imagine the result 2013 on-site site characterization work plan

43
Imagine the result Flint Hills Resources Alaska, LLC 2013 On-Site Site Characterization Work Plan North Pole Refinery North Pole, Alaska February 1, 2013

Upload: doananh

Post on 13-Feb-2017

214 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Imagine the result 2013 On-Site Site Characterization Work Plan

Imagine the result

Flint Hills Resources Alaska, LLC

2013 On-Site Site Characterization Work Plan

North Pole Refinery North Pole, Alaska February 1, 2013

Page 2: Imagine the result 2013 On-Site Site Characterization Work Plan
Page 3: Imagine the result 2013 On-Site Site Characterization Work Plan

2013 On-Site Site Characterization Work Plan.docx i

Table of Contents

Acronyms and Abbreviations vi

1.  Introduction 1 

1.1  Site Priorities 1 

1.2  Purpose 2 

1.3  ADEC Requests 3 

2.  Site Setting 8 

2.1  Property Description 8 

2.2  Physical Setting 8 

2.3  Current Groundwater Impacts 9 

2.4  Current Light Nonaqueous Phase Liquid Impacts 9 

2.5  Current Soil Impacts 10 

2.6  Current Remedial Operations 10 

3.  Current Conceptual Site Model 12 

4.  LNAPL Investigation 13 

4.1  LNAPL Baildown Testing Technical Background 13 

4.2  LNAPL Baildown Testing Schedule Revision 13 

4.3  Additional LNAPL Observation Well Installation for Transmissivity Testing 14 

4.4  Additional LNAPL Composition Evaluation 15 

5.  Phase 8 Groundwater Monitoring Well Installation 16 

5.1  Previously Proposed Phase 8 Monitoring Wells 16 

5.2  Upgradient Groundwater Delineation 16 

5.3  Proposed Additional Monitoring Wells for Further Characterization 16 

5.4  Additional Observation Wells for Groundwater Capture 17 

5.5  Proposed BTEX Characterization and Delineation 18 

5.6  Wells Proposed for Abandonment 18 

6.  Soil Characterization 19 

7.  Investigation-Derived Waste 20 

8.  Schedule 21 

Page 4: Imagine the result 2013 On-Site Site Characterization Work Plan

2013 On-Site Site Characterization Work Plan.docx ii

Table of Contents

9.  References 22 

Tables

Table 1 Proposed LNAPL Recovery and Observation Wells

Table 2 Proposed Wells for Additional Characterization and Delineation

Table 3 Proposed Locations for BTEX Characterization and Delineation

Figures

Figure 1 Site Location

Figure 2 Current Site Features

Figure 3 Site Plan – Onsite

Figure 4 Site Plan – Offsite

Figure 5 Proposed LNAPL Recovery and Observation Wells

Figure 6 Proposed Wells for Additional LNAPL Composition Analysis

Figure 7 Proposed Wells for Additional Characterization and Delineation

Figure 8 Proposed Locations for BTEX Characterization and Delineation

Figure 9 Proposed Soil Boring Locations, The Southwest Area (Former EU Wash Area)

Appendices

A Current Conceptual Site Model 

B Historical Residual LNAPL 

C Hydrographs 

Page 5: Imagine the result 2013 On-Site Site Characterization Work Plan

2013 On-Site Site Characterization Work Plan.docx iv

Acronyms and Abbreviations

AAC Alaska Administrative Code

ADEC Alaska Department of Environmental Conservation

ARCADIS ARCADIS U.S., Inc.

ASTM American Society for Testing and Materials

Barr Barr Engineering Company

bgs below ground surface

BTEX benzene, toluene, ethylbenzene, and total xylenes

city North Pole, Alaska

CSM conceptual site model

DPR dual-phase recovery

EU Extraction Unit

FHRA Flint Hills Resources Alaska, LLC

GAC granular activated carbon

GVEA Golden Valley Electric Association

IRAP Interim Removal Action Plan

IRAP Addendum Interim Removal Action Plan Addendum

ITRC Interstate Technology & Regulatory Council

LNAPL light nonaqueous phase liquid

NPR North Pole Refinery

Onsite FS Draft Final Onsite Feasibility Study

power plant electrical generating facility

Revised Draft Final HHRA Revised Draft Final Human Health Risk Assessment

RSAP Revised Sampling and Analysis Plan

site FHRA North Pole Refinery, an active petroleum refinery located on H and H Lane in North Pole, Alaska

TPT Technical Project Team

Page 6: Imagine the result 2013 On-Site Site Characterization Work Plan

2013 On-Site Site Characterization Work Plan.docx v

Acronyms and Abbreviations

USEPA United States Environmental Protection Agency

work plan 2013 Site Characterization Work Plan

WWTP wastewater treatment plant

µg/L micrograms per liter

Page 7: Imagine the result 2013 On-Site Site Characterization Work Plan

2013 On-Site Site Characterization Work Plan.docx 1

2013 On-Site Site Characterization Work North Pole Refinery North Pole, Alaska

1. Introduction

ARCADIS U.S., Inc. (ARCADIS) prepared this 2013 Site Characterization Work Plan (work

plan) on behalf of Flint Hills Resources Alaska, LLC (FHRA), for the FHRA North Pole

Refinery (NPR), an active petroleum refinery located on H and H Lane in North Pole, Alaska

(site). The site location and site features are shown on Figures 1 and 2.

This work plan addresses the recommendations presented in the Site Characterization

Report – Through 2011 (SCR – 2011; Barr Engineering Company [Barr] 2012) and the Alaska

Department of Environmental Conservation’s (ADEC’s) requests for additional site

assessment, as expressed at Technical Project Team (TPT) meetings and in general

communications between the ADEC and FHRA.

It is acknowledged that in 18 Alaska Administrative Code (AAC) 75.990(115), the ADEC

defines the term “site” as an “area that is impacted, including areas impacted by the migration

of hazardous substances from a source area, regardless of property ownership.” For this

work plan, the term “onsite” is the area that is located within the property boundary of the

FHRA NPR, and the term “offsite” is the area located outside the property boundary in the

downgradient north-northwest direction, based on the approximate extent of the dissolved-

phase sulfolane plume detected at concentrations above the laboratory limit of detection

(approximately 3 micrograms per liter [µg/L]).

Site conditions were previously evaluated in the Site Characterization and First Quarter 2011

Groundwater Monitoring Report (Barr 2011), the Site Characterization Work Plan Addendum

(ARCADIS 2011a), the Site Characterization Report – Through 2011 (SCR-2011; Barr 2012)

and the Site Characterization Report – 2012 Addendum (SCR-2012; ARCADIS 2013a). The

Revised Draft Final Human Health Risk Assessment (Revised Draft Final HHRA; ARCADIS

2012a) evaluates whether concentrations of site-related constituents in groundwater pose a

risk to onsite and offsite receptors.

ARCADIS and Shannon and Wilson, Inc. will complete the scope of work presented in this

work plan, including soil vapor investigation, well installation and abandonment, additional

groundwater monitoring, baildown testing, and soil boring advancement. Field activities will

be completed by qualified persons as defined by 18 AAC 75.990.

1.1 Site Priorities

In a letter to FHRA dated August 18, 2011 (ADEC 2011), the ADEC listed priorities for

the site per 18 AAC 75. FHRA has focused its work to address the ADEC’s priorities and

significant work has been completed toward achieving them. The additional

characterization activities proposed below continue to address the site priorities through

proposed enhancements to the monitoring network and collection of additional data to

support development of an aggressive cleanup plan.

