in the missouri court of appeals appellants joint brief as filed.pdfon august 30, 2016, grain belt...

70
1 IN THE MISSOURI COURT OF APPEALS EASTERN DISTRICT __________________________________________________________________ ED107886 __________________________________________________________________ MISSOURI LANDOWNERS ALLIANCE, ET AL., Appellants, v. PUBLIC SERVICE COMMISSION OF THE STATE OF MISSOURI, Respondent __________________________________________________________________ Appeal from the Public Service Commission of the State of Missouri Case No. EA-2016-0358 __________________________________________________________________ INITIAL JOINT BRIEF OF APPELLANTS EASTERN MISSOURI LANDOWNERS ALLIANCE DBA SHOW ME CONCERNED LANDOWNERS, CHRISTINA REICHERT, AND MISSOURI FARM BUREAU __________________________________________________________________ Paul A. Agathen Mo. Bar No. 24756 485 Oak Field Ct. Washington, MO 63090 636-980-6403 [email protected] Brent E. Haden Mo. Bar No. 54148 827 E. Broadway, Suite B Columbia, MO 65201 (573) 442-3535 (888) 632-7775 (fax) [email protected] Attorneys for Appellants

Upload: others

Post on 30-Dec-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

1

IN THE MISSOURI COURT OF APPEALS

EASTERN DISTRICT

__________________________________________________________________

ED107886

__________________________________________________________________

MISSOURI LANDOWNERS ALLIANCE, ET AL.,

Appellants,

v.

PUBLIC SERVICE COMMISSION OF THE STATE OF MISSOURI,

Respondent

__________________________________________________________________

Appeal from the Public Service Commission of the State of Missouri

Case No. EA-2016-0358

__________________________________________________________________

INITIAL JOINT BRIEF OF APPELLANTS

EASTERN MISSOURI LANDOWNERS ALLIANCE DBA

SHOW ME CONCERNED LANDOWNERS,

CHRISTINA REICHERT, AND MISSOURI FARM BUREAU

__________________________________________________________________

Paul A. Agathen

Mo. Bar No. 24756

485 Oak Field Ct.

Washington, MO 63090

636-980-6403 [email protected]

Brent E. Haden

Mo. Bar No. 54148

827 E. Broadway, Suite B

Columbia, MO 65201

(573) 442-3535

(888) 632-7775 (fax) [email protected]

Attorneys for Appellants

Page 2: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

2

TABLE OF CONTENTS

TABLE OF AUTHORITIES …......................………………………..…….4

JURISDICTIONAL STATEMENT ………………………………………..9

STATEMENT OF FACTS ………………………………………………...10

POINT RELIED ON…………………………………………………...…..18

STANDARD OF REVIEW ……………………………………………….20

ARGUMENT……………………………………………………………. 20

THE PUBLIC SERVICE COMMISSION OF THE STATE OF

MISSOURI (“COMMISSION”) ERRED IN GRANTING A

CERTIFICATE OF CONVENIENCE AND NECESSITY (“CCN”)

TO GRAIN BELT EXPRESS CLEAN LINE LLC (“GRAIN

BELT”) PURSUANT TO SECTION 393.170 BECAUSE THE

COMMISSION LACKED THE STATUTORY AUTHORITY AND

THUS THE SUBJECT MATTER JURISDICTION TO ISSUE THE

CCN, IN THAT GRAIN BELT IS NOT AN “ELECTRICAL

CORPORATION”, AS IS REQUIRED FOR ISSUANCE OF A

CCN UNDER SECTION 393.170.

A. Based on case law, Grain Belt is not an electrical corporation

because it is not subject to all of the statutes which comprise the

Public Service Commission Act………………………………22

B. Based on case law, Grain Belt is not an electrical corporation

because it will not be devoted to the “public use” …………...28

Page 3: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

3

i. The Grain Belt/FERC model for establishing rates and

other terms of service………………………………….29

ii. Given how Grain Belt is allowed to set its rates, under

applicable case law it does not serve a public use, and thus

is public utility………………………………………....35

C. Grain Belt is not an electrical corporation because it does

not meet the statutory definition of that term…………..……..51

CONCLUSION ……………………………………………………...….67

CERTIFICATES OF COMPLIANCE AND SERVICE……….……... 70

Page 4: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

4

TABLE OF AUTHORITIES

Cases

AMG Franchises, Inc. v. Crack Team USA, 289 S.W.3d 655

(Mo. App. 2009) ……………………………………………….……….66

Bachtel v. Miller County Nursing Home District, 110 S.W.3d 799

(Mo. banc 2003)…………………………………………………………49

Big River Telephone Co. v. Southwestern Bell Telephone

Company, 440 S.W.3d 503 (Mo. App. 2014). …………………………67

City of St. Louis v. Mississippi River Fuel Corp., 97 F.2d 726

(8th Cir. 1938) …………………………………………………..………42

Concerned Citizens and Property Owners v. Illinois Commerce

Commission, 112 N.E.3d 128 (Ill. App. 2018) …………………57, 58, 61

Dow Chemical Co. v. Dir. Of Revenue, 834 S.W.2d 742 (Mo. banc 1992)

………………………………………………………………………...……49

Grain Belt Express Clean Line LLC v. Public Serv. Comm’n,

555 S.W.3d 469 (Mo. banc 2018) …………………………………..15, 20

Grain Belt Express Clean Line LLC v. Public Serv. Comm’n, No.

