, >
|
I
I
• J
N
i11. ,_ J
N
00
+I
I
I
.
6_b_
_C
>E0000
U3O0II>-<:I
CO©©
D,
II>-
>fOEEm(13,
,O_U3O0mniioX>-
©
D,©000.
m_--I
LOgUDX>-
b_Dm
H
\
<D-U_
I
\
[3O
E >"H
E]\
lI
,-4
g@FF >
O_
©
o
•d
N
I
1
0 "_O6O
r
IF) Loi
×xb_
>E
|
_303H>-
©
_J
I
D,
II>-
>_EECO©.
.COU3mmHIgX>-
U3
m.©D,=_---I
U3_IgX>-
LL-3m
H
0_.
U_
OE0
>.rl
0\
,--I
0@fY >
U3
N
p,.
|
,X
J
0Q
d_
I
T__0(_
LL
>EO]O_
I
O0II>-<I
O]_9O]
|
O0I-4
II>-
>_EED©.
.CO
mll
X>-
LL_D
_mO]
00__.F-O)D,
X>-
DE>
D\
O@FY > h_
This page has been intentionally left blank
>EO)
I
r4
!IY
D_CO
II>-
>O)ED,
O)O.0)
O,
_J 11
X>- I<1<I
LLD
Nm
N-,t-Oa) 0
X>-
I iI
J
OE>
(I) D\
r--I
geln," >
o_
r4_
E_
_ --&."5
I
_' _:_0 o4
m W--!),
!
I
t'- _ i 1
>E
f
_J
II>-
_tmD,
|
rdO0II>-
>tOE©
@ •
O0O_
UOX>-<I<I
©0100
lO,
© IInOX>-
3m
H
F-0
Q.,
Um
I
0 >a -rl
N O\
I
D,
_J
O) "i
<
iI
01
©
N--', /i
_ ..i. 7 .
EI@rr > U_
AE-26002/1C2 Oct 97
TEST DATA SI:I'EET 7 (Sheet 1 Of 4)Scan Motion and Jitter Test (AI-1) (Paragraph 3.4.4.5)
Step No.7
9
10
11
12
13
14
15
DescriptionN
Scene 1-23.33 ostep
Scene 2-33.330 step
Scene 3-43.330 step
Scene 4-53.330 step
Scene 5-63.33 ° step
Scene 6-73.33 0step
Scene 7-83.330 step
Scene 8-93.33° step
16
Shop Order No.
RequirementStepping Slewing<8 sec period per Figure_"<35 msec rise time per Figure 7
< ±5% jitter per Figure 7< 3% overshoot for 10 msec
<35 msec rise time per Figure 7
< ±5% jitter per Figure 7< 3% overshoot for 10 msec
<35 msec rise time per Figure 7
z?8 G! ,
_,_,._'\" [ Test Result
< +5% jitter per Figure 7< 3% overshoot for 10 msec
35 r_=¢.-'-
/
Pass/Fail
P
P
P
_. 3S ,_,,5cC
< ±5% jitter per Figure 7 L, z 5 % (_< 3% overshoot for 10 msec ,_ 3 _,
<35 msec rise time per Figure 7 _ __S(_5c c [_
P/_35 na 5_.¢-
,d 35- _ ¢'¢-
_.-r_ ff "7,,_
<35 msec rise time per Figure 7
< ±5% jitter per Figure 7< 3% overshoot for 10 msec
<35 msec rise time per Figure 7
< ±5% jitter per Figure 7< 3% overshoot for 10 msec
<35 msec rise time per Figure 7
< ±5% jitter per Figure 7< 3% overshoot for 10 msec<35 msec rise time per Figure 7
< ±5% jitter per Figure 7< 3% overshoot for 10 msec
P
?
(>
P
P
Pass = PFail = F
A-10
TESTDATA SHEET 7 (Sheet 2 Of 4)Scan Motion and Jitter Test (A1-I)
AE-26002fIC2 Oct 97
Step No.17
18
19
2O
21
22
23
24
DescriptionScene 9-103.33* step
Scene 10-113.33 ° step
Scene 11-123.330 step
Scene 12-133.33 ° step
Requirement Test Result<35 msec dse time per Figure 7
< ±5% jitter per Figure 7< 3% overshoot for 10 msec
<35 msec rise time per Figure 7
< ±5% jitter per Figure 7< 3% overshoot for 10 msec
<35 msec rise time per Figure 7
< ±5% jitter per Figure 7< 3% overshoot for 10 msec
<35 msec rise time per Figure 7
< _'5% jitter per Figure 7< 3% overshoot for 10 msec
<:. 3S m 5cc
<: zS- %
_. 55 mS_.,--
< 37o
_. _5 mscc.
