in the gauhati high courtghconline.nic.in/judgment/wpc7382015.pdf · in the gauhati high court ......
TRANSCRIPT
1
IN THE GAUHATI HIGH COURT
(THE HIGH COURT OF ASSAM; NAGALAND; MIZORAM & ARUNACHAL PRADESH)
WP(C) 738/2015
1. M/S Kakoti Engineering Works
Represented by its partner Sri Rohit Prasad Kakoti,
A.T. Road, Sivasagar,
PIN-785640, Assam.
2. Sri Rohit Prasad Kakoti
S/o- Rpendra Prasad Kakoti
R/o- Phukan Nagar,
P.S.- Sivasagar,
Dist-Sivasagar, Assam.
….PETITIONERS
-versus-
1. The Oil and Natural Gas Corporation Limited
Represented by the Chairman having its registered at
Jeevan Bharati, Tower-II, 124, Indira Chowk,
New Delhi-110001.
2. The Chairman,
The Oil and Natural Gas Corporation Limited
Jeevan Bharati, Tower-II, 124, Indira Chowk,
New Delhi-110001.
3. The Chief Managing Director,
The Oil and Natural Gas Corporation Limited
Jeevan Bharati, Tower-II, 124, Indira Chowk,
New Delhi-110001.
2
4. The General Manager (MM)
Material Management Department
Contract Cell, Assam Asset,
ROB-II, First Floor, Nazira, Assam.
5. The Head MM
Material Management Department
Contract Cell, Assam Asset,
ROB-II, First Floor, Nazira, Assam.
6. The Executive Director,
Oil and Natural Gas Corporation Limited,
Assam Asset, Nazira, Sivasagar,
Dist-Sivasagar, PIN-785640, Assam.
7. The General Manager,
District Industries & Commerce Centre,
Sivasagar, Assam.
8. Bid Evaluation Committee/Technical Committee
Material Management Department
C/o- General Manager Head
Material Management Department
ONGC Ltd., Assam Asset, Nazira, Dist-Sivasagar, Assam.
9. Raju Ali
R/o- Gelakey Kal Gaon
PO-Gelakey, P.S. Sivasagar,
Dist-Sivasagar, Assam.
…RESPONDENTS
BEFORE
HON’BLE MR. JUSTICE MANOJIT BHUYAN
For the petitioners - Mr. P.K. Goswami, Senior Advocate
Mr. B.D. Goswami,
3
Mr. S. Borthakur, Mr. A. Borgohain,
Advocates For the Respondent Nos.1 to 8 - Mr. G.N. Sahewalla,
Senior Advocate Ms S. Senapati, Advocate
For the Respondent No.9 - Mr. D.K. Mishra, Senior Advocate
Mrs. M. Hazarika Senior Advocate
Ms. S. Khound, Advocate
Date of hearing - 26.5.2015
Date of delivery of judgment -
JUDGMENT AND ORDER (CAV)
Heard Mr. P.K. Goswami, learned Senior counsel assisted by Mr.
B.D. Goswami, Advocate for the petitioner. Also heard Mr. G.N.
Sahewalla, learned Senior counsel assisted by Ms. S. Senapati, Advocate
representing ONGC Ltd. as well as Mr. D.K. Mishra, learned Senior
counsel and Mrs. M. Hazarika, learned Senior counsel assisted by Ms. S.
Khound, Advocate representing the Private Respondent No.9.
2. The petitioner M/s Kakoti Engineering Works is a registered firm
having its own engineering workshop in the district of Sivasagar with
experience in repair and fabrication job of Oil Field/Rig Equipment and is
registered under Entrepreneur Memorandum Part II (hereinafter referred
to as ‘EM Part II’) and is also registered under the Assam Preferential
Stores Purchase Act, 1989.
4
3. By e-Tender dated 27.6.2014, issued from the Office of the
Respondent No.4, bids were invited for rate contract in repair/fabrication
work, painting rigs and equipment and bunk houses repairing. The
scheme of the bid was a two bid system, i.e. technical and financial. The
last date of submission of bid as well as for opening of technical bid was
fixed on 28.7.2014. Pursuant thereto, both the petitioner and the private
Respondent No.9, i.e. Raju Ali submitted their bids through e-Tender. Be
it mentioned that the parameters for evaluation of bid was governed
under the Bid Evaluation Criteria as well as under the Scope of Work and
Technical Specification as provided in Annexure-III, III(A) and IV to the
Bid Document. On 28.7.2014, the Respondent ONGC opened the techno-
commercial bids of both the petitioner and the Respondent No.9. It is the
case of the petitioner that on the date of opening of the technical bid,
certain glaring irregularities were found in the technical bid of the
Respondent No.9.
4. According to the petitioner, the Respondent No.9 did not have the
experience in repair and fabrication job related to drilling operations in
terms of Clause 2.1(a)(i) of the Bid Evaluation Criteria read with “Clause
A” of the Scope of Works and Technical Specifications governing the
tender. Also, the Respondent No.9 did not have its own workshop in
Sivasagar district duly registered in its name under the statute of the
Government of Assam in terms of Clause 3.0 of the Bid Evaluation
Criteria.
5. Accordingly, the petitioner represented before the Respondent
No.4 immediately on 30.7.2014, in writing, pointing out the defects in
the technical bid of Respondent No.9, followed by another representation
dated 4.8.2014 with copy forwarded to the General Manager, District
Industries and Commerce Centre (‘DICC’ for short), Sivasagar with
prayer to verify as to whether the Respondent No.9 has its own
registered workshop in Sivasagar district or not.
5
6. The reply received from the General Manager, DICC, indicated
that the Respondent No.9 is a registered unit as EM Part II vide
Acknowledgement No.18/16/12/01483 dated 18.6.2014.
7. Violation of the terms and conditions of the tender was also
alleged, in that, ONGC had permitted the Respondent No.9 to submit
documents even after the last date of submission of bid. One such
document is the Factory Licence of Respondent No.9 which, according to
the petitioner, in any case proves that the actual existence of a workshop
was from a date subsequent to the last date of submission of tender.