ED105932 (Mo. App. Feb. 27, 2018)….. …………………………..…..15

Humpreys v. Wooldridge, 408 S.W.3d 261 (Mo. App. 2013) ……..….…..59

Page 5: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

5

Hurricane Deck Holding v. Pub. Serv. Comm., 289 S.W.3d 260

(Mo. App. 2009) ……………………………………………………..…28

Illinois Landowners Alliance v. Illinois Commerce Commission,

90 N.E. 3d 448 (IL 2017)…………………………………………....….56

Illinois Landowners Alliance v. Illinois Comm. Comm’n,

60 N.E.3d 150 (Ill. App. 2016)…………………………………………..44

Khulusi v. Southwestern Bell Yellow Pages, Inc., 916 S.W.2d 227

(Mo. App. 1995) ………………………………………………….….41, 42

Kansas City Southern Railway Co. v. Garvey, 592 S.W.2d 703

(Mo. banc 1980) …………………………………………………………53

Lincoln County Stone Co. v. Koenig, 21 S.W.3d 142

(Mo. App. 2000) ………………………………………………….…..…56

May Department Stores Co. v. Union Electric Light & Power,

107 S.W.2d 41 (Mo. 1937) ………………………………………….46, 49

Osage Water Company v. Miller County Water Authority,

950 S.W.2d 569 (Mo. App. 1997) …………………………………...….41

Obetz v. Boatmen’s Nat. Bank, 234 S.W.2d 618 (Mo. 1950) …………..…53

Palmer v. City of Liberal, 64 S.W.2d 265 (Mo. 1933). ……………..…19, 40

Reinhold v. Fee Fee Trunk Sewer, 664 S.W.2d 599 (Mo. App. 1984)….....35

Snyder v. State, 288 S.W.3d 301 (Mo. App. 2009)…………………..……66

Page 6: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

6

Sonken-Galamba Corp. v. Missouri Pacific R.R. Co., 40 S.W.2d 524

(Mo. App. 1931) ………………………………………………………..26

Southern Star Central Gas Pipeline v. Murray, 190 S.W.3d 423

(Mo. App. 2006). ……………………………………………………….58

Standard Operations, Inc. v. Montague, 758 S.W.2d 442

(Mo. banc 1988) …………………………………………………….….52

State ex rel. Atmos Energy Corp. v. Pub. Serv. Comm’n.,

103 S.W.3d 753 (Mo. banc 2003)……………………………….….….20

State ex rel. Buchanan County Power Transmission v. Baker,

9 S.W.2d 589 (Mo. banc 1928) …………………………………19, 39, 40

State Ex Rel. City of Grain Valley v. Pub. Serv. Comm.,

778 S.W.2d 287 (Mo. App. 1989) ………………………………….…..35

State ex rel. Crutcher v. Koeln, 61 S.W.2d 750 (Mo. banc 1933)……......52

State ex rel. Howard Electric Cooperative v. Riney, 490 S.W.2d 1

(Mo. 1973) …………………………………………………………….27

State ex rel. Inter-City Beverage Co. v. Missouri Pub. Serv. Comm’n,

972 S.W.2d 397 (Mo. App. 1998) …………………………………….35

State ex rel. Kansas City Power & Light Co. v. McBeth,

322 S.W.3d 525 (Mo. banc 2010) …………………………………….56

State ex rel. Koeln v. Lesser, 141 S.W. 888 (Mo. 1911) ……………….53

Page 7: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

7

State ex rel. McKittrick v Missouri Pub. Serv. Comm’n,

175 S.W.2d 857 (Mo. banc 1943) …………………………..…19, 24, 30

State ex rel. M. O. Danciger & Co. v. Pub. Serv. Comm’n of Mo.,

205 S.W. 36 (Mo. 1918) ……………………………………..……passim

State ex rel. Doniphan Telephone Co. v. Pub. Serv. Comm’n,

377 S.W.2d 469 (Mo App. 1964) …………………………………..…..26

State ex rel. Public Counsel v. Public Service Comm., 259 S.W.3d 23

(Mo. App. 2008). ……………………………………………..……..….24

State ex rel. Utility Consumers Council v. Public Serv. Comm’n,

585 S.W.2d 41 (Mo. banc 1979) ………………………....…22, 24, 31, 49

State on inf. Barker v. Kansas City Gas Co., 163 S.W. 854

(Mo. banc 1913) ...………………………………………………..……..26

Tetzner v. State, 446 S.W.3d 689 (Mo. App. 2014) ………………..….…..21

Tsevis v. J & F Industries, 51 S.W.3d 91 (Mo. App. 2001) ……..….…….59

Union Electric Co. v. City of Crestwood, 499 S.W.2d 480

(Mo. 1973) ………………………………………………………..….….10

Statutes

Section 386.510 RSMo………………………………………………….….9

Section 477.050 RSMo…………………………………………………….10

Section 393.170 RSMo………………………………………………passim

Page 8: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

8

Section 386.020 RSMo ………… ……………………………….…passim

Section 393.130 RSMo ………………………………………………24, 30

Section 393.140 RSMo………………………………………………..... 55

Section 386.500 RSMo………………………………………………..... 65

Laws of Missouri

Laws of Missouri 1947 V. II p. 338…………………………….………..48

Laws of Missouri 1957 p. 502 …………………………………………..48

Missouri Supreme Court Rules

Rule 84.04 …………………………………………………….……...17, 65

Public Service Commission Rules

Rule 4 CSR 240-10.145 ……………………………………………..….55

Rule 4 CSR 240-3.175(1)…………………………………………….…55

Rule 4 CSR 240-2.160….…………………………………………….…65

Other

Am. Jur. ……….. ………………………………………………...……27

Am. Jur. 2d ……….. …………………………………………………...53

Corpus Juris Secundum ………………………………………….....46, 59

Page 9: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

9

JURISDICTIONAL STATEMENT

The Eastern Missouri Landowners Alliance DBA Show Me

Concerned Landowners (“Show Me”), Christina Reichert and Missouri Farm

Bureau appeal the “Report and Order on Remand” issued by the Public

Service Commission (“Commission”) on March 20, 2019, in case number

EA-2016-0358 (hereafter referred to as the “final Report and Order,” at A1

et seq.; Vol. 25, LF 4139 et seq.)1 Appellants contend the Commission

lacked the statutory authority and thus the subject matter jurisdiction to issue

a Certificate of Convenience and Necessity to Grain Belt. This issue does

not fall within the exclusive jurisdiction of the Supreme Court of Missouri

under Article V, Sec. 3 of the Missouri Constitution.

The Eastern District of the Court of Appeals has jurisdiction of this

appeal under § 386.510 (A97) because local public hearings in this case

were held by the Commission in Monroe and Ralls counties – both of which

1 Inadvertently, Volume 25 of the Legal File as originally filed with the

Court by the Commission was actually a duplicate copy of Volume 24. (See

Commission’s Motion to File Corrected Volume 25 of Legal File, filed June

13, 2019). Volume 25 (which includes the Commission Order on appeal)

can be found in the Case.net docket entries under “Other Motion”, following

the list of the “confidential exhibits” in the record on appeal.

Page 10: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

10

are within the territorial jurisdiction of this Court under § 477.050 (A100).2

See A6, n.4; LF 4144, n.4.

STATEMENT OF FACTS

Background and Procedural History.

On August 30, 2016, Grain Belt Express Clean Line LLC (“Grain

Belt”) filed an Application with the Commission for a Certificate of

Convenience and Necessity (“CCN”), seeking permission pursuant to §

393.170 to build an electric transmission line across eight counties in

northern Missouri. LF 95, 4143.

Grain Belt is an Indiana limited liability company. The ultimate

parent company of Grain Belt is Clean Line Energy Partners LLC (“Clean

Line”), a Delaware limited liability company. Both are headquartered in

Houston, Texas. LF 99-100.

A similar Application for a CCN was filed by Grain Belt in 2014, but

was rejected by the Commission. See Report and Order at A69 et seq.3

2 All statutory references are to RSMo 2016, as amended, except as otherwise

noted.

3 The courts may take judicial notice of Orders of the Public Service

Commission. See Union Electric Co. v. City of Crestwood, 499 S.W.2d 480,

485 n.3 (Mo. 1973) where the Court took judicial notice of several

Commission Orders.

Page 11: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

11

The appellants were among the two dozen or so entities and

individuals allowed by the Commission to intervene in the case below. LF

4144. In the “initial phase” of the case, testimony from supporters and

opponents of the line was submitted by 54 different witnesses. LF 1262-65.

(The term “initial phase” of this case refers here to proceedings at the

Commission prior to the remand from the Missouri Supreme Court, as

discussed hereafter).

As described in Grain Belt’s Application, the Missouri segment of the

proposed project is to be a part of a transmission line which would run

approximately 780 miles from western Kansas to Indiana. Grain Belt’s

objective is to collect and transmit over its line approximately 4,000

megawatts (MW) of renewable wind generation from wind farms in western

Kansas. Approximately 500 MW would be delivered to a converter station

in Ralls County, Missouri. The other 3,500 MW would be delivered to a

converter station near the Illinois-Indiana boarder. From there it would be

distributed to buyers in what is known as the PJM market, including states

along the Eastern Seaboard. LF 96, 101-03, 4147; Tr. Vol. 12, 481:15-18.

Grain Belt is not proposing to buy or sell any electricity. Instead, it

would only sell “capacity” on its proposed transmission line; i.e., the right to

use the line to transmit electrical energy which others would buy and sell.

Page 12: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

12

Grain Belt expects to sell capacity on the line to two primary types of

entities. The first would be wind farms in Kansas, which would buy

capacity on the line to transmit their energy to wholesale purchasers located

in Missouri and states further east (e.g., to traditional investor-owned

utilities or municipally-owned utilities). Second, capacity could be bought

by the wholesale purchasers themselves (the traditional utilities or

municipally-owned utilities, e.g.), which would buy energy from the Kansas

wind farms, and use the Grain Belt line to transmit that energy to their own

service areas. See LF 4149, par. 12 & 13; LF 4162, par. 71 & 72; LF 4176;

Exh 100, LF Exh. Vol. 76, 4638, 4659-60, 4666-67; Exh. 111, LF Exh. Vol.

81, 5150-51; Exh. 104, LF Exh. Vol. 42, 2080-81.

In other words, Grain Belt proposes to act as a link, or middleman,

between the Kansas wind generators on the one hand, and wholesale

purchasers in Missouri and states further east on the other. LF 2857; LF

4176; LF 4181.

Grain Belt has sold capacity on its line to two entities. It sold the

rights for 100 MW of capacity on the segment of the line from Kansas to

Missouri to an entity commonly referred to as MJMEUC, with an option for

MJMEUC to purchase an additional 100 MW. MJMEUC is an organization

which purchases power for its members, which consist primarily of

Page 13: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

13

municipally owned utilities in Missouri. Exh. 115, LF Exh. Vol. 82, 5243;

Exh. 475, LF Exh. Vol. 59, 3489.

Grain Belt also has a contract with Realgy Energy Services for 25

MW to be delivered in Missouri, and 25 MW in Illinois. Exh. 141, p. 3; LF

Exh. Vol. 71, 4277.

There is also a third option for the sale of the line’s capacity. Under

its amended contract with Grain Belt, MJMEUC also agreed to purchase 25

MW of capacity (with an option for a second 25 MW) which could be used

by municipal utilities to transmit their own power from Missouri to the

converter station in Illinois. LF 152, par. 26; Exh. 104, LF Exh. Vol. 42,

2080; Exh. 115, LF Exh. Vol. 82, 5243-44. However, none of the MJMEUC

member utilities have expressed any interest in using that 25 MW of

capacity. Tr. Vol. 16, 1078:2-5. Nor is there any evidence that any other

utility has purchased any of the available capacity on the segment of the line

from Missouri to Illinois.

Regardless of the type of entity which wishes to buy capacity on the

line, the Federal Energy Regulatory Commission (FERC) has authorized

Grain Belt to establish its rates for the entire 4,000 MW of capacity on its

line through individual negotiations with potential purchasers of that

Page 14: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

14

capacity. See FERC Order, LF Exh. Vol. 40, 1939, 1941, 1953; and Exh.

100, LF Exh. Vol. 76, 4660.

On a different subject, as Grain Belt noted in its Application to the

Missouri Commission the fundamental test for granting a CCN under the

applicable statute (§ 393.170) is whether the proposed project is “necessary

or convenient for the public service.” LF 104; and see statute at A101.

In making this determination, the Commission typically analyzes

these five criteria developed in an earlier CCN decision, commonly referred

to as the Tartan case4: (1) there must be a need for the service which the

applicant is proposing to provide; (2) the proposal must be economically

feasible; (3) the applicant must have the financial ability to provide the

proposed service; (4) the applicant must be qualified to provide the service;

and (5) the proposed service must be in the public interest. See LF 104, LF

4178.

The Commission issued a Report and Order in the initial phase of this

case on August 16, 2017, hereafter referred to as the “initial Report and

Order”. LF 2847 et seq. That decision did not reach the merits of whether

the proposed line met the Tartan criteria, and did not decide whether the

4 In re Tartan Energy, Report and Order, 3 Mo.P.S.C. 3d 173, Case No. GA-

94-127, 1994 WL 762882 (September 16, 1994).

Page 15: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

15

Grain Belt project would be necessary or convenient for the public service.

Id.

Instead, based on a decision from the Western District of the Court of

Appeals, the Commission found it could not lawfully issue a CCN until

Grain Belt had first gained the consent under § 229.100 to build the line

from the County Commission in each of the eight Missouri counties to be

traversed by the line. Finding that Grain Belt had not obtained all of those

consents, the Commission denied Grain Belt’s application for the CCN. LF

2858-61.

Grain Belt appealed the initial Report and Order to this Court. The

Court held that the Western District’s decision was in error, and that Grain

Belt was not required to obtain the county consents before the Commission

could issue the CCN. Grain Belt Express Clean Line LLC v. Public Serv.

Comm’n, No. ED105932 (Mo. App. Feb. 27, 2018).

On transfer, the state Supreme Court likewise held that the

Commission could issue the CCN before Grain Belt obtained all of the

needed county consents. Grain Belt Express Clean Line LLC v. Public Serv.

Comm’n, 555 S.W.3d 469 (Mo. banc 2018). The Supreme Court therefore

reversed the Commission’s initial Report and Order and remanded the case

Page 16: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

16

to the Commission “to determine whether Grain Belt’s proposed utility

project is necessary or convenient for the public service.” Id. at 473.

None of the parties to the appeal of the initial decision raised the issue

of whether the Commission had the statutory authority or the subject matter

jurisdiction under § 393.170 to issue the CCN to Grain Belt. Thus, the issue

was not addressed by either court.