Page 8: Imagine the result 2013 On-Site Site Characterization Work Plan

2013 On-Site Site Characterization Work Plan.docx 2

2013 On-Site Site Characterization Work North Pole Refinery North Pole, Alaska

1.2 Purpose

This work plan outlines proposed field activities and includes the scope, technical background

and rationale for each proposed activity. Progress of the proposed field activities will be

documented in Site Characterization Subgroup Meetings. The proposed field activities

include:

Conduct an investigation to evaluate the potential for soil vapor accumulation in and

beneath existing buildings onsite.

Implement light non-aqueous phase liquid (LNAPL) baildown testing during seasonal

groundwater hydrogeologic minimum.

Installation of one replacement LNAPL recovery well and additional LNAPL observation

wells for LNAPL baildown testing and additional potential recovery operations.

Additional LNAPL composition analysis of petroleum constituents to improve the spatial

understanding of the benzene, toluene, ethylbenzene, and xylene (BTEX) fraction of the

LNAPL.

Installation of groundwater monitoring wells at the property boundary downgradient of the

interim remedial measures to monitor groundwater quality.

Installation of upgradient groundwater wells for further delineation.

Installation of additional monitoring wells and well nests for further characterization and

delineation.

Complete vertical characterization of BTEX concentrations in groundwater in select

locations onsite.

Abandon tracer testing monitoring wells.

Perform soil characterization activities onsite to delineate soil impacts near the former

southwest wash area based on 2012 soil investigation findings, as reported in the SCR –

2012 (ARCADIS 2013a).

Conduct high density vertical soil sampling within the Southwest Area (Former Extraction

Unit [EU] Wash Area) to evaluate the distribution of sulfolane impacts in the soil column

in a known sulfolane source area.

Additional data collected during the proposed activities will further refine the conceptual site

model (CSM), the scoping of onsite remedial alternatives, the groundwater model presented

Page 9: Imagine the result 2013 On-Site Site Characterization Work Plan

2013 On-Site Site Characterization Work Plan.docx 3

2013 On-Site Site Characterization Work North Pole Refinery North Pole, Alaska

in the Groundwater Model Report (Geomega 2013 [In Press]) and the ongoing capture

evaluation of the current groundwater extraction system. The additional data will enhance the

project team’s understanding of the fate and transport of sulfolane, BTEX and LNAPL at the

site. The data will be used to develop the final Onsite Cleanup Plan. Appendix A of this work

plan presents the updated onsite CSM. Field activities will be completed by qualified persons

as defined by 18 AAC 75.990.

1.3 ADEC Requests

On January 18, 2013, ADEC issued a letter to FHRA detailing on-site data gaps identified by

the ADEC team. A summary of the requested activities, FHRA’s response to the identified

data gaps and any proposed efforts to address them are summarized below:

1. Sampling of onsite granular activated carbon (GAC). Evaluate formation of

intermediates in GAC filters. An evaluation of potential sulfolane intermediate products was

presented in the Interim Remedial Action Plan Addendum (IRAP Addendum; ARCADIS,

2013). FHRA will continue to work with the degradation subgroup to assess the potential for

formation of degradation intermediates. Sampling of the GAC filters is not included in this

work plan. Future sampling of the GAC, if necessary, will be proposed at a future date.

2. Additional soil borings at depth for LNAPL delineation. ARCADIS has reviewed

available soil boring logs, petroleum soil sampling data, LNAPL accumulation in current wells,

LNAPL accumulation in historic wells, and LIF data. These data provide a complete picture

of horizontal and vertical LNAPL delineation at the site. A compilation of the LNAPL

delineation data are presented on Plate 1 (Appendix B). ARCADIS will prepare a summary of

vertical delineation data and present it in the 2013 Site Characterization Report.

While FHRA believes that LNAPL delineation is complete, additional LNAPL assessment is

proposed in Section 5 of this work plan to collect additional information on the LNAPL

transmissivity within the LNAPL plume.

3.1 Soil gas assessment. FHRA is actively collecting information on building construction

details, including the presence or absence of vapor barriers, and ventilation system

configurations. FHRA will review that information in the near future with respect to the

suitability of the engineering controls for protecting human health at the facility. FHRA will

then provide a proposed path forward as an Addendum to this Work Plan that will include, if

appropriate, a proposal for soil gas assessment.

3.2 LNAPL composition analysis. FHRA has conducted extensive LNAPL composition

sampling to date. LNAPL composition data were collected as part of two studies from 19

total wells as reported in the Site Characterization Report – Through 2011 (Barr 2012). The

locations of wells where LNAPL compositional data have been collected to date are

presented on Figure 6.

Page 10: Imagine the result 2013 On-Site Site Characterization Work Plan

2013 On-Site Site Characterization Work Plan.docx 4

2013 On-Site Site Characterization Work North Pole Refinery North Pole, Alaska

As part of this Work Plan, FHRA will collect additional LNAPL samples for compositional

analysis of petroleum constituents to improve the spatial understanding of the BTEX fraction

of the LNAPL. These data will be valuable for consideration of the benefit of deployment of

remedial technologies that can target removal of the BTEX fraction from LNAPL.

Regarding conducting compositional analysis for sulfolane, additional testing of LNAPL for

sulfolane is not proposed at this time. FHRA believes that this is not necessary for the

following reasons. First,, it is acknowledged that sulfolane is present in LNAPL, likely related

to sulfolane partitioning from impacted groundwater into the LNAPL, and that the sulfolane

present in the LNAPL may be a relevant source of sulfolane to groundwater in the future due

to partitioning of sulfolane from LNAPL to groundwater. However, as described in Appendix A

of the Site Characterization Report – 2012 Addendum, LNAPL was an insignificant source of

the sulfolane that was released to the environment as compared to the other identified

sources of sulfolane. In addition, existing data on sulfolane in LNAPL indicate that the LNAPL

is currently a sink of or in equilibrium with sulfolane in groundwater rather than a source to

groundwater. Also, there are no remedial technologies for selectively targeting sulfolane in

LNAPL. Therefore the data will not inform remedial decision-making.

3.3 LNAPL mass estimate. FHRA has previously expressed the impracticability of

calculating LNAPL mass estimates. Estimates of this type are generally only accurate within

one to two orders of magnitude, and would not be useful for planning, implementing or

measuring the performance of a remedy.

4.1 Bench scale test for the dead-end pore space theory referred to in the groundwater model. It is FHRA's understanding that ADEC wants to develop a conceptual model to

explain the persistence of sulfolane in historical sulfolane release areas. FHRA shares this

desire as an improved understanding of sulfolane persistence will allow FHRA to improve the

reliability of any future sulfolane source area remedies to address.

FHRA believes that there are three reservoirs for sulfolane mass that currently discharge

sulfolane or in the future may discharge sulfolane to groundwater.

• Sulfolane in unsaturated soil and the capillary fringe. Soil sampling has shown that

sulfolane is present in unsaturated soils in former sulfolane release areas. Research has

been conducted by a number of groups to explore the persistence of ethanol impacts to

groundwater following a neat or denatured ethanol release. Like sulfolane, ethanol is

miscible in groundwater and would not be expected to be a persistent source of

groundwater contamination after a release to the environment. However, ethanol

impacts to groundwater persist for months to years after release, suggesting that there

must be a storage mechanism for ethanol.