Pass/Fail
PP
P??P
Scene 13-143.33 ° step
Scene 14-153.330 step
Scene 15-163.33 ° step
Scene 16-173.33 ° step
<35 msec rise time per Figure 7
< ±5% jitter per Figure 7< 3% overshoot for 10 msec
<35 msec rise time per Figure 7
< ±5% jitter per Figure 7< 3% overshoot for 10 msec
<35 msec rise time per Figure 7
< ±5% jitter per Figure 7< 3% overshoot for 10 msec
<. 35 ]_tSe._-
<Z5 "7o
3 E ,'n Sc.c..
L. :t...c %
_5 mScc.
<35 msec rise time per Figure 7
< ±5% jitter per Figure 7 _ _ E< 3% overshoot for 10 msec ,_-- -_
_. 3,7o
%%
?PPP?PP?
Pass = PFail = F
A-II
G,'7
AE-26002/lC2 Oct 97
TEST DATA SHEET 7 (Sheet 3 Of 4)Scan Motion and litter Test (AI-1)
Test Result Pass/FailStep No.25
26
27
28
29
3O
31
32
DescriptionScene 17-18
3.33 ostep
Scene 18-19
3.33° step
Scene 19-203.330 step
Scene 20-213.33° step
Scene 21-22'3.33ostep
Scene 22-233.33° step
Scene 23-243.33o step
Scene 24-253.33* step
Requirement<35 msec rise time per Figure 7
< -*-5%jitter per Figure 7< 3% overshoot for 10 msec
<35 msec rise time per Figure 7
< ±5% jitter per Figure 7< 3% overshoot for 10 msec
<35 msec rise time per Figure 7
< ±5% jitter per Figure 7< 3% overshoot for 10 msec<35 msec rise time per Figure 7
< ±5% jitter per Figure 7< 3% overshoot for 10 msec
<35 msec rise time per Figure 7
< ±5% jitter per Figure 7_< 3% overshoot for 10 msec
;<35 msec rise time per Figure 7
< ±5% jitter per Figure 7< 3% overshoot for 10 msec
<35 msec rise time per Figure 7
< ±5% jitter per Figure 7< 3% overshoot for 10 msec<35 msec rise time per Figure 7
< +5% jitter per Figure 7< 3% overshoot for 10 msec
Z__ _.5 nl st_
3,5" ,mSc-.c
L..35 _ f:.z.
_--3,5 _ 5ec:
3.5"m S r..c.
,_ x.ff %
< 2L5"-_ 5c-c..
_- 3,5-/i _'c-c...
3
P
P
P
P
P
P
P
P
P
P
P
P
Pass = PFail = F
A-12
TESTDATASI-IEET 7 (Sheet 4 Of 4)Scan Motion and Jitter Test (AI-I)
AE-26002/1C2 Oct 97
Step No.33
34
35
36
37
38
DescriptionScene 25-26
3.33 ° step
Scene 26-273.33 ° step
Scene 27-283.33 ° step
Requirement<35 msec rise time per Figure 7
< ±5% jitter per 15igure7< 3% overshoot for 10 msec<35 msec rise time per Figure 7
< ±5% jitter per Figure 7< 3% overshoot for 10 msec
<35 msec rise time per Figure 7
Test Result
__ 3,5-zn a-e-c
Pass/Fail
P
to
P
/9
P
< ±5% jitter per Figure 7 __. -__- %< 3% overshoot for 10 msec _ 3""7_
Scene 28-29 =<35 msec rise time per Figure 73.33 ° step L_ _,_ 5_._ P
/
3"2°
Scene 29-303.33 ° step
< ±5% jitter per Figure 7< 3% overshoot for 10 msec
Scene 30Cold Cal
35.0 ° slew
i<35 msec rise time per Figure 7
< ±5% jitter per Figure 7< 3% overshoot for 10 msec<0.21 sec slew time per Figure 10
< ±0.11_i ° jitter per Figure 11
39 Cold Cal - <0.40 see slew time per Figure 12 _L_ O__ o E_ cWarm Cal
96.67°slew <±0.165°jitterperFigure13 _. ± _1[=,5"_
P
P
P
Pass = PFail = F
Unit: , ./.._Y_ ff20 8--,/ - / "/"
D=o: / -Z 8 -
Test Engiaeer:_'-_ --7
Quality Assurance: It_ a '911
Customer Representative:, @ m I
A-13
AE-26002J1C2Oct97
TESTDATAStIEET8 (Sheet1 Of 4)ScanMotionandJitterTest(AI-2)(Paragraph3.4.4.5)
Step No.44
10
11
12
13
14
15
Description
Scene 1-23.33° step
Scene 2-33.33 ° step
Scene 3-43.33 ° step
Scene 4-53.330 step
Scene 5-63.33 ° step
Scene 6-73.330 step
Scene 7-83.330 step
Scene 8-93.330 step
16
Shop Order No.