Shortly after the case was remanded by the Supreme Court, the

Commission established a procedural schedule for the receipt of evidence

regarding any significant changes affecting the Grain Belt project in the two-

year period since the filing of the initial testimony in that case. LF 3314 et

seq.

The testimony in the remand phase showed (among other things) that

Grain Belt was proposing to sell itself to a company named Invenergy

Transmission LLC (“Invenergy”) A18-19; LF 4156-57. After two days of

additional hearings on remand (A7; LF 4145), on March 20, 2019, the

Commission issued the final Report and Order which is the subject of this

appeal. A1 et seq.; LF 4139 et seq.

In the final Report and Order the Commission unanimously granted

Grain Belt the CNN for which it had applied on August 30, 2016. A51; LF

4189.

Page 17: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

17

In reaching its decision, the Commission found that contrary to the

arguments of those opposing the line, Grain Belt qualified as an “electrical

corporation” under Missouri law. A37-40; LF 4175-78. Accordingly, the

Commission concluded it had the statutory authority to issue the CCN to

Grain Belt pursuant to § 393.170. Id.

The Commission also went into considerable detail as to why the

Grain Belt project met the five traditional Tartan criteria, and was necessary

or convenient for the public service. A40-47; LF 4178-85.

The appellants are not challenging the sufficiency of the evidence to

support the Commission’s final Report and Order. And as Rule 84.04(c)

indicates, the Statement of Facts need only include those facts which are

relevant to the questions presented on appeal. Accordingly, there is no need

here to set forth in any further detail the evidence and findings which

support the final Report and Order.

Facts related to the claim of error.

As discussed in Section C of the Argument below, the Commission

had the statutory authority to issue the CCN to Grain Belt under § 393.170

only if Grain Belt met the definition of an “electrical corporation” in §

386.020(15). A103. This question in turn depends on whether or not Grain

Page 18: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

18

Belt owns, operates, controls or manages any item of “electric plant,” as

defined in subsection (14) of that statute. A103.

The Commission found that Grain Belt qualified as an electrical

corporation under subsections (14) and (15) based on two types of electric

plant: (a) the 39 easements which it had secured on the right-of-way of the

proposed line, which the Commission found were “controlled” or

“managed” by Grain Belt; and (b) an unspecified amount of cash owned by

Grain Belt. A37; LF 4175.

Based on these findings, the Commission held that Grain Belt

qualified as an electrical corporation and a public utility, and could therefore

be granted the CCN under § 393.170. A37-38; LF 4175-76.

For purposes of the issues in this case, the terms “public utility” and

“electrical corporation” are essentially interchangeable. See the definition of

“public utility” at § 386.020(43), A104.

POINT RELIED ON

THE PUBLIC SERVICE COMMISSION OF THE STATE OF

MISSOURI (“COMMISSION”) ERRED IN GRANTING A

CERTIFICATE OF CONVENIENCE AND NECESSITY (“CCN”)

TO GRAIN BELT EXPRESS CLEAN LINE LLC (“GRAIN

BELT”) PURSUANT TO SECTION 393.170 BECAUSE THE

Page 19: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

19

COMMISSION LACKED THE STATUTORY AUTHORITY AND

THUS THE SUBJECT MATTER JURISDICTION TO ISSUE THE

CCN, IN THAT GRAIN BELT IS NOT AN “ELECTRICAL

CORPORATION”, AS IS REQUIRED FOR ISSUANCE OF A

CCN UNDER SECTION 393.170.

State ex rel. M. O. Danciger & Co. v. Pub. Serv. Comm’n of Mo., 205

S.W. 36 (Mo. 1918).

State ex rel. Buchanan County Power Transmission v. Baker,

9 S.W.2d 589 (Mo. banc 1928).

Palmer v. City of Liberal, 64 S.W.2d 265 (Mo. 1933).

State ex rel. McKittrick v. Missouri Pub. Serv. Comm’n, 175 S.W.2d

857 (Mo. banc 1943).

Sections 386.020(14) and (15) RSMo.

Page 20: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

20

STANDARD OF REVIEW

In Grain Belt’s appeal of the Commission’s initial Report and Order,

the Missouri Supreme Court described the standard of review in

Commission cases as follows:

Pursuant to section 386.510, appellate review of an order by the

Commission is two-pronged: first, the reviewing court must

determine whether the [Commission’s] order is lawful; and

second, the court must determine whether the order is

reasonable. The Commission’s order is presumed valid, and the

burden of showing the order is unlawful or unreasonable rests

with the appellant. All questions of law are reviewed de novo.

Grain Belt Express Clean Line, LLC, supra, 555 S.W.3d at 471.

(citations and internal quotation marks omitted).

As to the point regarding de novo review of legal issues, the Supreme

Court has also stated that “[t]here is no presumption in favor of the

Commission’s resolution of legal issues.” State ex rel. Atmos Energy Corp.

v. Pub. Serv. Comm’n., 103 S.W.3d 753, 759 (Mo. banc 2003).

ARGUMENT

THE PUBLIC SERVICE COMMISSION OF THE STATE OF

MISSOURI (“COMMISSION”) ERRED IN GRANTING A

Page 21: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

21

CERTIFICATE OF CONVENIENCE AND NECESSITY (“CCN”)

TO GRAIN BELT EXPRESS CLEAN LINE LLC (“GRAIN

BELT”) PURSUANT TO SECTION 393.170 BECAUSE THE

COMMISSION LACKED THE STATUTORY AUTHORITY AND

THUS THE SUBJECT MATTER JURISDICTION TO ISSUE THE

CCN, IN THAT GRAIN BELT IS NOT AN “ELECTRICAL

CORPORATION”, AS IS REQUIRED FOR ISSUANCE OF A

CCN UNDER SECTION 393.170.

Grain Belt has asked the Commission to grant it a CCN to build

an electric transmission line in Missouri, pursuant to § 393.170. LF95.

As it applies to this case, that statute essentially states that no

“electrical corporation” may construct any “electric plant” without first

obtaining a CCN from the Commission. See § 393.170 (1);A101.

Accordingly, if Grain Belt is not an electrical corporation, the

Commission has no authority under that statute (or any other statute cited by

the Commission or by Grain Belt) to approve the construction of the

proposed line.

If the Commission is not authorized by statute to grant the CCN, then

it lacks subject matter jurisdiction to do so. Tetzner v. State, 446 S.W.3d

689, 692 (Mo. App. 2014) (stating that “[a]s a basic tenet of administrative

Page 22: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

22

law, an administrative agency has only such jurisdiction as may be granted

by the legislature. If the agency lacks statutory authority to consider a

matter, it is without subject matter jurisdiction”). (citation and internal

quotation marks omitted). See also State ex rel. Utility Consumers Council

of MO v. Pub. Serv. Comm’n, 585 S.W.2d 41, 54 (Mo. banc 1979) (noting

that the PSC’s jurisdiction is set by statutes enacted by the legislature).

As discussed in points A, B and C respectively, appellants have three

lines of argument which independently demonstrate that Grain Belt is not an

“electrical corporation.” The first two are grounded on case law, while the

third is based strictly on the statutory definition of an electrical corporation.

A. Based on case law, Grain Belt is not an electrical corporation

because it is not subject to all of the statutes which comprise the Public

Service Commission Act.

The leading case on this issue was decided just 5 years after passage

of the Public Service Commission Act in 1913: State ex rel. M. O. Danciger

& Co. v. Pub. Serv. Comm’n of Mo., 205 S.W. 36 (Mo. 1918).

The Court held in Danciger that an entity either is a public utility, or it

is not. There is no middle ground. And one defining characteristic of a

public utility is that it must be subject to all of the laws in the Public Service

Page 23: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

23

Commission Act. If it is not subject to all of those provisions, then the

entity is not an electrical corporation under Missouri law.

In the words of Danciger: “It is certainly fundamental that the

business done by respondent either constitutes him a ‘public utility’ or it

does not. If he is a public utility, he is such within the whole purview, and

for all inquisitorial and regulatory purposes of the Public Service

Commission Act.” Id. at 40. (emphasis added).

As the Court went on to say, if the respondent in that case was in fact

a public utility, he must be subject to all provisions of that Act, including the

one which allows the Commission to compel him to provide service to all

entities within a defined geographic area. Id. Finding that the Commission

lacked such authority with respect to Danciger, the Court concluded that he

therefore was not a public utility. Id.

Here, it is undisputed that Grain Belt’s rates are to be regulated by the

FERC, and that they will not be regulated by the Missouri Commission.

Exh. 100, LF Exh. Vol. 76, 4660; LF 149, 171. Accordingly, Grain Belt will

not be subject to the laws in Missouri which specify how electric rates are to

be determined.

For instance, Missouri statutes provide for several specific methods by

which rates may be established for electric utilities subject to the jurisdiction

Page 24: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

24

of the Commission. State ex rel. Utility Consumers Council v. Public Serv.

Comm’n, supra, 585 S.W.2d 41, 48 (Mo. banc 1979). Because Grain Belt’s

rates will be regulated by the FERC, it will be exempt from the statutory

ratemaking provisions described in State ex rel. Utility Consumers Council,

supra.

Also, Missouri’s anti-discrimination laws, §§ 393.130.2. and

393.130.3 (A109-10), provide among other things that an electric utility may

have two or more rates if the rates are for different types of service, but is

forbidden from having two or more rates for the same service.5 State ex rel.

McKittrick v. Missouri Pub. Serv. Comm’n, 175 S.W.2d 857, 866 (Mo. banc

1943) (discussing § 5645, which is a predecessor of § 393.130. See

legislative notes to § 393.130, at A110). Grain Belt would be exempt from

these requirements as well.

Because Grain Belt will not be subject to the Missouri statutes dealing

with ratemaking, by definition it will not be subject to “the whole purview”

of the Public Service Commission Act. This is a simple, objective test,

5 The comparable laws for telephone service have been referred to as “anti-

discrimination” statutes. State ex rel. Public Counsel v. Public Service

Comm., 259 S.W. 3d 23, 32 (Mo. App. 2008).

Page 25: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

25

leaving no room for subjective interpretation. Accordingly, under Danciger,

the Court has no choice but to find that Grain Belt is not a public utility.

