infrastructure projects 2013

55
Compendium of Infrastructure Projects in Uganda 1 COMPENDIUM OF INFRASTRUCTURE PROJECTS IN TRANSPORT & ENERGY INVESTMENTS Willy Mutenza Head Office: 12 Eric Wilkins House, Avondale Square Estate, Old Kent Road, London SE1 5ES Tel: +207 237 7317 Mob: +447790 647 089 - Email: [email protected] Website: www.mm2capital.com Skype: willymutenza ---------------------------------------------------- Services: MM2 Capital, the convergence focal point for Investors and Business Entrepreneurs.

Upload: willy-mutenza

Post on 24-Jun-2015

53 views

Category:

Technology


0 download

TRANSCRIPT

Page 1: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

1

COMPENDIUM OF INFRASTRUCTURE PROJECTS IN

TRANSPORT & ENERGY INVESTMENTS

Willy Mutenza Head Office: 12 Eric Wilkins House, Avondale Square Estate, Old Kent Road, London SE1 5ES Tel: +207 237 7317 Mob: +447790 647 089 - Email: [email protected] Website: www.mm2capital.com Skype: willymutenza ---------------------------------------------------- Services: MM2 Capital, the convergence focal point for Investors and Business Entrepreneurs.

Page 2: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

2

TABLE OF CONTENTS

Transport projects……………………………………………………….….. 4 Roads Transport …………………………………….……………….…. 5 Alternative Route to Entebbe…………………………………………………….…… 6 Flyover between Jinja Road and Kibuye……………………………………….…… 7 Construction Equipment for Districts Roads…………………………………..…… .8 Kibuye - Busega - Mpigi Road……………………………………………………….. 9 Kampala Northern Bypass ………………………………………………………… 10 Kampala - Jinja ………………………………………………………………………11 Kampala (Zana) – Entebbe………………………………………………………… 12 Air Transport …………………………………………………….…. ….... 13 Commercial Free Zone…………………………………………………………… ….14 Cargo Center………………………………………………………...................... .....15 Rail Transport …………………………………………………..… ….... 16 Extension of Gulu Line to Juba………………………………………………………17 Reactivation of kampala – Kasese line and future extension of Rwanda and the Democratic Republic of Congo……………………………………………………….18 Water Transport ……………………………………………….………..... 19

Redevelopment of Portbell Port……………………………………………….…..…20

Energy projects………………………………………………….………. ….21

Karuma large hydro power site (200mw)………………………………………..….22 Isimba large hydro power project (87 mw)…………………………………….……23 Ayago north large hydro power project (304mw)…………………………….…….24 Ayago south large hydro power project…………………………………….……….25 Murchision large hydropower project (642mw)………………………….…………26 Bugumira large hydro power project (109mw)…………………………….……….27 Kakaka small hydro power project (7.2 mw)…………………………….…………28 Muyembe/sirimityo small hydro power project (9.0 mw)……………….…………29 Nyamabuye small hydro power project (2.2mw)……………………….………….30 Yerya, Mahoma confluence hydro power project (3.0 mw)………….…………..31 Siti small hydro power project (2.5 mw)…………………………………………….32 Sipi/chebonet small hydro power project (2.5mw)…………………………… … ..33

Page 3: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

3

Mvepi small hydro power project (2.4mw)………………………………………… .34 Sogahi small hydro power project (2.0 mw)……………………………………….. 35 Ela small hydro power project (1.5 mw)……….…………………………………….36 Ririma small hydro power project (1.5mw)………………………………………….37 Haisesero small hydro power project (1.0 mw)……………………………… …..38 Nyahuka small hydro power project (0.65mw)…………………………………......39 Nkusi small hydro power project (0.6mw)…………………………………………..40 Rwizi small hydro power project (0.5mw)……………………………………… …41 Sezibwa small hydro power project (0.5mw)……………………………………….42 Rwigo small hydro power project (0.48mw)……………………………… ………..43 Narwodo small hydro power project (0.4mw)……………………………… ………44 Agoi small hydro power project (0.35mw)…………………………………………..45 Kitumba small hydro power project (0.2 mw)……………………………………….46 Tokwe small hydro power project (0.4mw)………………………… ……………..47 Amua small hydro power project (0.18mw)…………………………………………48 Ngiti small hydro power project (0.15mw)…………………………..………………49 Leya small hydro power project (0.12mw)…………………………………………..50 Nyakibale hydro power project (0.1mw)……………………………………… …..51 Miria adua small hydro power project (0.1mw)……………………………………..52 Nkusi small hydro power project (11mw)……………………………………………53 Esia hydro power project (1.0 mw)…………………………………………… ……54 Manafwa small hydro power project (0.15mw)………………………………… …55

