increasing machine utilization using total productive

97
INCREASING MACHINE UTILIZATION USING TOTAL PRODUCTIVE MAINTENANCE IN DIE CAST MACHINE IN TOY MANUFACTURING COMPANY By Sarah Christina Philip ID No. 004201300048 A Thesis presented to the Faculty of Engineering President University in partial fulfillment of the requirements of Bachelor Degree in Engineering Major in Industrial Engineering 2018

Upload: others

Post on 04-Apr-2022

2 views

Category:

Documents


0 download

TRANSCRIPT

INCREASING MACHINE UTILIZATION USING

TOTAL PRODUCTIVE MAINTENANCE IN DIE CAST

MACHINE IN TOY MANUFACTURING COMPANY

By

Sarah Christina Philip

ID No. 004201300048

A Thesis presented to the Faculty of Engineering President

University in partial fulfillment of the requirements of Bachelor

Degree in Engineering Major in Industrial Engineering

2018

THESIS ADVISOR

RECOMMENDATION LETTER

This thesis entitled β€œIncreasing Machine Utilization Using Total

Productive Maintenance in Die Cast Machine in Toy

Manufacturing Company” is prepared and submitted by Sarah

Christina Philip in partial fulfillment of the requirements for the

degree of Bachelor Degree in the Faculty of Engineering has been

reviewed and found to have satisfied the requirements for a thesis fit to

be examined. I therefore recommend this thesis for Oral Defense.

Cikarang, Indonesia, May 9th, 2018

Anastasia Lidya Maukar, S.T.,M.Sc.,M.,T.

DECLARATION OF ORIGINALITY

I declare that this thesis, entitled β€œIncreasing Machine Utilization

Using Total Productive Maintenance in Die Cast Machine in Toy

Manufacturing Company” is to the best of my knowledge and belief,

an original piece of work that has not been submitted, either in whole

or in part, to another university to obtain a degree.

Cikarang, Indonesia, May 9th, 2018

Sarah Christina Philip

INCREASING MACHINE UTILIZATION USING

TOTAL PRODUCTIVE MAINTENANCE IN

DIE CAST MACHINE IN TOY MANUFACTURING

COMPANY

By

Sarah Christina Philip

ID No. 004201300048

Approved by

Anastasia Lidya Maukar, S.T.,M.Sc.,M.,T.

Thesis Advisor

Ir. Andira. M.T.

Head of Industrial Engineering Study Program

ABSTRACT

The purpose of this thesis is to reduce the number of high downtime in a toy

manufacturing company. Previously, the company was evaluated through overall

equipment effectiveness for all the production area and managed to highlight one

area that score lowest, which is the die cast area, with an average score of 54%. The

low availability of die cast impacted negatively on its OEE performance. Thus, to

reduce the high downtime, Total Productive Maintenance is employed through

some of its programs especially the preventive maintenance. The research will

analyze deep-dive to one pilot equipment that has been causing a high downtime to

the area. The research will design a preventive maintenance schedule and other

TPM implementation that focuses on total employee involvement, from top level

management to regular workers, in purpose to improve the overall equipment

effectiveness percentage, but also impacted the company culture to have a lean

thinking. The OEE result after the TPM implementation increased by 18%, from a

5-month average of 54% to 72% in 3 months progress. The increase of high

reliability has an impact to the equipment performance and to high OEE score.

Keywords: Die Cast Machine, Total Productive Maintenance, Preventive Maintenance,

Overall Equipment Effectiveness, Toy Manufacturing Industry.

ACKNOWLEDGMENT

This thesis is done with God’s blessings, The Lord Almighty, Jesus Christ and His

steadfast love towards me. And the endless support and motivations from my

significant others. Therefore, I would like to express my sincere thanks and

gratefulness to:

1. Anastasia Lydia Maukar S.T., M.Sc., M.MT. My thesis advisor who gave

guidance, direction, motivation, inspiration, and recommendation in doing

and accomplishing this thesis.

2. Ms. Ir. Andira, M.T. as the most understanding Head of Study Program of

Industrial Engineering

3. My beloved parents Philip and Jeanne who supports me through their

continuous prayers, guidance, love and tirelessly taught me a great deal

about the ups and downs of growing up.

4. My beloved siblings, Sheila, Sandra, Abe and Stefany who constantly cheer

me up with their life-is-a-peach innocence. Don’t ever grow up!

5. My schatz, mon cher, the fabulous mind reader; Albert Sebastian. Thank

you for the relentless motivation and support. Thank you for always being

here in every moment.

6. LSCO friends and collegues; Haris, Kemal, Wahyu, Putra and Daris, who

gave me chances to try out something new, support my ideas, give me

motivation, direction, and suggestion along my internship period. They are

my second family in heart.

7. My beloved classmates, Industrial Engineering batch 2013-2014, Putri,

Aldino, Antasara, Marsha, Elena, Anita, Egin, Elsa, Shelly, Salbi and Febi.

8. My incredible mentors; Crissy, Igun, Thania, Tomy and Gandi. Thank you

for giving light through all the advices and the insights to my thesis.

9. Others that I cannot mention one by one but always give me motivation.

TABLE OF CONTENT

THESIS ADVISOR RECOMMENDATION LETTER .......................................... i

DECLARATION OF ORIGINALITY ................................................................... ii

ABSTRACT ........................................................................................................... iv

ACKNOWLEDGMENT ......................................................................................... v

TABLE OF CONTENT ......................................................................................... vi

LIST OF FIGURES ............................................................................................... ix

LIST OF TABLES .................................................................................................. x

LIST OF TERMINOLOGIES ................................................................................ xi

CHAPTER I ............................................................................................................ 1

1.1 Problem Background ................................................................................. 1

1.2 Problem Statement ..................................................................................... 2

1.3 Objectives .................................................................................................. 2

1.4 Scope ......................................................................................................... 3

1.5 Assumption ................................................................................................ 3

1.6 Research Outline ........................................................................................ 3

CHAPTER II ........................................................................................................... 5

STUDY LITERATURE .......................................................................................... 5

2.1 Maintenance Management System ............................................................ 5

2.1.1 Maintenance Management Goal ......................................................... 6

2.1.2 Types of Maintenance ........................................................................ 6

2.2 Total Productive Maintenance (TPM) ....................................................... 7

2.2.1 TPM Definition .................................................................................. 8

2.2.2 TPM Components ............................................................................ 11

2.2.3 TPM Metric ...................................................................................... 14

2.3 Machine Reliability ................................................................................. 16

2.4 Distribution Function ............................................................................... 17

2.4.1 Failure Distribution .......................................................................... 17

2.4.2 Cumulative Distribution Function .................................................... 17

2.4.3 Reliability Function .......................................................................... 18

2.4.4 Index of Fit (r) .................................................................................... 18

2.5 Failure Distribution.................................................................................. 19

2.6 Distribution for Measuring Reliability .................................................... 21

2.6.1 Weibull Distribution ........................................................................... 21

2.6.2 Lognormal Distribution ...................................................................... 23

2.6.3 Normal Distribution ............................................................................ 24

2.6.4 Exponential Distribution ..................................................................... 26

2.7 Distribution Identification ....................................................................... 26

CHAPTER III ....................................................................................................... 28

3.1 Research Flowchart ................................................................................. 28

3.1.1 Initial Observation ............................................................................ 29

3.1.2 Problem Identification ...................................................................... 29

3.1.3 Literature Study ................................................................................ 29

3.1.4 Data Collection ................................................................................. 30

3.1.5 Data Analysis ................................................................................... 30

3.1.6 Conclusion and Recommendation .................................................... 31

3.2 Detail Framework .................................................................................... 32

CHAPTER IV ....................................................................................................... 33

DATA COLLECTION AND ANALYSIS ........................................................... 33

4.1 Initial Observation ................................................................................... 33

4.1.1 Machine Description ........................................................................ 33

4.1.2 Flow Process Die Cast and Plastic Injection Molding ..................... 35

4.2 Data Collection ........................................................................................ 36

4.2.1 Current Die Cast Machine Reliability .............................................. 36

4.2.1.1 Overall Equipment Effectiveness ............................................... 36

4.2.1.2 Current Machine Downtime ....................................................... 38

4.2.1.3 Functional Hazard Analysis ........................................................ 43

4.3 Data Calculation ...................................................................................... 45

4.3.1 Machine Reliability .......................................................................... 45

4.3.1.1 Current Machine OEE ................................................................. 46

4.3.1.2 Failure Data of Machine ............................................................. 50

4.3.2 Calculation of Mean Time to Repair (MTTR) and Meant Time to

Failure (MTTF) ......................................................................................... 55

4.3.3 Distribution Identification ................................................................ 57

4.3.4 Maintenance Cost Calculation ......................................................... 59

4.3.4.1 Calculation of Corrective Maintenance Cost (Cf) ...................... 60

4.3.4.2 Calculation of Preventive Maintenance Cost (Cp) ..................... 61

4.3.4.3 Component Replacement Interval Calculation ........................... 63

4.3.4.4 Proposed Preventive Maintenance Schedule .............................. 70

4.4 Data Analysis and Implementation .......................................................... 71

4.4.1 Machine Reliability .......................................................................... 71

4.4.1.1 Component Reliability Comparison ........................................... 71

4.4.1.2 Proposed Preventive Maintenance Scheduling ........................... 73

4.4.1.3 OEE Comparison after TPM Implementation ............................ 73

4.4.1.4 Cost Comparison ......................................................................... 75

4.4.2 TPM Implementation ....................................................................... 76

CHAPTER V ......................................................................................................... 82

CONCLUSION AND RECOMMENDATION .................................................... 82

5.1 Conclusion ............................................................................................... 82

5.2 Recommendation ..................................................................................... 83

REFERENCES ...................................................................................................... 84

APPENDIX ........................................................................................................... 85

LIST OF FIGURES

Figure 2.1 Lean House in Production System ___________________________ 10

Figure 2.2 The Eight Pillars Approach for TPM Implementation (JIPM) _____ 11

Figure 2.3 Typical Life Cycle Bathtub Curve ___________________________ 20

Figure 2.4 Effect of Scale Parameter on Weibull ________________________ 23

Figure 2.5 Lognormal Distribution Curve _____________________________ 24

Figure 2.6 Normal Distribution Curve ________________________________ 26

Figure 3.1 Research Flowchart ______________________________________ 28

Figure 3.2 Research Framework _____________________________________ 32

Figure 4.1 Die Cast Machine in Toy Manufacturing Company _____________ 33

Figure 4.2 4-UP Output Using Mold Combination _______________________ 34

Figure 4.3 Flow Process of Die Cast __________________________________ 35

Figure 4.4 OEE Trend in Production Area for August-December 2017_______ 37

Figure 4.5 Primary Process OEE Trends for August-December 2017 ________ 38

Figure 4.6 Bar Chart of Machine Downtime Issues ______________________ 40

Figure 4.7 Pareto Chart of Machine Downtime _________________________ 41

Figure 4.8 Pareto Chart of Die Cast Machine Failure Occurrences __________ 42

Figure 4.9 Top View of Nozzle initial condition and Nozzle Failure Condition 44

Figure 4.10 Side View of Nozzle initial condition and Nozzle Failure Condition 45

Figure 4.11 Line Chart of Machine A06 OEE Trend for August-December 201750

Figure 4.12 Cost per Unit of Time Replacement Nozzle __________________ 65

Figure 4.13 Cost per Unit of Time Replacement Gripper __________________ 67

Figure 4.14 Cost per Unit of Time Replacement Nipple __________________ 69

Figure 4.15 Nozzle and Gripper Preventive Maintenance Schedule in A06 for

January-March 2018 ______________________________________________ 70

Figure 4.16 Nipple Preventive Maintenance Schedule in A06 for January-March

2018 ___________________________________________________________ 71

Figure 4.17 Reliability Comparison __________________________________ 72

Figure 4.18 OEE Comparison Before and After TPM ____________________ 75

Figure 4.19 Cost Comparison of Current and Proposed Maintenance ________ 76

LIST OF TABLES

Table 2.1 The Impact of TPM in All Aspect ____________________________ 9

Table 2.2 OEE Score Comprehension ________________________________ 16

Table 2.3 World Class OEE Score ___________________________________ 16

Table 2.4 Weibull Distribution Shape Parameter Value ___________________ 21

Table 4.1 Machine Failure Issues and Occurrences ______________________ 39

Table 4.2 Machine’s Downtime Duration ______________________________ 40

Table 4.3 Detail of A06 Machine Failures and Frequency _________________ 42

Table 4.4 Output Report for 28 August 2017 ___________________________ 46

Table 4.5 OEE Calculation Result ___________________________________ 48

Table 4.6 OEE Trend of Machine A06 for August-December 2017 _________ 49

Table 4.7 Failure Time and Repair Finish Time of Nozzle Failure from August-

December 2017 __________________________________________________ 51

Table 4.8 Failure Time and Repair Finish Time of Hose Holder Leaking Failure

from August-December 2017 _______________________________________ 52

Table 4.9 Failure Time and Repair Finish Time of Water Cooling Holder Failure

from September-December 2017 ____________________________________ 54

Table 4.10 MTTR Value of Each Critical Component from August until December

2017 ___________________________________________________________ 55

Table 4.11 MTTF Value of Each Critical Component from August until December

2017 ___________________________________________________________ 56

Table 4.12 TTF Distribution for Each Component _______________________ 57

Table 4.13 TTF Distribution for Each Component _______________________ 59

Table 4.14 Replacement Interval Time of Nozzle _______________________ 63

Table 4.15 Replacement Interval Time of Gripper _______________________ 65

Table 4.16 Replacement Interval Time of Nipple ________________________ 67

Table 4.17 Interval Time of Component Replacement ____________________ 69

Table 4.18 Comparison of Time and Reliability _________________________ 72

Table 4.19 Machine A06 for January-March 2018 _______________________ 73

LIST OF TERMINOLOGIES

Die Casting Die casting, also known as metal casting, is a process of

injecting a metal liquid into a mold that has shaped

cavities.

OEE An abbreviation for Overall Equipment Effectiveness. It is

used as a metric or measurement tool to evaluate the

equipment effectiveness.

TPM Total Productive Maintenance (TPM) is a form of

teamwork between maintenance and production to

improve product quality, reduce wastes, reduce

manufacturing cost and increase equipment availability,

and enhance the sustainability of the company

Nozzle A cylindrical or round sprout at the end of a hose or tube

that is used to control a jet of liquid or gas.

Gripper A media or a tool that grips things or may refer to the tools

for building hand strength, the hand of the robot.

Nipple Something that connects two things together, especially

mechanical component or system.

4-UP 4-UP is a printing expression of designate impressions of

four different images or pattern at the same time.

2-UP 2-UP is a printing expression of designate impressions of

two different images or pattern at the same time.

Hazard A hazard is any source of potential damage, harm or

adverse health effects on something or someone under

certain conditions at work. Basically, a hazard can cause

harm or adverse effects (to individuals as health effects or

to organizations as property or equipment losses).

FHA Functional Hazard Analysis (FHA) is a method to

identifies every function of system and consider the

hazards that may result when each function fails in every

possible way.

PM Preventive Maintenance (PM) is a maintenance activity

performed through periodically inspection with a purpose

to prevent early breakdown while the operation/production

is running.

CM Corrective Maintenance (CM) is a maintenance activity

performed to refurbish the condition of the damaged

equipment until it’s become the desired condition.

Near Miss A safety term for any unplanned event that did not result

an illness, injury or damage, but had the potential to do so.

1

CHAPTER I

INTRODUCTION

1.1 Problem Background

The vast progress of technology and globalization has given a significant

development towards the industrial field, such as the involvement of advance

machineries and equipment in production floor and supplier activities. Hence, the

swiftness and result may contribute a good outcome to the organization. To survive

in the business, an organization needs to have a good strategy to maintain their

machines and equipment, because a degrading condition of machine productivity

can give a huge impact to the production process in the organization. Kutucuoglu

et al. (2001) stated that equipment is the major contributor to the performance and

profitability in manufacturing. Therefore, activities that involve in machine

maintenance are essential to prevent sudden production down time.

A lack of in-depth knowledge can cause misunderstandings and result a weak

maintenance in an organization. This failure can generate a relatively low number

of output produce and supply. Hence, to maximize the production output through

efficiency and effectiveness, is by maintaining all the asset through careful and

thorough maintenance management,

The observed company is a multinational toy manufacturing company in Indonesia

which produce dolls and toy cars, famously known around the world. The company

recently established its second plant, which is focused in producing toy cars, with a

wide range of toys, differentiated in shape, theme, machine and raw material. The

company produces numerous of high quality toy car assortments for each of every

theme, and every process is done in the company. The company divided the main

parts into two type of primary process; Die Casting and Injection Molding. Die

casting, producer of the body and chassis parts of the toy car, has 26 machines

which are all identical to one another. To produce high quality parts, die cast

machine must be well-maintained to sustain its good condition, hence the die cast

machine must have an organized maintenance activity.