The theory behind the Danciger decision makes perfect sense. A

policy would be fundamentally unsound if it recognizes a new class of

“quasi-utilities” which are permitted to enjoy certain benefits of the state’s

regulatory laws, while at the same time avoiding other provisions which

might prove to be inconvenient, if not insurmountable.

Were it not for the ruling in Danciger, for example, Grain Belt could

utilize § 393.179 to obtain a CCN from the Commission (which in turn

would presumably give it the right of eminent domain under § 523.010

(A130)), while at the same time avoiding other Missouri statutes which

would prevent it from setting its own rates through bilateral negotiations

with its customers.

Based on Grain Belt’s latest financial statements from the time of the

hearings in this case, the benefits of such a quasi-utility status are reflected

in Grain Belt’s own projection for its long-term rate of return on this project.

That figure was designated below as confidential by Grain Belt, but is

available at Confidential Tr. Vol. 15, 893:20 – 894:6. See also Id. at 891:13

– 892:2.

Page 26: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

26

Danciger inherently assumes that the Public Service Commission Act

is a complete, unified regulatory package. Exemption from one provision

means exemption from all. As such, the Act should not be subject to hit-or-

miss and pick-and-choose enforcement, regardless of the FERC’s

involvement. See Sonken-Galamba Corp. v. Missouri Pacific R.R. Co., 40

S.W. 2d 524, 528 (Mo. App. 1931) (finding that the intent of the Public

Service Commission Act was “to leave to the commission the entire subject

and field of rate regulation, including unjust discrimination and other abuses

….”); State on inf. Barker v. Kansas City Gas Co., 163 S.W. 854, 857-58

(Mo. banc 1913) (referring to the Act as an “elaborate law” which, to be

effective, “must possess the power of intelligent visitation and the plenary

supervision of every business feature to be finally … reflected in rates and

quality of service.”); and State ex rel. Doniphan Telephone Co. v. Pub. Serv.

Comm’n, 377 S.W.2d 469, 474 (Mo App. 1964) (describing the Public

Service Commission Act as “a complete system of law for the regulation of

public utilities by the Commission.”).

On another aspect of this issue, in pleadings at the Commission Grain

Belt subtly questioned the value of the Danciger opinion on the ground that

it was a “century-old case.” LF Vol. 24, 3865. But if anything, that factor

serves to bolster the precedential importance of that decision today.

Page 27: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

27

In State ex rel. Howard Electric Cooperative v. Riney, 490 S.W.2d 1,

9 (Mo. 1973) the Supreme Court described the logic behind that proposition.

Based on a passage from Am. Jur. Statutes, the Court described the

applicable law as follows:

The fact that the legislature has not seen fit by

amendment to express disapproval of a contemporaneous or

judicial interpretation of a particular statute, has been referred

to as bolstering such construction of the statute, or as

persuasive evidence of the adoption of the judicial

construction. In this respect, it has been declared that where

a judicial construction has been placed upon the language of

a statute for a long period of time, so that there has been

abundant opportunity for the lawmaking power to give further

expression to its will, the failure to do so amounts to

legislative approval and ratification of the construction placed

upon the statute by the courts, and that such construction

should generally be adhered to, leaving it to the legislature to

amend the law should a change be deemed necessary.

Page 28: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

28

Obviously, the General Assembly has chosen not to disturb the

holding in Danciger that an entity is not a public utility unless it is subject to

the entire purview of the Public Service Commission Act.

In fact, a 2009 decision from the Western District stated that “[t]he

statutory provisions on which Danciger relied remain largely unchanged

today, and more recent decisions continue to cite and follow Danciger’s

holding ….” Hurricane Deck Holding v. Pub. Serv. Comm., 289 S.W.3d

260, 264 (Mo. App. 2009).

Clearly, Danciger is still good law today. And so even without

further support or argument, as addressed in Sections B and C below, the

Danciger decision alone leaves the Court with no choice but to find that

Grain Belt is not an electrical corporation or public utility.

B. Based on case law, Grain Belt is not an electrical corporation

because it will not be devoted to the “public use”.

Appellants’ second argument based on case law is that the Grain Belt

project will not be devoted to the “public use”, as that term is defined in

decisions from Missouri and elsewhere. And if an entity is not devoted to

the public use, case law further says that it does not qualify as a public utility

or an electrical corporation.

Page 29: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

29

The reason why Grain Belt does not meet the public use requirement

established by case law lies in the manner by which Grain Belt’s rates and

other terms of service will be established under authority of the FERC.

Therefore, appellants will first discuss in more detail how Grain Belt’s rates

are established under applicable FERC regulations. They will then

demonstrate why the FERC/Grain Belt model does not qualify as a “public

use” under applicable case law.

i. The Grain Belt/FERC model for establishing rates and other

terms of service.

Grain Belt will not be selling any transmission service directly to

retail customers in Missouri. LF 123; LF Exh. Vol. 76, 4660. Instead, it

will sell the capacity on its line both to wind generators on the Kansas end of

the line, and to wholesale entities in Missouri and states further east (e.g., to

investor-owned or municipal utilities.) See, e.g., Exh. 100, LF Exh. Vol. 76,

4660.

The rates for this service will be subject to regulation by the FERC,

not the Missouri Commission. And under FERC regulation, Grain Belt has

the authority to establish rates for the entire capacity of the line through

bilateral negotiations with individual customers. Exh. 100, LF Exh. Vol. 76,

4660.

Page 30: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

30

In other words, under the FERC’s model for such transmission

projects, Grain Belt would negotiate one-on-one with a potential customer in

an attempt to reach agreement on the key rates, terms and conditions of the

purchase of capacity on the line. Exh. 111 p. 9-10; LF Exh. Vol. 81, 5155-

56.

And as one of Grain Belt’s witnesses observed, the FERC model to

which Grain Belt is subject is “markedly different” from the regulatory

model used for traditional utilities. Id. at p. 5; 5155.

As demonstrated below, establishing rates through bilateral

negotiations with each individual customer will inevitably produce different

rates for similarly situated customers. This practice, under Missouri law,

would be in direct violation of Missouri’s anti-discrimination statute, §

393.130.2, as discussed in State ex rel. McKittrick v Missouri Pub. Serv.

Comm’n, supra.

As one example of how the negotiation process actually works in

practice, as the projected in-service date of its proposed line was delayed,

MJMEUC approached Grain Belt about reducing the rates they had

negotiated earlier. As a result of further negotiations between the two

parties, MJMEUC secured a 30% reduction in its second 100 MW of

capacity. Tr. Vol. 24, 2115:1 – 2116:19. Establishing rates on the basis of a

Page 31: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

31

customer’s unique leverage with the supplier is not one of the ratemaking

procedures recognized and discussed in State ex rel. Utility Consumers

Council v. Public Serv. Comm’n, supra, 585 S.W.2d 41, 48 (Mo. banc

1979).

And as would be expected when a utility is allowed to negotiate

different rates with different customers, the rates for those customers are

bound to be different. Mr. Zadlo is a Senior Vice President with Invenergy,

the company poised to purchase the Grain Belt project. Exh. 145, p. 1; LF

Exh. Vol. 72, 4318. As Mr. Zadlo testified, under FERC regulation, two

somewhat similar, nearly identical customers, could end up with two

different rates as a result of the negotiating process. Tr. Vol. 22, 2038:222 –

2019:9.

One reason for the disparities lies in the very process used to select

the customers with whom Grain Belt (or Invenergy) will choose to negotiate.

As Mr. Zadlo explained:

And first you have an open season [an open solicitation of

bids], you see which individuals will -- are willing to pay. And

then you … chose the best – the offers – the best offers that you

receive and try to negotiate a rate with them.

Tr. Vol. 22, 2041:7-11.

Page 32: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

32

In other words, Invenergy (or Grain Belt) will begin its negotiations

with the highest bidders and work its way down. So, as Invenergy logically

seeks to maximize its profits, rate disparities in such a process are inevitable.

In addition, in its application to the FERC, Grain Belt stated that the

criteria used in its selection of customers would include a minimum

purchase of 50 MW of capacity, for a minimum term of at least five years.

Exh. 322; LF Exh. Vol. 40, 1947, par. 20.

On their face, these criteria produce inherent advantages to larger

customers over smaller customers. In fact, the latter are excluded from the

process all together. In contrast, of course, utilities subject to regulation by

the Commission are required to serve all customers within their service

territory, regardless of the size of the customer. And as the Court is no

doubt aware, customers are not routinely locked into a fixed-term contract

for their electric service.

As another example of how the FERC method works in practice,

Grain Belt has thus far negotiated contracts for the sale of capacity with only

two entities: MJMEUC, and Realgy Energy Services. Exh. 141, p. 3; LF

Exh. Vol. 71, 4277.

Under the amended contract with MJMEUC, its rate for capacity on

the Grain Belt line is $1,167 per MW per month (or $1.167 per KW per

Page 33: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

33

month), escalating at 2% annually. Exh. 480, LF Vol. 74, 4583, 4590. The

rate and escalation factor negotiated with Realgy are considered confidential

by Grain Belt, and therefore cannot be disclosed here. But that data are

available at Exh. 208C, Confidential Exh. Vol. 29, 1420, lines 6-7. Thus the

two rates may be readily compared by the Court if it so desires.

The manner in which Grain Belt applies its negotiated rate making

authority is also illustrated by the process in which it negotiated its initial

contract with MJMEUC.

When the Commission rejected Grain Belt’s Application for a CCN in

the 2014 CCN case, it noted that Grain Belt had not signed a single contract

for the sale of the 500 MW of capacity it proposed to deliver to Missouri.

Report and Order p. 10 par. 22; A79. The Commission also found that a

reasonably prudent Missouri electric utility would not be likely to obtain

wind energy transmission over the Grain Belt line. Id. at p. 23-24; A92-93.

In anticipation of a second application for a CCN in Missouri, Grain

Belt then made a concerted effort to sell capacity to Missouri buyers,

including Ameren, Associated Electric Cooperative, and individual

municipal systems. Tr. Vol. 10, 201:11-17; 200:23-201:6; 200:14-16; Tr.