Requirement _=
Stepping Slewing /_<8 sec period per Figure
Q."7, T_L,_,_'_ est Result
< _.05...,-
<35 msec rise time per Figure 7
< ±5% jitter per Figure 7< 3% overshoot for 10 msec<35 msec rise time per Figure 7
,_±5%'jitter per Figure 7< 3% overshoot for 10 msec<35 msec rise time per Figure 7
< ±5% jitter per Figure 7< 3% overshoot for 10 msec<35 msec rise time per Figure 7
< *-5% jitter per Figure 7< 3% overshoot for 10 msec
<35 msec rise time per Figure 7
< ±5% jitter per Figure 7< 3% overshoot for 10 msec
<35 msec rise time per Figure 7
< ±5% jitter per Figure 7< 3% overshoot for 10 msec<35 msec rise time per Figure 7
< ±5% jitter per Figure 7< 3% overshoot for 10 msec<35 msec rise time per Figure 7
< ±5% jitter p'er Figure 7< 3% overshoot for 10 msec
,z_ _% .....
3.5 ,H 5e..c..-
L_ 3S_Ye-<...
_. 3,5- m S_,
3"70
&±s%L. 3 _7c
E-L 3 "7o
Pass/Fail
P?
P
Pn
PPP
?P
?22
Pass = PFail = F
A-14
TEST DATA SHEET 8 (Sheet 2 Of 4)Scan Motion and JitterTest (A1-2)
AE-26002/1C2 Oct 97
Step No. Description Requirement Test Result Pass/Fail17
18
19
2O
21
22
23
24
Scene 9-103.33 ostep
Scene 10-113.330 step
Scene 11-123.33 ostep
Scene 12-133.330 step
Scene 13-143.330 step
Scene 14-153.33 o step
Scene 15-163.33 ° step
Scene 16-173.33 ° step
<35 msec rise time per Figure 7
< *-5% jitter per Figure 7< 3% overshoot for 10 msec
<35 msec rise time per Figure 7
< *-5% jitter per Figure 7< 3% overshoot for 10 msec
<35 msec rise time per Figure 7
< *-5% jitter per Figure 7< 3% overshoot for 10 msec
<35 msec rise time per Figure 7
< *-5% jitter per Figure 7< 3% overshoot for 10 msec
<35 msec rise time per Figure 7
< *-5% jitter per Figure 7< 3% overshoot for 10 msec
<35 msec rise time per Figure
< ±5% jitter per Figure 7< 3% overshoot for 10 msec
<35 msec rise time per Figure 7
< *-5% jitter per Figure 7< 3% overshoot for 10 msec
<35 msec rise time per Figure 7
< ±5% jitter per Figure 7< 3% overshoot for 10 msec
,_ k" _ °7o '
<.. _5_Sc c.
.T_L,c"An._-e.c.
PPP
?
P
PPPP
Pass = PFail = F
A-15
AE-26002/1C2 Oct 97
TEST DATA SI-IEET 8 (Sheet 3 Of 4)Scan Motion and Jitter Test (A1-2)
Step No.25
26
27
28
29
3O
31
32
DescriptionScene 17-183.330 step
Scene 18-19
3.33 ° step
Scene 19-203.330 step
Scene 20-21
3.330 step
Scene 21-223.33 ° step
Scene PP-233.33 ° step
Scene 23-24
3.33 ° step
Scene 24-253.33 ° step
Requirement Test Result Pass/Fail<35 msec rise time per Figure 7
< ±4% jitter per Figure 7< 3% overshoot for 10 msec
<35 msec rise time per Figure 7
< ±5% jitter per Figure 7< 3% overshoot for 10 msec
<35 msec rise time per Figure 7
< ±5% jitter per Figure 7< 3% overshoot for 10 msec
<35 msec risetime per Figure 7
/-- 3 '=7o
S _o
L 3S wn_-c c.