2

In the last semester of 2017, the average downtime which caused by the broken part

replacement in die cast per shift is 32.397 minutes long, with a cycle time of 8.2

seconds. Hence the machine performance loss is 6.1% output per shift leads to a

total of IDR 12,246,066 per shift. If this period of downtime is not immediately

improved, it could lead to starvation for the next process, because the lack of output

to supply by die cast to its next process, the electrostatic painting. In purpose to

reduce the high downtime, implementing total productive maintenance is mostly

recommended to improve machine reliability. Total Productive Maintenance

(TPM) method is a lean approach that reinforce total employee involvement with

its programs, which include preventive maintenance. Through scheduled

maintenance activities, unplanned breakdown can be prevented, thus could help to

reduce the number of high downtime in die cast. Lean approach has helped world

class manufacturing companies improve productivity through continuous

improvement. Thus, this research will be using the total productive maintenance

(TPM), to achieve maximum equipment effectiveness through employee

involvement and one of the TPM method, which is the OEE. OEE is employed to

measure the equipment performance by highlighting the real problem in the

equipment. Hence, the measurement of OEE is used as the basic for TPM activities.

(Ljunberg, 1998)

1.2 Problem Statement

The background of the problem is for improving die cast machine utilization and

availability as well as decreasing any unplanned equipment downtime.

Which machine failure takes the highest downtime?

What method will be used to reduce the downtime in production floor?

How does the company reduce the downtime?

1.3 Objectives

The main objectives of this research are:

To identify the most affecting factors of downtime

To define the correct method to reduce the downtime

To implement TPM programs to the company

3

1.4 Scope

Due to limited time and resources in doing this project, there will be some scope in

the research, such as:

1. The machine downtime data was collected from August-December 2017,

and its progress was observed in January-March 2018 with current condition

at that time.

2. The gathered data are based on production data, during 3 months of

observation and interviews with the relevant staff

3. The improvement will focus on one of the largest downtime contributor

machine

4. The type of machine observed is LK AVIS-II DC50, die cast machine A06.

1.5 Assumption

An assumption must be made to ensure the method implemented is accurate

All the observed machines are the same type of machine with the same age

and specifications.

Down time is counted only when machine is stopped because of failure, set

up time is not accounted.

The manpower and component price are constant

1.6 Research Outline

Chapter I Introduction

This chapter consists of the problem background, problem

statement, objectives, scopes, and assumptions as

introductory of the project at the company.

Chapter II Literature Study

This chapter delivers theoretical groundings on

Maintenance and Total Productive Maintenance (TPM).

Chapter III Research Methodology

The flow of this final project is explained in this chapter. It

starts from the research objective, literature study, data

4

collection, data calculation, data analysis, conclusion and

recommendation.

Chapter IV Data Collection and Analysis

This chapter consist of data collection from the research,

data calculation and analysis which will support in finding

the solution.

Chapter V Conclusion and Recommendation

This chapter will mention the conclusion as a result of the

entire project, and also the recommendation for future

research.

5

CHAPTER II

STUDY LITERATURE

2.1 Maintenance Management System

The principles of maintaining the condition of an equipment has gone through

various of development in the last three decades. The conventional perspective of

maintenance is to repair a damage or broken component. Hence the understanding

the act of maintenance was limited only to the tasks related to repairing or changing

equipment’s components. This approach is also known as the reactive maintenance,

breakdown maintenance and corrective maintenance.

The role of maintenance then evolves as time goes by and the vast development of

global competition. Maintenance role extends not only in breakdown emergencies

but to all the activities that aims to preserve and cultivate facilities in the same good

condition as it first installation, or the necessary condition to fulfill the production

functions (Gits, 1992). The extension of maintenance responsibility also requires a

proactive task, such as; a large scale inspection (overhaul, routine periodic and

component replacement). In terms to maintain and repair an equipment,

maintenance need to do a few extra activities, these activities include: planned

maintenance, the control of material purchases, staff management and quality

control.

The purpose of implementing this system is to minimize the lost, stabilize the

company’s operational, maximize production output and consistently produce

product with great quality. Maintenance is defined as the activity needed to be done

to maintain the equipment the same as its first installation, so it can continue to run

effectively according to its production capacity. Generally, maintenance

management is the act that relates to planning, organizing, hiring, implementing

program and maintenance control. Maintenance activities aim to optimize the

maintenance performance by increasing the reliability and availability from a

6

system or equipment through planning, organization, hiring management,

observation and good evaluation.

2.1.1 Maintenance Management Goal

(Developing performance indicators for managing maintenance)

The advantage from maintenance activities, according to Terry Wireman, are:

Identifying and implementing cost reduction/ cost saving

Maximizing production on a low cost with a high quality product in the

optimum safety standard

Gathering important information about maintenance cost

Optimizing maintenance resource

Optimizing equipment lifetime

Minimizing the use of energy

Minimizing supply

2.1.2 Types of Maintenance

There are several types of maintenance activities in a company, such as;

1. Breakdown Maintenance

This type of maintenance is executed only when the machine broke down.

There is no expense for preventive maintenance. This condition is only

suitable if there are enough supply of spare parts.

2. Routine Maintenance

Routine maintenance is perform periodically following a repeatable

operation cycle, it can also be in the form of daily maintenance, weekly

maintenance or based on the running hour. The activities that are being done

are sweeping, adjustment, oiling or replacement. This maintenance is to

prevent breakdown and reduce reparation cost.

3. Corrective Maintenance

Corrective maintenance is a maintenance that being perform to refurbish the

condition of the damaged equipment until it’s become the desired condition,

hopefully to increase the equipment productivity. This type of maintenance

7

is performed after failure happens. The formula of corrective maintenance

is expressed with:

𝐢𝑓 = 𝐷 + (𝐢 Γ— 𝐴) + (𝐸 Γ— 𝐢 Γ— 𝐡) (2-1)

Whereas:

A: Maintenance service

B: Production loss Cost

C: Downtime hours

D: Component price/unit

E: Machine Capacity

4. Preventive Maintenance

Preventive maintenance is performed through periodically inspection with

a purpose to prevent early breakdown while the operation/production is

running. Below is the calculation in determining the preventive maintenance

cost:

(2-2)

Whereas:

P = Component price

t = Downtime (hour)

f = Mechanic fare/hour

C = Production Capacity

PL = Production loss/product

5. Predictive Maintenance

Predictive maintenance is performed through forecasting of failure time,

replacement and repairmen equipment before failure. This maintenance is

to foresee the failure that will happen.

2.2 Total Productive Maintenance (TPM)

TPM, which stands for Total Productive Maintenance, was coined by a Japanese

company called Nippon Denso Co Ltd in 1971, from its employee Mr. Seiichi

Nakajima, who later received an honorary award from the Japan Institute of Plant

Maintenance (JIPM) for his contribution towards hundreds of plants in Japan and

πΆπ‘œπ‘ π‘‘ = 𝑃 + (𝑑 Γ— 𝑓) + (𝐢 Γ— 𝑑 Γ— 𝑃𝐿)

8

became known as the father of TPM and Nippondenso for its best maintenance

practices. Nippondenso was happened to be one of the main supplier of Toyota and

its practice become the important element in Toyota Production System (TPS)

which later be developed.

Nowadays, in strive to be in the loop of the global competition, which becomes

more challenging and evolve swiftly, an organization needs to prepare a reliable

strategy to manage all the resource in the organization correctly, effectively and

efficiently. Just In Time (JIT) and Total Quality Management (TQM) are some of

the strategies that have been implemented around the industrial world, and in these

recent time Total Productive Maintenance exists as one of the reliable tool to

maintain equipment with high quality, strategically. TPM focus on the maintenance

activities and transform it into an important role in business practices. TPM

initiatives help coordinate manufacturing function with other functions in order to

gain continuous benefits.

Total Productive Maintenance (TPM) has three main objectives:

1) Zero product defect

2) Zero unplanned equipment breakdown

3) Zero accident

These objectives can be achieved by doing gap analysis from historical data about

downtime, machine breakdown, product defect, and past accidents.

2.2.1 TPM Definition

TPM, stands for three words that each has a meaning of its own;

(1) Total. Indicates that TPM considers various of aspects and the need of

everybody’s involvement, from the top managements to workers.

(2) Productive. Forces all effort to try to maintain the condition of running

production while minimize the production problems that happens during the

maintenance.

9

(3) Maintenance. Sustain and preserve equipment independently by operator to

keep the equipment in good condition, through cleaning, greasing and

observing it.

The father of TPM, Mr. Seiichi Nakajima, realized that eliminating break downs

will not fully optimize equipment effectiveness, he encouraged the use of

autonomous maintenance, whereas the operator perform day to day activities in his

work station by himself. (Bhadury, 2000). In 1989, the Japan Institute of Plant

Maintenance (JIPM) saw that TPM as a culture that can prevent losses, widely

maximize productivity and it involves everyone in the organization (direct

management to workers) to participate in small groups. (JIPM, 1996). According

to (Chaneski, 2002) TPM is a maintenance management program that aims to

reduce the equipment break down While Besterfield et al. (1999) opinioned which

TPM is a form of good teamwork between maintenance and production to improve

the quality of a product, reduce wastes, reduce manufacturing cost, increase

equipment availability, and enhance the sustainability of the company.

Mobley define TPM as a comprehensive maintenance strategy which based on the

approach of the equipment life cycle that could minimize the break downs, defects

and incidents (Mobley, 2008). TPM involve whoever inside the organization, from

the top level management till the workers and technicians. The purpose is to

increase the availability continuously and prevent the equipment performance to

decline from its maximal effectiveness.

Table 2.1 The Impact of TPM in All Aspect

Measure Impact of TPM

Productivity Reduce the need for intervention

Reduce breakdowns

Quality Potential to reduce tolerance

Control of technology

Reduce start-up loss

Cost Reduce material, spares

Delivery Zero breakdowns predictability

10

Table 2.1 The Impact of TPM in All Aspect (Cont’d)

Measure Impact of TPM

Safety Less unplanned events & intervention

Controlled wear

Morale Better understanding of technology

More time to manage

Environment Closer control of equipment

Less unplanned events/human error

TPM itself is not a maintenance department program or a workshop event to

eliminate a handy worker (maintenance staff or technician). TPM is rather a method

to reach the maximum effectiveness of an equipment through employee

involvements. TPM has three basic principles, which are; to increase the Overall

Equipment Effectiveness, enhance maintenance skill and operations, involve

employees through a small group, closer approach to the employees with basic facts

for continuous improvement.

In Lean transformation, TPM focus as a base for productivity improvement process

and stability to the Lean house.

Figure 2.1 Lean House in Production System

Just-In-Time

Continues flow

Takt time

Pull system

Flexible resources

Jidoka

Segregate machine

and man work

Identify abnormal

situation

Poka yoke

Heijunka Standard work Kaizen

Stability (TPM Focus)

Employee

Involvement

Customer Satisfaction

11

The lean house foundation is stability, and above it lies Heijunka, standard work

and Kaizen. The Lean production system house has two founding pillars; Just-in-

Time and Jidoka. Just-in-Time consist of continuous flow, takt time, pull system,

flexible resources. While the Jidoka is all about building a better quality by

decreasing defect, rework and scrap, and most importantly eliminating waste.

Jidoka has several methods that are popular in manufacturing world, such as Andon,

a method to sign if there is a problem so can be resolve quickly, and Poka Yoke,

which is a Japanese term for error proofing in all aspect of manufacturing, customer

service and many more. Lean encourage employee involvement through respect for

people, team building, cross training, supplier relations, resources and many more.

Employee involvement is essential because it increase the moral and skill of

leadership, increasing the organization productivity, identify the SWOT of the

team, and develop the employee to become a problem solver.

2.2.2 TPM Components

According to (Ahuja & Kahamba, 2008) TPM offers a pathway to gain perfection

in terms of planning, monitoring, controlling, organizing, and through the eight

pillar method stands alone an independent maintenance called autonomous

maintenance, focused improvement, quality maintenance, education and training,

safety health and environment, office TPM and development management. The

visualization of the JIPM eight pillar is provided in Figure 2.1.

Figure 2.2 The Eight Pillars Approach for TPM Implementation (JIPM)

12

An organization that has succeed in implementing TPM always tend to achieve an

outstanding output, especially in reducing the frequency of equipment breakdowns,

minimizing downtime and interruptions, reduce the number of defects, increasing

productivity, cutting unnecessary resources and expenses, presses supplies,

reducing the probability of incident and embrace the role of workers, for example

in terms of suggestions of maintenance and reparations.

(1) 5S

5S stands as the concept of total productive maintenance (TPM) and as the

foundation of the eight pillars. 5S stands for sort out, set in order, shine,

standardize and sustain. The idea of 5S is about organizing the area of work for

efficiency and effectiveness to see the problems which previously gone

unnoticed. To make the problem visible and eliminate it, one must first sort

things properly, eliminate items that are not needed, clean workplace and

equipment thoroughly, organize tools and to help make things simpler, create

a 5S checklist and schedule a periodic audit to sustain a clean and proper

workplace.

(2) Autonomous Maintenance

Autonomous Maintenance aims to develop operator ownership. In other words,

AM is also to help raise the sense of belonging to operator and his work

equipment by performing day to day task and in turn, the operator skills will

improve and abnormality in the equipment will go unnoticed. Autonomous

maintenance program increases maintenance personnel availability for higher-

level tasks.

(3) Focused Maintenance

Focused Maintenance focused to reduce losses in the workplace that

contributes bottleneck to its efficiency. This pillar is about Kaizen, which is a

Japanese word, Kai means change, and Zen means better. Kaizen is where a

small group of people working together to seek incremental improvement in

the process. The people involved in the kaizen team are consist of cross

functional division and hierarchy, in order to easily identify and resolve

13

recurring problems. It is believed that small improvements with great numbers

have more impact than large improvement of small numbers in a company.

(4) Planned Maintenance

This pillar is about schedules maintenance tasks based on predicted and/or

measured failure rates, along with improving the product quality and raising

the output, therefore to raise the machine availability. Planned Maintenance

will significantly reduce unplanned downtime and inventory through better

control of wear and failure-prone parts. Methods that can be used are

Breakdown Maintenance, Preventive Maintenance and Corrective

Maintenance.

(5) Quality Maintenance

This pillar is about providing the customer with a high quality product, by

designing error detection and prevention into production processes. To

eliminate recurring problem (quality defects), a gap analysis must be done by

finding the root cause analysis.

(6) Education and Training

This pillar aimed to fill in the knowledge gaps necessary to achieve TPM goals.

The training and education subjects applied to operators, maintenance

personnel and managers, in purpose to have a multi-skilled work forces without

eliminating the tasks of the maintenance personnel. Maintenance will be taught

the techniques for proactive and preventive maintenance.

(7) Safety, Health and Environment

This pillar aimed to maintain a safe and healthy working environment. Safety,

Health and Environment plays an important role in the plant, as it is focused on

achieving Zero Accident. If this program is implemented, it can help the plant

to eliminate potential health and safety hazards, and eventually, an accident-

free workplace.

(8) Office TPM

This pillar applies TPM techniques to administrative functions. The benefit in

implementing this is the improvement of productivity and efficiency towards

administrative operations by removing procedural hassles and focus on

addressing cost related issues.

14

(9) Development Management

This pillar aimed to avoid repeating the same problem in the system by

minimizing the problem and making use of previous knowledge in developing

the maintenance practices for the new ones.

2.2.3 TPM Metric

TPM has a measuring system to measure its current performance. It was developed

to support TPM initiatives by accurately tracking progress towards achieving

perfect production.