Vol. 16, 1042:2-5. Those efforts, including Grain Belt’s initial attempts to

Page 34: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

34

sell capacity to MJMEUC, were all unsuccessful. Tr. Vol. 16, 990:1-6; 990:

9-12; Tr. Vol. 16, 1041:6-19; 1046:20-1047:5.

Eventually, Grain Belt made an offer which MJMEUC could not

refuse. In a special deal offered only to MJMEUC, the price for the first 100

of the 200 MW offer was initially set at only about 20% of the normal rate

which Grain Belt would charge to other customers for the same transmission

service from Kansas to Missouri. Tr. Vol. 14, 853:18-854:3. (And as

indicated above, Grain Belt later dropped the price for the second 100 MW

to this same low rate. Exh. 480, LF Exh. Vol. 74, 4582-83.)

Stated in other terms, Grain Belt’s price to MJMEUC amounted to

only one third of a cent per kwh for its transmission service. Tr. Vol. 14,

854:9-23. In contrast, Grain Belt estimated that its actual cost of moving the

power from Kansas to Missouri would be about five times that amount. Tr.

Vol. 14, 855:15-856:23. So Grain Belt effectively used its negotiated rate

authority from FERC to sell capacity at a rate drastically below its own cost

of providing that service. It is fair to assume this contract was the

culmination of Grain Belt’s effort to finally sign a contract for use of its line

in Missouri, which would hopefully sway the Commission when Grain Belt

filed its second application for a CCN.

Page 35: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

35

And Grain Belt expects to extract a higher price from future buyers.

Tr. Vol. 14, 948:6 – 950:13. In fact, if Grain Belt did not sell to other buyers

at a price above its own cost, it obviously could not survive.

If Grain Belt and Invenergy were subject to Missouri laws, its rates

and terms of service would clearly be in violation of Missouri’s anti-

discrimination statutes, § 393.130.2 and .3. See State Ex Rel. City of Grain

Valley v. Pub. Serv. Comm., 778 S.W.2d 287, 290 (Mo. App. 1989) (holding

that “differences in rates must be based upon a reasonable and fair difference

in conditions which equitably and logically justify a different rate….”, and

that normally these different conditions are based on a difference in the cost

of providing the service.) (internal quotation marks omitted); Reinhold v.

Fee Fee Trunk Sewer, 664 S.W.2d 599, 604 (Mo. App. 1984) (finding that

“[t]he purpose of the Public Service Commission Law … is to secure

equality in service in rates for all who need or desire these services who are

similarly situated.”); and State ex rel. Inter-City Beverage Co. v. Missouri

Pub. Serv. Comm’n, 972 S.W.2d 397, 400 (Mo. App. 1998) (stating that

Section 393.130.2 … “secures equality of services and rates for all who need

or desire the services and who are similarly situated.”)

ii. Given how Grain Belt is allowed to set its rates, under applicable

case law it does not serve a public use, and thus is not a public utility.

Page 36: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

36

The initial case in Missouri on the issue of “public use” was also State

ex rel. M. O. Danciger & Co. v. Pub. Serv. Comm’n of Mo., supra, 205 S.W.

36 (Mo. 1918). As to this particular issue, the main point of Danciger is that

in order to qualify as an “electrical corporation,” an entity must not only

meet the statutory definition of that term, but in addition must be devoted to

what the Court termed the “public use.” Id. at 40.

The relator in Danciger was a part owner and close affiliate of a

brewing company in Weston, MO, which had installed electric generation to

light its facilities and to operate a large part of the machinery used in its

brewing process. Danciger at 37.

The brewery found that it had excess capacity from its generating

facilities, and through its affiliate Danciger began selling electricity to

customers within a three block radius of the brewery. Eventually, Danciger

was selling electricity at different rates to the town of Weston; to between 20

and 30 other businesses; and to some 10 individual residences. Id. at 37-38.

Danciger later discontinued service to several of its customers, who

filed a complaint with the Public Service Commission. The Commission

found that Danciger qualified as a regulated public utility and ordered that

the service be restored. Id. at 39-40.

Page 37: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

37

On appeal, the state Supreme Court reversed that ruling. The key

issue was whether Danciger was or was not an “electrical corporation”, as

that term is defined in what is now § 386.020(15).6

The Supreme Court first found that although the statutory definition of

an “electrical corporation” includes no specific reference to public use, or to

the necessity that the sale of the electricity be to the public, “it is apparent

that the words ‘for public use’ are to be understood and to be read therein.”

Danciger at 40.

The Court concluded that the nature of the business in question did

not make Danciger a “public utility”. While Danciger did sell electricity to

some members of the public, the Court held there had been “no explicit

professing of public service, or undertaking to furnish lights or power to the

whole public, or even to all persons in that restricted portion thereof who

reside within three blocks of the Company’s plant ….” Id. (emphasis

added).

Similarly, Grain Belt will sell to those customers which are willing to

pay the highest price. That is the very essence of setting rates on the basis of

bilateral negotiations. Accordingly, Grain Belt is not undertaking to furnish

6 The current version of that statute is essentially unchanged from that at

issue in Danciger. See Id. at 39.

Page 38: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

38

service to the “whole public,” in the sense described by Danciger. And

given that Grain Belt will not be serving the general public indiscriminately,

under Danciger it does not fall within the jurisdiction of the Commission.

Id. at 41-42.

In fact, the finite capacity of the Grain Belt line means it will be able

to serve only a small portion of the customers which have expressed an

interest in buying capacity on the line. Exh. 111; LF Exh. Vol. 81, 5177,

lines 17-18. And yet Invenergy has no plans to make any substantial

changes to the 4,000 MW project, as it was proposed to the Commission in

this case. Exh. 145, p. 10; LF Exh. Vol. 75, 4327.

The Danciger Court went on to punctuate its ruling on this issue by

adopting this passage from what the Court termed an “excellent work on

Public Service Corporations:”

That the business of supplying gas is public in character is

now universally recognized, provided that the company

supplying is committed to supplying gas to the community in

general. But the case can be imagined of an institution with

a generating plant for its own supply, which might even

supply one neighbor, without being obliged to sell to all

others. In the same way the business of supplying electrical

Page 39: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

39

energy has generally been recognized as public in character.

There are, however, several cases where the company

supplying electricity has not professed to sell to the public

indiscriminately at regular rates, but has from the beginning

adopted the policy of entering into special contracts upon its

own terms; such companies are plainly engaged in private

business. (emphasis added)

Danciger at 41.

This last sentence in particular, quoted with approval by the Supreme

Court, precisely describes the proposed operation of the Grain Belt line.

Thus based on Danciger, Grain Belt is not an electrical corporation on two

separate grounds.

Another case based on “public use” is State ex rel. Buchanan County

Power Transmission v. Baker, 9 S.W.2d 589 (Mo. banc 1928). There, the

relator operated a single transmission line between a generation source and

the purchaser of the electricity -- the St. Joseph Railway Light, Heat and

Power Co. The basic issue was which state taxing authority had the right to

tax the transmission line, which in turn depended upon whether or not the

line was a “public utility.” Id. at 591.

Page 40: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

40

One of the taxing authorities argued that while the line did not serve

the public individually, “it is certainly an important link in the distribution of

electric energy to the people of St. Joseph, Missouri.” Id. at 592.

But relying upon Danciger, the Supreme Court found instead as

follows: “the mere purchase, transmission and sale of electric energy, a

commercial product, without more, contains no implication of public

service. On the showing made it must be held that relator is not a public

utility.” Id. at 582.

The service being provided there was essentially the same as what

Grain Belt is proposing here: acting as the transmission link between the

source of the generation and the customers which would buy the power.

Based on Buchanan County, the role of a mere transmission link is not

enough for an entity to qualify as a public utility.

Another applicable Missouri Supreme Court case is Palmer v. City of

Liberal, 64 S.W.2d 265 (Mo. 1933). There, a generating facility (the Cardin

Company) supplied electricity to the city of Liberal, and the city in turn sold

the power to its individual citizens. The Court ruled that under these

circumstances the generating facility was not an electrical corporation which

required a CCN from the Commission. As the Court stated: “The Cardin

Company does not propose to deal with the public, but only to furnish the

Page 41: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

41

city of Liberal with electric current. It is not dealing with the public and it

would not be necessary for the Public Service Commission to give a

certificate of convenience and necessity before it can start operating in this

State.” Id. at 268.

Here, Grain Belt has sold some of its capacity to MJMEUC, e.g.,

which in turn will sell that capacity to its member utilities, which in turn will

sell to the end-use customers. See Tr. Vol. 16, 984:21-23. However, Grain

Belt itself “is not dealing with the public” any more than was the Cardin

Company in the Palmer decision. Accordingly, just as in that case, Grain

Belt is not authorized by Missouri law to obtain a CCN from the

Commission.

The three Supreme Court cases discussed above have not been

overruled or diluted as to the basic principles relied upon here by the

appellants.

In a more recent case, one issue was whether the Southwestern Bell

Yellow Pages constituted a public utility. Khulusi v. Southwestern Bell

Yellow Pages, Inc., 916 S.W.2d 227 (Mo. App. 1995).

Relying in part on Danciger, the Court determined that that it did not.

Id. at 232. As summarized in Osage Water Company v. Miller County

Water Authority, 950 S.W.2d 569, 574 (Mo. App. 1997), “[t]he crucial

Page 42: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

42

factor in Khulusi that the court examined to determine that Southwestern

Bell Yellow Pages was not a public utility was that it used ‘private contracts’

to publish advertising, thereby removing it from the realm of public utility

status.”

Similarly, Grain Belt’s operations will be founded on “private

contracts,” negotiated individually with its customers. So on that basis,

Khulusi would say that Grain Belt is likewise not a public utility.

The 8th Circuit of the U.S. Court of Appeals has also weighed in

decisively on the appellants’ side of this issue. In City of St. Louis v.

Mississippi River Fuel Corp., 97 F.2d 726 (8th Cir. 1938), the utility

(Mississippi River) sold natural gas in St. Louis to one wholesale customer

(Laclede Gas), and to 14 industrial customers at retail. Id. at 728. The retail

sales were all “by special contracts, entered into after negotiations with the

customer.” Id. The question on appeal was whether the utility’s operations

were “for public use”, within the meaning of the Danciger decision.