Petitioner had raised objection before the Respondent No.4 vide letter
dated 6.2.2015. According to the petitioner, the various objections raised
in respect of the deficiencies appearing in the techno-commercial bid of
Respondent No.9 remained unheeded to. Through an e-mail received on
6.2.2015, the petitioner came to learn that the price bid would be
opened on 9.2.2015 at 3 PM and that ONGC authority had also decided
to open the price bid of the Respondent No.9 along with that of the
petitioner. Constrained thus, the instant writ petition came to be filed
and by order of this Court dated 9.2.2015, the Respondent ONGC was
restrained from opening the price bid until the next date fixed.
8. The challenge made to the action of the Respondent ONGC in
accepting the Technical Bid of Respondent No.9 and to open the price
bid of the said Respondent No.9 along with that of the petitioner is laid
primarily on two grounds;
i) The Respondent No.9 does not fulfill the requirement of
Clause 2.1(a)(i) of the Bid Evaluation Criteria as well as
Clause (A) of the Scope of Works, in that, he does not
have the experience in repair and fabrication job related
to drilling operations for the minimum period of three
years as stipulated;
6
ii) Respondent No.9 does not fulfill the requirement under
Clause 3.0 of the Bid Evaluation Criteria, in that, he has no
workshop of his own in Sivasagar district duly registered
in his name under the Act of the Government of Assam.
According to the petitioner, on both the counts above, the
techno-commercial bid of Respondent No.9 suffered rejection, which,
however, has been overruled by the Respondent ONGC. Be that as it
may, an adjudication to (ii) above is first taken up for consideration in
view of the fact that a decision thereof would indicate as to whether or
not the point at (i) above would require further attention of the Court.
For better appreciation, Clause 3.0 is extracted hereunder:
“3.0- Workshop facilities:-
The bidder/Indian joint venture company/technical
collaborator should have his own workshop in
Sivasagar district duly registered in the name of the
bidder/consortium member/Indian joint venture
company or partner/technical collaborator, under Act
of Govt. of Assam.
The workshop should be equipped with the equipment
& facilities as mentioned in special conditions of
contract.
* The bidder should submit details of workshop
facilities available.
* The workshop should be on bidders name only
and documentary evidence of ownership of the
workshop should be submitted.
* Proof of workshop along with above
equipments should be certified by District
7
Industries office. The certificate is to be
submitted.
* ONGC may also inspect the workshop for
assessment if required.
* All original certificates are to be shown to ONGC
for scrutiny, if required.”
9. In so far as Clause 3.0 of the Bid Evaluation Criteria is concerned,
Mr. P.K. Goswami, learned Senior counsel submits that the existence of
own workshop in Sivasagar district, duly registered in the name of the
bidder etc. and under the Act of the Govt. of Assam and equipped with
the equipment and facilities as mentioned in the Special Conditions of the
Contract is a vital technical condition, in absence of which, a bid would
stand rejected in terms of Clause-B relating to Rejection Criteria under
the Bid Evaluation Criteria.
10. Referring to the letter dated 21.1.2015, received from ONGC, Mr.
Goswami, learned Senior counsel submits that the requirement of a
Factory Licence and the supporting documents submitted along with the
tender of a date not later than the closing date of submission of bids, is
an indispensable condition.
11. Whether or not the Respondent No.9 had discharged/fulfilled the
requirement of a Factory Licence which is of a date prior to the closing
date of submission of bid and whether or not a Factory Licence is at all
necessary for the purpose of Clause 3.0 of the Bid Evaluation Criteria, the
following points have been urged by the learned Senior counsel, Mr.
Goswami.
12. Referring to the affidavit-in-opposition filed by ONGC and to the
documents at Annexure-A thereof, Mr. Goswami, learned Senior counsel
submits that on the basis of the Memorandum filed for a manufacturing
enterprise at Gelakey Kal Gaon, Nazira in the district of Sivasagar, the
8
Respondent No.9 was granted the Certificate of Issuance (EM Part II) on
18.6.2014 by DICC, Sivasagar. As per the Note appended to the said
Certificate, it was made clear that the Certificate would not bestow any
legal right and the enterprise concerned is required to seek requisite
clearance/Licence/permit required under the statutory obligations
stipulated under the laws of Central / State Govt. / UT
Administration/Court’s order. Further, referring to the Sl. No.3 under
“N.B” thereof, learned Senior counsel submits that the acknowledgement
of Part II is only for the purpose of enabling the unit to apply for various
incentives under the State/Central Govt.
13. In so far as the Application Form for EM Part-II of Respondent
No.9 is concerned, Mr. Goswami, learned Senior counsel contends that
while making the application, Respondent No.9 had inappropriately
declared that it is registered under Section 2(m)(i), 2(m)(ii) of the
Factories Act, 1948, having plant and machineries installed in May, 2010
with a proposed installed capacity of 800 tonnes per annum and having
anticipated power load of 5 KW with a work force of 28 workers.
14. From the list of plant and machineries enclosed to the application
for EM Part II with the date of commissioning shown as 15.5.2010 read
with the Certificate dated 20.5.2015 issued by APDCL, Gorgaon, learned
Senior counsel submits that with a sanctioned load of 5 KWs it is
improbable that the type of heavy machineries, as indicated in the list,
can at all be operated with a power load of 5 KWs. In fact, and as would
be apparent from the certificate of APDCL, electricity with 5 KW load was
sanctioned only for running welding machine in the premises of
Respondent No.9.
15. Reference to the list of plant and machineries and the sanctioned
load of 5 KW has been made by the petitioner for the purpose of urging
that the Respondent No.9 was not equipped with the equipments and
facilities as mentioned in the Special Conditions of Contract, which is,
9
Annexure-III (A) of the Bid Document and a requirement under Clause
3.0, as above. According to Mr. Goswami, learned Senior counsel, the list
of plant and machineries submitted by Respondent No.9 was only for the
purpose of showing fulfillment of Clause 7 of the Special Conditions of
Contract on paper.