Overall Equipment Effectiveness (OEE)

OEE was proposed by Nakajima (1988) as one of the tool to evaluate the progress

through reparation initiatives as part of TPM philosophy and defined OEE as a

metric or measurement tool to evaluate the equipment effectiveness. OEE strive to

identify area that require resource, production losses and expenses that go

unnoticed. According to Ericsson (1997) OEE gives a significant contribution to

total production cost. OEE is the ground base to measure whether the TPM

implementation has succeed. This loss/ disadvantages is formulated as a function

from a few inclusive integrated components; Availability, Performance and

Quality. Basically, OEE is calculated by multiplying these three components, as

shown below:

(2-3)

Whereas:

1. Availability

Availability accounts the downtime loss, which includes anything that could

stop the production for a long period of time. (Typically a few minutes or

longer). Below is the formula to calculate availability:

π΄π‘£π‘Žπ‘–π‘™π‘Žπ‘π‘–π‘™π‘–π‘‘π‘¦ (𝐴) = π‘‚π‘π‘’π‘Ÿπ‘Žπ‘‘π‘–π‘›π‘” π‘‡π‘–π‘šπ‘’

π‘ƒπ‘™π‘Žπ‘›π‘›π‘’π‘‘ π‘ƒπ‘Ÿπ‘œπ‘‘π‘’π‘π‘‘π‘–π‘œπ‘› π‘‡π‘–π‘šπ‘’ (2-4)

𝑂𝐸𝐸 = π΄π‘£π‘Žπ‘–π‘™π‘Žπ‘π‘–π‘™π‘–π‘‘π‘¦ Γ— π‘ƒπ‘’π‘Ÿπ‘“π‘œπ‘Ÿπ‘šπ‘Žπ‘›π‘π‘’ 𝐸𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑐𝑦 Γ— π‘…π‘Žπ‘‘π‘’ π‘œπ‘“ π‘„π‘’π‘Žπ‘™π‘–π‘‘π‘¦

15

2. Performance

Performance accounts the speed loss, which includes all factor that can cause

the production to run with less than the maximum speed adjusted for running.

π‘ƒπ‘’π‘Ÿπ‘“π‘œπ‘Ÿπ‘šπ‘Žπ‘›π‘π‘’ (𝑃) = π΄π‘π‘‘π‘’π‘Žπ‘™ 𝑂𝑒𝑑𝑝𝑒𝑑÷ π‘‚π‘π‘’π‘Ÿπ‘Žπ‘‘π‘–π‘›π‘” π‘‡π‘–π‘šπ‘’

πΌπ‘‘π‘’π‘Žπ‘™ 𝑅𝑒𝑛 π‘…π‘Žπ‘‘π‘’ (2-5)

3. Quality

Quality accounts the quality loss/ defect, including all the factor that may

cause the product to not qualify from the given standard, this also applies for

product that requires a rework.

π‘„π‘’π‘Žπ‘™π‘–π‘‘π‘¦ = π΄π‘π‘‘π‘’π‘Žπ‘™ π΄π‘šπ‘œπ‘’π‘›π‘‘βˆ’π·π‘’π‘“π‘’π‘π‘‘ π‘Žπ‘šπ‘œπ‘’π‘›π‘‘

π΄π‘π‘‘π‘’π‘Žπ‘™ π‘Žπ‘šπ‘œπ‘’π‘›π‘‘ (2-6)

OEE measures the effect of the 6 big losses, which are (Cudney, 2009)

1. Breakdowns 4. Minor Stoppages

2. Setups and adjustments 5. Quality factors

3. Idling 6. Rework

OEE application can be implemented in various level of manufacturing with

purposes, such as:

1. Benchmarking to measure the early performance in a plant as overall. In this

case the measurement of the current OEE result can be compared to the next

OEE result, hence quantify a level of improvement.

2. An OEE score, which is measured in a line of production, can be used to

compare the performance of the production line in the whole plant, thus

focusing oneself to the worst production line.

3. If the machine operates by itself is the case, an OEE measurement can identify

the bad performance by the machine and then revealed where to focus on the

source of TPM.

16

Table 2.2 OEE Score Comprehension

OEE Score

100% Perfect production

85% World class for discrete manufacturers

60% Fairly typical for discrete manufacturers

40% Not uncommon for manufacturers without TPM or lean programs

Most of the world discrete manufacturers that implement TPM or lean programs

has world class OEE, which is a standard used for comparison and benchmarking

(McKone et al., 1999).

Table 2.3 World Class OEE Score

OEE Factor World Class

Availability 90%

Performance 95%

Quality 99%

OEE 85%

Additionally, besides to identify the equipment true performance, OEE also used as

a decision leverage for buying a new set of equipment. In this case, the company

will take the decision from the capacity of the current equipment until the decision

can be made in terms to fulfil the customer’s demand.

2.3 Machine Reliability

(1) Mean Time to Repair (MTTR)

Mean Time to Repair (MTTR) is the average time of the breakdown equipment

or component reparation while operation. MTTR can be calculated using the

formula below:

𝑀𝑇𝑇𝑅 = π‘‡π‘œπ‘‘π‘Žπ‘™ π‘…π‘’π‘π‘Žπ‘–π‘Ÿ π‘‡π‘–π‘šπ‘’

π‘π‘’π‘šπ‘π‘’π‘Ÿ π‘œπ‘“ πΉπ‘Žπ‘–π‘™π‘’π‘Ÿπ‘’ (2-6)

(2) Mean Time to Failure (MTTF)

Mean Time to Failure is the average time of the next expected failure from a

system or component. In terms for a repairable component, Mean Time to

17

Failure is the component period of time from which its first usage until failure/

breakdown happen. MTTF formula is as follow:

𝑀𝑇𝑇𝐹 = π‘‡π‘œπ‘‘π‘Žπ‘™ π‘ˆπ‘π‘‘π‘–π‘šπ‘’ π‘Žπ‘“π‘‘π‘’π‘Ÿ π‘…π‘’π‘π‘Žπ‘–π‘Ÿ

π‘π‘’π‘šπ‘π‘’π‘Ÿ π‘œπ‘“ πΉπ‘Žπ‘–π‘™π‘’π‘Ÿπ‘’ (2-7)

(3) Mean Time Between Failure (MTBF)

Mean Time Between Failure is the average duration between one component

failure to another. In other words, MTBF shows how reliable the equipment

condition in producing a product. MTBF formula is as follow:

𝑀𝑇𝐡𝐹 = π‘‡π‘–π‘šπ‘’ 𝐡𝑒𝑑𝑀𝑒𝑒𝑛 πΉπ‘Žπ‘–π‘™π‘’π‘Ÿπ‘’

π‘π‘’π‘šπ‘π‘’π‘Ÿ π‘œπ‘“ πΉπ‘Žπ‘–π‘™π‘’π‘Ÿπ‘’

(2-8)

2.4 Distribution Function

2.4.1 Failure Distribution

Failure distribution is a mathematical expression for equipment failure’s age and

pattern. The characteristics of each equipment failure will impact to the applied

approach to test the suitability and to measure the parameter of failure distribution

function.

Commonly, the character from each machine failure is not the same especially if

operates and treated in different environments. An equipment that has the same

characteristics and has been operated in the same condition may also result a time

gap between different failures.

2.4.2 Cumulative Distribution Function

Cumulative distribution function is a function that describes the probability of

failure before time t. The probability of a system or equipment experiencing failure

in operating before time t, is a function from time which mathematically can be

written as follows:

𝐹(𝑑) ∫ 𝑓(𝑦)𝑑𝑑𝑑

0 π‘“π‘œπ‘Ÿ 𝑑 β‰₯ 0 (2-9)

Whereas:

𝐹(𝑑): Cumulative distribution function

18

𝑓(𝑦): Probability density function

𝑑 ∢ time

The ranges of the value of cumulative distribution function lies between 0 ≀𝐹(𝑑) ≀ 1

setting 𝑑 = ∞, then yields F(t) = 1

2.4.3 Reliability Function

Reliability is the probability of a system or component functioning until a certain

amount of time (t) (Ebeling, 1997). The definition of reliability is the probability of

a component operating in a good condition without failure in one period in time (t)

with the set operational condition. Probability density function can be expressed as

such:

𝐹(𝑑) = 𝑃(𝑇 ≀ 𝑑) (2-10)

Whereas:

𝐹(𝑑): The probability of a failure before time T = t (distribution function)

𝑇: Continues random variable that expresses the time of failure

Reliability can be elaborate as follows:

𝑅(𝑑) = 𝑃(𝑇 β‰₯ 𝑑) (2-11)

Whereas:

𝑅(𝑑): The probability that failure will not happen before time (t) or probability of

failure time is bigger or equal to t.

2.4.4 Index of Fit (r)

In terms of determining which distribution to use to calculate the Mean Time to

Failure (MTTF), Mean Time to Repair (MTTR) and reliability, the process that

needs to be done is to find the value of r for each distribution until the biggest value

of r is obtained and later will be tested again according to the distribution

hypothesis.

19

2.5 Failure Distribution

Failure rate is the number of times a component fails and is denoted by Ξ» and the

failure capacity is characterized with Ξ»(t). An organization may not be able to

determine the frequency of equipment failure, but rather be aware and prepare from

the likelihood of the next failure.

(1) Failure Rate Function

Failure rate function is defined as a limit of failure rate with βˆ†π‘‘ β†’ 0, thus instant

failure rate function and failure rate function can be yield as follows:

πœ†(𝑑) = limβˆ†π‘‘+0

βˆ’[R(t+βˆ†π‘‘)βˆ’π‘…(𝑑)]

βˆ†π‘‘.

1

𝑅(𝑑) (2-12)

πœ†(𝑑) = βˆ’π‘‘π‘…(𝑑)

𝑑𝑑.

1

𝑅(𝑑)

πœ†(𝑑) = 𝑓(𝑑)

𝑅(𝑑) π‘“π‘œπ‘Ÿ 𝑑 β‰₯ 0

Whereas

πœ†(𝑑) ∢ Failure rate function

𝑓(𝑑) ∢ Probability density function

𝑅(𝑑) ∢ Reliability function

(2) Increasing Failure Rate

Increasing failure rate Ξ»(t) will change through time from the product experiencing

force. The bathtub curve is a curve that show the increasing failure rate in common

for a product. Generally, failure rate is a system that continuously changing

corresponding to the time given. From an experiment, it can be known that the

failure of a product will follow a pattern such as below:

20

Figure 2.3 Typical Life Cycle Bathtub Curve

Source: No MTBF

According to (Patrick, 2001) every time period has its own unique characteristics

depends on the failure rate, which is:

a. Early Failure

This stage is also known as the wear in period or the running period, signed by the

decreasing failure rate. The failure rate in this phase is also known as the early

failure. The cause could factor from the incorrect design, incorrect usage, wrong

packing, not qualified quality controls, material and labor below standard and many

more.

b. Useful Life Region

This period is signed with the significant increase on the failure rate because the

worsen condition of the current equipment. It is recommended to do a preventive

maintenance if an equipment has reached this phase to anticipate a more fatal

failure.

c. Wear Out Failure

Based on the figure above, it is safe to say that the early failure is related with

Weibull distribution, while the useful life region or the chance failure can fulfill

with Weibull distribution and Exponential distribution. Thus, the wear out failure

period is correlated with Weibull distribution and Lognormal distribution.

21

2.6 Distribution for Measuring Reliability

In this research, the distribution scope used in reliability theory is Weibull

distribution, Normal distribution, Lognormal distribution and Exponential

distribution. The reliability theory uses a continues random variable. However, if

the random variable is discrete then the failure is undefined.

2.6.1 Weibull Distribution

Weibull distribution is widely used for breakdown time data in reliability analysis,

especially to calculate the component’s age, because this distribution can be used

for increasing failure rate and decreasing failure rate. Generally, this distribution is

used for mechanical component of machine.

Table 2.4 Weibull Distribution Shape Parameter Value

Value Failure Rate

0 < 𝛽 < 1 Decreasing Failure Rate

𝛽 = 1 Constant Failure Rate

1 < 𝛽 < 2 Increasing Failure Rate

Curve shape is concave

𝛽 = 2 Linier Failure Rate

Rayleigh Distribution

𝛽 < 2 Increasing Failure Rate

Curve shape is convex

1 < 𝛽 < 2 Increasing Failure Rate

Curve shape is symmetric

Normal Distribution

There are two parameter used in Weibull distribution: which are Ξ² (Beta), the shape

parameter and ΞΈ (Teta), the scale parameter, wherein to assume πœƒ > 0, 𝛽 > 0, 𝑑 β‰₯

0 hence the reliability function obtain from Weibull according to Ebeling (1997) :

Probability Density Function

𝑓(𝑑) = 𝛽

πœƒ(

𝑑

πœƒ)

π›½βˆ’1

𝑒(π‘‘πœƒ

)𝛽

22

(2-13)

Cumulative Distribution Function

𝐹(𝑑) = 1 βˆ’ π‘’βˆ’(π‘‘πœƒ

)𝛽

(2-14)

Reliability Function

𝑅(𝑑) = π‘’βˆ’(π‘‘πœƒ

)𝛽

(2-15)

Weibull Failure Rate Function

πœ†(𝑑) = 𝑓(𝑑)

𝑅(𝑑)=

𝛽

πœƒ(

𝑑

πœƒ) π›½βˆ’1

(2-16)

Cost per Unit of Time

𝐢(𝑑) = (𝐢𝑝 Γ— 𝑅(𝑑) + 𝐢𝑒 [1 βˆ’ 𝑅(𝑑)]

∫ 𝑅(𝑑)𝑑𝑠𝑑

0

)

(2-17)

Whereas:

𝐢𝑝 = Cost of planned replacement (Preventive)

𝐢𝑒 = Cost of unplanned (Corrective)

𝑅(𝑑) = Reliability function

𝑑 = Preventive maintenance time

23

Figure 2.4 Effect of Scale Parameter on Weibull

Source: Weibull.com

The changing values of the shape parameter (Ξ²) shows the failure rate as seen in the

table below. If parameter Ξ² (Beta) affects the failure rate, then parameter ΞΈ (Teta)

affect the mean of the data pattern.

2.6.2 Lognormal Distribution

Lognormal distribution uses two parameters; s the shape parameter and π‘‘π‘šπ‘’π‘‘, the

location parameter as a mean of a distribution failure. This distribution has several

types, thus is not uncommon for data with Weibull distribution compatible with the

Lognormal distribution. Reliability function consist in Lognormal distribution

(Ebeling, 1997) is as follows:

Probability Density Function

𝑓(𝑑) =1

π‘ π‘‘βˆš2πœ‹π‘’ [

1

2𝑠2(𝑙𝑛

𝑑

π‘‘π‘šπ‘’π‘‘)]

(2-18)

Where 𝑠 > 0, π‘‘π‘šπ‘’π‘‘ > 0 π‘Žπ‘›π‘‘ 𝑑 > 0

24

Cumulative Distribution Function

𝐹(𝑑) = πœ™ (1

𝑠𝑙𝑛

𝑑

π‘‘π‘šπ‘’π‘‘

)

(2-19)

Reliability Function

𝑅(𝑑) = 1 βˆ’ 𝐹(𝑑) = 1 βˆ’ βˆ… (1

𝑠𝑙𝑛

𝑑

π‘‘π‘šπ‘’π‘‘

)

(2-20)

Failure Rate Function

πœ†(𝑑) = 𝑓(𝑑)

𝑅(𝑑)=

πœ™ (1𝑠

𝑙𝑛𝑑

π‘‘π‘šπ‘’π‘‘)

𝑠𝑑𝑅(𝑑)

(2-21)

Mean Time To Failure

𝑀𝑇𝑇𝐹 = π‘‘π‘šπ‘’π‘‘. 𝑒

(2-22)

Figure 2.5 Lognormal Distribution Curve

Source: Wikipedia

2.6.3 Normal Distribution

Normal distribution is a widely used distribution function and is suitable for wear-

out phenomena. Where πœ‡ (mean) and 𝜎 (standard deviation) are the distribution

parameters. Since it is still relevant with Lognormal distribution, this distribution is

25

also useful for analyzing Lognormal probability. Reliability function consist in

Normal distribution (Ebeling, 1997) is defined as:

Probability Density Function

𝑓(𝑑) =1

𝜎√2πœ‹π‘’ [

(𝑑 βˆ’ πœ‡)2

2𝜎2]

(2-23)

Where πœ‡ > 0, 𝜎 > 0 π‘Žπ‘›π‘‘ 𝑑 > 0

Cumulative Distribution Function

𝐹(𝑑) = πœ™ (1

𝑠𝑙𝑛

𝑑

π‘‘π‘šπ‘’π‘‘

)

(2-19)

Reliability Function

𝑅(𝑑) = 1 βˆ’ 𝐹(𝑑) = 1 βˆ’ βˆ… (1

𝑠𝑙𝑛

𝑑

π‘‘π‘šπ‘’π‘‘

)

(2-20)

Failure Rate Function

πœ†(𝑑) = 𝑓(𝑑)

𝑅(𝑑)=

πœ™ (1𝑠

𝑙𝑛𝑑

π‘‘π‘šπ‘’π‘‘)

𝑠𝑑𝑅(𝑑)

(2-21)

Mean Time To Failure

𝑀𝑇𝑇𝐹 = πœ‡

(2-22)

26

Figure 2.6 Normal Distribution Curve

2.6.4 Exponential Distribution

Exponential distribution is used for calculating the reliability of a failure

distribution that has constant failure rate. This distribution has failure rate that is

constant to time, in other words the probability of failure is not dependable to the

equipment’s age. Exponential distribution is relatively the easiest distribution to

when conducting an analysis. The parameter used in exponential distribution is Ξ»,

which show the average failure time. The reliability function in the exponential

distribution (Ebeling, 1997) is defined as:

π‘…π‘’π‘™π‘–π‘Žπ‘π‘–π‘™π‘–π‘‘π‘¦ π‘“π‘’π‘›π‘π‘‘π‘–π‘œπ‘›: 𝑅(𝑑) = π‘’βˆ’πœ†π‘‘ (2-16)

Where 𝑑 > 0, πœ† > 0

2.7 Distribution Identification

By collecting data from downtime history, compatibility of the distribution can be

theoretically in 3 processes, such as:

1. Distribution identification, the formula used are included

2. Assumption of the reliability distribution parameter

3. Display distribution data with Goodness of fit test

The Goodness of Fit test is conduct by comparing the null hypothesis (𝐻0) that

stated the failure date is distributed with a certain distribution and the alternative

hypothesis stated the opposite which is the data is not distributed. The statistic

calculation of this test is based on the sample data of time failure. The result of the

27

calculation will be compared with the critical value earned from the table. If the

result of the statistic calculation is smaller than the critical value obtain from the

minitab calculation then 𝐻0 is accepted, which conclude that the failure data follows

a certain distribution. However if the statistic calculation result is bigger than the

critical value, then the alternative hypothesis (𝐻1) is accepted, meaning that the

failure data is not following a distribution.