t-, -'3' =7c,
< ±5% jitter per Figure 7 f_. E 5- _¢_< 3% overshoot for 10 msec<35 msec rise time per Figure 7
< ±5% jitter per Figure 7< 3% overshoot for 10 msec
<35 msec rise time per Figure 7
< ±5% jitter per Figure 7< 3% overshoot for 10 msec<35 msec rise time per Figure 7
< __.5%jitter per Figure 7< 3% overshoot for 10 msec<35 msec rise time per Figure 7
< ±5% jitter per Figure 7< 3% overshoot for 10 msec
_-. T 5 "7,-A. z 70
PP
P
f
fF
r
F
:37c
3Sml _'e.c. ?
P
Pass = PFail = F
A-16
TEST DATA SHEET 8 (Sheet4 Of 4)
ScanMotionandJitterTest(AI-2)
AE-2600211C
2 Oct97
Step No.33
34
35
36
37
38
39
Descriptionscene 25-26
3.33 ° step
' scene 26-27
3.33 ° step
scene 27-28
3.33 ° step
Scene 28-293.33°step
Scene 29-30
3.33°step
Scene 30Cold Cal
35.0 ° slew
ColdCal-Warm Cal
96.67 ° slew
Requirementi<35 msec rise time per Figure 7
I< ±5% jitter per Figure 7< 3% overshoot for 10 msec
<35 msec rise time per Figure 7
< ±5% jitter per Figure 7< 3% overshoot for 10 msec<35 msec rise time per Figure
< ±5% jitter per Figure 7< 3% overshoot for 10 msec<35 msec rise time per IZigure 7
< ±5% jitter per Figure 7< 3% overshoot for 10 msec<35 msec rise time per Figure 7
< .-5% jitter per Figure 7< 3% overshoot for 10 msec<0.21 sec slew time per Figure 10
0 *o •< _0.165 ptter per Figure 11
<0.40 sec slew time per Figure 12
< ±0.165 ° jitter per Figure 13
Test Result
55 _se.c
,4...'_ S °1o
z. 35" _ 5e-c.
/-.3.5-_ sex..
O,, 2.(0 5e.c.
4_o./6_ 7c
0."/0 Sc-c.
< _ 0./_a- 2c
Pass/Fail
P
Pf
PP
P
P
Pass = PFail = F
u_,: 19:-6 cpO/9-,: -
s_,i_ No.: 20Z
?7"/
_
Customer Representative: _p_ t
A-17
OE0_,
Ub,
OE>| ";-I
0 D D
I
w
(n
.j
0 _
b--
]
T
_r
11 X "_
Xl tl_
C_
AE-26002/1C2 Oct 97
TEST DATA SHEET 9
28V Bus Peak Current and Rise Time Test (Paragraph 3.4.4.6)
/_ ,, 4.0
Test Setup Verifiexl:_ Shop Order No. 2- ? /
C_
Step No. Requirement ' ' Test Result Pass/Fail
4 < 1 A peak any place in the scan _'_f 0 /_ _ /3
> 35 psec rise time, 3.33* step5
6 > 35 psec rise time, start of WC slew
6 > 35 psec rise time, end of WC slew
./,..5"6,2 ,,__'<..c
/, E6 Z t'n 5e. o
P
Ptl,
Pass = PFail = F
_s.i,: /5'm-_;oo _ - r - ( T"
Sena_No.: 2, O
Date:
Quality Assurance:
A-18
rn"O
N
tOflOtdQtO fit(D,,0") C3
flOl WO}ll fFllOL
X>-
Q
0
I
i
i
!
tOo
4-
i
i
0
0
EO)
@
O)O)O)
i!
t!
m7J
N7-©©
O,,0_
001
nDX>-
' A i_v
N-F
t'---' 0I
t ,
iI
Q|
0
I
@orYco
>-_Xl7JllxnLL>-
GOW.
LLO_
iI
IlIi!
O
OJ_O_
"I
II
!
i
i
i
I
I E! m
II
!L
|
[11O
N _',__
---0 ___
I X \Ix. _-
I
i
i
I
i
i-
!