Quoting extensively from Danciger, the 8th Circuit held that the

utility’s operations in St. Louis were not for public use. Among the findings

and conclusions made by the 8th Circuit in reaching that decision were the

following:

Page 43: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

43

● We conclude that under Missouri law the term “for public

use” as used in the ordinance under consideration, means the

sale of gas to the public generally and indiscriminately, and not

to particular persons upon special contract. This construction

of the phrase is the one generally understood and applied.

Id. at 730.

● To constitute a public use all persons must have an equal

right to the use, and it must be in common, upon the same

terms, however few the number who avail themselves of it.

(internal quotations marks omitted.)

Id.

● The sale to the Laclede Company [at wholesale] alone is not

sufficient to transform what is otherwise a private business into

a public business any more than would the sale of a locomotive

to a railroad company make the seller a common carrier.

Id.

Based upon this language from the 8th Circuit, Grain Belt is definitely

not a public utility. In particular, its wholesale contracts with MJMEUC and

Realgy do not transform its business into one “of public use.”

Page 44: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

44

The issue of “public use” was addressed at some length in a recent

decision from an Illinois appellate court, Illinois Landowners Alliance v.

Illinois Comm. Comm’n, 60 N.E.3d 150, 158-160 (Ill. App. 2016).7 That

case involved the question of whether the Rock Island Clean Line (a sister

line of Grain Belt, also owned by Clean Line8) was or was not a “public

utility” under Illinois law. The rates for capacity on the Rock Island line

were also to be established through bilateral negotiations, under authority of

the FERC. Id. at 155.

As in the Danciger case, the Illinois court held that in order to qualify

as a “public utility” the entity in question must not only meet the statutory

definition of a public utility, but must also meet what was essentially the

second test established in Danciger: “a public utility also must provide its

product or service ‘for public use,’ carrying with it the duty of the producer

or manufacturer to serve the public and treat all persons alike, without

discrimination.” Id. at 158.

7 As discussed shortly, this case was transferred to the Illinois Supreme

Court. That Court also found that the Rock Island line was not a public

utility, based on a second line of reasoning from the appellate court.

8 Ex. 100, LF Exh. Vol. 76, 4657.

Page 45: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

45

The Court found that the proposed line did not meet this test, stating

that “[a] private company that provides public utility services according to

its own terms and conditions does not meet the statutory definition of a

public utility.” Id. at 159.

Furthermore, the court found that in order to qualify as a public utility,

the entity must offer its assets for public use without discrimination. But as

the court concluded, the Rock Island line “is not for public use without

discrimination.” Id.

Finally, the Illinois appellate court relied on an earlier Illinois

Supreme Court decision which found that the Mississippi River Fuel

company did not qualify as a public utility in Illinois.

As described in the appellate court decision, that company sold

natural gas through individual contracts with 23 private industrial retail

customers, as well as to 2 public utilities which in turn resold the gas to their

retail customers. In relying on the Illinois Supreme Court’s decision, the

appellate Court found that the company’s contracts were not based on fixed

rates, and instead varied as to terms and conditions; and that the company’s

act of selling gas to a limited group of customers could not be characterized

as “public use.” Id.

Page 46: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

46

Notably, this decision did not turn on any statutory language in

Illinois which differed from that in Missouri.

Appellants’ point here is further reinforced by Corpus Juris

Secundum, which begins the topic of Public Utilities § 7 with the following

statement of the law: “It is a fundamental principle that a public utility may

not discriminate in the distribution of services or the establishment of rates.”

As it goes on to say, “[a] utility must act toward all members of the public

impartially, and treat all alike.” Id.

One other case is instructive as to appellants’ second point based on

case law: May Department Stores Co. v. Union Electric Light & Power, 107

S.W.2d 41 (Mo. 1937). Although the case does not deal directly with the

issue of “public use”, it certainly supports appellants’ position on that

question.

In the May case, an electric generator signed several contracts in 1912

to supply power at specified rates to May and to other nearby customers. Id.

at 45-47. One year later the Public Service Commission Act was passed,

and the threshold question before the Court was whether the passage of that

Act in effect nullified the private contracts for the sale of electricity. Id. at

48.

Page 47: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

47

The Court held that the power of the Commission overrides all such

contracts, Id., and that the provisions of the contracts regarding rates and

service could not stand if they were inconsistent with those adopted by the

Commission. Id. at 49.

Particularly significant here are the following observations and

findings by the Supreme Court in that case:

● Prior to enactment of the Public Service Commission Act in 1913,

customers were left to make the best deal they could negotiate with

competing suppliers. The Act was passed as a result of the growing feeling

that this practice was inadequate to protect the public, and thus was replaced

by “impartial treatment of everyone under regulations approved and

enforced by the State.” Id. at 48.

● Regulation of rates could not be successful without regulating all

rates. Id.

● “The purpose of providing public utility regulation was to secure

equality in service and in rates for all who needed or desired these services

and who were similarly situated.” Id. at 49.

● And finally, in an observation which has proven prophetic in this

case, the Court stated that if rates and other terms of service established by

the Commission could be superseded by private contracts, “the certain result

Page 48: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

48

would be inequality between consumers. If all consumers similarly situated

are to be treated alike, a contract dealing with one on a different basis from

others cannot be recognized.” Id.

While not expressly stating so, the gist of this case is that a system of

privately negotiated contracts does not serve a public use.

Based upon the above decisions, particularly those from our own

Supreme Court, Grain Belt does not qualify as an electrical corporation

under two separate criteria established by case law.

In further support of this position, appellants respectfully refer the

Court to several well established rules of statutory construction (in this case,

construction of the statute defining an electrical corporation).

First, subsequent to the Supreme Court’s decision in Danciger, the

General Assembly on several occasions reenacted §§ 386.020(14) and (15),

which together define the term “electrical corporation”. See summary of

legislative history of § 386.020 at A105, and the 1947 and 1957

reenactments of that section at A120 et seq. and A125 et seq., respectively.

And case law holds that in reenacting those provisions, one must

presume the legislature concurred in Danciger’s conclusions regarding what

does and does not qualify as an electrical corporation under the reenacted

Page 49: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

49

statutes. See State ex rel. Utility Consumers Council, supra, 585 S.W2d at

55.

Similarly, the Supreme Court has held that “[t]he construction of a

statute by a court of last resort becomes a part of the statute as if it had been

so amended by the legislature.” Dow Chemical Co. v. Dir. Of Revenue, 834

S.W.2d 742, 745 (Mo. banc 1992) (internal quotation marks omitted). That

being the case, the statutes defining an electrical corporation have been

imprinted over the years with the decisions cited here by appellants.

Finally, “[i]nsight into the legislature’s object can be gained by

identifying the problems sought to be remedied and the circumstances and

conditions existing at the time of the enactment.” Bachtel v. Miller County

Nursing Home District, 110 S.W.3d 799, 801 (Mo. banc 2003). As

discussed in May Department Stores Co., supra, 107 S.W.2d 41 at 48, a

primary reason for passage of the Public Service Commission Act was to

eliminate the inequalities inherent in individually negotiated contracts for

electric service. Accordingly, the statutes in question should not be

interpreted in a manner which would encourage a return to the very practice

which the General Assembly sought to eliminate.

Page 50: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

50

Grain Belt will no doubt point out, as it did in the Commission

proceedings, that under FERC regulations Grain Belt’s rates must be “just

and reasonable”, and not “unduly discriminatory”. See LF Vol. 24, 3865-66.

But assuming the actual results of Grain Belt’s bilateral negotiations

do meet these FERC ratemaking standards, it is apparent that those quoted

terms have a different meaning to the FERC than they do under Missouri

law. As is clear from the case law cited above, and despite the FERC’s

views on the subject, the ratemaking process employed by Grain Belt would

be inconsistent with Missouri’s own statutory procedures for setting rates.

Appellants are not questioning the wisdom or legality of FERC’s

policy of allowing Grain Belt to establish its rates and other terms of service

through bilateral negotiations with its customers. Nor do appellants contend

on this appeal that any of Grain Belt’s practices fail to comply with

applicable FERC regulations – including the below-cost rate to MJMEUC.

See FERC Order at Exh. 322, LF Exh. Vol. 40, 1939 et seq.

What appellants are saying is that by choosing to build a transmission

line which brings it within FERC’s ratemaking authority, however

meritorious the FERC model may be, Grain Belt cannot at the same time

serve a “public use” as defined by the laws of this state.

Page 51: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

51

C. Grain Belt is not an electrical corporation because it does not meet

the statutory definition of that term.

In addition to its failure to meet the judicially-imposed requirements

discussed above, Grain Belt does not even meet the statutory definition of an

electrical corporation. To qualify as an electrical corporation, an entity must

own, operate, control or manage, in the present tense, some item of “electric

plant”. Section 386.020(15); A103.

Subsection (14) of that statute states that electric plant consists of the

following items: real estate, fixtures, personal property, conduits, ducts or

other devices, materials, and apparatus or property for containing, holding or

carrying conductors used for transmission of electricity. A103. So, if Grain

Belt does not presently own, operate, control or manage any such item of

electric plant, then under § 386.020(15), it does not qualify as an electrical

corporation.

In its final Report and Order, the Commission found that Grain Belt

qualifies as an electrical corporation because it held two types of assets

which the Commission viewed as “electric plant”. One was cash, which the

Commission considered to fall within the term “personal property” under the

definition of electric plant. The second was the 39 easements which Grain

Belt has secured on the proposed right-of-way in Missouri. LF 4175. (To

Page 52: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

52

put this number in perspective, the line will cross the property of

approximately 750 landowners in Missouri. LF 4149).

Starting with the first of these items, appellants contend that cash is

not the type of asset which the General Assembly intended to include within

the definition of “electric plant.”

Instead, appellants contend that the list of items constituting electric

plant is intended to include only assets which will become part of the facility

itself. In other words, “electric plant” means what one would commonly

think of as “electric plant.” And cash does not fit within the type of assets

which are specifically enumerated by the General Assembly in defining the

term “electric plant”, as listed above.