28

CHAPTER III

RESEARCH METHODOLOGY

3.1 Research Flowchart

The following section determines the methodology used for analyzing this research.

Figure 3.1 Research Flowchart

Initial Observation

Problem Identification

Literature Study

Data Collection and

Analysis

Conclusion and

Recommendation

Initial Observation

Direct observation of production process

in a toy manufacturing industry

Problem Identification

Current problem identification

Problem and objective identification.

Determination of scopes and assumption

Literature Study

Lean Manufacturing

Total Productive Maintenance

Data Collection and Analysis

All information needed for Die Cast

machine analysis

Machine Performance Analysis

Downtime comparison between method

results

Conclusion and Recommendation

Conclusion based on the calculation and

analysis of the research

Recommendation for company and reader

in improvisation and future reesearch or

development.

29

3.1.1 Initial Observation

The observation is conducted in toy manufacturing company, starting by identifying

the problem. An in-depth understanding about the company process and the

problem is important to have an accurate research and solution to the problem. This

research is start by direct observation to current method and determination of the

suitable method that may create an improvement at the end of this research.

The direct observation is through one of Lean method; Gemba. Gemba is observing

in the production line of what is happening. Other than observation through Gemba

in the line, another way to gain deep comprehension of the problem is by going

through the production data; performance report, output report and find the red

string by analyzing the data.

3.1.2 Problem Identification

After collecting all the necessary data. Furthermore, the research objectives are

constructed in order to keep the research on track and can be accomplished on time:

Address one major loss, based on equipment specific OEE & down time data

Identify every performance aspect and decide one of the die cast machine to be

the improvement’s target

Collect detailed information on symptoms of the problem/ main cause in the

chosen die cast machine

Determine the proper method for improvement

Establish a ground understanding of why the failure in die cast machine

Determine the saving cost the company will get by implementing Total

productive maintenance

The assumption of this model is machine A06, which is the subject to be analyzed,

since that it has a higher downtime during 2017 and Total Productive maintenance

has not been applied in the company before.

3.1.3 Literature Study

Literature study is done as a theoritical base from problem solving to related issue

faced by the company. Literature study is also as the basic of this research

30

execution. The literature study is collected from books, journals, and other

resources to analyze the problem and find the solution to answer the questions. The

explanantion of literature study include:

Maintenance management in general

Lean manufacturing concepts, about the common terms and explanation related

about the method used in this research

Total Productive Maintenance (TPM) and its Implementation

3.1.4 Data Collection

In order complete analyze and complete the research, supporting data has been

collected from the lagging indicators, in regards to analyze and improve the future

process.

The collected lagging indicator that will be analyze are:

Process flow

Output

Machine down time & reparations time historical data

Machine OEE performance

3.1.5 Data Analysis

After collecting all the necessary data, the next step is to identify the root cause

using lean manufacturing tools. Firstly, by selecting the most damaging problem

that have a great impact in decreasing the organization performance and afterwards

do the improvement.

The data that will be identified using lean manufacturing tools are:

Identify the root cause analysis

Identify the problem which contribute highly in affecting the availability

Locate the main problem

Determine the right method for the improvements

Compare the company previous and future performance after the

implementation of the proposed improvements.

31

The steps of the procedure in the data analysis are:

1. Analyzing the current production flow process, maintenance method, ouput

part report, downtime report and performance rate and current expenses the

company spent. The information above is essential to support the research

to analyze and identify the real problem and which has greater impact to the

company performance.

2. Through observation, calculation and analyzation, from interview and the

provided data aims to find the proper and suitable maintenance schedule to

reduce the high downtime in the machine.

3. Compare the current reliability performance with the propose reliability

performance. Propose the implementation for the TPM programs so as to

improve the company overall performance. After 8 months of observation,

the OEE of the observed area before and after TPM Implementations is

being compared. If the improvements succeeded, the company should

develop SOP (Standard Operation Procedure) and WI (Work Instruction) in

order to sustain the good practices.

3.1.6 Conclusion and Recommendation

The last phase of this research consist of conclusion of the improvement. It refers

to the research objectives, how optimal the method achive the objectives. In

addition, the recommendation also includes in this phase. The recommendation is

addressed for both the company and the readers. It is recommended that the

company makes a continuous improvement since there is still limitations in doing

this research.

32

3.2 Detail Framework

In general, the whole research is visually summed up through a brief framework.

Figure 3.2 Research Framework

Preventive Maintenance

Schedule

Initial Observation

Machine Downtime

Problem Identification

Reliability Calculation

Data Collection

OEE performance

Component Failure Data

Time to Failure (TTF) Time to Repair (TTR)

Calculate MTTR and MTTF

Break Down Maintenance Cost

Calculation

Comparison Reliability,

Maintenance Cost

Conclusion &

Recommendation

TPM Programs and

Implementation

OEE Comparison Before

and After TPM

33

CHAPTER IV

DATA COLLECTION AND ANALYSIS

4.1 Initial Observation

The research is done in a company based in Indonesia, Cikarang, specifically in Die

Cast machine, the core activity of the production in the company. Generally, the

company has two main processes; Die Cast and Plastic Injection Molding. Plastic

Injection Molding machine produces the car’s body, interior, wheels and chassis

along with its designated colors using resin as its main material. Meanwhile, the

Die Cast machine, producer of the toy car’s body and chassis, uses Zinc Aluminum

as its raw material. However, die cast process needs to undergo a more complex

sequence of production, hence, the complexity of the flow process makes the die

cast toy car more expensive than the plastic ones. Therefore, improving the

production efficiency at die cast machine will impact greatly to products sales.

4.1.1 Machine Description

The figure below is the die cast machine used in the company production line. The

company has 26 identical die cast machines, but for now only 15 are actively

running. As a new factory, the company choose die cast and several other machines

by referring to other factories that produce the same products, HW toy cars. The die

cast machine is believed to have a high safety standard, low defective rate, high

reliability and operating efficiencies.

Figure 4.1 Die Cast Machine in Toy Manufacturing Company

34

Figure 4.2 4-UP Output Using Mold Combination

The die cast machines use two types of mold, the 2-UP and the 4-UP. The 2-UP

mold means the mold has 2 cavities, which a single shot from the machine can

produce 2 parts, while the 4-UP mold can produce 4 up to 8 different parts. The

machines that uses 2-UP has a cycle time of 6-7 seconds/shot and the 4-UP machine

has a cycle time of 8-10 second/shot.

Nevertheless, currently die cast machine in the company that uses 4-UP only use

the mold with 4 cavities. The die cast machine that is being observed in this research

uses 4-UP molds. An example of a 4-UP mold output is shown in Figure 4.2 below.

35

4.1.2 Flow Process Die Cast and Plastic Injection Molding

Figure 4.12 below is the complete summary of Die Cast process using a flow

process chart, which commonly used as a symbolic representation of process

activities in the work piece. Die cast process undergo a longer process than plastic

injection molding. The plastic injection molding process is a lot shorter, after the

machine produce the part, it will henceforth to the tampo process. And if it, the die

cast parts, passes the QC inspection without a flash, and it will go forward to the

assembly and packout.

Figure 4.3 Flow Process of Die Cast

Nevertheless, for the die cast part (body/chassis) is formed from the die cast

machine and will be degated (separated) from the runner by an auto degating

machine. Afterwards all the part will be put inside an air pocket chamber to separate

the air pocket that still sticks with the part and will be smoothened with media

stones in wet tumbling with a massive vibration to create a friction between the

Raw material ingot

(Zn Al) store

Furnace, high

pressure die casting

machine

Auto-Degating

Air Pocket

Separator

Wet Tumbling

QC

Inspection Reclaim Trimming

ESP

Tampo

Plating

Finished Goods

store

Assembly &

Packout

Delivery

Not Pass Pass

36

stones to the die casted parts. The part will be checked by the quality control, if the

product is defect it will be compile and later will be processed in reclaim, which is

an area to reform the part by melting it and form it back into a bar of ingot (die cast

raw material ZnAl). However, if it passes the QC, it will continue to Electrostatic

painting, where the parts will be painted according to each of the design.

Additionally, plating is a process to make the die cast part look shiny and clean.

After those process, the die cast part will be delivered to Tampo, for the cars

decoration and painting and later will be assemble in Assembly and Packout area

and will be stored in the finished goods store which later will be distributed to the

company’s customers.

4.2 Data Collection

The data collection in this research generally consist of a brief summary of the

company machines data and the problem that will be resolved.

4.2.1 Current Die Cast Machine Reliability

Current machine reliability performance counted from the percentage of Overall

Equipment Effectiveness (OEE) and the number of downtime occurred. Here are

details of current system analysis:

4.2.1.1 Overall Equipment Effectiveness

OEE takes into those three metrics above which are availability, performance and

quality to reduce six big losses in production process. Therefore, to accurately track

the progress of the die cast area, OEE is used to measure die cast achievement

before TPM improvement implementation:

𝑂𝐸𝐸= π΄π‘£π‘Žπ‘–π‘™π‘Žπ‘π‘–π‘™π‘–π‘‘π‘¦ Γ— π‘ƒπ‘’π‘Ÿπ‘“π‘œπ‘Ÿπ‘šπ‘Žπ‘›π‘π‘’ Γ— π‘„π‘’π‘Žπ‘™π‘–π‘‘π‘¦ (4-1)

𝑂𝐸𝐸= 75% Γ— 91% Γ— 99%

𝑂𝐸𝐸= 68%

OEE recognizes the rate of arranged generation time that is really profitable. Figure

4.4 shows the previous OEE during research before TPM implementation, and die

cast area achieved only 68.37%. Based on the research result in calculating

availability, performance, quality and OEE score above, it showed that the track

37

record of machines’ reliability is quite good, but based on industry standards for

discrete manufacturing and strive for world class result, 60% OEE is fairly typical

for discrete manufacturers, but indicates there is room for improvement.

Below is the bar chart displaying the OEE performance from all the production area

in the company:

Figure 4.4 OEE Trend in Production Area for August-December 2017

The problem in Die Cast began to surface after the OEE percentage of all area were

shown. In the figure 4.5 below, shown that the OEE performance in Die cast, in the

past 5 months constantly below the goal and lower than the other primary process

performance; the Plastic injection molding. The plastic injection molding OEE

percentage scored 80% in the past 5 months, and so did Vacuum Forming (VUM)

81%, OMC and A&P, scored 82% and 83% respectively. The true reason behind

die cast low OEE percentage is because of the frequent and unexpected machine

downtime occurred in the die cast machines.

80%

68%

81%

73% 71%

77%82% 83%

0.00%

10.00%

20.00%

30.00%

40.00%

50.00%

60.00%

70.00%

80.00%

90.00%

100.00%

PIM Die

Cast

VUM ESP Barbell Tampo OMC A&P

OEE

Availability

Performance

Quality

38

Figure 4.5 Primary Process OEE Trends for August-December 2017

4.2.1.2 Current Machine Downtime

The research was conducted in die casting machine in production area. All the die

cast machine have the same characteristics. Thus, the research conducted in all the

machine as sample. Data collection are taken based on the machine components

that are having component failure to disrupt production process.

Based on the downtime reports in die cast area, below are the five biggest issues

that caused downtime in production line. Below is the following explanation about

each failure:

1. Material Leaking (Nozzle Failure)

Material leaking is when a small amount of liquid zinc, drool to the cover

of half die. This phenomenon happens when there is a gap between nozzle

and the sprue bush. Generally, the nozzle is supposed to be change every

100,000 shots, which means it needs to be replace weekly. If not replace

regularly, nozzle leaking can cause a serious fire hazard.

2. Nozzle Damage (Nozzle Failure)

Nozzle damaged occurs when the nozzle and the sprue bush is not in one

alignment. Additionally, material nozzle corrosive from the heat of iron

contact with aluminum, which caused a reaction towards the nozzle, causing

the nozzle to damage.

39

3. Hose Holder Leaking (Gripper Failure)

The hose holder has friction with the machine movements. This

phenomenon happens due to the improper placement of the hose holder. The

hose holder is usually replaced every week or every 150,000 shots.

4. Nozzle Stuck (Nozzle Failure)

When the nozzle temperature is too low/ heat loss to the sprue bush causing

the nozzle to stuck. To prevent fire hazard, the nozzle is supposed to be

change every 100,000 shots, which means it needs to be replace weekly.

5. Water Cooling Mold Leaking (Nipple Failure)

Water cooling mold leaks when the mold hose had rough friction with the

machine movement, due to the improper installation of the water cooling

nipple. The nipple needs to be replace every 450,000 shots, which means it

needs to be replace more than less every 2 weeks.

Table 4.1 Machine Failure Issues and Occurrences

No Issue Frequency Cumulative

Frequency

Frequency

Percentage Cumulative

Percentage

1 Nozzle Leaking 95 95 34% 34%

2 Hose Holder Leaking 82 177 29% 63%

3

Water Cooling

Holder Leaking 54 231 19% 82%

4 Nozzle Damaged 35 266 12% 94%

5 Nozzle Stuck 16 282 6% 100%

Total 282 282 100% 100%

The failure data that has been collected of the die cast machines for the research,

has been analyzed and identified the five critical issues and the total occurrences in

the available die cast machine around the 5 months’ period, which is 282 machine

failure occurrences. Nozzle leaking occurs the most often in the past five months,

followed by hose holder leaking 82 occurrences, water cooling holder leaking 54

occurrences and the rest of the 51 occurrences are from Nozzle damaged and nozzle

stuck, in that order.

40

Figure 4.6 Bar Chart of Machine Downtime Issues

The bar chart above identifies which breakdowns are the most critical to the

machine availability performance. Nozzle leaking, nozzle damaged and nozzle

stuck basically has the same solution, which is replacing the nozzle component.

Nozzle and gripper are classified as one of the critical component in the die cast

machine. Hence, the total cost of repair and, component replacement cost and the

loss of production per hour will be accounted in this research. The critical

components will be calculated to determine the preventive maintenance schedule

which will be focused on these five big issues.

Furthermore, the data obtained in this research is also from machine downtime from

the five big issues/failures. This data can identify which issue causes the longest

downtime in die cast area.

Table 4.2 Machine’s Downtime Duration

No Issue Occurrences Downtime

(hour)

1 Nozzle Leaking 95 63.7

2 Hose Holder Leaking 82 54.7

3 Water Cooling Holder Leaking 54 35.1

4 Nozzle Damaged 16 10.2

5 Nozzle Stuck 35 21.9

Total 282 185.6

41

From Table 4.2 above and the Pareto chart below, the same five issues are also the

highest downtime contributor based on downtime hour percentage. Nozzle leaking,

hose holder leaking and the rest are still placing in the same rank as the biggest

occurrences and the downtime contributor.

Figure 4.7 Pareto Chart of Machine Downtime

The nozzle leaking contributes the longest downtime by 34% out of a total of 3,824

minutes, which equivalent to 63.7 hours. The second biggest downtime is 29% by

hose holder leaking. This failure managed to contribute 3,285 minutes which

equivalent to 54.75 hours. The third is the water cooling holder leaking, the

replacement of the component took 2,108 minutes in five months overall. This

failure downtime percentage is 19%. Basically, the more often the failure occurs,

the longer time the downtime period will become. These issues will be further

analyzed to make a subtler preventive maintenance schedule to reduce downtime.

In terms to apply TPM, among many, the company should only choose one critical

equipment that causes the highest number of downtime to the inflicted area, to be

the focus or the subject of the study (Brophy, 2013). The Pareto chart below shows

the number of frequency of machine failure from all the die cast machine regarding

to the top 5 failures only.