"[] _
xo_OO
GOrY.,iiiU]_ 8S[ i._....
d_ ooOl W._II _0
X>-8]I]
T
--w
0. X
0X
I '_
_-I >,
_o
lav
I
@
O O_r @O_ n
Oq-
_O_" ",,I
,.
iO)
|
°1• i
I
I XU.
!
!
COI I
_0) OO 0 >-,-_00OI W. • XIW,
11IZO 0 "OIIIZO110 LL_ t3 O] X]3LLO]
X>- I ]3 1 LL>-.L
I 1I
,°
&!
\
@@O
£fl_
Ds
o
O}I
O}0"}
_____] 0"}
{Xl._)-
[:: I-,..
0"} ""
O]@0
',.9_0
½
I ×LL
\
TEST DATA SHEET I0
Gain/Phase Margin (AI-1) (Paragraph 3.4.4.8)
Test Setup Verified: ?_,_
_rTemperature: ,7/. 5 °C
Shop OrderNo. _ _ _ 6"'6/
Dq
AE-26002/1C
2 Oct 97
Requirement
9.2 dB minimum
25 degrees minimum
Test Result
_,, -'_.ss'_,_ a_2 - £,5,/7 ct6
\ \ ',,,,\ \ \ \'%,,,,,. \ \ ",,,,,,,,\.\
1 7/. Z b_.,72 ?Q. ?.3 _/_
- I
\4\\\ \\k\\\_ \\ \ \\, ,'\'\
Pass/Fail
f,#
#
P (tg/LP ct_sro_L
':" c_9-a'ss=P _1
Fail = F
_ni,: /35-6 oo z%/- (7
serial No.: ZO
D=o: /-zo- ?S
Test Engineer:_
Quality Assurande:_ _ _
Customer Representative: III t
A-19
AE-26002/1C2 Oct 97
D_
TEST DATA SHEET 11
Gain/Phase Margin (A1-2) (Para_aph 3.4.4.8)
_FTemperature: 7_,.3 "C
'Requirement
9.2 dB minimum
25 degrees minimum
1
23
i\5,i2
3
\s\
Test Result
-7, e47z cC8.\\\\\ \-'\ " "\ "X " "\,, \
Pass/Fail
Pp
P
•' 2;7'
Pass = PFail = F
>t_ _qLOPEP,.
6_LfTOI_E_.E_EsTIt_
. ,I- e./-__(U
u_,: /35-( oo _-- /
so_ No.: 2 07__..
_,,o: /-zz-?_
.... I J ' _)# _.* __uaJztT Assurancc:._l___.___l__
Customer Representative: I1_ I _11
A-20
_d>0
q_QI"I ....
E
0|
\ _0 EN O)13 L:> I
J
J
, I
>0
>,<,m
: i
0@
0O)I
_Z
I
o_aJ _.
._I-_-',_I
-_
X.
x "@_LL
TEST DATA SHEET 12
C_erafional Gain Margin (A1-l) (Paragraph 3.4.4.9)i-) r/till __
Test Setup Verified: __J e ShopOrderNo.. =_'_(
Temperature:" r vl C
E5
AE-26002/1C2 Oct 97
Step No.
11
12
16
RequirementR58 Resistance (kohms)
Test Pot Resistance (kohms)
Oscillation Frequency (Hz)
Gain Margin, 8 dB minimum
Test ResuR
1 36. 7"/ /_ "£'="
3 36,03 _ .a.._1 /7f, c'7 /'tt"_
2 /7/.o? _ ,,y
Pass/Fail
P
P
?
Pass = PFail = F
Unit:
Serial No.:
i3Sc_oo _-t- l T
20Z-
//ATest Engineer: /_ i/_/'_ Z
z j=.oDate: i--z9- _ g
a •
A-21
AE-26002/1C2Oct97
TESTDATA SHEET 13
Operational Gain Margin (A1-2) (Para_aph 3.4.4.9)
Test Setup Verified: _l,.Jl('_h/_A]_,'_//_ Shop Order No. Z_'_,ff(_/
Temperature: _'e F*C
_q
Step No.
