inspection and testing plan
TRANSCRIPT
Inspection and Testing Plan
Customer: Cakna Enterprise Sdn. Bhd Contract No:Project name: HUSM (Pakej 1)
INSPECTION AND TEST PLAN FOR : MECHANICAL & ELECTRICAL
No Work/ActivityInspections/
testing required
Sampling/
Frequency
Responsibility RecordsRequirement
/standard/specification
Acceptance criteria
Inspection/test
procedure
Check Verify Approval
1Material Approval
Mock-up form
Each material used
RE RE PMock-up file
Refer B.QSpecification & codes
Check DO
2Material inspection
Confirm to order
Each delivery
RE/CoW RE -Delivery dockets
Orders as placed
Specifications & codes
Visual
3
Storage and protection As specifiedEach week
CS ME - ChecklistSpecification, as attached
Safe, secure/ adequate protection
Visual
4
Preliminary activitiesTask completion
Each work area
CS ME - Checklist
Specifications/ OHS practice & regulations
All tasks completed
Visual
5Material installation
Check shopdrawings
Each work area
ME ME - ChecklistShopdrawings
Checklist and test panel
Checked
6Pre-handover activities
All matters finalized, clean and tidy
Each work area
CS ME MEShopdrawings
Specification, as attached
All items completed to specified
Final inspection
* RE = Resident Engineer, CoW = Clerk of Work, P = Principle, ME, Mechanical & Electrical Engineer, CS = Other CESB staff
Customer: Cakna Enterprise Sdn. Bhd Contract No:Project name: HUSM (Pakej 1)
INSPECTION AND TEST PLAN FOR ARCHITECH
No Work/ActivityInspections/
testing required
Sampling/
Frequency
Responsibility RecordsRequirement
/standard/specification
Acceptance criteria
Inspection/test
procedure
Check Verify Approval
1Material Approval
Mock-up form
Each material used
Mock-up file
Refer B.QSpecification & codes
Check DO
2Material inspection
Confirm to order
Each delivery
Delivery dockets
Orders as placed
Specifications & codes
Visual
3
Storage and protection As specifiedEach week
ChecklistSpecification, as attached
Safe, secure/ adequate protection
Visual
4
Preliminary activitiesTask completion
Each work area
Checklist
Specifications/ OHS practice & regulations
All tasks completed
Visual
5Surface preparation
Ready to paint, clean and smooth
Each work area
ChecklistSpecification, as standard
Smooth and clean
Visual
6Brick layer
Confirm to specified
Each work area
ChecklistSpecification, as standard
Specifications & codes
Visual
7Plastering
All maters finalized, clean and tidy
Each work area
ChecklistSpecification, as standard
Smooth and clean
Visual
8Rendering
All maters finalized, clean and tidy
Each work area
ChecklistSpecification, as standard
Smooth and clean
Visual
9Railing
Location and level
Each work area
ChecklistSpecification, as standard
All tasks completed
Visual
10
Painting
Full& uniform cover, smooth, color
Each work area
ChecklistSpecification, as standard
Checklist and test panel
Visual
* RE = Resident Engineer, CoW = Clerk of Work, P = Principle, ME, Mechanical & Electrical Engineer, CS = Other CESB staff