42

Figure 4.8 Pareto Chart of Die Cast Machine Failure Occurrences

Hence, after a deep-dived analysis through die cast downtime report, machine A06

appears to have the highest number of machine breakdown regarding to the top 5

critical failure occurrences, with a total of 55 occurrences. The break down detail

of the 55 occurrences is shown in table 4.4 below. Additionally, A06 is currently

the only die cast machine that runs a 4-UP mold, which produces more output than

the other die cast machine that runs with a 2-UP mold. As mentioned before, a 4-

UP mold can produce 4 up to 8 parts in a single shot. Therefore, machine A06

components are is more likely to wear out than the other machines, thus higher

maintenance is needed for this particular machine. This research will be focused on

machine A06.

Table 4.3 Detail of A06 Machine Failures and Frequency

No Failure Frequency

1 Nozzle Leaking 13

2 Nozzle Damage 6

3 Nozzle Stuck 3

4 Hose Holder Leaking 21

5 Water Cooling Mold Leaking 11

Table 4.3 break downs the 55 occurrences that has happened in machine A06 from

August-December 2017. Nozzle has 3 types of failures, leaking, damage and stuck.

43

Leaking is the most often to occur, among the other nozzle failure with the

frequency of 13 occurrences.

4.2.1.3 Functional Hazard Analysis

Functional hazard analysis helps to identify the component functions and

abnormalities, from any potential safety hazards, health risk or malfunction hazards.

Functional hazard analysis is also for assessing the probability of failure (machine

or human error) if not being identified and handle immediately, could lead to some

greater consequences. In this research, there are 3 type of component failures in die

cast machine that will be discussed, such as nozzle leaking, nozzle damage, and

nozzle stuck. The nozzle failure will be the highlight because it is the most critical

component among the 3 components discussed in this research. Nozzle failure has

the consequences of violating safety hazard and may develop into fire hazard if not

being maintain properly.

Die cast machine has a back and forth movement and there are some

components that are greatly affected by this intensive impact, and one of it is

the nozzle. The nozzle in the die cast machine, has the function to control the

direction or the flow of the metal liquid (zinc). Whenever the nozzle collided

with the mold holder, it creates a friction. The harder the collision, the bigger

the friction to the nozzle, causing the tip of the nozzle to erode. The example

of a condition of a new nozzle and the failed nozzle is illustrated in figure 4.9

below.

44

Figure 4.9 Top View of Nozzle Initial Condition and Nozzle Failure Condition

The figure above shows the difference between a new nozzle that has not been

installed to the machine (left) and the nozzle that has aged 99,500 shots, which

has been experiencing leaking because of its distorted and eroded edges that

caused the metal liquid to leaked from the gaps of the tip or the edges. Nozzle

leaking could lead to a fire hazard if not immediately identify and take action.

According to the die cast process engineer, the tip of the nozzle is supposed to

have a conical shape and have a precise diameter. The nozzle has a lifetime of

an approximately 100,000 shots, which usually last for 7 days long. The

material of the nozzle is not to be thicker than the mold holder, otherwise it

would damage the holder, which could lead to greater consequences. A nozzle

leaking component could lead to a nozzle damage, if not immediately identify

and take action. The term damage in nozzle damage means that there is a crack

or a gap on the tip of the nozzle. Nozzle damage can occur because of the

excessive pressure from the injection of the metal liquid and the impact of the

holder. It can also occur if it was dropped or scratched during installation or

cleaning. Nozzle damage also have the consequence of fire hazard, considering

its condition is worse than nozzle leaking.

45

Figure 4.10 Side View of Nozzle Initial Condition and Nozzle Failure Condition

There are some factors that can lead to a nozzle stuck, such as the temperature

and clogging. A good nozzle needs to have the same temperature as the

machine. A normal temperature of die cast machine is around 420 Celsius, from

a range of 390-480 Celsius. Therefore, nozzle replacement took 10-15 minutes

long for heating up the nozzle, to have the same temperature as the machine.

Nozzle stuck happens when the nozzle has different temperature (colder) with

the machine, causing the sprue stuck to the mold, which creates a leftover

frozen zinc covering the nozzle tip. This phenomenon can be identified by the

loud impact noises from the mold crashing to the sprue. If this failure is not

handle immediately, it could lead to zinc flooding (splash), where the output or

the material to exit randomly, not at its designated exit. Zinc flooding opens

the possibility of the output to vault, risking the operator to be in contact with

hot material, if the cover of the machine is not closed.

4.3 Data Calculation

4.3.1 Machine Reliability

This research will use Total Productive Maintenance to find the failure time of

machine’s component. The result will be used to propose preventive maintenance

schedule to the company management. Preventive maintenance schedule will be

very useful for the company in order to reduce downtime.

46

4.3.1.1 Current Machine OEE

TPM uses OEE as a quantitative metric for measuring the productivity in

manufacturing operations. OEE helps to focus on the potential of a process and

highlight the previous obscured problems. According to Jeong & Philips (2001),

OEE acts as the core metric for measuring the success of TPM implementation

program. Nevertheless, before the research can identify the percentage value of

three metrics; availability, performance and quality, it needs to calculate the

supporting data taken from the output report.

Table 4.4 Output Report for 28 August 2017

TT

Bri

ef

-ing

5S AT

Total

Breakdo

wn Time

OT

Std.

Outpu

t

Act.

Output Reject G/O

34 40 40 32.67 584 22.93 15,543 15,150 130 15,020

Below is the detail calculation of an example taken from appendix 1, Machine A06

on 28 August 2017, shift 1.

4-UP Available Time (AT) = π‘‡π‘œπ‘‘π‘Žπ‘™ π‘‡π‘–π‘šπ‘’ βˆ’ (π΅π‘Ÿπ‘–π‘’π‘“π‘–π‘›π‘” +5𝑆

60 π‘šπ‘–π‘›)

4-UP Available Time (AT) = 34 β„Žπ‘œπ‘’π‘Ÿ βˆ’ (40 π‘šπ‘–π‘› +40 π‘šπ‘–π‘›

60 π‘šπ‘–π‘›)

4-UP Available Time (AT) = 34 β„Žπ‘œπ‘’π‘Ÿ βˆ’ (80 π‘šπ‘–π‘›

60 π‘šπ‘–π‘›)

4-UP Available Time (AT) = 34 β„Žπ‘œπ‘’π‘Ÿ βˆ’ (1.3 β„Žπ‘œπ‘’π‘Ÿ)

4-UP Available Time (AT) = πŸ‘πŸ. πŸ”πŸ• 𝒉𝒐𝒖𝒓s

Since the machine uses a 4-UP mold, that produces 4 output in a single shot, the

company, by default, multiplied every calculation of time by 4, hence to find the

actual available time for 4-UP is by dividing it back by 4, as the following below:

Actual Available Time (AT) = (32 β„Žπ‘œπ‘’π‘Ÿ

4)

47

Actual Available Time (AT) = 8 β„Žπ‘œπ‘’π‘Ÿs

4-UP Operating Time (OT) = π΄π‘£π‘Žπ‘–π‘™π‘Žπ‘π‘™π‘’ π‘‡π‘–π‘šπ‘’ βˆ’ (π‘‡π‘œπ‘‘π‘Žπ‘™ π΅π‘Ÿπ‘’π‘Žπ‘˜π‘‘π‘œπ‘€π‘› π‘‘π‘–π‘šπ‘’

60 π‘šπ‘–π‘›)

4-UP Operating Time (OT) = 32.67 β„Žπ‘œπ‘’π‘Ÿ βˆ’ (584 π‘šπ‘–π‘›

60 π‘šπ‘–π‘›)

4-UP Operating Time (OT) = 32.67 β„Žπ‘œπ‘’π‘Ÿ βˆ’ 9.73 hour

4-UP Operating Time (OT) = 𝟐𝟐. πŸ—πŸ‘ hour

Since the machine uses a 4-UP mold, that produces 4 output in a single shot, the

company, by default. multiplied every calculation of time by 4, hence to find the

actual operating time for 4-UP is by dividing it back by 4, as the following below:

Actual Operating Time (OT) = (22.93 β„Žπ‘œπ‘’π‘Ÿ

4)

Actual Operating Time (OT) = 5.73 β„Žπ‘œπ‘’π‘Ÿs

The company will use the 22.93 hours as the operating time, because it represents

the 4 output produced. The purpose of the calculation above is only to inform the

readers about the company’s calculation.

Good Output (G/O) = π΄π‘π‘‘π‘’π‘Žπ‘™ 𝑂𝑒𝑑𝑝𝑒𝑑 βˆ’ 𝑅𝑒𝑗𝑐𝑒𝑐𝑑

Good Output (G/O) = 15,150 π‘π‘Žπ‘Ÿπ‘‘ βˆ’ 130 π‘π‘Žπ‘Ÿπ‘‘

Good Output (G/O) = πŸπŸ“, 𝟎𝟐𝟎 𝒑𝒂𝒓𝒕s

After the QC inspects the produced output, they will report and input the number

of reject parts to the output report. In terms of the output calculation, the company

did not multiply the produced parts by 4, but rather as is actual value, which is

15020 of good parts.

Variance (Var) = π΄π‘π‘‘π‘’π‘Žπ‘™ 𝑂𝑒𝑑𝑝𝑒𝑑 βˆ’ π‘†π‘‘π‘Žπ‘›π‘‘π‘Žπ‘Ÿπ‘‘ π‘œπ‘’π‘‘π‘π‘’π‘‘

Variance (Var) = 15150 π‘π‘Žπ‘Ÿπ‘‘ βˆ’ 15,543 π‘π‘Žπ‘Ÿπ‘‘

Variance (Var) = βˆ’πŸ‘πŸ—πŸ‘ 𝒑𝒂𝒓𝒕𝒔

48

The term variance in this research is actually the difference of the actual output

compare to the standard output, in purpose to inform the reader whether the machine

has achieved the given target (the standard output) or not.

Availability = (π‘‚π‘π‘’π‘Ÿπ‘Žπ‘‘π‘–π‘›π‘” π‘‡π‘–π‘šπ‘’

π΄π‘£π‘Žπ‘–π‘™π‘Žπ‘π‘™π‘’ π‘‡π‘–π‘šπ‘’ ) Γ— 100%

Availability = (22.93 β„Žπ‘œπ‘’π‘Ÿ

32.67 β„Žπ‘œπ‘’π‘Ÿ ) Γ— 100%

Availability = (0.702) Γ— 100%

Availability = πŸ•πŸŽ. 𝟐%

Performance Calculation

π‘ƒπ‘’π‘Ÿπ‘“π‘œπ‘Ÿπ‘šπ‘Žπ‘›π‘π‘’ = (π΄π‘π‘‘π‘’π‘Žπ‘™ 𝑂𝑒𝑑𝑝𝑒𝑑

π‘†π‘‘π‘Žπ‘›π‘‘π‘Žπ‘Ÿπ‘‘ π‘œπ‘’π‘‘π‘π‘’π‘‘ ) Γ— 100%

π‘ƒπ‘’π‘Ÿπ‘“π‘œπ‘Ÿπ‘šπ‘Žπ‘›π‘π‘’ = (15,150

15,543) Γ— 100%

π‘ƒπ‘’π‘Ÿπ‘“π‘œπ‘Ÿπ‘šπ‘Žπ‘›π‘π‘’ = (15,150

15,543) Γ— 100%

π‘ƒπ‘’π‘Ÿπ‘“π‘œπ‘Ÿπ‘šπ‘Žπ‘›π‘π‘’ = (15,150

15,543) Γ— 100%

π‘ƒπ‘’π‘Ÿπ‘“π‘œπ‘Ÿπ‘šπ‘Žπ‘›π‘π‘’ = (0.975) Γ— 100%

π‘·π’†π’“π’‡π’π’“π’Žπ’‚π’π’„π’† = πŸ—πŸ•. πŸ“%

Quality = (πΊπ‘œπ‘œπ‘‘ 𝑂𝑒𝑑𝑝𝑒𝑑

π΄π‘π‘‘π‘’π‘Žπ‘™ π‘œπ‘’π‘‘π‘π‘’π‘‘ ) Γ— 100%

Quality = (15,020

15,150 ) Γ— 100%

Quality = (15,020

15,150 ) Γ— 100%

Quality = (0.991) Γ— 100%

Quality = πŸ—πŸ—. 𝟏%

Table 4.5 OEE Calculation Result

Availability Performance Quality OEE

70.2% 97.5% 99.1% 67.8%

49

After each metric has been calculated, the next step is to find the OEE percentage,

by multiplying the three metrics together, which yields to:

OEE = π΄π‘£π‘Žπ‘–π‘™π‘Žπ‘π‘–π‘™π‘–π‘‘π‘¦ Γ— π‘ƒπ‘’π‘Ÿπ‘“π‘œπ‘Ÿπ‘šπ‘Žπ‘›π‘π‘’ Γ— π‘„π‘’π‘Žπ‘™π‘–π‘‘π‘¦

OEE = 70.2% Γ— 97.5% Γ— 99.1%

OEE = 67.8%

The following table 4.6 is the OEE trend of Machine A06 from August 2017-

December 2017. In table 4.6, the values shown in each of the metrics (availability,

performance and quality) are actually the average value of the data in the whole

month.

Table 4.6 OEE Trend of Machine A06 for August-December 2017

Month Availability Performance Quality OEE

August 69.5% 80.3% 99.6% 55.5%

September 694% 86.7% 99.0% 59.6%

October 62.7% 78.0% 99.3% 48.6%

November 65,8% 80.6% 99.2% 52.7%

December 64.3% 86.5% 99.3% 55.3%

66.3% 82.4% 99.3% 54.3%

It can be seen from the Quality column, machine A06 achieved an impeccable score

on the quality, which has an average of 99% of good parts, but due to its relatively

low availability in the past 5 months, which average is 66%, machine A06 only

managed to score 54% on the overall OEE. The long period of downtime is also

affecting the performance, causing speed loss and thus the performance has an

overall average percentage of 82%. This phenomenon is shown in the figure below,

especially in October where the performance significantly dropped to 78% due to

its low availability.

50

Figure 4.11 Line Chart of Machine A06 OEE Trend for August-December 2017

4.3.1.2 Failure Data of Machine

As mentioned before, the machine’s breakdown and component failure data was

obtained from August 2017 until December 2017. The research becomes more

focused into the 3 critical components which failure occurs frequently than other

components. The table 4.7 below shows the occurrence dates of the failure of nozzle

(nozzle leaking, nozzle damage and nozzle stuck). This table also shows the period

of time of when the failure starts and downtime finish. Regarding to this failure, the

component that needs to be replaced is the nozzle.

This research only focus on component replacement. Replacement activity, in

maintenance term, is when a component of a machine is worn out or broken and

thus cannot be repaired, the mechanic will come to fix the machine by changing or

replacing the component into a new one. Nevertheless, repairing is an activity that

mainly focus on fixing a component through setting or adjustment without the need

to change any of the component.

85%

55.50%59.60%

48.60%52.70%

55.30%

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

August September October November December

A06 Die Cast OEE Trend

Goal OEE

51

Table 4.7 Failure Time and Repair Finish Time of Nozzle Failure from August-

December 2017

Start Failure Finish Failure Duration

(min)

TTR

(hour)

TTF

(hour) Date Time Date Time

03/08/2017 0:05 03/08/2017 0:50 45 0.75 N/A

12/08/2017 4:00 12/08/2017 4:55 55 0.92 219

18/08/2017 5:20 18/08/2017 6:23 63 1.05 144

25/08/2017 6:21 25/08/2017 7:27 66 1.10 167

31/08/2017 7:25 31/08/2017 8:17 52 0.87 143

06/09/2017 2:20 06/09/2017 2:58 38 0.63 138

15/09/2017 13:13 15/09/2017 13:57 44 0.73 226

23/09/2017 4:30 23/09/2017 5:42 72 1.20 158

30/09/2017 16:42 30/09/2017 17:50 68 1.13 179

04/10/2017 0:07 04/10/2017 0:50 43 0.72 78

13/10/2017 8:01 13/10/2017 8:41 40 0.67 223

19/10/2017 1:35 19/10/2017 2:19 44 0.73 136

25/10/2017 13:03 25/10/2017 13:57 54 0.90 154

04/11/2017 0:14 04/11/2017 1:17 63 1.05 202

09/11/2017 23:00 09/11/2017 23:51 51 0.85 141

17/11/2017 22:41 17/11/2017 23:32 51 0.85 166

25/11/2017 22:30 25/11/2017 23:05 35 0.58 190

02/12/2017 21:10 02/12/2017 22:18 68 1.13 166

08/12/2017 20:02 08/12/2017 20:47 45 0.75 141

13/12/2017 19:52 13/12/2017 20:30 38 0.63 119

22/12/2017 19:02 22/12/2017 19:54 52 0.87 214

30/12/2017 18:24 30/12/2018 19:20 56 0.93 190

The table above also shares the information of the Time to Repair (TTR) and Time

to Failure (TTF), generated from the start failure and finish failure, time and date.