Researchers studying ethanol persistence have found that high concentrations of ethanol

are present in soil moisture above the water table and within the capillary fringe

Page 11: Imagine the result 2013 On-Site Site Characterization Work Plan

2013 On-Site Site Characterization Work Plan.docx 5

2013 On-Site Site Characterization Work North Pole Refinery North Pole, Alaska

(McDowell and Powers 2003; Freitas and Barker 2011). These observations have been

linked to the miscibility of ethanol and to the density of ethanol, which is lower than

groundwater. While the latter mechanism would not be relevant to the sulfolane-laden

wastewater that was released, which would be expected to be slightly more dense than

groundwater, the solubility of sulfolane likely would have resulted in transfer of sulfolane

into soil pore water. Additionally, a high concentration of sulfolane may be present in the

capillary fringe as has been observed in the ethanol studies.

The persistence of sulfolane in unsaturated soils is also likely related to minimal

infiltration in the impacted areas due to soil compaction in road and equipment areas, site

grading to minimize accumulation of water at grade and soil capping (Lagoon B and

Sump 02/04-2). Groundwater fluctuation brings sulfolane in contact with the impacted

soils resulting in transfer of sulfolane from soil to groundwater.

• Sulfolane in immobile saturated zone pore space. Sulfolane may be stored in

saturated soils of low permeability below the water table at the site, such as soil layers

that have a silt matrix, resulting in dual-porosity transport behavior. Most soils consist of a

mixture of both slowly and rapidly conducting pore sequences, and groundwater

velocities in the smallest pores may be extremely slow and even negligible. This results

in slow or incomplete mixing of solutes and results in tailing.

Field tests conducted at the site have demonstrated a nearly four-order-of-magnitude

range in hydraulic conductivity that is correlated with changes in grain size distribution

and is consistent with the horizontally layered structure of site soils. For example, it is not

uncommon at the site to find layers and lenses of gravel, sand, and silt that were

deposited in a fluvial environment. Where low-permeability soil layers such as silt are

surrounded by relatively high-permeability layers such as sand and gravel, sulfolane may

enter the low permeability layers and be stored there in immobile groundwater and result

in tailing and dual-porosity behavior.

This “dual-porosity conceptual model” was first investigated and described by

researchers such as Martinus van Genuchten and Jacob Bear in the 1960s and 1970s

(e.g., van Genuchten and Wierenga 1976; Bear 1972). Since then, numerous bench-

scale and field-scale tests have been performed by groundwater scientists to test and

validate the dual-porosity conceptual model, which has resulted in a large body of

scientific work to the extent that the dual-porosity conceptual model is considered “the

state of the science”.

• Sulfolane in LNAPL. As discussed above LNAPL sulfolane data collected to date

indicate that LNAPL is likely a sink of or in equilibrium with sulfolane in groundwater.

The immobile pore-space concept has been conducted by others to demonstrate the physical

viability of the concept. FHRA will prepare a white paper and bibliography of relevant

Page 12: Imagine the result 2013 On-Site Site Characterization Work Plan

2013 On-Site Site Characterization Work Plan.docx 6

2013 On-Site Site Characterization Work North Pole Refinery North Pole, Alaska

technical literature if desired. Site-specific bench-scale testing will not provide benefit

because disturbance of the soil structure through soil collection and placement in a testing

vessel would yield results that are not representative of field conditions. Field testing using

tracers was completed in 2012 and determined that the mobile porosity in the vicinity of the

field test was five percent, which demonstrates that the immobile pore space concept is

relevant at the site. Based on the availability of existing literature and the field testing

conducted previously, bench scale testing will not be pursued.

However, FHRA does see value in assessing the distribution of sulfolane impacts in the soil

column in a known sulfolane source area. These data will refine our understanding of the

vertical distribution of sulfolane within impacted soil and our conceptual model for sulfolane in

soil as an ongoing contribution to sulfolane impacts in groundwater. FHRA proposes high

density vertical soil sampling within the Southwest Area (Former EU Wash Area) to assess

the vertical distribution of sulfolane in soil in a known sulfolane source area. Soil moisture

data will also be collected in order to correlate the soil data to the presence of the capillary

fringe. The proposed data collection location and methodology are summarized in Section

6.0.

4.2 Equilibrium solubility testing of sulfolane in LNAPL. Equilibrium solubility testing of

sulfolane in LNAPL has been discussed previously in the context of achieving a lower

sulfolane detection limit in LNAPL compared to historical testing. As discussed above,

additional LNAPL sulfolane testing is not being proposed at this time.

4.3 Additional soil and groundwater assessment (vertical and horizontal) in areas of

highest sulfolane concentrations (MW-138, MW-176, O-1, MW-110, SB-143, plus deep

delineation in vicinity of former bolted tanks and other locations where hydropunch showed

deep sulfolane and/or benzene). Additional soil and groundwater investigations proposed at

the site are summarized in Sections 7 and 6, respectively. Recommendations for further

evaluation of deep BTEX concentrations are presented in Section 5.5. Additional

characterization near well nest MW-176 is proposed in the LNAPL Section (Section 4).

4.4 Bench scale test to evaluate if sulfolane becomes a solid or gel in colder temperatures.

FHRA has interviewed operations personnel to determine sulfolane gelling or solidification

occurs within the process equipment or could have occurred related to historic sulfolane

discharges to the environment. The feedback from operations personnel is discussed in brief

below.

Sulfolane is received at the facility as a concentrated water solution, which remains a liquid at

relevant temperatures. As part of the sulfolane recovery process in the Extraction Unit, steam

is used to strip the aromatics and most water from the sulfolane, resulting in a highly

concentrated or “neat” sulfolane. While it is not free of all water, it is concentrated enough that

it forms a gel at ambient temperatures above freezing in some locations in the Extraction

Unit. However, it does not form identifiable crystals that separate from the solution, even as it

Page 13: Imagine the result 2013 On-Site Site Characterization Work Plan

2013 On-Site Site Characterization Work Plan.docx 7

2013 On-Site Site Characterization Work North Pole Refinery North Pole, Alaska

gels or hardens, depending on the temperature. This sulfolane is reused within the extraction

unit.

The sump in the Extraction Unit is emptied by a pump based on the fluid level, and there is

residual water in the base of the sump even at the low level pump shut off. If gelled sulfolane

were to enter the sump, it would dissolve immediately in the water standing in the base of the

sump, so there is no reasonable mechanism for gelled sulfolane to be released to the

environment. While historical released from the sump have been in relatively high

concentrations, they would have still been in aqueous phase.

We do not believe bench testing of sulfolane forming a gel or solid is needed as the nature of

the concentrated form of sulfolane is adequately understood. We also believe it is highly

unlikely that sulfolane could act in the soils in a way to leave behind a residual solid, crystal,

or gel. Historic sulfolane releases have been from aqueous wastewater sources.

5. Plan for the interim remedy performance monitoring. A plan for interim remedy

performance monitoring, including the installation of additional performance monitoring wells,

was included in the IRAP Addendum, submitted on January 18, 2013 (ARCADIS 2013b).

Page 14: Imagine the result 2013 On-Site Site Characterization Work Plan

2013 On-Site Site Characterization Work Plan.docx 8

2013 On-Site Site Characterization Work North Pole Refinery North Pole, Alaska

2. Site Setting

2.1 Property Description

The site is located on 240 acres inside the city limits of North Pole, Alaska (the city). The city

is located approximately 13 miles southeast of Fairbanks, Alaska, within Fairbanks North Star

Borough (Figure 1). NPR is an active petroleum refinery that receives crude oil feedstock

from the Trans-Alaska Pipeline. The site was developed in the mid-1970s and operations

began in 1977.