16. Learned Senior counsel also refers to the documents at
Annexure-C and Annexure-D enclosed to the affidavit-in-opposition of
ONGC to show that the Respondent No.9 had applied for a Factory
Licence before the Office of the Chief Inspector of Factories, Assam on
12.6.2014, which was granted only on 29.12.2014. As such, the
contention is that the Respondent No.9 did not possess a Factory Licence
on any date prior to the closing date of submission of bid. In this
connection, attention has also been drawn to Annexure-13 of the
affidavit-in-reply filed by the petitioner, which is a letter issued by the
Chief Inspector of Factories, Assam and addressed to the Respondent
No.9. By the said letter, Respondent no.9 was restrained from carrying
out manufacturing process until the Certificate of Stability is obtained
from the competent person and accepted by the Chief Inspector of
Factories, Assam.
17. All the factors above, according to Mr. Goswami, learned Senior
counsel, lead to the inevitable conclusion that until 29.12.2014, the
Respondent No.9 did not possess a Factory Licence. Notwithstanding the
fact that the Respondent No.9 was granted Factory Licence on
29.12.2014 by the letter issued by the Chief Inspector of Factories,
Assam, the Respondent No.9 was restrained from carrying out
manufacturing process until fulfillment of the conditions stipulated in the
said letter. The said letter was only limited to the extent of permitting the
Respondent No.9 to go ahead with the construction of the proposed
factory. Attention has also been drawn to the document at Annexure-2 of
the affidavit-in-opposition filed by the Respondent No.9, which is a
certificate issued by the General Manager, DICC, Sivasagar, to say that
10
being a small enterprise registered with DICC, Sivasagar for EM Part II
under the Micro, Small and Medium Enterprise Development Act, 2006
(hereinafter referred to as ‘MSME’ Act, 2006), the Respondent No.9 was
only entitled to the benefits under the MSME Scheme.
18. What is the “Act of Govt. of Assam”, as mentioned in Clause 3.0
of the Bid Evaluation Criteria, under which a workshop needs to be duly
registered. This is the core question involved for adjudication of the point
at (ii) above and also looking at the other requirements of technical
conditions at Clause 3.0.
19. Senior counsel, Mr. Goswami, refers to the meaning of “factory”
as given in Section 2(m)(i) and 2(m)(ii) of the Factories Act, 1948
(hereinafter referred to as ‘Act, 1948’). In terms of the said provisions it
means any premises including the precincts thereof where a
manufacturing process is being carried on, with or without the aid of
power subject to number of workers employed therein and as clearly
specified in Section 2(m)(i) and 2 (m)(ii). Mr. Goswami further submits
that the expression “manufacturing process”, as defined in Section 2(k)(i)
of the Act, 1948, takes within its fold the nature of the work for which
the tender was invited. The power of the State Government to make
Rules, as envisaged under Section 6 of the Act, 1948 is also referred to
by making special reference to Section 6(aa) and 6(d) thereof. For ready
reference, the relevant portions are extracted hereunder:
“6. Approval, licensing and registration of factories.-
(1) The State Government may make rules-
(a) …………………………….
(aa) requiring the previous permission in writing of
the [State Government] or the Chief Inspector to be
obtained for the site on which the factory is to be
11
situated and for the construction or extension of any
factory or class or description of factories;
(b) ……………………..
(c) …………………………..
(d) requiring the registration and licensing of factories
or any class or description of factories, and prescribing
the fees payable for such registration and licensing
and for the renewal of licences;
(e) ………………………………...”
20. According to Mr. Goswami, the State of Assam has enacted the
Assam Factories Rules, 1950 (hereinafter referred to as the Rules, 1950).
In terms of Rule 3-A of the Rules, 1950, no site is to be used for the
location of a factory or no building in a factory be construed as a factory
unless previous permission in writing is obtained from the State
Government or the Chief Inspector of Factories. Application for such
permission is to be made in Form I accompanied by the documents
specified therein. Under Rule 3-B of the Rules, 1950, no manufacturing
process is to be carried on in the premises so specified which has been
taken into use as factory or part of a factory until a certificate of stability
is received from the Manager or occupier of the factory and accepted by
the Chief Inspector of Factories. Rule 4 of the Rules, 1950, prescribes for
application for registration and grant or renewal of licence and notice of
occupation and Rule 6 thereof postulates grant of licence by the Chief
Inspector of Factories in Form No.4 prescribed for the purpose.
21. A conjoint and harmonious reading of the Rules, 1950, according
to Mr. Goswami, leaves no room for doubt that a “factory within the
meaning of Section 2(m)(i) and 2(m)(ii) of the Act, 1948 must require a
Licence in terms of Rule 3-A, Rule 4 and Rule 5 of the Rules, 1950.
12
22. Taking it forward, Mr. Goswami submits that another vital
technical condition envisaged in Clause 3.0 is that the workshop should
be equipped with the equipment and facilities as mentioned in the
Special Conditions of Contract, which is Annexure-III(A) of the Bid
Document. Clause 7 thereof which lists the equipments reads as:
“7. WORKSHOP FACILITIES
The workshop should be equipped with the following
equipments:
1) Lathe :- 02 No’s
Bed length :- 12 ft
Hollow spindle :- 05 inch
Centre length :- 500 mm
2) Small lathe :- 02 nos.
Bed length :- 6 ft
Hollow spindle :- 75 mm
Centre length :- 300 mm
3) Radial drilling machine, 2-inch capacity :- 02 nos.
4) Welding generator 350 amps :- 05 nos.
5) Welding transformer 450 amps :- 10 nos.
6) Angle grinder :- 05 nos.
7) Gas cutting sets :- 05 nos.