11
12
16
RequirementR58 Resistance (kohms)
Test Pot Resistance (kohms)
Oscillation Frequency (Hz)
Gain Margin, 8 dB minimum
"I /'_ nil,, #
2 _,_
1231
12:3
Test Result
4' Ac't/-;'zs_q_ 37,b7_v,)3'4.37_ K/-_---
; _'/. z.s-/_/ ,_o,o _ g-.3_, I'qOI _(88. b(,,G7
Pass/FaU
P,i
P
P
Pass = PFail = F
Unit:
Serial No.:
I35"6 O0 _- _ -- I T
ZOZ
Test Engineer: _A__//_
,, 7 ff/Qu ity suranc¢: |,_ _5.'_-_'S'_ _
Da,o:l-z?-?8
A-22
53-55NFSD 89-0 (June 30, 1989) FORMS
N/LRANational Aeronautics and
Space AdmlnisVation
Report Documentation Page
1. Report No, 2. Government Accession No.
4. Title and Subtitle
integrated Advanced Microwave Sounding Unit-A
(AMSU-A), Performance Verification Report
7. Author(s)
A. Nieto
9. Performing Organization Name and Address
Aerojet1100 W. HollyvaleAzusa, CA 91702
12. Sponsoring Agency Name and Address
NASA
Goddard Space Flight Center
Greenbelt, Maryland 20771
3. Recipient's Catalog No.
5. Report Date
July 1998
6 Performing Organization Code
18. Performing Organization Report No.
11183
10. Work Unit No.
11. Contract or Grant No.
NAS 5-32314
13. Type of Report and Period Covered
Final
14. Sponsonng Agency Code
___
15. Supplementary Notes
16. ABSTRACT (Maximum 200
words )
This is the Performance Verification Report, EOS AMSU-A1 Antenna Drive Subassy, PIN
1356008-1, SIN 202 for the Integrated Advanced Microwave Sounding Unit-A (AMSU-A).
17. Key Words (Suggested by Author(s))
EOS
Microwave System
18. Distribution Statement
Unclassified- Unlimited
19, Security Classif, (of this report)
Unclassified
20. Security Classif. (of this page)
Unclassified
21. No. of pages 22. Pdce
NASA FORM 1626 OCT 86
NASA FAR SUPPLEMENT 18-53.303-1626
53-56 FORMS (June 30, 1989) NFSD 89-0
PREPARATION OF THE REPORT DOCUMENTATION PAGE
The last page of-a report facing the third cover is the Report Documentation Page, RDP. Information presented on this page isused in announcing and ca_Joging reports as well as prepadn 9 the cover ano title page. Thus, it is important that the inzormauonbe correct. Instruaions 1or Tiling tn eacn OIOCKOTme Torm are as rollOWS:
Block 1. Report No. NASA report series number, if
preassigned.
Block 2. Government Accession No. Leave blank.
Block 3. Recipient's Catalo 9 No.. Reserved for use by each
report recipient.
Block 4. "13tle and Subtitle. Typed in caps and lower case with
dash or period separating subtitle from title.
Block 5. Report Date. Approximate month and year the report
will be published.
Block 6. Performing Organization Code. Leave blank.
Block 7. Authors. Provide full names exactly as they are to
appear on the title page. If applicable, the word editor should
follow a name.
Block 8. Performing O_, anization Re_ No. NASA installation
report control number and, if desired, the non-NASA performing
organization report control number.
Block 9. Performing Organization Name and Address. Provide
affiliation (NASA program office, NASA installation, or contractor
name) of authors.
Block 10. Work Unit No. Provide Research and Technology
Objectives and Plants (RTOP) number.
Block 11. Contract or Grant No. Provide when applicable.
Block 12. Sponsodn,q A,qenc-_ Name and Address. National
Aeronautics and Space Administration, Washington, D.C. 20546-
0001. If contractor report, add NASA installation or HQ program
office.
Block 13. Type of Report and Period Covered. NASA formal
report series; for Contractor Report also list type (interim, final)
and period covered when applicable.
Block 14. Sponsorin¢l A.qency Code. Leave blank.
Block 15. Supplementary Notes• Information not included
elsewhere: affiliation of authors if additional space is required
for Block 9, notice of work sponsored by another agency, monitor
of contract, information about supplements (file, data tapes, etc.)
meeting site and date for presented papers, journal to which an
article has been submitted, note of a report made from a thesis,
appendix by author other than shown in Block 7.
Block 16. Abstract. The abstract should be informative rather
than descriptive and should state the objectives of the
investigation, the methods employed (e.g., simulation,
experiment, or remote sensing), the results obtained, and the
conclusions reached.