Three crude oil processing units are located in the southern portion of the site, making up the

process area. Only one of the processing units is currently operating. Tank farms are located

in the central portion of the site. Truck-loading racks are located immediately north of the tank

farms and a railcar-loading rack is located west of the tank farms. Previously, a truck-loading

rack was located between the railcar-loading rack and the tank farms, near the intersection of

Distribution Street and West Diesel. Wastewater treatment lagoons, storage areas, and two

flooded gravel pits (the North and South Gravel pits) are located in the western portion of the

site. Rail lines and access roads are located in the northernmost portion of the site. Along the

southern site boundary, partially surrounded by the NPR, is an electrical generating facility

(power plant) operated by Golden Valley Electric Association (GVEA). FHRA representatives

indicated that the power plant burns heavy aromatic gas oil (diesel 4) or other fuels produced

at the site. The property south of the site and the GVEA power plant is occupied by the Petro

Star, Inc. Refinery. Site features are presented on Figure 2.

North of the site are residential properties and the city’s wastewater treatment plant (WWTP).

The North Pole High School is located immediately north and west of the WWTP and

residential properties. An undeveloped parcel, owned by the Alaska Department of Natural

Resources, lies between the site and the WWTP. The Tanana River is located to the west,

flowing in a northwesterly direction toward Fairbanks. East of the site is property that is

residential or undeveloped, the Old Richardson Highway, and the Alaska Railroad right-of-

way. Current site features are presented on Figure 2. Onsite and offsite site plans are

presented on Figures 3 and 4, respectively.

2.2 Physical Setting

The site and the surrounding North Pole area are located on a relatively flat-lying alluvial plain

that is situated between the Tanana River and Chena Slough (locally known as Badger

Slough). The site is located on the Tanana River Floodplain. Up to 2 feet of organic soils are

typically found in the undeveloped portions of the site. A discontinuous silt and silty sand

layer that varies in thickness from 0 to 10 feet typically occurs beneath the organic soils.

Alluvial sand and gravel associated with the Tanana River are present below the organic soil

and silty layers. Depth to bedrock has been estimated at 400 to 600 feet below ground

surface (bgs).

Page 15: Imagine the result 2013 On-Site Site Characterization Work Plan

2013 On-Site Site Characterization Work Plan.docx 9

2013 On-Site Site Characterization Work North Pole Refinery North Pole, Alaska

The city is located within an area of Alaska characterized by discontinuous permafrost

(Ferrians 1965). Permafrost tends to act as a confining unit, impeding and redirecting the flow

direction of groundwater (Glass et al. 1996). Based on regional information (Williams 1970,

Miller et al. 1999), permafrost is assumed to be absent beneath the Tanana River.

The aquifer beneath the alluvial plain between the Tanana River and Chena Slough generally

consists of highly transmissive sands and gravels under water table conditions (Cederstrom

1963, Glass et al. 1996). The Tanana River has a drainage area of approximately 20,000

square miles upstream of Fairbanks (Glass et al. 1996). Near the site, this aquifer is

reportedly greater than 600 feet thick (at least 616 feet thick near Moose Creek Dam) (Glass

et al. 1996). Beyond the zones of influence of the site groundwater recovery system,

groundwater flow directions are controlled by discharge from the Tanana River to the aquifer

and from the aquifer to the Chena River, as described by Glass et al. (1996). Variations in

river stage through time are believed to be the primary cause of variations in flow direction

through the aquifer between the rivers (Lilly et al. 1996, Nakanishi and Lilly 1998). Based on

data from U.S. Geological Survey water table wells, the flow direction varies up to 19 degrees

from a north-northwesterly direction to a few degrees east of north. The flow direction trends

to the north-northwest in spring and more northerly in the summer and fall (Glass et al. 1996).

2.3 Current Groundwater Impacts

On-site groundwater monitoring data collected during the most recent annual and quarterly

reporting periods (second and third quarter 2012, respectively) are generally consistent with

data collected during previous reporting periods. Maximum concentrations of benzene

(27,300 micrograms per liter [µg/L]), toluene (23,100 µg/L), ethylbenzene (1,450 µg/L) and

total xylenes (16,100 µg/L) were detected in groundwater collected from monitoring well MW-

138 during the second quarter 2012; these impacts are limited to the developed portion of the

site. Sulfolane concentrations continue to be detected in both on-site groundwater

observation and monitoring wells at concentrations up to 4,940 µg/L (O-1) and in offsite

groundwater monitoring wells at concentrations up to 286 µg/L (MW-161B). The plume

geometry inferred from third quarter 2012 monitoring well data is generally consistent with

previous monitoring events (ARCADIS 2012b). Second and third quarter 2012 data are

presented in quarterly groundwater monitoring reports (ARCADIS 2012b and 2012c,

respectively)

2.4 Current Light Nonaqueous Phase Liquid Impacts

Depth to LNAPL measurements are regularly collected from a network of monitoring,

observation, and recovery wells screened across the water table onsite. During the third

quarter 2012, LNAPL accumulation was measured in 21 wells during July 2012, in 22 wells

during August 2012, and in 28 wells during September 2012. A visible sheen or trace (not

measureable in the field) was recorded in seven wells during July 2012, in eight wells during

August 2012, and in two wells during September 2012. During the reporting period (on

Page 16: Imagine the result 2013 On-Site Site Characterization Work Plan

2013 On-Site Site Characterization Work Plan.docx 10

2013 On-Site Site Characterization Work North Pole Refinery North Pole, Alaska

September 19, 2012), a maximum LNAPL thickness of 2.89 feet was measured at monitoring

well MW-176A (Figure 2). LNAPL thicknesses are consistent with historical LNAPL

measurements.

2.5 Current Soil Impacts

Soil samples were collected at the site as described in the SCR – 2011 (Barr 2012).Based on

recommendations outlined in the SCR – 2011 (Barr 2012), FHRA conducted further soil

characterization of soil impacts at the site from May to August 2012. Areas for focused

investigation included:

Area around boring SB-143, the Southwest Area (Former EU Wash Area)

Area near the exchanger wash skid

Area around boring O-6, west of the railcar-loading rack in the historical storage yard

Area around boring O-27, west of the current truck-loading rack area

Area north of the asphalt-truck loading rack and O-25

Lagoon B

Area northwest of Lagoon B

As part of this supplemental investigation, FHRA collected and submitted 146 soil samples

for laboratory analysis. Delineation of sulfolane and BTEX was achieved at some locations.

However, laboratory analysis of the soil samples showed potential source-area level

concentrations of sulfolane in the Southwest Area (Former EU Wash Area). Samples in this

area were collected from the surface (0-2 feet bgs) and immediately above the air-

groundwater interface (approximately 5-9 feet bgs). Additional borings were added during

the investigation, but delineation of the elevated concentrations was not completed. Results

of the soil investigations are discussed in the SCR – 2012 (ARCADIS 2013a).

2.6 Current Remedial Operations

FHRA is currently in the final stages of implementing the interim corrective actions described

in the Interim Remedial Action Plan (IRAP; Barr 2010) to optimize the existing groundwater

pump and treat remediation system to address LNAPL and impacted groundwater onsite.

Operation of the remediation system currently involves groundwater recovery from five

recovery wells (R-21, R-35R, R-39, R-40, and R-42). Recovered groundwater is treated

through a prefilter for solids removal, a coalescer for LNAPL removal, and four air strippers

for removal of volatile organic compounds before accumulating in the Gallery Pond. The

groundwater from the Gallery Pond is then pumped through sand filters for solids removal

and a four-vessel GAC system for sulfolane removal. Installation and startup of the sand

filters and GAC treatment system was completed during the second quarter 2011 and active

operation was initiated on June 9, 2011.