8) Hoisting device/crane of cap 20 MT. :- 01 no
9) Plate bending machine to handle up to 15 mm thick MS
plate
:-01 no.
10) Sheet bending machine up to 4 mm
Thickness MS plate :-01 no
The bidders should also have sufficient covered and
uncovered space for executing the jobs at his premises.”
Having regard to the list of equipments which are required as a
vital technical condition and the electricity power that would be required
to run the same, it is urged that the premises, be it called a workshop, is
13
a factory for which a Licence is a pre-condition for carrying on
“manufacturing process”. It is further urged that the requirement of a
Factory Licence is implicit and is a necessary condition imposed by the
respondent ONGC, as would be evident from the ONGC letter dated
21.1.2015 (Annexure-12 to writ petition) whereby the petitioner was
asked to provide valid Factory Licence (notary attested) which expired on
31.12.2014. The said letter also indicated that in the case of furnishing
deficient documents, such supporting documents must be of a date not
later than the closing date of submission of bids. In this connection and
by referring to the relevant documents available on record, it is
submitted that the Respondent No.9 was granted Factory Licence only on
29.12.2014 pursuant to the application dated 12.6.2014. Apparently, a
Factory Licence being a sine qua non under Clause 3.0 and a valid
Licence not being with Respondent No.9 on any date prior to the closing
date of submission of bid, as such, the technical bid of Respondent No.9
automatically suffered rejection on account of Clause 3.0.
23. Touching upon another important aspect of the matter with
regard to the applicability of the Micro, Small and Medium Enterprises
Development Act, 2006 (MSME Act, 2006), Mr. Goswami submits that,
contrary to the arguments advanced by the respondents, as would be
noticed later in this judgment, it is only an Act to provide for facilitating
the promotion and development and enhancing the competitiveness of
micro, small and medium enterprises. This is an Act framed as per the
declaration as to expediency of control by the Union under Section 2 of
the Industries (Development and Regulation) Act, 1951. Referring to
Section 8 of the MSME Act, 2006 and in the backdrop of the Statements
of Objects and Reasons thereto, Mr. Goswami submits that if any person
intends to establish a micro or small or a medium enterprise, he is
required to file a Memorandum with such authority as specified by the
State Government under sub-section (4) or the Central Government
under sub-section (3) of Section 8 of the MSME Act, 2006. In terms of
14
the amended format for the Entrepreneur Memorandum under the MSME
Act, 2006 after inclusion of the amendments vide Notification No. S.O.
941(E) dated 7.6.2007, the Memorandum is required to be filed with the
District Industries Centre under which jurisdiction the enterprise is
proposed to be located. The form of Memorandum is in two parts. Part I
is in respect of the intention to establish the enterprise in question and
Part II is when the enterprise starts production or starts providing or
rendering services. For Part II, an Acknowledgement has to be issued by
the concerned office, i.e. the District Industries Centre in the form of a
Certificate of Issuance (EM Part-II).
24. Referring to the Certificate of Issuance (EM Part-II) dated
18.6.2014 in favour of Respondent No.9, issued by the General Manager,
DICC, Sivasagar, Mr. Goswami submits that, commensurate to the
objects of the MSME Act, 2006, the said Certificate only enables the unit
to apply for various incentives under the State/Central Government. It
does not bestow any legal right and the entrepreneur is required to seek
requisite clearance/licence/permit required under statutory obligation
stipulated under the laws of Central Government/State Government/UT
Administration/Court Orders. According to the senior counsel, the said
prescriptions can be had from the “Note” and Serial No.(3) of “NB”
mentioned in the said Certificate of Issuance.
25. The sum and substance of Mr. Goswami’s contentions is that the
MSME Act, 2006 has nothing to do with the registration of a workshop
for the purpose of carrying on manufacturing process. It only
contemplates an acknowledgement in the form of a Certificate of
Issuance (EM Part-II) for getting or enabling the unit to apply for
incentives under the State/Central Government. It is the Factory Licence
which is a statutory requirement under the Assam Factories Rules, 1950
that is envisaged as “under Act of Govt. of Assam” in Clause 3.0 of the
Bid Evaluation Criteria.
15
26. Lastly, Mr. Goswami submits that the requirement of a Factory’s
Licence was all along within the comprehension of ONGC authority. A
waiver of the statutory requirement would only render the action as
arbitrary and discriminatory in the teeth of the law laid down by the Apex
Court in the case of Ramana Dayaram Shetty vs. International
Airport Authority of India and others, reported in (1979) 3 SCC
489=AIR 1979 SC 1628. Such waiver, if it had been expressly
declared in the Tender, would have had the participation of more
bidders. Reference is also made to the case of Khudiram Das vs. The
State of W.B., reported in AIR 1975 SC 550 to say that the Court has
the power to interfere when an authority has come to a conclusion so
unreasonable that no reasonable authority could ever come to it. A
legitimate inference may be drawn that either the authority did not
honestly form that view or that in forming it could not have applied its
mind to the relevant facts. In such a case the power of the Court to
interfere is not as an appellate authority to override the decision of the
authority, but as a judicial authority which is concerned only to see
whether the statutory authority has contravened the law by acting in
excess of the power the legislature has confided in it. Mr. Goswami
emphasizes that “there is nothing like unfettered discretion immune from
judicial reviewability.”
27. On the grounds above, prayer has been made for setting aside
the decision of the ONGC authority in accepting the technical bid of
Respondent No.9 as well as for a direction to the respondent ONGC not
to go ahead with the opening of price bid of Respondent No.9 along with
the petitioner in connection with the e-Tender dated 27.6.2014.