Page 4: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

4

TRANSPORT PROJECTS

A. ROADS B. AIR C. RAIL D. WATER

TOTAL NUMBER OF PROJECTS: 12 TOTAL ESTIMATED COST USD: 1,620,900,000

Page 5: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

5

A) ROADS TRANSPORT

NUMBER OF PROJECTS: 07

PROJECT NAMES:

1) Alternative Route to Entebbe 2) Flyover between Jinja Road and Kibuye 3) Construction Equipment for Districts Roads 4) Kibuye – Busega – Mpigi Road 5) Kampala Northern By pass 6) Kampala – Jinja Road 7) Kampala (zana) - Entebbe

TOTAL ESTIMATED COST USD: 782.4 MILLION

Page 6: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

6

1) ALTERNATIVE ROUTE TO ENTEBBE (40KM) Project Description/Scope

Feasibility Study Detailed Engineering Design Construction

Estimated Costs (US $)

50 Million Project Status

Feasibility Study and Detailed Engineering Design in progress

Responsible Institution

Ministry of Works and Transport

Page 7: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

7

2) FLYOVER BETWEEN JINJA ROAD AND KIBUYE (4.7KM)

Project Description/Scope

Feasibility Study Detailed Engineering Design Construction

Estimated Costs (US $)

75 Million Project Status

To be in place by year 2018 Responsible Institution

Ministry of Works and Transport

Page 8: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

8

3) SUPPLY OF CONSTRUCTION EQUIPMENT

FOR DISTRICT ROADS Project Description/Scope

Supply of Equipment After sales Service Managing Workshops Training Managers and operators

Estimated Costs (US $)

80 Million Project Status/Remarks

Government will meet the cost of constructing the mechanical workshops

Responsible Institution

Ministry of Works and Transport

Page 9: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

9

4) KIBUYE – BUSEGA – MPIGI (32 KMS) Project Description/Scope

Review of detailed studies Construction works for dualling the road and construction consultancy supervision services

Estimated Costs (US $)

128 Million Project Status

Procurement of consultancy services for the feasibility study, detailed engineering designs and other tender assistance is on course

Responsible Institution

Ministry of Works and Transport

Page 10: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

10

5) KAMPALA NORTHERN BY PASS (18.6 KMS) Project Description/Scope

Review of detailed studies Construction works for dualling the road and construction consultancy supervision services

Estimated Costs (US $)

74.4 Million Project Status

Procurement of consultancy services for the feasibility study, detailed engineering designs and other tender assistance is on course

Responsible Institution

Ministry of Works and Transport

Page 11: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

11

6) KAMPALA – JINJA (72 KMS) Project Description/Scope

Review of detailed studies Construction works for dualling the road and construction consultancy supervision services

Estimated Costs (US $)

288 Million Project Status

Procurement of consultancy services for the feasibility study, detailed engineering designs and other tender assistance is on course

Responsible Institution

Ministry of Works and Transport

Page 12: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

12

7) KAMPALA – (ZANA) ENTEBBE (32 KMS) Project Description/Scope

Review of detailed studies Construction works for dualling the road and construction consultancy supervision services

Estimated Costs (US $)

87 Million Project Status

Procurement of consultancy services for the feasibility study, detailed engineering designs and other tender assistance is on course

Responsible Institution

Ministry of Works and Transport

Page 13: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

13

B) AIR TRANSPORT

NUMBER OF PROJECTS: 02

PROJECT NAMES:

1) Commercial Free Zone 2) Cargo Center

TOTAL ESTIMATED COST USD: 55 MILLION

Page 14: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

14

1) COMMERCIAL FREE ZONE Project Description/Scope

Feasibility Study Detailed Engineering Design Construction

Estimated Costs (US $)