In analyzing this issue, the maximum “noscitur a sociis” is directly on

point. That term is of course an aid in statutory construction, meaning that

words coupled together “are to be understood in the same general sense and

are to be regarded as of the same nature.” State ex rel. Crutcher v. Koeln, 61

S.W.2d 750, 754 (Mo banc 1933). See also Standard Operations, Inc. v.

Montague, 758 S.W.2d 442, 444 (Mo. banc 1988).

Here, cash is clearly not of the “same nature” as real estate, fixtures,

conduits, ducts or other devices, materials, and apparatus or property for

Page 53: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

53

containing, holding or carrying conductors used for transmission of

electricity.

Although the term “personal property” is also included in the

definition of electric plant, the meaning of that term depends upon the

context in which it is used. See Kansas City Southern Railway Co. v.

Garvey, 592 S.W.2d 703, 705-06 (Mo banc 1980) (deciding whether or not

the term personal property means tangible personal property subject to ad

valorem taxation); Obetz v. Boatmen’s Nat. Bank, 234 S.W.2d 618, 623

(Mo. 1950) (debating whether the term personal property was used in a will

in its “limited and restricted sense”, or in the broad and general sense,

meaning everything except real estate); and State ex rel. Koeln v. Lesser, 141

S.W. 888 (Mo. 1911) (discussing whether for tax purposes the term

“personal property” did or did not include stock in companies not located in

Missouri).

The term personal property obviously does include cash in some

contexts, but that need not always be the case. The statute defining electric

plant is a perfect example of why the following warning was included in

Am. Jur. 2d Property, § 5:

Page 54: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

54

Δ Caution. Where the term property is used in a context

indicating that only physical property is intended, the meaning

of the term is accordingly so limited.

The only sensible conclusion here is that “personal property”, as an

item of electric plant, was intended to encompass property such as

transmission cables and components of the steel support towers – items of

the same general nature as those expressly included in the statutory list of

items which constitute electric plant.

Furthermore, the inclusion of cash within the definition of electric

plant would lead to some rather strange results, no doubt beyond what the

General Assembly had in mind when deciding what qualifies as an electrical

corporation.

For instance, under the Commission’s definition of electric plant, a

$10 bill, being “personal property,” and which an individual intended to use

as a down-payment on a small back-up generator for that person’s home,

would in and of itself constitute “electric plant”. Yet that $10 bill certainly

does not square with the common understanding of that term.

And based upon the Commission’s theory, if the person owning that

$10 bill for the back-up generator agreed to sell emergency power to his or

her neighbor for say a share of the fuel cost, that individual would

Page 55: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

55

automatically become an “electrical corporation” under the terms of §

386.020(15) -- even if the purchase of the generator was still in the planning

stage.

This in turn would make that unsuspecting individual subject

immediately to all of the Commission reporting requirements applicable to

electrical corporations. As just two of many examples, § 393.140(6) would

require that the individual file a detailed annual report of his or her utility

operations with the Commission. A113-14. See also Commission Rule 4

CSR 240-10.145, A118. And Commission Rule 4 CSR 240-3.175(1) would

further require that a detailed depreciation study be filed annually by that

individual with the Commission Staff and the Office of Public Counsel.

A119.

In both instances, there is no exemption from the filing requirement

for electrical corporations which are not even operational, or which plan at

some point to own only a single back-up electric generator to be shared with

a neighbor.

In addition, the new one-person electrical corporation would

presumably be subject to all other statutes not even in the Public Service

Commission Act which affect electric utilities – such as those dealing with

Page 56: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

56

tax assessments. See, e.g., State ex rel. Kansas City Power & Light Co. v.

McBeth, 322 S.W.3d 525, 534 n.1 (Mo. banc 2010).

This logical extension of the Commission ruling on this issue is surely

not what the General Assembly had in mind when defining the term electric

plant. Consequently, the Commission’s decision also runs afoul of the

general rule that “statutes should be construed in such a way as to avoid

unreasonable, oppressive or absurd results.” Lincoln County Stone Co. v.

Koenig, 21 S.W.3d 142, 146 (Mo. App. 2000).

In Illinois, in order to qualify as a public utility the entity must own,

control, operate or manage “any plant, equipment or property” used or to be

used in connection with the provision of utility services. Illinois

Landowners Alliance v. Illinois Commerce Commission, 90 N.E. 3d 448,

459, par. 37 (IL 2017).

This list of assets is quite similar in nature to those which constitute

“electric plant” in Missouri. And significantly, the Illinois Supreme Court

referred to these categories of assets as “utility-related property or

equipment” – even though that term is not part of the definition itself. Id. at

42, par. 48. Cash certainly does not fit the description of “utility-related

property or equipment.”

Page 57: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

57

In any event, in a unanimous decision the Illinois Supreme Court

found that the applicant owned none of the required assets, and thus did not

qualify as a public utility. Id. at 460, par. 40.9 Appellants submit that based

on comparable language in Missouri, in the normal sense of the word cash is

not “utility-related property or equipment”.

Based on that Illinois Supreme Court decision, an Illinois appellate

court then found that the Grain Belt line likewise did not qualify as a public

utility. Concerned Citizens and Property Owners v. Illinois Commerce

Commission, 112 N.E.3d 128 (Ill. App. 2018). As the Court noted, Grain

Belt did not own any “utility infrastructure assets”, as was required by the

Illinois Supreme Court decision regarding the Rock Island line. Id. at 134,

par. 16.

As is apparent, the Illinois courts assumed that the statutory definition

of “any plant, equipment or property” implicitly included only “utility

infrastructure assets” and “utility-related property and equipment.” And in

the ordinary sense of the word, “cash” does not fall within the meaning of

those terms.

9 Based on this conclusion, the Supreme Court found it was not necessary to

address the second basis for the decision by the appellate court. Illinois

Landowners Alliance v. Illinois Commerce Commission, supra, 90 N.E.3d at

463, par. 51.

Page 58: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

58

Notably, the Grain Belt decision in Illinois makes no mention of any

contention by Grain Belt that money or cash qualified as “property” used in

providing utility service. Concerned Citizens, 112 N.E.3d 128, supra.

Obviously, Grain Belt decided against even making that argument in Illinois.

As to the 39 easements, they do not constitute electric plant in

Missouri for two reasons. First, Grain Belt clearly does not “own” the real

estate over which it holds these easements. Southern Star Central Gas

Pipeline v. Murray, 190 S.W.3d 423, 430 (Mo. App. 2006).

Therefore, the only issue is whether the Commission was correct in

finding that Grain Belt currently “controls” or “manages” the real estate on

which it holds those easements. A37; LF 4175.

The standard form easement agreement used by Grain Belt generally

gives it the right to build and repair the proposed transmission line, including

support structures, on the real estate for which it has the easement.

Specifically, “The Easement will be used for the transmission of electric

energy, whether existing now or in the future, in order to deliver electrical

energy and for all communication purposes related to delivering electrical

energy.” Exh. 113 Sch. DKL-4 par. 2b, LF Exh. Vol. 82, 5233. And see Id.

at LF Exh. Vol. 81, 5219.

Page 59: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

59

Paragraph 4 of the easement only prohibits activities and the addition

of structures which would “interfere with Grain Belt’s use of the

easement….” Exh. 113 Sch. DKL-4, LF Exh. Vol. 82, 5234-35.

This provision reflects the general rule that landowners may erect

structures upon and use their real estate so long as they do not interfere with

the enjoyment of the easement by the easement holder. Tsevis v. J & F

Industries, 51 S.W.3d 91, 93 (Mo. App. 2001). See also Humpreys v.

Wooldridge, 408 S.W.3d 261, 267 (Mo. App. 2013) (holding that the

landowner “’retains the right of full dominion and use of the land affected by

the easement; he may control and use his property in any way that does not

substantially interfere with the reasonable use of the easement by the

easement holder.’”); and Corpus Juris Secundum, Easements, § 222 (stating

that “the servient estate’s owner retains the rights of full dominion and use

of the land except so far as a limitation thereof is essential to the reasonable

enjoyment of the dominant estate.”)

So theoretically, a landowner could build a new home today in the

middle of the right-of-way, and would not interfere with Grain Belt’s use of

the easement until Grain Belt actually begins construction of the line. There

is certainly no evidence in this case that the new home or any other activity

Page 60: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

60

on the part of the landowner would interfere with Grain Belt’s use of its

easement prior to the start of construction.

Accordingly, at the present time Grain Belt has no right to control or

manage the real estate on which it has an easement, and will not be

authorized to control or manage that real estate until it actually begins to

construct the proposed transmission line. That being the case, at this point

Grain Belt does not “control” or “manage” any real estate which would

qualify as electric plant.

Mr. Zadlo seemed to suggest that construction of the line might begin

in another year or so. Tr. Vol. 22, 2046:3-8. But even that projection is

overly optimistic. Before it may begin construction, Grain Belt/Invenergy

must first secure all eight of the County Consents under § 229.100, which it

has not yet accomplished. LF 2861; 2811-15. And it must also secure major

permits and consents from additional state and federal agencies, such as the

Missouri Dept. of Transportation, the U.S. Fish and Wildlife Service, and

the Corps of Engineers. Tr. Vol. 22 1978-79; Exh. 115, LF Exh. Vol. 82,

5248-49.

Another impediment to the start of construction is that Grain

Belt/Invenergy must first secure the debt financing to build the project. Exh.

147 p. 3, LF Exh. Vol. 72, 4437. Before it can even secure such financing,

Page 61: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

61

Invenergy will need to secure contracts with buyers of additional capacity on

its line, and will not begin construction until six to nine months after the

construction loan is secured. Exh. 146, LF Exh. Vol. 72, 442930 (as

corrected at Tr. Vol. 22, 2003:8-11.

Perhaps most significantly, before Grain Belt may build the project it

will need a certificate from the Illinois Commerce Commission. Tr. Vol. 22,

1930:21-24. Its first attempt to gain such approval took almost three years,

from the time it applied with the Commission until the matter was resolved

in court against Grain Belt. Concerned Citizens, supra, 112 N.E. 3d at 130.

There is no reason to believe Grain Belt or Invenergy will receive final

permission to build the line in any significantly shorter period of time after

they eventually file a new application in Illinois.