28. Mr. G.N. Sahewalla, learned Senior counsel representing the
ONGC Ltd, opens his arguments by saying that for the work in question
the significant purpose is to ensure whether a person would be capable
to execute the work or not. Referring to the affidavit-in-opposition it is
averred that the Respondent No.9 owns a running workshop which
16
satisfied the requirement of Clause 3.0. Further, a Committee of three
senior ONGC Executives had visited the workshop of Respondent No.9
and had carried out inspection of the plant and machinery, manpower as
well as verification of documents. According to the Report of the
Committee dated 27.10.2014, the Respondent No.9 was found to be the
owner of the workshop and the machines/worker were found to be in
operation. On the basis of the Report, the ONGC authority held that the
contention of the petitioner was baseless and motivated. According to
Mr. Sahewalla, learned senior counsel, the system for seeking documents
after the opening of tender, without alteration of the original bid
structure, is as per the internal guidelines of ONGC. The same is resorted
to in order to enhance competition amongst the participating bidders.
29. In so far as the question of requirement of Factory Licence is
concerned, Mr. Sahewalla submits that in the present case the ownership
of the workshop was established by carrying out Inspections on
20.10.2014 and 21.10.2014 respectively. The requirement of Factory
Licence not being essential, as such, there was no lacunae on the part of
the Respondent No.9 in not submitting the Factory Licence along with
the bid. According to Mr. Sahewalla, although there was no requirement
for a Licence, nevertheless the Respondent No.9 had submitted the letter
from the Additional Chief Inspector of Factories certifying that
Respondent No.9 had applied for the Factory Licence on 12.6.2014. In
the opinion of ONGC, the Respondent No.9 was found technically
acceptable after a detailed technical scrutiny and inspections so carried
out in terms of Clause 3.0 of the Bid Evaluation Criteria.
30. Mr. Sahewalla, learned Senior counsel, further submits that since
Clause 3.0 only makes reference to a workshop and not a factory, as
such, the applicability of the Factories Act, 1948 and that of the Assam
Factories Rules, 1950 is irrelevant in the context of the case.
17
31. Reliance is placed in the case of B.S.N. Joshi & Sons Ltd. v.
Nair Coal Services Ltd. And ors, reported in (2006) 11 SCC 548 to
say that right accrues upon the party issuing the tender to punctiliously
and rigidly enforce it but at the same time can deviate from the
guidelines in a given situation subject to the fact that it does not result in
arbitrariness or discrimination. Further, as a matter of general
proposition an authority issuing the tender has the latitude not to give
effect to every term indicated in the tender in meticulous details, save
and except a technical irregularity which cannot be waived. As the
requirements of a tender come within two categories - those which lay
down the essential conditions of eligibility and others which are merely
ancillary or subsidiary with the main object to be achieved by the
condition, it is urged that the dominant object in the present case is the
decision of ONGC Ltd as to whether the person would be capable to
achieve successful completion of the work or not.
On judicial review of administrative action, reliance is placed in the case
of Jagdish Mandal v. State of Orissa, reported in (2007) 14 SCC
517 as well as in the case of Michigan Rubber (India) Ltd. v. State
of Karnataka, reported in (2012) 8 SCC 216. On the grounds where
interference under Article 226 of the Constitution of India is called for,
reference is made to paragraph 24 in Michigan Rubber (India) Ltd.
(supra), which is extracted hereunder;
“24. Therefore, a court before interfering in tender or contractual matters, in exercise of power of judicial review , should pose to itself the follow ing questions;
(i) Whether the process adopted or decision made by the authority is mala fide or intended to favour someone; or whether the process adopted or decision made is so arbitrary and irrational that the court can say: “the decision is such that no responsible authority acting reasonably and in accordance w ith relevant law could have reached”? and
18
(ii) Whether the public interest is affected?
I f the answers to the above questions are in the negative, then there should be no interference under Article 226.”
32. According to Mr. Sahewalla, learned Senior counsel, in the teeth
of the Apex Court decisions laying down the power of the Court and the
parameters for exercise of powers of judicial review over administrative
actions, it is contended that in the absence of malafide, arbitrariness,
irrationality and any intention to favour the Respondent No.9, no
interference is called for in respect of the decision of the ONGC authority
in allowing the technical bid of Respondent No.9.
33. Lastly, Mr. Sahewalla submits that the price bid not having been
opened, the writ petition is premature, in as much as, the award of the
work will be dependent upon the outcome of the price bids and it is not
a case where the petitioner has been thrown out of the competition.
34. Mr. D.K. Mishra, learned Senior counsel representing the
Respondent No.9, opens his argument by saying that Factory Licence is
not a requirement under Clause 3.0. It is only the assumption of the
petitioner. What is essentially required is the existence of a workshop in
Sivasagar district. From the very pleadings in the writ petition, any
controversy that the Respondent No.9 did not have a workshop in
Sivasagar, stands dispelled. The basic foundation of the petitioner’s case
is that from inputs received from field-level personnel there is no
government registered workshop standing in the name of the
Respondent No.9 in Sivasagar district, save and except, being a
registered unit as Entrepreneur Memorandum Part-II under the
provisions of the MSME Act, 2006. Reference is made to the Certificate of
Issuance dated 18.6.2014 issued in favour of the Respondent No.9 and
also to the List of Plant & Machineries installed in the Factory/Workshop
to say that the same are in due compliance of the requirements under
Clause 3.0. Attention is also drawn to the Certificate dated 18.6.2014
19
(Annexure-2 to the Affidavit-in-opposition of Respondent No.9) to show
that the unit is registered with the District Industries & Commerce
Centre, Sivasagar vide EM Part-II of MSME Act, 2006. The fact that
Respondent No.9 has a running workshop satisfying the requirements of
Clause 3.0 has been reinforced and established by the Inspection Report
of the Committee which had visited the workshop site on 20.10.2014 and
21.10.2014.