TTR is the time or duration needed to repair a component or machine which has

failure while operating. In the TTR column, the three longest time to replace

occurred in September 23, 30, and December 2. The TTF column describes the

period of time from a good condition unto the next failure occur.

Below is the example of detail calculation of TTR and TTF for Nozzle Failure

replacement activity taken from September 23, 2017:

Since the company never record the waiting time data, thus the research

assumed the duration of the Time to Repair is the same with the duration of

the breakdown time. The machine started to repair at 04.30 AM and finished

52

at 05:42 AM, hence the duration is 72 minutes, (05:42:00 – 04:30:00 = 72

minutes) which is also equal to 1.2 hour.

Time to failure is the period of time from a good condition unto the next

failure occur. The machine started to operate again after being maintain on

September 15 at 13:57 PM, then the nozzle failure occurs again on

September 23 at 04.30 AM. The TTF calculation is as follows:

(23 September 2017, 04.30 AM – 15 September 2017, 13:57 PM) and the

result of the subtraction is divided by 60, to convert the unit from minute to

hour, which yield the time to failure of nozzle failure to 158 hours.

Table 4.8 Failure Time and Repair Finish Time of Hose Holder Leaking Failure

from August-December 2017

Start Failure Finish Failure Duration

(min)

TTR

(hour)

TTF

(hour) Date Time Date Time

08/08/2017 13:12 08/08/2017 13:52 40 0,67 NA

14/08/2017 4:20 14/08/2017 5:28 68 1,13 134

22/08/2017 12:19 22/08/2017 13:03 44 0,73 198

29/08/2017 6:06 29/08/2017 6:47 41 0,68 161

04/09/2017 15:30 04/09/2017 16:20 50 0,83 152

12/09/2017 13:28 12/09/2017 14:26 58 0,97 189

20/09/2017 8:25 20/09/2017 9:11 46 0,77 185

27/09/2017 7:30 27/09/2017 8:15 45 0,75 166

03/10/2017 6:05 03/10/2017 6:37 32 0,53 141

10/10/2017 8:31 10/10/2017 9:18 47 0,78 169

15/10/2017 8:10 15/10/2017 8:55 45 0,75 118

23/10/2017 0:20 23/10/2017 1:25 65 1,08 183

31/10/2017 3:04 31/10/2017 4:01 57 0,95 193

06/11/2017 7:05 06/11/2017 7:50 45 0,75 147

14/11/2017 8:31 14/11/2017 9:05 34 0,57 192

20/11/2017 13:55 20/11/2017 14:52 57 0,95 148

28/11/2017 9:35 28/11/2017 10:19 44 0,73 186

05/12/2017 7:05 05/12/2017 7:40 35 0,58 164

10/12/2017 5:11 10/12/2017 6:00 49 0,82 117

18/12/2017 5:57 18/12/2017 6:45 48 0,80 191

25/12/2017 5:18 25/12/2017 5:58 40 0,67 166

Table 4.6 above shows the information of hose holder failure’s downtime hours,

from start until finish period. The data above is taken from the downtime report

53

from the period of August 2017-December 2017. The component in this failure that

require to be replace is the gripper.

The table above also shares information of the Time to Repair and Time to Failure,

which is generated from the start failure and finish failure, time and date. TTR is

the time or duration needed to repair a component or machine which has failure

while operating. In the TTR column, the longest time to repair and replace were

occurred in August 14, September 12 and October 23, these period of occurrences

took longer than others. The TTF column describes the period of time from a good

condition unto the next failure occur. The value of the TTF is relatively various,

even though generally it occurs every 7 days, the downtime could happen less or

more than 7 days. Therefore, the TTF can be used to design a preventive

maintenance schedule in order to determine the suitable time for the machine to be

maintain. The formula of TTR and TTF is attached in Chapter 2.

Below is the example of detail calculation of TTR and TTF for hose holder failure

on August 14, 2017:

Since the company never record the waiting time data, thus the research

assumed the duration of the Time to Repair is the same with the duration of

the breakdown time. The machine started to repair at 04.20 AM and finished

at 05:28 AM, hence the duration is 68 minutes, (05:28:00 – 04:20:00 = 68

minutes) which is also equal to 1.13 hour.

Time to failure is the period of time from a good condition unto the next

failure occur. The machine started to operate again after being maintain on

August 8 at 13:52 PM, then the nozzle failure occurs again on August 14 at

04.20 AM. The TTF calculation is as follows:

(14 August 2017, 04.20 AM – 8 August 2017, 13:52 PM) and the result of

the subtraction is divided by 60, to convert the unit from minute to hour,

which yield the time to failure of nozzle failure to 134 hours.

54

Table 4.9 Failure Time and Repair Finish Time of Water Cooling Holder Failure

from September-December 2017

Start Failure Finish Failure Duration

(min)

TTR

(hr)

TTF

(hr) Date Time Date Time

8/5/2017 3:10 8/5/2017 3:44 34 0.57 NA

8/19/2017 14:58 8/19/2017 15:24 26 0.43 347

9/1/2017 15:40 9/1/2017 16:00 20 0.33 312

9/13/2017 11:33 9/13/2017 11:57 24 0.40 283

9/30/2017 13:06 9/30/2017 13:38 32 0.53 409

10/14/2017 5:12 10/14/2017 5:48 36 0.60 327

10/24/2017 13:28 10/24/2017 13:50 22 0.37 247

11/10/2017 5:10 11/10/2017 5:50 40 0.67 399

11/24/2017 7:20 11/24/2017 7:51 31 0.52 337

12/4/2017 6:18 12/4/2017 6:48 30 0.50 238

12/20/2017 0:40 12/22/2017 1:02 22 0.37 377

Table 4.5 above shows the information of water cooling holder failure’s downtime

hours, from start until finish period. The data above is taken from the downtime

report from the period of August 2017-December 2017. The component in this

failure that require to be replace is the nipple.

The table above also shares information of the Time to Repair and Time to Failure,

which is generated from the start failure and finish failure, time and date. TTR is

the time or duration needed to repair a component or machine which has failure

while operating. In the TTR column, the longest time to repair and replace occurred

in August 5, October 14 and November 10, these period of occurrences took longer

than others. The TTF column describes the period of time from a good condition

unto the next failure occur. The value of the TTF is relatively various, even though

generally it occurs every 14 days, the downtime could happen less or more than 7

days. Therefore, the TTF can be used to design a preventive maintenance schedule

in order to determine the suitable time for the machine to be maintain. The formula

of TTR and TTF is attached in Chapter 2.

Below is the example of detail calculation of TTR and TTF for water cooling holder

leaking replacement activity taken from November 10, 2017:

55

The company did not record the waiting time data, thus the research

assumed the duration of the time to repair is the same with the duration of

the breakdown time. The machine started to repair at 05.10 AM and finished

at 05:50 AM, hence the duration is 40 minutes, (05:50:00 – 05:10:00 = 40

minutes) which is also equal to 0.67 hour.

Time to failure is the period of time from a good condition unto the next

failure occur. The machine started to operate again after being maintain on

October 24 at 13:50 PM, then the nozzle failure occurs again on November

10 at 05.10 AM. The TTF calculation is as follows:

(10 November, 05:10 AM– 24 October 2017, 13:50 PM) and the result of

the subtraction is divided by 60, to convert the unit from minute to hour,

which yield the time to failure of nozzle failure to 399 hours.

4.3.2 Calculation of Mean Time to Repair (MTTR) and Meant Time to Failure

(MTTF)

Mean Time to Repair (MTTR) is an average time which needed to repair a

component or machine which has failure while operation. Based on the distribution

identification, each failure has its own distribution which can be chosen. MTTR

could be calculated using equation (2-8) in Chapter 2. Hereby, Mean Time to Repair

for each failure shown in table below:

Table 4.10 MTTR Value of Each Critical Component from August until December

2017

Failure Component Frequency Downtime

(Hour)

MTTR

(Hour)

Nozzle Leaking

Nozzle

13 11.83 0.91

Nozzle Damage 6 4.94 0.82

Nozzle Stuck 3 2.27 0.75

Hose Holder Leaking Gripper 21 16.5 0.78

Water Cooling Holder

Leaking Nipple 11 5.28 0.48

The total downtime and frequency of each failure is provided in Table 4.10 and

Table 4.11. From the table above, the value of MTTR from each critical component

56

is able to be calculated, resulting the nozzle leaking repairmen time to be 0.91 hour

in average, hose holder leaking took 0.75 hour in average and water cooling mold

leaking took 0.48 hour in average.

An example of the calculation of MTTR taken from water cooling holder leaking

failure from Appendix 8, as follows:

𝑀𝑇𝑇𝑅 = Ξ£TTR

π‘‘π‘œπ‘‘π‘Žπ‘™ π‘œπ‘π‘π‘’π‘Ÿπ‘’π‘›π‘π‘’π‘ 

𝑀𝑇𝑇𝑅 = (0.57+0.43+0.33+0.40+0.53+0.60+0.37+0.67+0.52+0.50+0.37)

11

𝑀𝑇𝑇𝑅 = 5.28 hour

11

𝑀𝑇𝑇𝑅 = 0.48 β„Žπ‘œπ‘’π‘Ÿ

Meanwhile, Mean Time to Failure plays an important part in this research. As

mentioned before, MTTF is an average time of a component from a good condition

until the next failure happens. Mean Time to Failure is used to calculate an

unrepairable item or component, and hence could be transform to make a preventive

maintenance schedule. The formula of MTTF is available in Chapter 2, formula

(2-6). Below is the table of Mean Time to Failure that shows the total downtime,

number of frequency and total uptime is provided in Table 4.11.

Table 4.11 MTTF Value of Each Critical Component from August until December

2017

Failure Component Frequency Downtime

(Hour)

MTTF

(Hour)

Nozzle Leaking

Nozzle

13 11.83 172.53

Nozzle Damage 6 4.94 721

Nozzle Stuck 3 2.27 184.67

Hose Holder Leaking Gripper 21 16.50 165

Water Cooling Mold Leaking Nipple 11 5.28 328

From the table above, it can be seen that the mean time to failure of nozzle leaking

is 172.53 hours, the mean time to failure for nozzle damage is 721 hours, and mean

time to failure of nozzle stuck is 184.67 hours.

57

An example of the calculation of MTTF taken from water cooling holder leaking

failure from table 4.9, as follows:

𝑀𝑇𝑇𝐹 = Ξ£TTF

π‘‘π‘œπ‘‘π‘Žπ‘™ π‘œπ‘π‘π‘’π‘Ÿπ‘’π‘›π‘π‘’π‘ 

𝑀𝑇𝑇𝐹 = (347+312+283+409+327+247+399+337+238+377)

11

𝑀𝑇𝑇𝐹 = 3280 hour

10

𝑀𝑇𝑇𝐹 = 328 β„Žπ‘œπ‘’π‘Ÿπ‘ 

Mean Time to Failure is also familiar as uptime. Uptime is the period of time of an

equipment that has been operating and available. The hose holder failure uptime is

165 hours and the water cooling mold leaking failure uptime is 328 hours.

4.3.3 Distribution Identification

The next phase in this research, after calculating the time to repair and time to

failure, is selecting the suitable distribution for each component. The calculation is

supported by a statistical software to determine the supporting values for this

research such as the parameter, the Anderson Darling and P-value from the

goodness of fit test. The table below shows the result of the fit of distribution from

time to failure (TTF).

Table 4.12 TTF Distribution for Each Component

Component Distribution Goodness of fit test

Acceptance Coefficient

correlation AD P-Value

Nozzle

Normal 0.351 0.436 Fit 0.978

Exponential 5.912 <0.003 Do not fit *

Weibull 0.419 >0.250 Fit 0.972

Lognormal 0.458 0.238 Fit 0.951

Gripper

Normal 0.544 0.141 Fit 0.966

Exponential 6.73 <0.003 Do not fit *

Weibull 0.466 0.238 Fit 0.982

Lognormal 0.718 0.051 Fit 0.952

Nipple

Normal 0.191 0.863 Fit 0.986

Exponential 4.436 <0.003 Do not fit *

Weibull 0.371 >0.250 Fit 0.948

Lognormal 0.696 0.047 Fit 0.892

58

Table 4.12 shows that each of the component tends to follow a certain distribution,

which is the main use of the goodness of fit test. The information from the table

above also tells that about how goodness of fit generates the value of Anderson-

Darling and P-Value, correlation coefficient and the parameter. Anderson Darling

(AD) determines how well the data follow a particular distribution. The result of

the parameter gives the fit test result, which is either fit or not fit with the

distribution.

In order to be able to schedule the preventive maintenance, the step is to determine

the distribution of time to repair and time to failure, through the comparison

between the result of the p-value and significance level (Ξ±). P-value is the

probability of a failure that is gained from the research in the statistical calculation.

while the significance level (Ξ±) in this research shows how extreme an ideal is, thus

can prove the difference of data exists (reject H0). The value of (Ξ±) is set to 0,05,

which indicates a 5% risk that there is a difference when there is no actual

difference.

𝐻0 = Data follows a distribution

𝐻1 = Data does not follow a distribution

The reason why the research compares the value of Ξ± and the p-value is to know if

the observed data is significantly different, comparing to what has been stated in

the null hypothesis (H0). If the p-value is less than or equal to the value of Ξ±, then

the null hypothesis is rejected, which means the result of the research, statistically,

is significant. Otherwise if the p-value is less than Ξ±, means that the research is

statistically insignificant. (Ross, 2004)

After the value of (Ξ±) is set, other statistic values can be determined, an example of

it is the (r) or known as the coefficient correlation or index of fit. If the value of (r)

that is closer to 1, means that the relations between parameters and the distribution

function is strong.

59

Table 4.13 TTF Distribution for Each Component

Component Distribution Parameter Std.

deviation Scale T-med Shape

Nozzle Normal - 0.85 - 39.05

Gripper Weibull 176.73 - 7.45 -

Nipple Normal 327.6 63.6

Table 4.13 indicates the parameter for each of the component, the distribution it

follows. In nozzle and nipple replacement, the fitted distribution is normal

distribution. Normal distribution has 2 parameters, which are t-med and standard

deviation. T-med has the value of 0.802 while the standard deviation is 39.05. The

gripper component follows Weibull distribution. Weibull distribution has 2

parameters, the shape value (Ξ²) and the scale value (ΞΈ), the detail information about

Weibull is available in Chapter 2. These information is essential for the next step,

which is the maintenance interval calculation.

4.3.4 Maintenance Cost Calculation

Conducting a preventive maintenance is to do the maintenance in a certain time that

has been calculated based on the reliability target, which has been set before. The

application of preventive maintenance will require some necessary cost, such as

preventive cost because there is an organized scheduled machine maintenance. This

cost will later be compare with the cost without preventive maintenance, also

known as corrective maintenance or failure cost. Corrective maintenance is the cost

that appear because of an expected failure occur causing production machine to stop

operating and disrupting the production time that was running. Therefore, to be able

to identify the costs that die cast area has spent and need to spend with current and

proposed maintenance system, below are the costs that are required to be considered

in calculating failure cost.

For the maintenance cost calculation, the data used was provided from the

maintenance and machine records. If ever a failure occurs, the company,

particularly the die cast machines are to be maintain with internal maintenance labor

60

from the company. Hence, in order to determine the maintenance, cost these data

below will be useful for supporting the calculation:

The die cast machine has a cycle time of 8.2 seconds/shot which is equivalent

to 0.13 minutes/shot

The machine capacity per minute yield to 7 shot/minute, but since the die cast

machine output consist of 4 parts in a single shot, the machine capacity will

be times by 4 which is equal to 28 shot/minute.

The production loss from machine failure is IDR 27,000/shot. The die cast

machine only produce 2 types of parts which are body and chassis. The price

of a body, cost IDR 8,500 and the chassis cost, IDR 5,000 respectively. Each

of these parts, the body and chassis, consist of 2 parts from a single shot.

The mechanic’s fee per minute is IDR 308 or costs IDR 18,450 if converts to

hour. The minimum salary for labor according to the government jurisdiction

in 2017 in Jababeka is IDR 3,837,600

The component price per unit for nozzle leaking, nozzle stuck and nozzle

damage or any abnormality of the nozzle that requires it to be replace is IDR

234,000

The component price per unit for hose holder leaking failure, which

component is the gripper, costs IDR 417,500

The component price per unit for water cooling holder leaking failure, which

component is the nipple, costs IDR 180,000

4.3.4.1 Calculation of Corrective Maintenance Cost (Cf)

In corrective maintenance, not every time a failure occurs, component replacement

is necessary. If the condition of the component is still good, then the component

only needs to be repair. However, if the component is worn-out (low reliability),

then the component needs to be immediately replace.

