2nd BrightnESS Best Practice Workshop: Installation aspects of large-scale In-Kind projects
Installation CoordinationTarget Division
Tobias Lexholm
Installation Coordinator, Target Division
www.europeanspallationsource.seJune 2017
Overview
• Overview of Target Building • Target division Critical Path• Target division Site Organization• Challenges during installation
2
Targets first installations
8
Maintenance Cell Process Cell
Active Cells Conduits - March 2017
Maintenance Cell Floor
Storage Pits
Process Cell Floor
Liner Beams
Active Cells Liner BeamsMay 2017
Building sequence driven by Target – Priorities for access to D02
9
Active Cells
Utility Monolith A2T
TechnicalArea – Zone 2
TechnicalArea – Zone 1
TechnicalArea – Zone 3
Admin & Transport Area Area
12
3a
3b
4a
4b
4c
5
1 5
Proposed Sequenceof Construction
Parallel Access / BAS-U
Parallel Contractor refers to an external contractor, employed by ESS Division other than CF that will carry out works on the site, before SEC’s completion of works and final handover to ESS. In many instances the completion of the Parallel Contractors works will be required prior to SEC being in a position to complete their own scope of works. The Parallel Contractor’s works do not form part of SEC’s scope of works nor are SEC responsible for managing or delivering these works, unless a scope transfer is performed from the ESS Division to SEC/CF. Parallel works relates to the period of time that the Parallel Contractor will be performing works, concurrently to SEC.
BAS-U: The building work environment coordinator for construction (Skanska)
10
Impact on Target Installations Early Access Dates
11
New Key Milestone dates proposed by Conv. Facilities:
Early Access Active Cell (inside) Mar -18Early Access Triang. Rooms Utility Oct -18Early Access HVAC Room A2T Mar -19Early Access Utility Sep -18Early Access High Bay Crane Apr -19
Active Cell (inside) - Mar -18
Triangular Rooms Utility - Oct -18
HVAC Room A2TMar -19
Utility - Sep -18
High Bay Crane -Apr -19
Impact on Target InstallationsMobile Crane solution
12
Lifting Zone for MonolithInstallation Sep 2018 – Mar
2019 Minimum Period
1
2
3
45
1 5
General Sequence ofBuilding Construction
E-Buildings
D03, D04
D02
D01 Phase 1, D06, D07D01 Phase 2, D08
Opening in Roof& Wall
Critical Path WP 3, Moderator & ReflectorCryo installation2 Days Float
14
Linked to WP 4 MonolithVesselInstallation
4 days float
2 days float
Critical Path WP 4, Monolith SystemsInserts & Light shutters (Bunker Area)78 Days Float ?????
17
78 days float
OrganizationOver all site organization
18
ESS Installation Coordinator
Deputy ESS Installation Coordinator
ESS QCInstallation Inspection
Receival inspectionNDT (X-ray, PT, UT etc.)
Accredited Inspection Body AIB Accredited Body AB
Final quality documentation
Site AdminTime Schedule
Financial controlProcurement inst. hardware/manpower
Temporary ServicesScaffolding
Laydown Areas Crane Drivers
Logistics/TransportWarehouseHeavy lifting
Temporary Power & FluidsConcrete Boring/Drilling
Survey/Alignment Waste
TD Installation Coordinator
ACCInstallation Coordinator
NSS Installation Coordinator
ICSInstallation Coordinator
CF Installation Coordinator
Framework Agreements
WeldersFitters
ElectricalI&C
TechniciansEtc.
OrganizationTarget project site organization
Target Installation Coordinator
Tobias Lexholm
InstallationPackageLeader
WP2Target Wheel
QCInstallation Inspection
Receival inspectionNDT (X-ray, PT, UT etc.)
Accredited Inspection Body AIB Accredited Body AB
Final quality documentation
Site AdminDocument control
Time ScheduleWork Permit
Accommodation (Site & Hotel)Financial control
Procurement inst. hardware/manpowerNCR (Non Conformity Report)
Temporary ServicesScaffolding
Laydown Areas Crane Drivers
Logistics/TransportWarehouseHeavy lifting
Temporary Power & FluidsConcrete Boring/Drilling
Survey/Alignment Waste
ESS Installation Coordinator
InstallationPackageLeader
WP3Moderator &
Reflector
InstallationPackageLeader
WP4Monolith Systems
InstallationPackageLeader
WP5Fluid Systems
InstallationPackageLeader
WP6Remote
Handling
InstallationPackageLeader
WP7Target Control
Framework Agreements
WeldersFitters
ElectricalI&C
TechniciansEtc.
IPLICS
Challenges during installation
• Greenfield site
• Tolerances / Communication
• Responsibility / Delivery limits during installation
• Who is paying for temporary services? Contractor / IK / ESS / Skanska?
• Late deliveries to site -> Impact on installation sequence
• Orphan scope
• Schedule changes (Workers from abroad) delay costs?
• Parallell activities (Skanska / TD/ AD / ICS / NSS). Agressive schedule
• ”Clean installations” in parallel with construction work (vacuum environment)
20