30 Million Project Status/Remarks

Pre-feasibility already done Responsible Institution

Ministry of Works and Transport

Page 15: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

15

2) CARGO CENTRE Project Description/Scope

Feasibility Study Detailed Engineering Design Construction

Estimated Costs (US $)

25 Million Project Status/Remarks

To be in Place by year 2012 Responsible Institution

Ministry of Works and Transport

Page 16: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

16

C) RAIL TRANSPORT

NUMBER OF PROJECTS: 02

PROJECT NAMES:

1. Extension of Gulu line to Juba (320km) 2. Reactivation of Kampala-Kasese line (333km) and

future extension to Rwanda and the Democratic Republic of Congo

TOTAL ESTIMATED COST USD: 770 MILLION

Page 17: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

17

1) EXTENSION OF GULU LINE TO JUBA (320KM) Project Description/Scope

Feasibility Study Detailed Engineering Design Construction

Estimated Costs (US $)

420 Million Project Status

The cost covers all the items listed in the project scope Responsible Institution

Ministry of Works and Transport

Page 18: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

18

2) REACTIVATION OF KAMPALA-KASES LINE (333KM) AND FUTURE EXTENSION OF LINE TO RWANDA AND THE DEMOCRATIC REPUBLIC OF CONGO

Project Description/Scope

Feasibility Study Detailed Engineering Design Construction

Estimated Costs (US $)

350 Million Project Status/Remarks

The cost only covers the rehabilitation of the existing line up to Kasese

Responsible Institution

Ministry of Works and Transport

Page 19: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

19

D) WATER TRANSPORT

NUMBER OF PROJECTS: 01

PROJECT NAME:

1. Redevelopment of Port Bell Port

TOTAL ESTIMATED COST USD: 13.5 MILLION

Page 20: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

20

1) REDEVELOPMENT OF PORT BELL PORT Project Description/Scope

Feasibility Study Detailed Engineering Design Construction

Estimated Costs (US $)

420 Million Project Status/Remarks

The cost includes rehabilitation of the Port and terminal building facilities

Responsible Institution

Ministry of Works and Transport

Page 21: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

21

ENERGY PROJECTS

A) LARGE HYDRO POWER PROJECTS - NUMBER OF PROJECTS - 06 B) SMALL HYDRO POWER PROJECTS

- NUMBER OF PROJECTS - 28

TOTAL NUMBER OF ENERGY PROJECTS: - 34

Page 22: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

22

1) DEVELOPMENT OF KARUMA LARGE HYDRO POWER SITE (200MW)

Estimated Costs (US $)

300 - 700 Million1 Project Status/Remarks

To be developed as a Public Project Responsible Institution

Ministry of Energy and Mineral Development

1 Note: Hydro power project development costs in Uganda range between US$ 1.5 Million and US$ 3.5 Million per MW (Electricity Regulatory Authority)

Page 23: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

23

2) DEVELOPMENT OF ISIMBA LARGE HYDRO POWER PROJECT (87 MW)

Estimated Costs (US $)

130 – 304.5 Million Project Status/Remarks

Preliminary Studies are available Responsible Institution

Ministry of Energy and Mineral Development

Page 24: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

24

3) DEVELOPMENT OF AYAGO NORTH LARGE HYDRO POWER PROJECT (304MW)

Estimated Costs (US $)

456 Million – 1.064 Billion Project Status/Remarks

Preliminary studies have been done and are available Responsible Institution

Ministry of Energy and Mineral Development

Page 25: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

25

4) DEVELOPMENT OF AYAGO SOUTH LARGE HYDRO POWER PROJECT

Estimated Costs (US $)

351- 819 Million Project Status/Remarks

Preliminary studies done and are available Responsible Institution

Ministry of Energy and Mineral Development

Page 26: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

26

5) DEVELOPMENT OF MURCHISION LARGE HYDROPOWER PROJECT (642MW)

Estimated Costs (US $)

963 Million – 2.247 Billion Project Status/Remarks

Preliminary Studies have been done and are available. Project has adverse environment effects

Responsible Institution

Ministry of Energy and Mineral Development

Page 27: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

27

6) DEVELOPMENT OF BUGUMIRA LARGE HYDRO POWER PROJECT (109MW)

Estimated Costs (US $)