Corrective maintenance is a maintenance that being perform to refurbish the

condition of the damaged equipment until it’s become the desired condition,

hopefully to increase the equipment productivity. The formula of corrective

61

maintenance is expressed in Chapter 2, in formula (2-1). The complete calculation

of corrective maintenance for each component are as follow:

Failure Cost = Component Price + (Mechanic fee/hr Γ— Downtime/hr) +

Production Loss

Production Loss = Downtime/hr Γ— Machine Capacity Γ— Mechanic fee/hr

Nozzle Abnormalities (leaking, damage and stuck)

Cf = IDR 234,000 + (IDR 18,450/hr Γ— 0.8683 hour) + IDR 39,387,926

= IDR 234,000 + IDR 16,020 + IDR 39,387,926

= IDR 39,637,968.65

Hose Holder Leaking

Cf = IDR 417,000 + (IDR 18,450/hr Γ— 0,7866 hr) + IDR 35,682,307

= IDR 417,000 + IDR 14,512.77 + IDR 35,682,307

= IDR 36,114,321.56

Water Cooling Holder Leaking

Cf = IDR 180,000 + (IDR 18,450/hr Γ— 0.4803 hr) + IDR 21,786,544

= IDR 180,000 + IDR 8,861.53 + IDR 21,786,544

= IDR 21,975,405.2

From applying the corrective maintenance formula to the gathered data, the

following information is obtained, which is the amount of money the company

spent for replacing nozzle, for which every nozzle abnormality (leak, damage and

stuck) is IDR 39,637,968.65. The replacement of gripper, the component essential

in hose holder leaking cost IDR 36,114,321.56 and for water cooling holder leaking

the replacement of its component, spends IDR 21,975,405.2 or $1,574 if converts

to USD. From the three component has an overall total cost of IDR 97, 727, 695.88

4.3.4.2 Calculation of Preventive Maintenance Cost (Cp)

Preventive maintenance cost is a cost that occur due to the scheduled equipment

maintenance, while failure cost is a cost that occur due to any unexpected or

unplanned downtime from unanticipated equipment failure that causes the

62

production to stop running. The formula of preventive maintenance cost is

expressed in Chapter 2, in formula (2-2). The complete calculation of preventive

maintenance for each component are as follow:

Preventive Cost = Component Price + (Mechanic fee/hr Γ— Downtime/hr) +

Production Loss

Production Loss = (Total part price/shot) Γ— 2

Nozzle Abnormalities (leaking, damage and stuck)

Cp = IDR 234,000 + (IDR 18,450/hr Γ— 0.5833 hr) + (0.5833 hr Γ— 1,680

part/hr Γ— 27,000)

= IDR 234,000 + IDR 10,761 + IDR 26,460,000

= IDR 26,704,762

Hose Holder Leaking

Cp = IDR 417,000 + (IDR 18,450/hr Γ— 0.4167 hr) + (0.4167 hr Γ— 1,680

part/hr Γ— IDR 27,000)

= IDR 417,000 + IDR 7,688 + IDR 18,900,000

= IDR 19,325,187

Water Cooling Holder Leaking

Cp = IDR 180,000 + (IDR 18,450/hr Γ— 0.2500 hr) + (0.2400 hr Γ— 1,680

part/hr Γ— IDR 27,000)

= IDR 180,000 + IDR 4,612+ IDR 11,340,000

= IDR 11,524,612

From the calculation of preventive maintenance cost above, the following

information is obtained, which is the amount of money the company spent for

replacing nozzle, for which every nozzle abnormality (leak, damage and stuck) is

reduced 33% from corrective maintenance, which is equal to IDR 26,704,780. The

replacement of gripper, the component essential in hose holder leaking cost IDR

19,325,200 equivalents to $1,389.69.58 and for water cooling holder leaking the

replacement of its component, spent IDR 15,306,160 or $1,100.6 if converts to USD

63

and is 48% reduce from the current corrective cost. The total preventive

maintenance cost is 57,554,562, which is 41% less than the corrective cost total.

4.3.4.3 Component Replacement Interval Calculation

After identifying the fitted distribution for each of the component, the next step is

to calculate the interval of component replacement, also known as maintenance

interval. Maintenance interval is and the result will later determine the scheduling

for preventive maintenance for the mechanic to do the replacement activity.

Table 4.14 Replacement Interval Time of Nozzle

t (hour) f(t) F(t) R(t) H(t) C(t)

200 0.007054156 0.805343683 19% 0.105940691 IDR 154,520

190 0.008510235 0.727343947 27% 0.068308497 IDR 154,802

180 0.009615274 0.636355786 36% 0.044809837 IDR 158,227

170 0.010174321 0.536917089 46% 0.029689202 IDR 164,009

166 0.01021808 0.499172544 50% 0.025521877 IDR 166,665

160 0.010082607 0.435103715 56% 0.019723052 IDR 171,791

150 0.009357588 0.337440025 66% 0.013041317 IDR 181,478

140 0.008133521 0.249671199 75% 0.008520535 IDR 193,161

134 0.007245674 0.203505879 80% 0.006542511 IDR 201,225

124 0.00567063 0.138910201 86% 0.004130815 IDR 216,681

114 0.004156306 0.089912584 91% 0.002529807 IDR 235,132

The table above shows the replacement interval for nozzle component. The time to

failure of nozzle accepted the Normal distribution and hence the calculation from

the table above is regarding to Normal distribution formula. The detail calculation

of table 4.14 that follows a normal distribution, is explained below:

Probability density function

𝑓(𝑑) =1

𝜎√2πœ‹π‘’ [

(𝑑 βˆ’ πœ‡)2

2𝜎2]

𝑓(𝑑) =1

39.5√6.28𝑒 [

(200 βˆ’ 166.381)2

(2 Γ— 39.05)2]

𝑓(𝑑) =1

39.5 π‘₯ 2.506𝑒 [

(33.619)2

(78.1)2]

𝑓(𝑑) = 0.007054156

64

Cumulative distribution function

𝐹(𝑑) = πœ™ (𝑑 βˆ’ πœ‡

𝜎)

𝐹(𝑑) = πœ™ (200 βˆ’ 166.381

39.05)

𝐹(𝑑) = 0.805343683

Reliability function

𝑅(𝑑) = 1 βˆ’ 𝐹(𝑑)

𝑅(𝑑) = 1 βˆ’ 0.805343683

𝑅(𝑑) = 0.1946563

Cumulative hazard function

𝐻(𝑑) = 𝑓(𝑑)

𝑅(𝑑)

𝐻(𝑑) = 0.007054156

0.1946563

𝐻(𝑑) = 0.105940691

Cost per unit of time

𝐢(𝑑) = (𝐢𝑝 + [𝐢𝑓 Γ— 𝐻(𝑑)]

𝑑)

𝐢(𝑑) = (𝐼𝐷𝑅 26,704,763 + [39,638,025 Γ— 0.105940691]

200)

𝐢(𝑑) = 𝐼𝐷𝑅 154,520

65

Figure 4.12 Cost per Unit of Time Replacement Nozzle

Based on the calculation above, it shows that the interval time is related with cost.

It can be seen that the cost and time are moving inversely, the shorter the length of

interval time is, the higher the cost gets. Additionally, regarding to the time

movement, as it becomes shorter, the reliability of time will also increase. The

condition is illustrated in figure 4.12 above.

Table 4.15 Replacement Interval Time of Gripper

t (hour) f(t) F(t) R(t) H(t) C(t)

170 0.069367676 0.527059054 47% 0.00774 IDR 158,891

166 0.052677938 0.46586049 53% 0.006203 IDR 162,353

160 0.035745303 0.3791757 62% 0.004507 IDR 168,021

155 0.026345651 0.313614596 69% 0.00348 IDR 173,179

150 0.019654789 0.255298474 74% 0.002698 IDR 178,745

145 0.014789773 0.204666215 80% 0.002095 IDR 184,744

140 0.011189635 0.161653683 84% 0.001626 IDR 191,209

135 0.008487881 0.125833319 87% 0.001259 IDR 198,183

130 0.006438684 0.096545186 90% 0.000971 IDR 205,717

The table above shows the replacement interval for gripper component. The time to

failure of gripper accepted the Weibull distribution and hence the calculation from

the table above is regarding to Weibull distribution formula. Based on the

calculation above, it shows that the interval time is related with cost.

0

50

100

150

200

250

IDR 0

IDR 50,000

IDR 100,000

IDR 150,000

IDR 200,000

IDR 250,000

Cost VS Time Nozzle

C(t) t (hour)

66

Probability density function

𝑓(𝑑) = 𝛽

πœƒ(

𝑑

πœƒ)

π›½βˆ’1

𝑒(π‘‘πœƒ

)𝛽

𝑓(𝑑) = 7.44828

176.733(

170

176.733)

7.44828βˆ’1

𝑒(170

176.733)7.44828

𝑓(𝑑) = 0.069367676

Cumulative distribution function

𝐹(𝑑) = 1 βˆ’ π‘’βˆ’(

π‘‘πœƒ

)𝛽

𝐹(𝑑) = 1 βˆ’ π‘’βˆ’(170

176.733)7.44828

𝐹(𝑑) = 0.527059054

Reliability function

𝑅(𝑑) = 1 βˆ’ 𝐹(𝑑)

𝑅(𝑑) = 1 βˆ’ 0.527059054

𝑅(𝑑) = 0.4729409

Hazard failure function

𝐻(𝑑) = 𝑓(𝑑)

𝑅(𝑑)

𝐻(𝑑) = 0.069367676

0.4729409

𝐻(𝑑) = 0.0077396

Cost per unit of time

𝐢(𝑑) = (𝐢𝑝 + [𝐢𝑓 Γ— 𝐻(𝑑)]

𝑑)

𝐢(𝑑) = (𝐼𝐷𝑅 19,325,188 + [36,157,061 Γ— 0.0077396]

170)

𝐢(𝑑) = 𝐼𝐷𝑅 158,891

67

Figure 4.13 Cost per Unit of Time Replacement Gripper

It can be seen that the cost and time are moving inversely, the shorter the length of

interval time is, the higher the cost gets. Additionally, regarding to the time

movement, as it becomes shorter, the reliability of time will also increase. The

condition is illustrated in figure 4.13.

Table 4.16 Replacement Interval Time of Nipple

t (hour) f(t) F(t) R(t) H(t) C(t)

400 0.003282219 0.872515903 13% 0.107612 IDR 34,724

327 0.006273989 0.496236449 50% 0.015488 IDR 36,284

300 0.005710435 0.332157922 67% 0.00782 IDR 38,988

290 0.005268265 0.277194897 72% 0.00603 IDR 40,197

280 0.004741648 0.227101118 77% 0.00462 IDR 41,522

270 0.00416346 0.18255782 82% 0.003511 IDR 42,970

260 0.003566504 0.14391522 86% 0.002643 IDR 44,549

250 0.002980537 0.111208597 89% 0.001967 IDR 46,271

240 0.002430018 0.08420072 92% 0.001446 IDR 48,152

The table above shows the replacement interval for nipple component. The time to

failure of nipple accepted the Normal distribution and hence the calculation from

the table above is regarding to Normal distribution formula. Based on the

calculation above, it shows that the interval time is related with cost.

0

20

40

60

80

100

120

140

160

180

IDR -

IDR 50,000

IDR 100,000

IDR 150,000

IDR 200,000

IDR 250,000

1 2 3 4 5 6 7 8 9

Cost VS Time Gripper

C(t) t (hour)

68

Probability density function

𝑓(𝑑) =1

𝜎√2πœ‹π‘’ [

(𝑑 βˆ’ πœ‡)2

2𝜎2]

𝑓(𝑑) =1

63.6√6.28𝑒 [

(400 βˆ’ 327.6)2

(2 π‘₯ 63.6)2]

𝑓(𝑑) = 0.003282219

Cumulative distribution function

𝐹(𝑑) = πœ™ (𝑑 βˆ’ πœ‡

𝜎)

𝐹(𝑑) = πœ™ (400 βˆ’ 327.6

63.6)

𝐹(𝑑) = 0.872515903

Reliability function

𝑅(𝑑) = 1 βˆ’ 𝐹(𝑑)

𝑅(𝑑) = 1 βˆ’ 0.872515903

𝑅(𝑑) = 0.1274841

Cumulative hazard function

𝐻(𝑑) = 𝑓(𝑑)

𝑅(𝑑)

𝐻(𝑑) = 0.003282219

0.1274841

𝐻(𝑑) = 0.107612

Cost per unit of time

𝐢(𝑑) = (𝐢𝑝 + [𝐢𝑓 Γ— 𝐻(𝑑)]

𝑑)

𝐢(𝑑) = (𝐼𝐷𝑅 11,524,613 + [21,975,435 Γ— 0.107612]

400)

69

𝐢(𝑑) = 𝐼𝐷𝑅 34,724

Figure 4.14 Cost per Unit of Time Replacement Nipple

It can be seen that the cost and time are moving inversely, the shorter the length of

interval time is, the higher the cost gets. Additionally, regarding to the time

movement, as it becomes shorter, the reliability of time will also increase. The

machine reliability is set to reach 85%. The condition is illustrated in figure 4.14.

Component replacement activity is conducted in order to prevent unexpected

failure, which could impact to the production process. The interval calculation

shows when to do the replacement activity at the right time to reduce the risk of a

failure occur. Hence, the table below tells about when is the right time to replace

the component.

Table 4.17 Interval Time of Component Replacement

Component Distribution

Replacement

Interval Time Reliability Last Failure

Occurrence (h) (days)

Nozzle Normal 134 6 80% 12/30/2017

Gripper Weibull 145 6 80% 12/25/2017

Nipple Normal 270 11 82% 12/22/2017

0

50

100

150

200

250

300

350

400

450

IDR -

IDR 10,000

IDR 20,000

IDR 30,000

IDR 40,000

IDR 50,000

IDR 60,000

1 2 3 4 5 6 7 8 9

Cost VS Time Nipple

C(t) t (hour)

70

The replacement time are determined through the calculation in table 4.14, table

4.15 and table 4.16. Component replacement time is the key to design the proper

preventive maintenance schedule. Future preventive maintenance for nozzle

replacement took 134 hours to change, gripper will be done every 145 hours and

nipple will be done every 270 hours. The future calculation of preventive

maintenance will be proposed to the company. The goal of this scheduling is to

minimize maintenance cost spent by company. The company has set a goal of 80%

of the machine reliability. This information will be essential to the next phase,

which is designing the preventive maintenance schedule.

4.3.4.4 Proposed Preventive Maintenance Schedule

The preventive maintenance schedule is derived from the calculation result of the

interval time from each component. Every component has different time to perform

the maintenance activity, which is the replacement. Figure 4.15 are the preventive

maintenance schedule for the 3 observed component in this research to be replace.

The schedule will begin from January 1, 2018 until March 31, 2018.

Figure 4.15 Nozzle and Gripper Preventive Maintenance Schedule in A06 for January-March

2018

To reach the goal of 80%, the PM should be done based on the following schedule

on figure. 4.15. The color that represent the nozzle replacement is green, while the

gripper is purple. The component nozzle and gripper require the same time interval

in the maintenance activity, and since both of the component replacement time is

close to one another, it is recommended to do the maintenance activities on the same

day rather than on two different days, which could decrease the number of

downtime.

71

Figure 4.16 Nipple Preventive Maintenance Schedule in A06 for January-March 2018

Figure 4.14 is the proposed PM schedule for nipple component. As mentioned

before, the nipple component lifetime only last for less than 2 weeks, which is

approximately equal to 450,000 shots. The schedule begins in January 3, 2018

which last failure occurred in December 22, 2017, as it can be seen in figure 4.13.

There are several times where the nipple replacement occurs on the same day as the

nozzle and gripper replacement, such as; February 5 and February 15. Additionally,

although the nipple replacement is done every 11 days, the maintenance activity is

still close to the nipple and gripper replacement schedule, thus, if possible could be

made on the same day.

4.4 Data Analysis and Implementation

The next step, after improvement planning and calculation has been conduct, is to

go through the implementation. This subchapter will explain about further data

analysis from the calculations and the implementation of preventive maintenance

and TPM implementation, which is still regarding to the 8 pillars of TPM. This

system will be implemented by the company.