For the above reasons, any use of the real estate by the landowners

will not interfere with Grain Belt’s easement rights for at least another year –

and probably longer. Therefore, Grain Belt does not presently control or

manage the real estate, as would be required in order for the easements to

qualify as electric plant.

An additional problem regarding the easements is that according to

the terms of the Commission’s final Report and Order, Grain Belt’s

easements must incorporate a document referred to as the Missouri

Page 62: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

62

Landowner Protocol. A35, par. 121; LF 4173. However, the 39 easements

relied upon by the Commission were secured before that final Report and

Order was issued, as evidenced by reference to those easements in that very

Report and Order. Thus those 39 easements did not incorporate the

Landowner Protocol, as required by the Commission in its final Report and

Order. (See Grain Belt’s standard form easement at the time, at Exh. 113

Sch. DKL-4, LF Exh. Vol. 82, 5233. That easement makes no mention of

the Landowner Protocol). Accordingly, Grain Belt’s 39 easements fail to

satisfy the mandates of the very Order granting the CCN to Grain Belt.

As described by the Commission, this Protocol “is a comprehensive

policy of how Grain Belt Express interacts, communicates, and negotiates

with affected landowners….” It includes a variety of provisions intended to

protect the landowners. A32-33; LF 4170-71. And according to the

Commission, the Protocol is one of the factors intended to mitigate any

negative impacts of the Grain Belt project on the land and landowners. A46;

LF 4184.

Moreover, Grain Belt’s CEO testified they would hire an appraisal

firm to perform “refreshed” county-wide market data studies to determine

the average per acre value in each county. These updated appraisals were to

Page 63: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

63

become a part of the Protocol, which was to be incorporated into the

easement agreements with landowners. Exh. 100, LF Exh. Vol. 76, 4654.

The landowners who signed easements before this new appraisal was

performed obviously did not have the advantage of the new appraisals

promised by Grain Belt. Nor do their easements incorporate the terms of the

Landowner Protocol, which the Commission intended as an added protection

for the landowners. LF 4184.

Because the existing 39 easements are not in compliance with the

Commission’s final Report and Order, they should be deemed unenforceable

at this point by Grain Belt against the landowners granting those easements.

Accordingly, those landowners should be perfectly within their rights in

simply ignoring any request by Grain Belt based on any of the 39 easements

which fail to conform to the Commission’s Order.

Section 393.170.3 authorizes the Commission to impose such

conditions “as it may deem reasonable and necessary” when issuing a CCN.

A101. It makes little sense to say that having exercised that statutory

authority, an easement which fails to comply with a Commission-imposed

condition is just as effective as one which does comply. This is particularly

true in light of the purpose which that condition was intended to serve.

Page 64: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

64

Moreover, Grain Belt voluntarily agreed to the condition that the

Landowner Protocol be incorporated “into the easement agreements with

landowners.” A35, par. 121; LF 4173. Grain Belt did not agree to

incorporate the Protocol into some but not all of the easement agreements.

Having agreed to that condition, Grain Belt should not now be allowed to

argue that its agreement means something other than what it says.

After the final Report and Order was issued, Grain Belt could

conceivably attempt to incorporate the Landowner Protocol into the 39

easements relied upon by the Commission. Even if they did so, however, at

the moment the Commission issued its final Order those easements failed to

satisfy a key condition imposed by the Commission. Accordingly, at that

point (which is the only point that matters) the 39 easements did not qualify

as electric plant.

Appellants have found no case law dealing with the legal

repercussions of a Commission condition imposed in a CCN Order. But

given that the 39 easements do not conform to Grain Belt’s own agreement,

or to the lawful conditions of the Commission’s final Order, they should not

be allowed to validate the very Order which they violate.

Grain Belt may certainly purchase whatever real estate or easements it

desires, and may lawfully build its proposed line in Missouri just as other

Page 65: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

65

construction projects are typically built in this state. Grain Belt has cited no

law which would preclude it from doing so. Appellants’ point is that the

Commission has no statutory authority to assist Grain Belt in this process by

granting it the CCN.

For the foregoing reasons, when the Commission issued its final

Report and Order on March 20, 2019, Grain Belt did not own, operate,

control or manage any property falling within the definition of “electric

plant”. Therefore, Grain Belt does not qualify as an electrical corporation,

and cannot be issued a CCN pursuant to § 393.170.

This issue was preserved for appellate review.10 Show Me has argued

from the outset that Grain Belt is not an electrical corporation, and therefore

does not qualify for a CCN. See Statement of Position, filed with the

Commission just prior to the evidentiary hearings, LF 1344; and Initial

Brief to the Commission, LF 1959, 1962-67. Pursuant to Section 386.500

RSMo and 4 CSR 240-2.160, Appellants Show Me and Christina Reichert

also preserved this argument in their Joint Application for Rehearing with

the Commission. See A133-135; A136-137; LF 4246 et seq. Similarly,

pursuant to Section 386.500 RSMo and 4 CSR 240-2.160, Appellant

10 This subject is addressed here in conformance with Rule 84.04(e).

Page 66: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

66

Missouri Farm Bureau preserved this argument in its Application for

Rehearing to the Commission. See A133-135; A136-137; LF 4254, et seq.

As a final note on this matter, in the initial Report and Order in this

case the Commission rejected Grain Belt’s application for the CCN. See

A6; LF 4144. Thus, at that point, the appellants had prevailed completely

in the Commission case. Accordingly, there was no logical reason for

appellants to appeal that decision on the ground it is raising here or on any

other ground.

In fact, according to the Commission, a party may not lawfully file an

appeal from a Commission case in which it prevailed. (See Motion to

Dismiss Notice of Appeal, October 20, 2017, filed in case ED106023,

which was later consolidated with ED105932.)11

But even if appellants could have raised the jurisdictional issue in the

initial appeal, but did not do so, that fact would be of no consequence in this

current appeal. The issue of subject matter jurisdiction may be raised for

the first time on appeal. AMG Franchises, Inc. v. Crack Team USA, 289

S.W.3d 655, 659 (Mo. App. 2009). In fact, a party is allowed on appeal to

challenge the subject matter jurisdiction of the Commission even if that

11 As this Court has stated, “we take judicial notice of our own records.”

Snyder v. State, 288 S.W.3d 301, 304 n.1 (Mo. App. 2009).

Page 67: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

67

issue was not raised in its Application for Rehearing at the Commission.

Big River Telephone Co. v. Southwestern Bell Telephone Company, 440

S.W.3d 503, 509-10 (Mo. App. 2014). Accordingly, the jurisdictional issue

would be subject to review on this appeal even if it had not been made an

issue in the Commission proceedings below.

CONCLUSION

The Commission is firmly convinced that we are in the midst of a

worldwide, long-term movement to renewable energy. LF 4185. But

regardless of how accurate or laudable that view might be, in reaching its

decision on the Grain Belt line the Commission was nevertheless bound by

this fundamental rule of law: “Neither convenience, expediency or necessity

are proper matters for consideration in the determination of whether or not

an act of the commission is authorized by statute.” State ex rel. Mo. Cable

Telecomms. Ass’n v. Mo. Pub. Serv. Comm’n, 929 S.W.2d 768, 772 (Mo.

App. 1996) (internal quotation marks omitted).

Thus, however well-intentioned and expedient the issuance of the

CCN may have been, and however valuable the Commission thought the

Grain Belt project would be, its decision must be reversed by the Court if it

was not authorized by statute.

Page 68: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

68

And authorized, it was not. To begin with, Grain Belt is not subject to

the entire purview of state statutes governing the regulation of electric

utilities. In addition, its rates will be established by special contracts with

individual customers, set ultimately on terms negotiated by Grain Belt.

Accordingly, respondents respectfully submit that under state Supreme

Court precedent, this Court has no choice but to find that Grain Belt does not

fall within the definition of an “electrical corporation.”

In addition, Grain Belt does not presently own, operate, control or

manage any item of “electric plant”. Therefore, it does not qualify as an

electrical corporation under §§ 386.020(14) and (15).

Because Grain Belt is not an electrical corporation, the Commission

did not have the jurisdiction or statutory authority under § 393.170 to issue

the CCN to Grain Belt for construction of the proposed line.

Accordingly, the appellants respectfully ask the Court to reverse the

Commission’s Final Report and Order on Remand, issued March 20, 2019,

and to remand the case to the Commission for further action in accordance

with the Court’s decision.

Respectfully submitted,

/s/ Paul A. Agathen

Paul A. Agathen

Page 69: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

69

MO Bar No. 24756

485 Oak Field Ct.

Washington, MO 63090

636-980-6404 [email protected]

Attorney for

Show Me and Christina Reichert

AND

/s/ Brent E. Haden

Brent E. Haden, Mo. Bar No. 54148

827 E. Broadway, Suite B

P.O. Box 7166

Columbia, MO 65201

(573) 442-3535

(888) 632-7775 (fax) [email protected] HADEN & HADEN

Attorney for

Missouri Farm Bureau

Page 70: IN THE MISSOURI COURT OF APPEALS APPELLANTS JOINT BRIEF AS FILED.pdfOn August 30, 2016, Grain Belt Express Clean Line LLC (“Grain Belt”) filed an Application with the Commission

70

CERTIFICATE OF COMPLIANCE WITH RULE 84.06(c)

I certify pursuant to Rule 84.06(c) that this brief includes the information

required by Rule 55.03 (except that counsel for Show Me and Christina

Reichert does not have a facsimile number), and complies with the

limitations contained in Rule 84.06(b). I further certify that this brief

contains 12,171 words in total, as determined by the word count feature of

Microsoft Word.

/s/ Paul A. Agathen

Paul A. Agathen

/s/ Brent E. Haden

Brent E. Haden

CERTIFICATE OF SERVICE

I hereby certify that on this 12th day of August, 2019, the foregoing Brief

and accompanying Appendix were filed electronically with the Clerk of the

Eastern District of the Missouri Court of Appeals, to be served by operation

of the Court’s electronic filing system pursuant to Missouri Supreme Court

Rule 103.8.

/s/ Paul A. Agathen

Paul A. Agathen

/s/ Brent E. Haden

Brent E. Haden