35. On the question that in the Application Form for EM Part-II the
Respondent No.9 had indicated that it is registered under Sections
2(m)(i), 2(m)(ii) of the Factories Act, 1948, without actually being so,
Mr. Mishra submits that the same was done in contemplation of setting
up of a factory for some other work. As regards the sanctioned power
load of 5 KWs, which the petitioner argues that under no circumstances
it is sufficient to run the machines as given in the List of Plant &
Machineries alleged to have been installed in the workshop of
Respondent No.9, Mr. Mishra counters the same by saying that apart
from the three Welding Generators at serial nos. 4, 5 and 6 of the List,
the remaining machines can be operated with power load of 5 KWs. The
nature of the business of Respondent No.9 necessitates utilization of the
Welding Generators at field-sites mostly. Lathe machines can be
operated by a minimum load of 1.5 KW and so in the case of the other
machines apart from the Welding Generators. In respect of the
manpower indicated in the said Application Form, standing at 28 nos.,
Mr. Mishra submits that they had been working in other places and are
not covered by the Factories Act, 1948.
36. Mr. Mishra further submits that if the Certificate of Issuance (EM
Part-II) is held to be not in compliance of Clause 3.0, it would only mean
that no workshop employing ten or more workers, with or without the
aid of power, will ever be able to run/operate in the absence of a Factory
Licence. According to Mr. Mishra, this is too extreme a proposition.
20
Taking it forward, it is contended that the requirement of a Factory
Licence is nowhere stipulated as an essential condition of the tender.
37. Once again the issue boils down to the point - what is the
meaning of “Act of Govt. of Assam”. Whether the registration of the
workshop, as required of under Clause 3.0, would find due compliance
with the registration of the unit as EM Part-II under the MSME Act, 2006
or with registration and licence under the Factories Act, 1948 read with
the Assam Factories Rule, 1950 in the given facts of this case.
38. Mr. Mishra, learned Senior counsel, refers to the Industries
(Development and Regulation) Act, 1951 (IDR Act) to say that by virtue
of Section 2 thereof, a comprehensive central enactment for providing an
appropriate legal framework facilitating the growth and development of
micro, small and medium enterprises was brought about by the statute
called the Micro, Small and Medium Enterprises Development Act, 2006
(MSME Act, 2006). A reading of Section 11 B of the IDR Act as well as
Section 8 of the MSME Act, 2006 would go to show that it is not just a
beneficial enactment, as made out by the petitioner. The filing of
Memorandum under Section 8 of the MSME Act, 2006 is a mandatory
provision, contravention of which would invite penalty under Section 27
thereof. Mr. Mishra further submits that it is rather the Factories Act,
1948, which is a beneficial piece of legislation, as would be apparent
from the Statement of Objects and Reasons thereof.
39. To sum it up, Mr. Mishra contends that the e-Tender does not
specify that participation is only open to units coming under the purview
of the Factories Act, 1948 and the Rules framed thereunder by the State.
Mr. Mishra emphasizes that Clause 3.0 only contemplates registration of
the workshop with the DICC as EM Part-II and not under the Factories
Act, 1948.
21
40. On the principles of judicial restraint in administrative action and
the contours of power of the Court under Article 226 of the Constitution
of India, Mr. Mishra places reliance on the following case laws:
(i) (1991) 3 SCC 273 (Poddar Steel Corporation v. Ganesh
Engineering Works & ors.)
(ii) (2007) 1 SCC 477 (Rajasthan Housing Board & anr. v.
G.S. Investments & anr.)
(ii i) (2007) 14 SCC 517 (Jagdish Mandal v. State of Orissa &
ors.)
(iv) (2013) 10 SCC 95 (Rashmi Metaliks Limited & anr. v.
Kolkata Metropolitan Development Authority & ors.)
(v) (2014) 11 SCC 288 (Siemens Aktiengselischaft and
Siemens Ltd. V. Delhi Metro Rail Corporation Limited)
The general proposition as laid down in the case laws above, as in the
case laws relied upon by Mr. Sahewalla, are in the same vein. Mr. Mishra
contends that the modern trend points to judicial restraint in
administrative action and the Court does not sit as a court of appeal but
merely reviews the manner in which the decision was made. The
Government must have freedom of contract as a ‘fair play in the joints’ is
a necessary concomitant for an administrative body functioning in an
administrative sphere.
41. Lastly, Mr. Mishra argues that having regard to the aspect that
EM Part-II is due compliance of Clause 3.0 and in the absence of any
element of arbitrariness, malafides and bias, as such, no interference is
warranted in respect of the decision of the ONGC authority in holding
that Respondent No.9 had qualified in the technical bid.
22
42. Having noticed the rival pleadings, the first endeavour would be
to deal with the scope of judicial review in government contracts having
regard to the Apex Court decisions placed by the parties.
43. In Ramana Dayaram Shetty (supra), the respondent
authority had bestowed a favour on one of the bidders without insisting
upon a requirement in the tender notice, which was an essential
condition of eligibility. The Apex Court having examined the question as
to whether the respondent authority could have validly condoned the
shortcoming in the tender of the beneficiary, held that the action
amounted to illegal discrimination. Regarding the power or discretion of
the Government in the matter of grant of largesse, the Apex Court held
that such power or discretion must be confined and structured by
rational, relevant and non-discriminatory standard or norm. A departure
thereof would make the action of the Government liable to be struck
down unless it can be shown that the departure was not arbitrary but
was based on some valid principle which in itself was not irrational,
unreasonable and discriminatory.
44. In Khudiram Das (supra), the proposition of law laid down is
that where in a case the authority has reached a conclusion so
unreasonable that no reasonable authority could ever come to it, then
interference by the Court is not as an appellate authority but as a judicial
authority, in as much as, there is nothing like unfettered discretion
immune from judicial reviewability.
45. In B.S.N. Joshi & Sons Ltd. (supra), it was held that the
requirements in a tender notice generally fall into two categories-
essential and ancillary or subsidiary. Whereas the essential conditions of
eligibility are to be rigidly enforced, the latter can be deviated from
without insistence upon a strict literal compliance with the condition in
appropriate cases. The common thread in the cases of Jagdish Mandal
(supra) and Michigan Rubber (supra) is with regard to the caveat in the
23
exercise of power of judicial review. Interference under Article 226
comes into play only if the process adopted or decision made by the
authority is malafide or intended to favour someone or is so arbitrary
and irrational that the Court can hold that “the decision is such that no
responsible authority acting reasonably and in accordance with relevant
law could have reached.”