163.5 – 381.5 Million Project Status/Remarks

Preliminary studies are available Responsible Institution

Ministry of Energy and Mineral Development

Page 28: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

28

7) DEVELOPMENT OF KAKAKA SMALL HYDRO POWER PROJECT (7.2 MW)

Estimated Costs (US $)

10.8 – 25.2 Million Project Status/Remarks

Preliminary technical studies carried out in 1999 and 2003

Responsible Institution

Ministry of Energy and Mineral Development

Page 29: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

29

8) DEVELOPMENT OF MUYEMBE/SIRIMITYO SMALL HYDRO POWER PROJECT (9.0 MW)

Estimated Costs (US $)

13.5 – 31.5 Million Project Status/Remarks

Pre feasibility technical studies carried out Responsible Institution

Ministry of Energy and Mineral Development

Page 30: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

30

9) DEVELOPMENT OF NYAMABUYE SMALL HYDRO POWER PROJECT (2.2MW)

Estimated Costs (US $)

3.3 – 7.7 Million Project Status/Remarks

Preliminary technical studies carried out. Responsible Institution

Ministry of Energy and Mineral Development

Page 31: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

31

10) DEVELOPMENT OF YERYA, MAHOMA CONFLUENCE HYDRO POWER PROJECT (3.0 MW)

Estimated Costs (US $)

4.5 – 10.5 Million Project Status/Remarks

Preliminary technical studies are available Responsible Institution

Ministry of Energy and Mineral Development

Page 32: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

32

11) DEVELOPMENT OF SITI SMALL HYDRO POWER PROJECT (2.5 MW)

Estimated Costs (US $)

3.75 – 8.75 Million Project Status/Remarks

Preliminary technical studies are available Responsible Institution

Ministry of Energy and Mineral Development

Page 33: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

33

12) DEVELOPMENT OF SIPI/CHEBONET SMALL HYDRO POWER PROJECT (2.5MW)

Estimated Costs (US $)

3.75 – 8.75 Million Project Status/Remarks

Preliminary studies are available Responsible Institution

Ministry of Energy and Mineral Development

Page 34: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

34

13) DEVELOPMENT OF MVEPI SMALL HYDRO POWER PROJECT (2.4MW)

Estimated Costs (US $)

3.6 – 8.4 Million Project Status/Remarks

No studies Responsible Institution

Ministry of Energy and Mineral Development

Page 35: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

35

14) DEVELOPMENT OF SOGAHI SMALL HYDRO POWER PROJECT (2.0 MW)

Estimated Costs (US $)

3.75 – 7 Million Project Status/Remarks

No studies. Responsible Institution

Ministry of Energy and Mineral Development

Page 36: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

36

15) DEVELOPMENT OF ELA SMALL HYDRO POWER PROJECT (1.5 MW)

Estimated Costs (US $)

2.25 – 5.25 Million Project Status/Remarks

Preliminary studies are available Responsible Institution

Ministry of Energy and Mineral Development

Page 37: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

37

16) DEVELOPMENT OF RIRIMA SMALL HYDRO POWER PROJECT (1.5MW)

Estimated Costs (US $)

2.25 – 5.25 Million Project Status/Remarks

Pre feasibility studies are available Responsible Institution

Ministry of Energy and Mineral Development

Page 38: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

38

17) DEVELOPMENT OF HAISESERO SMALL HYDRO POWER PROJECT (1.0 MW)

Estimated Costs (US $)

1.5 – 3.5 Million Project Status/Remarks

No studies Responsible Institution

Ministry of Energy and Mineral Development

Page 39: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

39

18) DEVELOPMENT OF NYAHUKA SMALL HYDRO POWER PROJECT (0.65MW)

Estimated Costs (US $)

0.975 – 2.275 Million Project Status/Remarks

Preliminary technical studies are available Responsible Institution

Ministry of Energy and Mineral Development

Page 40: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

40

19) DEVELOPMENT OF NKUSI SMALL HYDRO POWER PROJECT (0.6MW)

Estimated Costs (US $)

0.9 – 2.1 Million Project Status/Remarks

Preliminary technical studies are available Responsible Institution

Ministry of Energy and Mineral Development

Page 41: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

41

20) DEVELOPMENT OF RWIZI SMALL HYDRO POWER PROJECT (0.5MW)

Estimated Costs (US $)