Page 17: Imagine the result 2013 On-Site Site Characterization Work Plan

2013 On-Site Site Characterization Work Plan.docx 11

2013 On-Site Site Characterization Work North Pole Refinery North Pole, Alaska

A fifth recovery well (R-42) was installed as part of the IRAP (Barr 2010) implementation and

pumping from well R-42 was initiated on July 26, 2011. Also, in accordance with the IRAP

(Barr 2010), nested monitoring wells MW-186 A/B/C were installed and a capture zone test

was conducted in late August and early September 2011. Performance monitoring was

conducted to evaluate the horizontal and vertical capture of the groundwater pump and treat

remediation system. Results of the performance monitoring are discussed in the SCR – 2011

(Barr 2012).

FHRA is in the process of completing installation of four additional recovery wells (R-43, R-

44, R-45, and R-46). These new wells will replace R-39 and R-40, and augment capture in

the R-21 area. Recovery wells existing prior to 2012 are shown on Figure 3. A technical

memorandum describing the proposed recovery wells was submitted to ADEC on September

14, 2012, and approval of the plan was received from the ADEC on October 3, 2012 (ADEC,

pers. comm. 2012b). The proposed wells are designed with dual-phase capability to allow for

a greater increase in both groundwater and LNAPL recovery. The proposed design includes

deeper wells with larger diameter casings and longer screened intervals compared to the

existing recovery wells. Each proposed well will have a submersible groundwater recovery

pump and a floating LNAPL skimmer pump.

Pneumatic LNAPL recovery systems are continuously operated at MW-138, R-20R, R-21, R-

35R and R-40. Additional pneumatic LNAPL recovery systems are operated seasonally at R-

32, R-33 and S-50. The LNAPL recovery system currently utilized at S-50 was previously

installed at O-2, but was moved due to low LNAPL recovery. FHRA also uses a hand-held

product recovery pump at other locations (e.g., R-39) if LNAPL is present and recovery is

possible. Recent LNAPL recovery data are included in the third quarter groundwater

monitoring report (ARCADIS 2012c). An expanded LNAPL recovery network was proposed in

the IRAP Addendum (ARCADIS 2013b).

Recovered LNAPL is recycled within the refinery process unit. In addition, LNAPL recovered

from the groundwater stream by the groundwater recovery pumps is collected for recycling in

a coalescer installed ahead of the air stripper. FHRA installed replacement recovery wells for

R-21, R-39, and R-40 during the fourth quarter 2012. Development and operation of these

new wells will be completed in second quarter 2013 to increase the system’s ability to capture

groundwater and LNAPL (Barr 2012).

Page 18: Imagine the result 2013 On-Site Site Characterization Work Plan

2013 On-Site Site Characterization Work Plan.docx 12

2013 On-Site Site Characterization Work North Pole Refinery North Pole, Alaska

3. Current Conceptual Site Model

An updated ADEC onsite CSM was most recently updated in connection with the Revised

Draft Final HHRA (ARCADIS 2012a) and was presented in the Draft Final Onsite Feasibility

Study (Onsite FS; ARCADIS 2012d) and is included in Appendix A of this work plan. The

CSMs will be refined as needed to account for additional data collected in the future.

Page 19: Imagine the result 2013 On-Site Site Characterization Work Plan

2013 On-Site Site Characterization Work Plan.docx 13

2013 On-Site Site Characterization Work North Pole Refinery North Pole, Alaska

4. LNAPL Investigation

LNAPL investigation activities proposed in this work plan include revisions to the baildown

testing schedule, installation of additional or replacement LNAPL recovery wells, and an

additional LNAPL composition evaluation. Baildown testing supports characterization of

LNAPL transmissivity at the site. The LNAPL transmissivity results are used to quantify

relative LNAPL recoverability to focus LNAPL recovery efforts in areas that have higher

recovery potential and to establish practical limits of recovery. Additional LNAPL composition

data will be used to assess the spatial distribution of BTEX in LNAPL.

4.1 LNAPL Baildown Testing Technical Background

The recoverability of LNAPL at an environmental site is influenced by many factors including

LNAPL saturation in the impacted soil, soil permeability, and physical properties of the

LNAPL. The saturation and permeability directly influence the relative permeability of LNAPL.

Due to the interactions of groundwater, air, and LNAPL within petroleum-impacted soil, the

relative permeability of LNAPL is less than the overall soil permeability. Moreover, the

physical properties of the LNAPL influence the rate that LNAPL can flow within the formation.

An empirical method to assess LNAPL recoverability at the field scale is to test LNAPL

transmissivity, which integrates all of the relevant factors influencing LNAPL recoverability.

LNAPL transmissivity is commonly characterized using short-term duration LNAPL stress

testing, also called LNAPL baildown testing.

An LNAPL baildown test is initiated by quickly removing LNAPL accumulated in a well,

making it analogous to a groundwater rising-head slug test. The rate of LNAPL flow into the

well is a function of soil and LNAPL properties discussed above and the magnitude of the

initial hydraulic gradient toward the well developed during LNAPL removal. The baildown test

response is influenced by the prevalent fluid levels at the time of testing. Therefore, to obtain

optimal results, baildown testing should be performed during seasonal hydrogeologic lows.

4.2 LNAPL Baildown Testing Schedule Revision

Baildown testing is currently performed semiannually during the second and fourth quarters.

The LNAPL baildown testing schedule will be revised to target local hydrogeologic cycle

minima instead of a calendar based schedule. Targeting the groundwater “low” will provide

LNAPL baildown testing results that are more representative of the maxima of the

transmissivity range.

The transducer network includes monitoring wells MW-113, MW-186A, MW-186B, MW-186C,

MW-186E, O-12 and S-43 which are within or adjacent to the LNAPL body. The available

transducer data from these wells were evaluated to determine the timing of the approximate

seasonal hydrogeologic lows. The hydrographs for the wells listed above are included as

Appendix C, and generally indicate a period of low seasonal groundwater elevations from

Page 20: Imagine the result 2013 On-Site Site Characterization Work Plan

2013 On-Site Site Characterization Work Plan.docx 14

2013 On-Site Site Characterization Work North Pole Refinery North Pole, Alaska

approximately November to March. However, due to regional weather patterns, November

through February is not a reliable period for conducting field work. Therefore, while data

collection in March may be impeded by suboptimal weather conditions, LNAPL baildown

testing is proposed for annual implementation in March. Testing during this will provide an

assumed maximum LNAPL transmissivity. To evaluate transmissivity during periods of higher

groundwater an additional test will be completed later in the year, no later than October.

LNAPL baildown testing will be conducted according to procedures outlined in the Revised

Sampling and Analysis Plan (RSAP), which was most recently submitted with the Work Plan

for Evaluation of Perfluorinated Compounds–Phase II (ARCADIS 2012e). Hydrographs are

included in Appendix C.

4.3 Additional LNAPL Observation Well Installation for Transmissivity Testing

Active remediation is ongoing to recover LNAPL at the site. From 1986 through the end of

2012, approximately 394,000 gallons of LNAPL were recovered at the site. Annual recovery

volumes have generally decreased as remediation has progressed and the volume of

recoverable LNAPL has decreased. However, based on LNAPL baildown testing conducted

in 2012, LNAPL transmissivities measured at the site indicate high LNAPL recoverability

(ARCADIS 2012c; ARCADIS 2013c [In Press]). LNAPL baildown testing and transmissivity

monitoring will take place at the wells specified below to support development of the Final

Onsite FS and the Onsite Cleanup Plan.

LNAPL recovery is the physical removal of LNAPL from a well and reduces LNAPL saturation

until it reaches residual saturation. At residual saturation, LNAPL will not flow and hydraulic

recovery is no longer possible (Interstate Technology & Regulatory Council [ITRC] 2009).