46. The case of Poddar Steel Corporation (supra) is a precursor to
the case of BSN Joshi & Sons Ltd. (supra) in the exposition of the
essential and ancillary conditions in a tender notice. In the same vein are
the other cases relied upon by the Respondent No.9. In Rajasthan
Housing Board (supra), the Apex Court relied and referred to earlier
decisions touching upon the principles which have to be applied in
judicial review of administrative decisions, especially those relating to
acceptance of tender and award of contract. Under quotes, the Apex
Court referred to the propositions that the principles of judicial review
shall apply in order to prevent arbitrariness or favouritism on the part of
government bodies. Further, although the modern trend points to judicial
restraint in administrative action and a fair play in the joints is a
necessary concomitant for an administrative body, however, the decision
must be tested by the application of Wednesbury principles of
reasonableness and must be free from arbitrariness, bias and malafides.
Although the State can choose its own method to arrive at a decision
and grant any relaxation for bonafide reasons, such relaxation is
permissible only if the tender conditions permit.
47. A conspectus of the case laws cited above makes it abundantly
clear that notwithstanding the freedom of contract, fair play in the joints,
power of granting relaxation and to choose its own method available
with the State, the Court in exercise of power of judicial review can
certainly examine whether the “decision-making process” was
reasonable, rational, not arbitrary and not violative of Article 14 of the
Constitution.
24
48. It now takes us to Clause 3.0 of the Bid Evaluation Criteria to first
ascertain as to whether the requirement is an essential condition in the
tender notice that cannot be permitted to be relaxed or is ancillary or
subsidiary where a strict literal compliance cannot be insisted upon. From
the Bid Document pertaining to e-Tender No.R16SC14012, Annexure II
thereof relates to “Bid Evaluation Criteria”. Clause A of the said Criteria
prescribes the vital criteria for acceptance of bids; clause B with regard
to rejection criteria, which takes within its fold the requirement of
eligibility and experience of the bidder as well as the requirement of
workshop facilities etc. For the purpose of this instant case, sub-clause
B.1.1 and B.1.3.0 finds relevance. According to sub-clause B.1.1. the
vital technical conditions under Clause B are to be strictly complied with,
failing which the bid stands to be rejected. In other words, the
prescription is that incomplete and non-conforming bids will suffer
rejection outright. Amongst the vital technical conditions is sub-clause
B.1.3.0 relating to the requirements of workshop facilities. Without much
elucidation and having regard to the plain language in Clause B under
the heading of “Rejection Criteria”, there is no manner of doubt that the
requirements of workshop facilities under clause B.1.3.0 or 3.0 simply
put, is an essential condition of the tender notice that has to be rigidly
enforced without permitting any deviations therefrom.
49. Even at the cost of repetition, the essential condition under
Clause 3.0 prescribes the requirement of a workshop in Sivasagar
district, duly registered in the name of the bidder etc. under the Act of
the Government of Assam. Further, the workshop must be equipped with
the equipments and facilities as mentioned in the Special Conditions of
Contract and proof of the workshop along with the listed equipments
should have certification of the District Industries office.
50. Registration under which statute ? - is the foremost point to be
decided first. To start with the Factories Act, 1948, Section 112 thereof
confers power upon the State Government to make rules providing for
25
any matter which, under any of the provisions of the Act of 1948 is to be
or may prescribed or which may be considered expedient in order to give
effect to the purposes of the Act of 1948. This brings us to the provisions
under Section 6 of the Act of 1948 which empowers the State
Government to make rules, amongst others, requiring the registration
and licensing of factories or any class or description of factories, and
prescribing the fees payable for registration and licensing and for
renewal of licence. Section 6 also provides the requirement of previous
permission in writing of the Chief Inspector to be obtained for the site on
which the factory is located and for the construction or extension of any
factory or class or description of factories.
51. Before proceeding further it would be relevant to first ascertain
the status/category of the establishment of Respondent No.9.
Considering the fact that the establishment employs more than 20
persons, with or without the aid of power and on the own showing by
respondent no. 9 with regard to the particulars given in his Application
for EM Part-II, it falls within the definition of “factory” given in Section
2(m) of the Act, 1948. What then are the requirements and the
conditions precedent for the purpose of carrying out any “manufacturing
process” as defined in Section 2(k) of the Act, 1948, in the said
establishment.
52. In exercise of powers conferred by Section 112 of the said
Factories Act, 1948, the State of Assam has enacted the Assam Factories
Rules, 1950. As noticed earlier, Rule 3-A of the Rules, 1950 requires
permission in writing of the State Government or the Chief Inspector of
Factories before any site is used for the location of a factory or to be
construed as a factory. In so far as carrying out manufacturing process,
Section 3-B or the Rules, 1950 prescribes for a certificate of stability in
respect of the establishment to be sent by the occupier or Manager of
the factory to the Chief Inspector and accepted by him. The said
certificate of stability has to be in the form prescribed under the Rules.
26
Rule 4 thereof requires submission of application for registration as well
as for grant or renewal of licence and notice of occupation to the Chief
Inspector, whereof a licence for a factory shall be granted by the Chief
Inspector in the prescribed format in exercise of powers under Rule 5.
53. In the instant case, the Respondent No.9 made application for a
factory licence before the office of the Chief Inspector on 12.6.2014,
which was granted on 29.12.2014. Without any dispute, Respondent
No.9 did not possess the Factory Licence on or before the last date of
submission and/or on the date and time of opening of the techno-
commercial bids.