0.75 – 1.75 Million Project Status/Remarks

Preliminary studies are available Responsible Institution

Ministry of Energy and Mineral Development

Page 42: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

42

21) DEVELOPMENT OF SEZIBWA SMALL HYDRO POWER PROJECT (0.5MW)

Estimated Costs (US $)

0.75 – 1.75 Million Project Status/Remarks

Preliminary technical studies are available Responsible Institution

Ministry of Energy and Mineral Development

Page 43: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

43

22) DEVELOPMENT OF RWIGO SMALL HYDRO POWER PROJECT (0.48MW)

Estimated Costs (US $)

0.72 – 1.68 Million Project Status/Remarks

No studies Responsible Institution

Ministry of Energy and Mineral Development

Page 44: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

44

23) DEVELOPMENT OF NARWODO SMALL HYDRO POWER PROJECT (0.4MW)

Estimated Costs (US $)

0.6 – 1.4 Million Project Status/Remarks

Preliminary studies are available Responsible Institution

Ministry of Energy and Mineral Development

Page 45: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

45

24) DEVELOPMENT OF AGOI SMALL HYDRO POWER PROJECT (0.35MW)

Estimated Costs (US $)

0.525 –1.225 Million Project Status/Remarks

No studies Responsible Institution

Ministry of Energy and Mineral Development

Page 46: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

46

25) DEVELOPMENT OF KITUMBA SMALL HYDRO POWER PROJECT (0.2 MW)

Estimated Costs (US $)

0.3 – 0.7 Million Project Status/Remarks

No studies Responsible Institution

Ministry of Energy and Mineral Development

Page 47: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

47

26) DEVELOPMENT OF TOKWE SMALL HYDRO POWER PROJECT (0.4MW)

Estimated Costs (US $)

0.6 –1.4 Million Project Status/Remarks

Preliminary technical studies Responsible Institution

Ministry of Energy and Mineral Development

Page 48: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

48

27) DEVELOPMENT OF AMUA SMALL HYDRO POWER PROJECT (0.18MW)

Estimated Costs (US $)

0.27 – 0.63 Million Project Status/Remarks

No studies Responsible Institution

Ministry of Energy and Mineral Development

Page 49: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

49

28) DEVELOPMENT OF NGITI SMALL HYDRO POWER PROJECT (0.15MW)

Estimated Costs (US $)

0.225 – 0.525 Million Project Status/Remarks

Preliminary technical studies are available Responsible Institution

Ministry of Energy and Mineral Development

Page 50: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

50

29) DEVELOPMENT OF LEYA SMALL HYDRO POWER PROJECT (0.12MW)

Estimated Costs (US $)

0.18 – 0.42 Million Project Status/Remarks

No studies Responsible Institution

Ministry of Energy and Mineral Development

Page 51: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

51

30) DEVELOPMENT OF NYAKIBALE HYDRO POWER PROJECT (0.1MW)

Estimated Costs (US $)

0.15 – 0.35 Million Project Status/Remarks

No studies Responsible Institution

Ministry of Energy and Mineral Development

Page 52: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

52

31) DEVELOPMENT OF MIRIA ADUA SMALL HYDRO POWER PROJECT (0.1MW)

Estimated Costs (US $)

0.15 – 0.35 Million Project Status/Remarks

Preliminary studies are available Responsible Institution

Ministry of Energy and Mineral Development

Page 53: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

53

32) DEVELOPMENT OF NKUSI SMALL HYDRO POWER PROJECT (11MW)

Estimated Costs (US $)

16.5 – 38.5 Million Project Status/Remarks

No studies Responsible Institution

Ministry of Energy and Mineral Development

Page 54: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

54

33) DEVELOPMENT OF ESIA HYDRO POWER PROJECT (1.0 MW)

Estimated Costs (US $)

1.5 – 3.5 Million Project Status/Remarks

Preliminary studies are available Responsible Institution

Ministry of Energy and Mineral Development

Page 55: Infrastructure projects 2013

Compendium of Infrastructure Projects in Uganda

55

34) DEVELOPMENT OF MANAFWA SMALL HYDRO POWER PROJECT (0.15MW)

Estimated Costs (US $)

0.225 – 0.525 Million Project Status/Remarks

Preliminary technical studies carried out Responsible Institution

Ministry of Energy and Mineral Development