4.4.1 Machine Reliability

4.4.1.1 Component Reliability Comparison

The need to conduct a comparison of the reliability level is to evaluate the impact

to the machine performance before and after the improvement. The preventive

maintenance is set to 80%. The company will provide the necessary data and

equipment to ease the administration and reporting of downtime for the mechanics

by providing a computer PC in the pit stop (maintenance room). Below is the

comparison between the current and proposed preventive maintenance system

72

Table 4.18 Comparison of Time and Reliability

Component

Current Proposed

t (hours) Current R(t) t (hours) Proposed R(t)

Nozzle 166.381 50% 134 80%

Gripper 165.849 53% 145 80%

Nipple 327.6 50% 270 82%

It can be concluded from the table 4.18 above, that the earliest the maintenance

activity is conduct, the higher the reliability as well. For the nozzle, the machine

reliability increased from 50% into 80%. The gripper increased from 53% into 80%,

and also for the Nipple, the machine reliability increased 32% from the current state

of 50% reliability.

Figure 4.17 Reliability Comparison

Figure 4.17 clearly illustrates the reliability difference from each component of the

current and proposed maintenance system. As seen above, nozzle reliability

increased by 30%, gripper and the nipple increased by 27% and 32%. Therefore, it

is recommended for the company to implement this system, thus will increase the

machine reliability.

50% 53% 50%

80% 80% 82%

0%

20%

40%

60%

80%

100%

Nozzle Gripper Nipple

Reliability Comparison

Current R(t) Proposed R(t)

73

4.4.1.2 Proposed Preventive Maintenance Scheduling

4.4.1.3 OEE Comparison after TPM Implementation

To evaluate and validated the TPM implementation, overall equipment

effectiveness, also known as OEE is employed in this research. OEE focus on 3

metrics which are the availability, performance and quality. The OEE score is

obtained by multiplying all of the 3 metrics together. The table below is the result

of OEE from 3 months’ progress after the improvement. The detailed data is

available in Appendix 22-24.

Table 4.19 Machine A06 for January-March 2018

Month Availability Performance Quality OEE

Jan 75% 90% 99% 67%

Feb 86% 90% 99% 76%

Mar 87% 91% 99% 79%

80% 90% 99% 72%

The result of the OEE after the TPM implementation shows quite a significant

progress, compared to the observed period from August-December 2017. The OEE

trend keeps going up, starting from January 2018, which has an OEE score of 67%,

with the availability of 75% and an impeccable quality and performance of 99%

and 90%. On February, the availability increases 11%, which boost up the OEE

score into 76%, and on March, the availability increases by 1%, thus impacting the

performance to gain another 1% and managed to score 79%.

Below are the examples of the OEE metrics calculation, taken from January 2, 2018

in Appendix 22.

Availability = (π‘‚π‘π‘’π‘Ÿπ‘Žπ‘‘π‘–π‘›π‘” π‘‡π‘–π‘šπ‘’

π΄π‘£π‘Žπ‘–π‘™π‘Žπ‘π‘™π‘’ π‘‡π‘–π‘šπ‘’ ) Γ— 100%

Availability = (22.93 β„Žπ‘œπ‘’π‘Ÿ

32.67 β„Žπ‘œπ‘’π‘Ÿ ) Γ— 100%

Availability = (0.702) Γ— 100%

Availability = πŸ•πŸŽ. 𝟐%

74

Performance Calculation

π‘ƒπ‘’π‘Ÿπ‘“π‘œπ‘Ÿπ‘šπ‘Žπ‘›π‘π‘’ = (π΄π‘π‘‘π‘’π‘Žπ‘™ 𝑂𝑒𝑑𝑝𝑒𝑑

π‘†π‘‘π‘Žπ‘›π‘‘π‘Žπ‘Ÿπ‘‘ π‘œπ‘’π‘‘π‘π‘’π‘‘ ) Γ— 100%

π‘ƒπ‘’π‘Ÿπ‘“π‘œπ‘Ÿπ‘šπ‘Žπ‘›π‘π‘’ = (15,150

15,543) Γ— 100%

π‘ƒπ‘’π‘Ÿπ‘“π‘œπ‘Ÿπ‘šπ‘Žπ‘›π‘π‘’ = (15,150

15,543) Γ— 100%

π‘ƒπ‘’π‘Ÿπ‘“π‘œπ‘Ÿπ‘šπ‘Žπ‘›π‘π‘’ = (15,150

15,543) Γ— 100%

π‘ƒπ‘’π‘Ÿπ‘“π‘œπ‘Ÿπ‘šπ‘Žπ‘›π‘π‘’ = (0,975) Γ— 100%

π‘·π’†π’“π’‡π’π’“π’Žπ’‚π’π’„π’† = πŸ—πŸ•. πŸ“%

Quality = (πΊπ‘œπ‘œπ‘‘ 𝑂𝑒𝑑𝑝𝑒𝑑

π΄π‘π‘‘π‘’π‘Žπ‘™ π‘œπ‘’π‘‘π‘π‘’π‘‘ ) Γ— 100%

Quality = (15,020

15,150 ) Γ— 100%

Quality = (15,020

15,150 ) Γ— 100%

Quality = (0,991) Γ— 100%

Quality = πŸ—πŸ—. 𝟏%

Hence, the average availability, performance and quality from January until March

2018 months are calculated to determine the average OEE score:

𝑂𝐸𝐸 = π΄π‘£π‘Žπ‘–π‘™π‘Žπ‘π‘–π‘™π‘–π‘‘π‘¦ π‘₯ π‘ƒπ‘’π‘Ÿπ‘“π‘œπ‘Ÿπ‘šπ‘Žπ‘›π‘π‘’ π‘₯ π‘„π‘’π‘Žπ‘™π‘–π‘‘π‘¦

𝑂𝐸𝐸 = 80% Γ— 90% Γ— 99%

𝑂𝐸𝐸 = 72%

75

Figure 4.18 OEE Comparison Before and After TPM

Although, some managers are probably quite satisfied with the value of each metric,

as it seems like everything is running well. However, when the 3 metrics are

multiplied, the real picture emerge. The company has set a goal for every area to

reach 85% in their OEE score and are obligated to sustain it. Die cast area still have

a lot of room for improvement and OEE really helps to highlight the equipment’s

problem area. In this case, the area that needs to be improve is the availability and

performance. Availability is associated with breakdown, long period of changeover

while performance is associated with equipment’s speed loss.

4.4.1.4 Cost Comparison

Besides to reduce the downtime, the essence of this research is to know whether the

new system could support cost saving by decreasing the price of maintenance

activity. TPM implementation before and after results are being compared in prices.

The preventive maintenance is more likely to occur, but breakdown will less likely

to happen with longer time.

54%

72%

0%

10%

20%

30%

40%

50%

60%

70%

80%

OEE Before TPM OEE After TPM

76

Figure 4.19 Cost Comparison of Current and Proposed Maintenance

The comparison of each component is display in Figure 4.19, where the red bar

symbolizes the current cost and the green bar is the proposed cost. The most

significant difference can be seen in the gripper where the cost is dropped by 16

million IDR.

4.4.2 TPM Implementation

To fully improve the company efficiency and effectiveness, TPM strategy must be

employs to everyone, from the top level management to the workers, by practicing

the TPM pillars, which have been mentioned in Chapter 2. The implementation will

begin in just one pilot area, which is die cast, so it will be easier to manage and

controlled. Besides preventive maintenance, there are 7 other pillars in TPM

classification that the company needs to consider and adopt, in order to improve its

manufacturing performances, some of the company initiative of the TPM

implementation are as follows:

1. 5S

5S are considered to be the ground rule/foundation of the TPM pillars. 5S

includes cleaning and organizing work area to helps uncover the problem

that may have gone unnoticed (Wakjira & Singh, 2012). The company wants

Nozzle Gripper Nipple

Current Cost IDR 32,645,125.56 IDR 35,103,146.23 IDR 21,975,435.21

Proposed Cost IDR 26,704,780.00 IDR 19,325,200.00 IDR 15,306,160.00

IDR -

IDR 5,000,000

IDR 10,000,000

IDR 15,000,000

IDR 20,000,000

IDR 25,000,000

Cost Comparison

Current Cost Proposed Cost

77

to make 5S as a culture and thus, every day, everyone is reminded to do 5S

every 2 hours for less than 3 minutes, using a special 5S song through the

speakers, to make the work less stressful.

Recently, the company has provided the die cast area with 1 large cabinet

for documents keeping, 2 level locker for water bottles storage, 2 shelves

for PPE storage, 2 boxes for tool keeping and 26 acrylics for each machine

to store its SOP, WI, Standard Schedule Conformance (SSC), and

Autonomous Checklist paper. All the places mentioned above has its own

identification so as to keep everything in its own place. Identification helps

to easily find items and easily spot things that are not being put in its proper

place. The illustration is available in Appendix 17.

In die cast area, 5S is to be done before the shift begins and after the shift

ends, with a given time of 10 minutes to sort out the tools, clean up the

machine and workplace. This practice aims to create a behavior of care and

self-belonging to everyone, the staff and workers, towards their workplace

and tools.

2. Autonomous Maintenance

Autonomous Maintenance aims to develop operator ownership. In the

company, the form of action for the autonomous maintenance is through

audit and inspection using a standardize checklist, designed by the process

engineer of the area. The maintenance staff tutor the operator on the basic

procedure on how to properly clean and maintain. This program’s aim is

neither to replace nor take over the maintenance job, but rather to help them

focus on repairing or replacement and avoid to do menial tasks, such as

cleaning, lubricating, inspection on equipment condition and adjustment.

Autonomous maintenance inspection is to be check regularly in the

beginning of the shift. The example of an autonomous maintenance for die

cast operator is available in Appendix 18.

3. Planned Maintenance

The company’s initiatives toward planned maintenance are as follows:

78

Develop from reactive to proactive methods and work attitude

Sustaining the good availability of the machine and enhancing its

research equipment to be able to perform predictive maintenance so as to

improve maintenance work efficiently and effectively.

Create a team that focus on collecting and reporting equipment condition

on a daily basis to determine the schedule/ the need for maintenance

requirements. The processed data will eventually analyze by the

engineers and the production to track equipment performance anytime.

Established Andon, blue tag and PM check sheets. Andon is a tool to

inform about the machine condition which in the form of 3 lights with

different colors. Green andon is a sign that the machine is operating,

yellow is to sign the material handler that material is running out and red

andon is to sign the technician that the machine is experiencing

abnormality and needs to be repair.

Blue Tag form is a short summarize report that is made only when there

is an abnormality in the equipment during production time. The flow of

the blue tag is when the operator, the person who is responsible to report

the abnormality, reported to the line leader of the abnormal occurrence

and the line leader will write down the Blue Tag form which will be

inputted in the blue tag board. The maintenance will come as soon as they

have received the Blue Tag form. The detail flow of Blue Tag reporting

is available in Appendix 19.

4. Education and Training

The department of Lean, Training and HSE are working together to give an

extensive knowledge and education towards the worker, with a goal to

create a factory full of valuable and knowledgeable workers. These training

includes;

Basic to Intermediate study of production system

The English language (oral and written)

In-depth study of each production process in the company

79

Health and Safety awareness

On the field training about proper techniques

Lean tools and methods

The aim of this program is to develop the character and knowledge of the

worker from a β€œknow-how” into a β€œknow-why”. Eventually, the workers

will be motivated to learn, apply their knowledge in work and pass on their

knowledge to others.

As a simple application of education and training in the line, is the line

leader. The line leader is responsible to give a 5-10-minutes briefing to the

workers to give them work motivation and insights before the workers can

start their job.

5. Quality Maintenance

The goal of this program is to make zero defect in the manufacturing. The

following points are the company initiatives towards a better quality

maintenance:

Use visual management in a form of a board called, β€œshow and tell”,

which consist of the example of parts that are below the limit, accepted

limit and above the limit. This portable information board is to guide the

QC operator to decide easily on the good and defect parts. The illustration

of this implementation is attached in Appendix 20.

6. Kaizen

The concept of true TPM is where everyone, from the top level

management to regular workers, involved in the improvement program

to care for the equipment maintenance. Through TPM pillar, Kaizen, the

workers are allowed to participate in a problem solving event. Thus, they

can express their ideas and be a part in the decision making of the

meeting.

80

7. Environmental, Health & Safety

Visual Management

The department of Health Safety and Environment (HSE) associated with

the department of Lean Supply Chain (LSCO) use visual management to

promote and communicate safety by PPE signs, warning signs and stickers,

MSDS, safety posters, safety videos, near miss announcement board,

Triangle of safety and many more.

Risk Assessment

A fully risk assessment has been conducted for equipment and everyone

who is involve in the process of die cast, starting from the SWAT (line

leader), operator, QC, material handler, technician and even janitors. The

risk assessment should also be revise if ever there was a change of process

or equipment in the future.

Near Miss

The HSE team has reinforced everyone, in the die cast area to be more aware

of near miss and other potential safety hazard in their workplace. HSE

department has provided a near miss form to every production and non-

production area to report the near misses back to them, so any potential

hazards can be solved immediately. Every month, the HSE department will

give complementary gifts as a token of appreciation to any employee who

has reported many near miss in a month.

On The Spot Training

Every Thursday, each of the HSE engineers will go to a designated area and

for 30 minutes explain to 10 workers about potential safety hazards in the

workplace, near miss, emergency situation, emergency exit and how to use

emergency tools, such as fire extinguisher and fire hydrant in case of an

emergency. Actually, these topics has been explained before at the first time

they join the company through the labor orientation. This program aims to

81

remind the workers about safety awareness and to create a strong safety

culture to the workers.

The aim of TPM application in the company is not merely to have a high OEE

percentage to show off, but to continuously improve and sustain all the good

progress made from the TPM programs by the company. Some of the

documentation of the TPM implementation is attached in the Appendix 17-

Appendix 21, as evidence of the die cast progress in adopting TPM in its workplace

environment.

82

CHAPTER V

CONCLUSION AND RECOMMENDATION

.

5.1 Conclusion

The objectives in this research, which are to reduce the downtime and TPM

implementation has been achieved. After calculating and analyze all the necessary

data several points of conclusion can be drawn from this research, based on the

research objectives:

The performance of a toy manufacturing company has been analyzed and

thoroughly study. The die cast area has been specifically chosen as the subject

of the research because of its low equipment availability score impacted the

OEE trend. The research took a pilot machine, die cast A06, to be the main

subject of the research, which is the one that caused the highest downtime

with a total time of 40.3 hours in 5 months. After thorough observation, the

factors that mostly affecting the downtime are classified into five failures

which are nozzle leaking, nozzle damage, nozzle stuck, hose holder leaking

and water cooling mold leaking.

TPM implementation, through preventive maintenance and other initiatives in

the company, has successfully increase the reliability and OEE in the die cast

area. Nozzle reliability has increased by 30%, gripper and the nipple

reliability increased by 27% and 32%. The OEE gradually increasing, starting

from January 2018, which has an OEE score of 67%. On February, the OEE

score boost up to 76%, and on March managed 79%. The die cast machine

A06 in 3 months after TPM implementation has succeed to increase its OEE

by 18%, from an average of 54% in 2017 to its current score, 72%.

83

5.2 Recommendation

The following recommendation is taken based on the latest performance and is for

future improvement in any near research:

1. To synchronize the production schedule and maintenance schedule to avoid

conflicted schedule.

2. To reduce the use of paper for reporting so as the company can start to comply

with industry 4.0 standards

3. To develop the workers to have a Lean thinking in their work, thus will create

a more multi-skilled and effective people in the company.

84

REFERENCES

Ahuja, I., & Kahamba, J., Total Productive Maintenance and Performance:

Literature Review. International Journal of Quality & Reliability Management, Vol

25, 2008, pp 56-709.

Bhadury, B., Management of Productivity Through TPM, 2000, pp 51-241.

Brophy, A., The Financial Guide . In LEAN. Edinburg: Pearson Education Limited,

2013.

Chaneski, W., Total Productive Maintenance; An Effective Technique. Retrieved

from Modern Machine Shop: https://www.mmsonline.com/columns/total-

productive-maintenance-increases-machine-efficiency, 2002.

Dhillon, B., Engineering Maintenance. Florida: CRC Press LLC, 2002.

Gits, C., Design of Maintenance Concept. International Journal of Production

Economics, Vol 24, 1992, pp 217-226.

Kutucuoglo, K. H., A Framework for Managing Maintenance Using Performance

Measurement System. International Journal of Operations & Prodcutions, XIV,

2001, pp 172-194,

Mobley, K. R., Maintenance Engineering Handbook 7th Edition. New York : Mc

Graw Hill, New York, 2008.

Ross, S. M., Introduction to Probability and Statistics. San Diego: Elsevier

Academic Press, 2004.

Wakjira, M. W., & Singh, A. P., Total Productive Maintenance: A Case Study in

Manufacturing Industry. Global Journal of Researches in Engineering, Vol 12,

2012, pp 26.