54. Whether a Factory Licence was required or not for the purpose of
the work in question, attention may be had to the ONGC letter dated
21.1.2015 (Annexure-12 to the writ petition) whereby the petitioner was
asked to provide Factory Licence (notary attested) which expired on
31.12.2014. By the said letter dated 21.1.2015, although dated post the
opening date of techno-commercial bid, it clearly indicates that
submission of deficient documents/supporting documents must be of a
date not later than the closing date of submission of bids. In paragraph 9
of the affidavit-in-opposition of ONGC, it is indicated that the Respondent
No.9 was asked to submit the Factory Licence, although there was no
such requirement in the tender document. In response thereto, the
Respondent No.9 submitted the Factory Licence dated 29.12.2014.
Statement is also made to the effect that the Respondent No.9 had
submitted the letter of the Additional Chief Inspector of Factories
certifying that Respondent No.9 had applied for the factory licence on
12.6.2014. This was done prior to the opening of tender on 28.7.2014.
Also, amongst the documents submitted by Respondent No.9 along with
bid is the Certificate of Issuance (EM Part-II), which makes mention at
Sl. No.10 of the Application Form enclosed therewith, to the effect that
the unit of Respondent No.9 is registered under the Factories Act, albeit
incorrectly at that point of time.
27
55. From the foregoing discussion it is amply clear that the
requirement of a Factory Licence has been one of the dominant factors
and a necessary condition in respect of the work in question.
56. At Clause 3.0 of the Bid Evaluation Criteria, a fine distinction is
made to show that the requirement of registration under “Act of Govt. of
Assam”, on the one hand, and the requirement of “proof of workshop”,
on the other, are two different factors altogether. Whereas, the former is
a requirement that can be had by means of a licence, the latter can be
had by a certificate issued from the office of the concerned District
Industries. One cannot be a substitute for the other.
57. The Certificate of the District Industries is directly proportional to
the provisions under the MSME Act, 2006. Read with the Statements of
Objects and Reasons thereto, any person intending to establish a micro
or small or medium enterprise has to submit a Memorandum before the
appropriate authority as specified by the State Government which,
according to the Notification No. S.O. 941 (E) dated 7.6.2007, is the
District Industries Centre under which jurisdiction the enterprise is
proposed to be located. The Certificate of Issuance in the form of
Entrepreneur Memorandum Part-II, in proof of the establishment of the
enterprise as well as commencement of production/activity, comes with
an Acknowledgement issued by the District Industries Centre. The filing
of a Memorandum under section 8 of the MSME Act, 2006 is a
mandatory requirement and attracts the penalty under section 27 in case
of contravention. Without any doubt, the unit of respondent no. 9 is
registered with the District Industries & Commerce Centre, Sivasagar
vide EM Part-II under the MSME Act, 2006. It is a running workshop and
proof thereof can be had not only from the Certificate of Issuance (EM
Part-II) dated 18.6.2014 but also from the Inspection Report of the
Committee deputed by the respondent ONGC, which had visited the
workshop site of respondent no. 9 on 20.10.2014 and 21.10.2014.
28
58. To what extent a Certificate of Issuance (EM Part-II) is
beneficial? The answer can be had from the Certificate itself. It enables
the unit to apply for various incentives under the State/Central
Government, as is apparent from serial no. (3) of the “NB” thereto. The
issuance of an Acknowledgement does not confer any right, in as much
as, the entrepreneur is required to seek requisite
clearance/licence/permit as statutorily required under the laws of the
Central Government/State Government/UT Administration/Court Orders.
This part is clarified in the “Note” appearing in the Certificate itself. The
MSME Act, 2006 which came about by virtue of the declaration made
under section 2 of the IDR Act, 1951 is a central enactment providing for
an appropriate legal framework in order to facilitate the growth and
development of micro, small and medium enterprises. The legal
framework involves the grant of Certificate of Issuance (EM Part-II) by
the District Industries Centre in proof of the existence of the
workshop/unit as well as the basis for seeking incentives under the
various schemes of the State/Central Government.
59. The foregoing discussions points to the direction that the
provisions under the MSME Act, 2006, to the extent applicable in the
facts and circumstances of this case, is for ascertaining due compliance
of proof of existence of the workshop. Registration of the unit for the
purpose of carrying on “manufacturing process” would require a Factory
Licence under the Assam Factories Rules, 1950, framed under the
provisions of the Factories Act, 1948.
60. Clause 3.0 of the Bid Evaluation Criteria is an essential condition
of the tender which has to be rigidly enforced. The Factory Licence
under the Assam Factories Rules, 1950 is sine qua non for due
compliance of the requirement of registration under “Act of Govt. of
Assam”. At the same time there is also the requirement of a Certificate
to be issued from the District Industries office, but only to the extent of
29
ascertaining “proof of workshop”. Both the requirements are distinct
from each other, flowing out from two distinct statutes.
61. In view of all the discussions above, the stand of the respondent
ONGC in deciding to open the price bid of respondent no. 9, despite non-
fulfillment of an essential condition of the tender under Clause 3.0,
operates as a decision which no responsible authority acting reasonably
could have reached having regard to the relevant law in force.
Accordingly, the said decision of respondent ONGC to open the price bid
of respondent no. 9 cannot be allowed to stand. It is set aside and
declared null and void. In this connection it is clarified that power is
being exercised as a judicial authority on been satisfied that the
statutory authority i.e. ONGC Ltd. acted in excess of its power in
contravention of the essential condition of the tender as well as its power
which the legislature has confided in it.
62. The techno-commercial bid of respondent no. 9 cannot survive
being in violation of Clause 3.0 of the Bid Evaluation Criteria to the
extent indicated above. The adjudication on this point alone is sufficient
to hold that the decision of the respondent ONGC is bad in law, without
entering into any further debate on the question as to whether the
respondent no. 9 had the experience in repair and fabrication job related
to drilling operations for a minimum period of three years, as envisaged
under Clause 2.1(a)(i) of the Bid Evaluation Criteria or to any other
challenge posed.
63. Resultantly, the writ petition stands allowed and the parties are
made to bear their own costs.
JUDGE
gunajit