The effectiveness of LNAPL recovery is dependent on the flow of LNAPL into the recovery

well at which recovery operations are conducted.

To further assess LNAPL transmissivity and potentially improve LNAPL recovery at the site,

one replacement LNAPL recovery well and eight new LNAPL observation wells are

proposed:

R-32R – This well is proposed to replace existing well R-32. Well R-32 is currently

installed as a shallow culvert and LNAPL recovery is limited due to groundwater elevation

fluctuations below the bottom of the well. It is expected that a new, properly constructed

LNAPL recovery well at this location will improve LNAPL recovery.

O-31 through O-34 and O-36 through O-38 – These wells will provide additional LNAPL

observation well density for baildown testing and potential future recovery operations

within or near areas with known LNAPL impacts.

Page 21: Imagine the result 2013 On-Site Site Characterization Work Plan

2013 On-Site Site Characterization Work Plan.docx 15

2013 On-Site Site Characterization Work North Pole Refinery North Pole, Alaska

O-35 – This well is proposed near the MW-176 well nest. Manual recovery is ongoing on

well MW-176A which is a 2-inch PVC well. Properly constructed wells in this area will

optimize transmissivity measurements and potential future recovery operations at this

location.

Recovery and observation wells will be constructed as four-inch stainless steel risers with

stainless steel wire-wrapped screens and installed according to procedure outlines in the

RSAP. Proposed LNAPL recovery and observation wells are summarized in Table 1 and

shown on Figure 5.

4.4 Additional LNAPL Composition Evaluation

As previously mentioned, LNAPL composition data were collected as part of two studies from

19 total wells as reported in the Site Characterization Report – Through 2011 (Barr 2012).

FHRA will collect additional LNAPL samples for compositional analysis of petroleum

constituents from the following wells to improve the spatial understanding of the BTEX

fraction of the LNAPL:

New LNAPL recovery and observation wells (R-32R and O-31 through O-38) proposed in

Section 4.3, if LNAPL is present.

Wells for additional LNAPL composition analysis: MW-186A, MW-334-15, O-19, and O-

27.

Select wells that have been previously evaluated for LNAPL composition: MW-138, R-33,

and S-51.

Figure 6 presents the wells proposed for additional LNAPL composition analyses and

locations where historical LNAPL composition data were collected.

Page 22: Imagine the result 2013 On-Site Site Characterization Work Plan

2013 On-Site Site Characterization Work Plan.docx 16

2013 On-Site Site Characterization Work North Pole Refinery North Pole, Alaska

5. Phase 8 Groundwater Monitoring Well Installation

Phase 7 monitoring well installation was completed in August 2012 (ARCADIS 2013a) to

provide additional site characterization at the site. Phase 8 wells are proposed to further

enhance the understanding of the vertical and lateral extent of the sulfolane and BTEX

plumes and monitor contaminant removal by the remediation system.

5.1 Previously Proposed Phase 8 Monitoring Wells

Phase 8 monitoring wells at the north property boundary were proposed in the IRAP

Addendum (ARCADIS 2013b). These previously proposed Phase 8 monitoring wells are

summarized in Table 2 and presented on Figure 7.

5.2 Upgradient Groundwater Delineation

While upgradient monitoring wells (MW-105, MW-105A, MW-192A, MW-192B and MW-196

provide adequate upgradient monitoring data for the site, these wells are greater than 500

feet upgradient of the sulfolane source areas. To better define conditions upgradient of the

process areas, FHRA proposes to install five new monitoring wells upgradient of Crude Units

1 and 2 and the sulfolane extraction unit. Proposed wells will be screened across the water

table and are summarized in Table 2 and presented on Figure 7.

5.3 Proposed Additional Monitoring Wells for Further Characterization

Horizontal and vertical delineation of the sulfolane plume has progressed; however, to further

enhance the understanding of the nature and extent of sulfolane impacts, FHRA proposes to

install 11 additional onsite monitoring wells. Proposed wells described below are summarized

in Table 2 and presented on Figure 7.

An additional deeper monitoring well (8-L) near the MW-154 well cluster will be installed to

evaluate sulfolane concentrations deeper than the screened interval of MW-154B to support

air sparge barrier design testing proposed in the IRAP Addendum (ARCADIS 2013b). During

installation of well MW-154B, permafrost was observed at approximately 102 ft bgs, which

may limit the installation depth of the additional well.

An additional deeper monitoring well (8-M) will be installed near MW-110 to further

characterize sulfolane concentrations at 10 to 55 feet below the water table.

A new monitoring well (MW-174-15) is proposed to replace decommissioned well MW-111.

The replacement well will be located near the MW-174 well cluster north of Lagoon C. Well

MW-174-15 will be screened across the water table to support delineate of sulfolane

concentrations identified during the Hydropunch investigation (ARCADIS 2013a).

Page 23: Imagine the result 2013 On-Site Site Characterization Work Plan

2013 On-Site Site Characterization Work Plan.docx 17

2013 On-Site Site Characterization Work North Pole Refinery North Pole, Alaska

A well cluster (8-N) will be installed to evaluate sulfolane concentrations in the area northwest

of observation well O-1. This cluster will consist of a water table well, and a well installed

approximately 50-ft below the water table.

Five new monitoring wells will be installed in the vicinity of well MW-138 for further

characterization of the sulfolane plume downgradient of the extraction unit sump source area.

One well (MW-337-20) will be installed just northeast of well MW-138 and screened a few

feet below seasonal LNAPL fluctuations to monitor sulfolane concentrations without the

presence of LNAPL during sampling. Four nested wells (MW-336-15, MW-336-20, MW-336-

35, and MW-336-55) will be installed farther east-northeast of well MW-138 to further

characterize sulfolane concentrations across the water table and 10 to 55 feet below the

water table identified during the Hydropunch investigation (ARCADIS 2013a).

Three wells were proposed in the 2012 Site Characterization Work Plan (ARCADIS 2012f) for

well nest 7-J: one screened across the water table and two screened at depth. Of these, two

wells (MW-334-15 and MW-334-65) were installed. Installation of the third proposed well was

temporarily postponed based on monitoring results from the other two wells. During the third

quarter 2012, groundwater collected from well MW-334-65 exhibited an estimated sulfolane

concentration of 6.21J µg/L. Therefore, the third well (MW-334-85) is proposed for installation

and will be screened at a depth between 55 and 90 feet below the water table.

Soil samples will be collected during installation of these proposed wells, and will be

submitted for laboratory analysis in accordance with the RSAP. Select soil samples will be

submitted for laboratory analysis to determine concentrations of BTEX by US EPA Method

8021B, gasoline range organics by AK101, diesel range organics by AK102, polynuclear

aromatic hydrocarbons by 8270C, and sulfolane by USEPA modified Method 8270D.

The additional proposed wells will also be sampled in conjunction with quarterly groundwater

monitoring events according to procedures outline in the RSAP. Collected groundwater

samples will be analyzed for sulfolane by modified USEPA Method 1625 with isotope

dilution.

5.4 Additional Observation Wells for Groundwater Capture

FHRA updated the progress on the Recovery Well Replacement Project, an upgraded

groundwater extraction system and LNAPL dual-phase recovery (DPR) program, in the IRAP

Addendum (ARCADIS 2013b). The objectives of groundwater extraction and DPR operations

are to provide capture of the shallow dissolved-phase sulfolane and BTEX plumes at the site

and to recover LNAPL within the zone of treatment (Barr 2012).