Block 17. Key Words. Identifying words or phrases to be used
in cataloging the report.
Block 18. Distribution Statement. Indicate whether report is
available to public or not. If not to be controlled, use
"Unclassified-Unlimited." If controlled availability is required,
list the category approved on the Document Availability
Authorization Form (see NHB 2200.2, Form FF427). Also
specify subject category (see "Table of Contents" in a current
issue of STAR ) in which report is to be distdbuted.
Block 19. Security. Classification (of the report}. Sehr-
explanatory.
Block 20. Security_ Classification (of this page). Self-
explanatory.
Block 21. No. of Pages. Count front matter pages beginning with
iii, text pages including internal blank pages, and the RDP, but
not the title page or the back of the title page.
Block 22. Price Code. If Block 18 shows =Unclassified-
Unlimited," provide the NTIS pdce code (see "NTIS Pdce
Schedules" in a current issue of STAR) and at the bottom of the
form add either "For sale by the National Technical Infon'nation
Service, Springfield, VA 22161-2171" or "For sale by the
Supedntendent of Documents, U.S. Government Pdnting Office,
Washington, D.C. 20402-O001 ," whichever is appropriate.
PART 53 - FORMS 53.301-298
Form
ApprovedREPORT DOCUMENTATION PAGE OMBNo.
0704-0188
Public reporting burden f_hts collection ofinformaUo_ is estimatedto average 1 hour per res_se,induding the tJm_or re.v__ .g inst_uct_..ssearching ex_._ring data s(_urcegathering andmaintaining It_at_ needed_.nd completing andrevtewmg Ihe¢.ollecttoninformation. Send comments rega.rd=.t_.th=s_roe_ estate or any omer as_ Otm=scollec'donof infont_tJon, including suggestiofar reduang th_si_Jrdento Washington Headquarters _ervce_Directorate tor !ntom_ahon UIIIIIIIIl_ratJonsno_ewts. ]zl:> JenersoDavis Highway, Suite 1204. Arlington. VA 22202-4302. and to the Office of Management and Budget, Paperwork Reduc_on Prqlect (07040188). Washtngton, DC 20503.
1. AGENCY USE ONLY ( Leave
blank )
2. REPORT DATE
4. TITLE AND SUBTITLE
Integrated Advanced Microwave Sounding Unit-A
(AMSU-A), Performance Verification Report
6. AUTHOR(S)A. Nieto
7. PERFORMING ORGANIZATION NAME(S) AND ADDRESS(ES)
Aerojet
1100 W. Hollyvale
Azusa, CA 91702
9. SPONSORING/MONITORING AGENCY NAME(S) AND ADDRESS(ES)
NASA
Goddard Space Flight Center
Greenbelt, Maryland 20771
3. REPORT TYPE AND DATES COVERED
5. FUNDING NUMBERS
NAS 5-32314
8. PERFORMINGORGANIZATIONREPORTNUMBER
11183
July 1998
10. SPONSORING/MONITORING
AGENCY REPORT NUMBER
11. SUPPLEMENTARY NOTES
12a, DISTRIBUTION/AVAILABILITY STATEMENT 12b. DISTRIBUTION CODE
13. ABSTRACT (Maximum 200
words )
This is the Performance Verification Report, EOS AMSU-A1 Antenna Assy, PIN 1356008-1,
SIN 202 for the Integrated Advanced Microwave Sounding Unit-A (AMSU-A).
14. SUBJECT TERMS
EOS
Microwave System
17. SECURITY CLASSIFICATIONOF REPORT
Unclassified
18, SECURITY CLASSIFICATIONOF THIS PAGE
Unclassified
NSN 7540-01-280-5500
19. SECURITY CLASSIFICATIONOF ABSTRACT
Unclassified
15. NUMBER OFPAGES
16. PRICE CODE
20. LIMITATION OFABSTRACT
SAR
Standa_ Form298 (Rev. 2-89)P_ byANSI Std 239-182g6-1GZ
53-301-298 FEDERAL ACQUISITION REGULATION (FAR)
GENERAL INSTRUCTIONS FOR COMPLETING SF 298The Report Documentation Page (RDP) s used in announcing and cataloging reports. It is important that this information becons stent w th the rest of the repo..rt, particulany the .cover an(_ title page. instructions _or filing in each block of the formfo low. It is important to stay within the rues [o meet opt cal scanning requirements.
Block 1. Agency Use Only(Leave blank)
Block 2. Report Date Full publication date including day,month, an_ear, if available (e.g., 1 Jan 88). Must cite at least
the year.
Block 3. Type of Report and Dates Covered. Statewhether
report is interim, final, etc. If applicable,enterinclusive report
dates (e.g., 10 Jun 87 - 30 Jun 88).
Block 4. Title and Subtitle A title is takenfrom the part of the
report that provides the most meaningful and complete
information. When a report it_repared in more than one volume
report the primary title, add volume number_nd include subtitle
for the specific volume. On classified documentsenter the titleclassification in parentheses.
Block 5. Funding Numbers To include contract and grant
numbers; may include program element number(s), project
number(s), tasksnumber(s), andwork unit number(s). Use the
following labels:
C Contract PR Project
G Grant TA Task
PE Program WU Work UnitElement Accession No.
Block 6. A_hor(s_ Name(s) of person(s) responsible for
writing the report, performingthe research, or credited with the
content of thereport. If editoror compiler, this shouldfollow the
name(s).
Block 7. Perforrnin,q O_, anization Name(s) and Address(es).
Serf-explanatory.
Block 8. Performin,q Or qanizationReport Number. Enterthe
unique alphanumeric report number(s) assigned by the
organization performing the report.
Block 9. Sponsoring/Monitoring Agency Name(s) and
Address(es) Self-explanatory.
Block 10. Sponsorin.q/Monitorin.qAgencyReports Number. (ff
known).
Block 11. Supplementar_otes_ Enter informatiomot included
elsewhere such as: Prepared in cooperation with ...; Trans. of
...; To be published in ... When a report is revised, include a
statementwhether the new report supersedes or supplements
the older report.
Block 12.a Distribution/Availability StatementDenotes public
availability or limitations. Cite any availability to the public.
Enter additional limitations or special markings in all capitals
(e.g., NOFORN, REL, ITAR).
DOD - See DoDD 5230.24Distribution Statement on
Technical Documents
DOE - See authorities.
NASA - See Handbook NHB 2200.2.
NTIS Leave blank.
Block 12.b Distribution Code.
DOD - Leave blank.
DOE Enter DOE distribution categories from the
standard Distribution for Unclassified
Scientific and Technical Reports.
NASA - Leave blank.
NTIS - Leave blank.
Block 13. Abstract. Include a brief Maximum 200 wnrd_
factual summary of the most significant information contained in
the report.
Block 14. Subject Terms. Keywords or phases identifying major
subjects in the report.
Block 15. Number of Pages.Enter the total number of pages.
Block 16. Price Code. Enter appropriate price code_TIS
only),
Block 17- 19.Security Classifications. Serf-explanatory. Enter
U.S. Security Classification in accordance with U.S. Security
Regulations (i.e., UNCLASSIFIED). If form contains classified
information, stamp classification on the top and bottom of the
page.
Block 20. Limitation of Abstract.This block must be completed
to assign a limitation to the abstract. Enter either UL (unlimited
or SAR (same as report). An entry in this block is necessary if
the abstract is to be limited. If blank, the abstract is assumed tc
be unlimited.
Standard Form 298 Back(Rev. 2-89)
53-86
DOCUMENT APPROVAL SHEET
__ II_J,,ql =,_ ___u 'wm,__-- - •
TITLE
Performance Verification Report
Subassembly and Complete Instrument AssemblyEOS AMSU-A1 Antenna Drive Subassembly, P/N 1356008-1, S/N 202
DOCUMENT NO.
Report 11183
July 1998
INPUT FROM: DATE
A. NietoCDRL:
2O8
CHECKED BY: DATE
SPECIFICATION ENGINEER:
JOB NUMBER:
DATE
DATE
APPROVED SIGNATURES
Engineering (T. Higgins) (--_.,
Product Team Leader (A. Nieto)
Systems Engineer (R. Platt) _'P.
Design Assurance (E. Lorenz)
Quality Assurance (R. Taylor)
Technical Director/PMO (R. Hauerwaas) _/)/_\\
Management (J. Cavanaugh)/_Configuration
,_j//,
By my signature, I certify the above document has been reviewed by me and concurs with the technical
requirements related to my area of responsibility.
DEPT. NO.
7831
8341
8311
8331
7831
4001
8361
DATE
RELEASE (Data Center) FINAL