Performance monitoring will be conducted to evaluate the effectiveness of the groundwater

extraction system through assessment of hydraulic capture of downgradient contaminant

concentrations in groundwater. To further evaluate trends and improve monitoring of

Page 24: Imagine the result 2013 On-Site Site Characterization Work Plan

2013 On-Site Site Characterization Work Plan.docx 18

2013 On-Site Site Characterization Work North Pole Refinery North Pole, Alaska

contaminant capture of sulfolane and BTEX concentrations, additional wells screened in the

10 to 55 feet below water table groundwater zone are proposed for installation adjacent to

observation wells O-5, O-12, O-24 and O-26 located downgradient of the groundwater

extraction system. Proposed wells are summarized in Table 2 and presented on Figure 7.

Proposed wells will be installed according to procedures outlined in the RSAP. Groundwater

samples will be analyzed for BTEX by USEPA Method 8021 and sulfolane by modified

USEPA Method 1625 with isotope dilution.

5.5 Proposed BTEX Characterization and Delineation

As described in the SCR – 2011, FHRA proposed a “one-time” sampling of a subset of

monitoring wells screened in the 10-55’ BWT zone and the 55-90’ BWT zone for BTEX (Barr

2012). Additionally, the SCR – 2011 recommended a discrete interval groundwater sampling

investigation to obtain additional BTEX data, which was implemented and reported as the

Hydropunch investigation in the SCR – 2012 (ARCADIS 2013a). Results from the

Hydropunch investigation indicated that additional data within the vicinity of borings HP-14,

HP-16, HP-45, HP-46 and downgradient of the BTEX monitoring wells will further refine site

characterization in the 10 to 55 feet below water table and 55 to 90 feet below water table

groundwater zones. To support BTEX delineation, FHRA proposed to collect “one-time”

groundwater samples from four wells near HP-14 and HP-16 (MW-175, MW-186B/C, and

MW-334-65), eight wells near HP-45 and HP-46 (MW-176B/C, MW-178B/C, MW-179B/C,

and MW-180BC) and three wells downgradient from the BTEX monitoring wells (MW-101

and MW-154A/B). Wells proposed for additional BTEX characterization are summarized in

Table 3 and presented on Figure 8.

Groundwater will be sampled according to procedures outline in the RSAP and groundwater

samples will be analyzed for BTEX by USEPA Method 8021.

5.6 Wells Proposed for Abandonment

Wells INJ-MW-1 through INJ-MW-4 were installed to support a large-scale tracer test

conducted in March 2012. The wells were constructed with 20-foot screens specifically to

monitor injected water associated with the tracer test. Because the well screens span two

separate groundwater zones (water table and 10 to 55 feet below water table), the wells are

not suitable to monitor the sulfolane plume; therefore FHRA proposes to abandon wells INJ-

MW-1 through INJ-MW-4 according to procedures outlined in the RSAP.

Page 25: Imagine the result 2013 On-Site Site Characterization Work Plan

2013 On-Site Site Characterization Work Plan.docx 19

2013 On-Site Site Characterization Work North Pole Refinery North Pole, Alaska

6. Soil Characterization

An extensive onsite soil investigation was conducted in 2011 to evaluate soil impacts at the

site. Results from this investigation and specific recommendations for further soil

characterization activities are summarized in the SCR – 2011 (Barr 2012). Further soil

characterization activities were conducted in the Southwest Area (Former EU Wash Area) to

delineate sulfolane concentrations identified in soil boring SB-143 during the 2011 soil

investigation. Samples were collected from the surface (0-2 feet bgs) and immediately above

the air-groundwater interface (approximately 5-9 feet bgs) at locations SB-188 through SB-

197 and SB-235 through SB-251 (Figure 9). The maximum sulfolane concentration detected

at each boring is depicted on Figure 9.

To delineate the southern lateral extent of sulfolane impacts near the Southwest Area

(Former EU Wash Area), two additional soil borings will be advanced to the southeast of

boring SB-249, to a depth of approximately 10 feet bgs and sampled for sulfolane by USEPA

modified Method 8270D with isotope dilution. Boring advancement, soil sampling, soil

classification, soil screening and field quality control measures will be completed in

accordance with the procedures described in the RSAP. Similar to soil investigation activities

completed in 2012, finer-grained soil layers will be targeted for analytical sampling. Boring

logs will be prepared for each boring and submitted to the ADEC.

Additionally, FHRA proposes high density vertical soil sampling within the vicinity of boring

SB-238 in the Southwest Area (Former EU Wash Area) to assess the vertical distribution of

sulfolane in soil. The proposed soil boring will be advanced to approximately 10 feet bgs by

continuous coring methods. A soil sample will be collected at every foot within the vadose

zone and every three inches within the capillary fringe zone and analyzed for sulfolane by

USEPA modified Method 8270D with isotope dilution. To determine where the top of the

capillary fringe zone is encountered, soil moisture data will be collected and evaluated in the

field with a soil moisture meter. Additionally, one sample from within the soil column will be

collected and analyzed for bulk density. The proposed location for high density vertical soil

sampling is depicted on Figure 9. The Southwest Area (Former EU Wash Area) contains

elevated sulfolane concentrations in soil, and is therefore considered a target area where

remedial activities may be conducted in the future. Data from the additional soil borings will

assist FHRA in determining appropriate remedial activities for this area.

Page 26: Imagine the result 2013 On-Site Site Characterization Work Plan

2013 On-Site Site Characterization Work Plan.docx 20

2013 On-Site Site Characterization Work North Pole Refinery North Pole, Alaska

7. Investigation-Derived Waste

Waste materials generated during site investigation activities will be removed from the site

and disposed of in a timely manner, in accordance with the RSAP.

Page 27: Imagine the result 2013 On-Site Site Characterization Work Plan

2013 On-Site Site Characterization Work Plan.docx 21

2013 On-Site Site Characterization Work North Pole Refinery North Pole, Alaska

8. Schedule

Data collected during the proposed additional site investigation activities will be added to the

extensive historical site data set. The CSM and groundwater model will be refined if

appropriate, based on the findings of these assessments. The data will support the

preparation of the Final Onsite FS and Onsite Cleanup Plan.

Activities proposed in this work plan are anticipated to be completed during the 2013 field

season. Updates on data collection will be presented to the ADEC during TPT meetings, Site

Characterization Subgroup Meetings, and in quarterly groundwater monitoring reports.

Page 28: Imagine the result 2013 On-Site Site Characterization Work Plan

2013 On-Site Site Characterization Work Plan.docx 22

2013 On-Site Site Characterization Work North Pole Refinery North Pole, Alaska

9. References

Alaska Department of Environmental Conservation. 2011. Letter to FHRA dated August 18,

2011.

ARCADIS U.S., Inc. 2012a. Revised Draft Final Human Health Risk Assessment. May

2012.

ARCADIS U.S., Inc. 2012b. Second Quarter 2012 Groundwater Monitoring Report. July

2012.

ARCADIS U.S., Inc. 2012c. Third Quarter 2012 Groundwater Monitoring Report. October

2012.

ARCADIS U.S., Inc. 2012d. Draft Final Onsite Feasibility Study. May 2012.

ARCADIS U.S., Inc. 2012e. Work Plan for Evaluation of Perfluorinated Compounds–Phase II. December 2012

ARCADIS U.S., Inc. 2012f. 2012 Site Characterization Work Plan. May 2012.

ARCADIS U.S., Inc. 2013a. Site Characterization Report – 2012 Addendum. January 2013.

ARCADIS U.S., Inc. 2013b. Interim Remedial Action Plan Addendum. January 2013.

ARCADIS U.S., Inc. 2013c. In Press. Fourth Quarter 2012 Groundwater Monitoring Report.

Barr Engineering Company. 2010. Interim Removal Action Plan. Revised September

2010.

Barr Engineering Company. 2011. Site Characterization and First Quarter 2011

Groundwater Monitoring Report. May 2011.

Barr Engineering Company. 2012. Site Characterization Report – Through 2011.

December 2012.

Bear, J. 1972. Dynamics of Fluids in Porous Media. American Elsevier, New York.

Cederstrom D.J. 1963. Ground-Water Resources of the Fairbanks Area Alaska: U.S.

Govt. Print. Off., U.S. Geological Survey Water-Supply Paper 1590. 84 p.

Ferrians, O.J. 1965. Permafrost Map of Alaska. U.S. Geological Survey Miscellaneous

Investigations Series Map I-445. 1 plate.

Page 29: Imagine the result 2013 On-Site Site Characterization Work Plan

2013 On-Site Site Characterization Work Plan.docx 23

2013 On-Site Site Characterization Work North Pole Refinery North Pole, Alaska

Freitas, Juliana G. and James F. Barker. 2011. Oxygenated gasoline behavior in the

unsaturated zone – Part 1: Source zone behavior. Journal of Contaminant Hydrology, v 126,

pp 153 – 166.

Geomega Inc. 2013. In Press. The Groundwater Model Report, Geomega Inc. 2525 8th

Street, Suite 200 Boulder, CO 80301.

Glass, R.L., M.R. Lilly, and D.F. Meyer. 1996. Ground-water levels in an alluvial plain between

the Tanana and Chena Rivers near Fairbanks, Alaska, 1986-93: U.S. Geological Survey

Water-Resources Investigations Report 96-4060, 39 p. + 2 appendices.

Hunkeler, D., R. Aravena, and B.J. Butler. 1999. Monitoring microbial dechlorination of

tetrachloroethene (PCE) in groundwater using compound-specific stable carbon isotope

ratios: microcosm and field studies. Environmental Science and Technology, 33(16), 2733-

2738.

Interstate Technology and Regulatory Council. 2009. Evaluating LNAPL Remedial

Technologies for Achieving Project Goals. LNAPL-2. Washington, D.C.: Interstate

Technology & Regulatory Council, LNAPLs Team. www.itrcweb.org.

Lilly, M.R., K.A. McCarthy, A.T. Kriegler, J. Vohden, and G.E. Burno. 1996. Compilation and

Preliminary Interpretations of Hydrologic and Water-Quality Data from the Railroad Industrial

Area, Fairbanks, Alaska, 1993-94. U.S. Geological Survey Water-Resources Investigations

Report 96-4049. 75 p.

McDowell, Cory J. and Susan E. Powers. 2003. Mechanisms Affecting the Infiltration and

Distribution of Ethanol-Blended Gasoline in the Vadose Zone. Environmental Science and

Technology, v 37, pp 1803 – 1810.

Miller, J.A., R.L. Whitehead, D.S. Oki, S.B. Gingerich, and P.G. Olcott. 1999. Ground Water

Atlas of the United States: Segment 13, Alaska, Hawaii, Puerto Rico, and the U.S. Virgin Islands.

U.S. Geological Survey Hydrologic Atlas Number 730-N. 36 p.

Nakanishi, A.S., and M.R. Lilly. 1998. Estimate of aquifer properties by numerically simulating

ground-water/surface-water interactions, Fort Wainwright, Alaska: U.S. Geological Survey

Water-Resources Investigations Report 98-4088, 35 p.

Van Genuchten, M. Th. and P.J. Wierenga. 1976. Mass Transfer Studies in Sorbing Porous

Media I. Analytical Solutions. Soil Science Society of America Journal 40(4): Pp. 473-480.

Williams, J.R. 1970. Ground Water in the Permafrost Regions of Alaska. U.S. Geological Survey

Professional Paper 696. U.S. Government Printing Office, Washington, D.C. 83 p.

Page 30: Imagine the result 2013 On-Site Site Characterization Work Plan

Tables

Page 31: Imagine the result 2013 On-Site Site Characterization Work Plan

Table 1Proposed LNAPL Recovery and Observation Wells

North Pole RefineryNorth Pole, Alaska

R-32R Replace 24-inch culvert to improve LNAPL recoveryO-31 Potential area of high LNAPL recovery based on LNAPL baildown test

data near well O-131

O-32 Evaluate LNAPL transmissivity in the proposed area.O-33 Evaluate LNAPL transmissivity in the proposed area.O-34 Evaluate LNAPL transmissivity in the proposed area.O-35 Proposed to improve LNAPL recovery at the MW-176 well nest.O-36 Evaluate LNAPL transmissivity in the proposed area.O-37 Evaluate LNAPL transmissivity in the proposed area.O-38 Evaluate LNAPL transmissivity in the proposed area.

Notes:

LNAPL light non-aqueous phase liquids

Well

Rationale Notes

1 Baildown testing data collected in October 2012 and will be reported in the forthcoming Fourth Quarter 2012 Groundwater Monitoring Report (ARCADIS In Press).

Table 1 ‐ Proposed LNAPL Recovery and Observation Wells.xlsx ARCADIS Page 1 of 1

Page 32: Imagine the result 2013 On-Site Site Characterization Work Plan

Table 2Proposed Wells for Additional Characterization and Delineation

North Pole RefineryNorth Pole, Alaska

(feet bwt)

8-A 15 (WT), 25, 35, 50, 80, PF Downgradient Well; monitor the north property boundary8-B 15 (WT), 20, 40, 60, PF Downgradient Well; monitor the north property boundary8-C 15 (WT), 35, 50, 80, PF Downgradient Well; monitor the north property boundary8-D 15 (WT), 35, 50, 80, PF Downgradient Well; monitor the north property boundary8-E 15 (WT), 25, 35, 50, 65, 80, PF Downgradient Well; monitor the north property boundary8-F 15 (WT), 35, 50, 80, PF Downgradient Well; monitor the north property boundary

8-G WT Upgradient Well; monitor near the process area8-H WT Upgradient Well; monitor near the process area8-I WT Upgradient Well; monitor near the process area8-J WT Upgradient Well; monitor near the process area8-K WT Upgradient Well; monitor near the process area

8-L 90-160 Support air sparge barrier design testing8-M 10-55 Vertical delineation well for MW-1108-N WT and 10-55 Further characterization northwest of O-1

MW-174-15 WT Replacement well for MW-111MW-336-15 WT Northeast of MW-138 to further characterize sulfolane plumeMW-336-20 10-55 Northeast of MW-138 to further characterize sulfolane plumeMW-336-35 10-55 Northeast of MW-138 to further characterize sulfolane plumeMW-336-55 10-55 Northeast of MW-138 to further characterize sulfolane plumeMW-337-20 10-55 Northeast of MW-138 to monitor sulfolane below LNAPLMW-334-85 55-90 Vertical delineation well for MW-334-65

O-5 10-55 Additional nested well to monitor groundwater captureO-12 10-55 Additional nested well to monitor groundwater captureO-24 10-55 Additional nested well to monitor groundwater captureO-26 10-55 Additional nested well to monitor groundwater capture

Notes:BWT Below water tablePF PermafrostWT Water table

Proposed Additional Monitoring Wells for Further Characterization

Upgradient Groundwater Delineation

Additional Observation Wells for Groundwater Capture

Well

Depth Zone(relative to water table)

Rationale

Previously Proposed Phase 8 Monitoring Wells

Table 2 ‐ Proposed Wells for Characterization.xlsx ARCADIS Page 1 of 1

Page 33: Imagine the result 2013 On-Site Site Characterization Work Plan

Table 3Proposed Locations for BTEX Characterization and Delineation

North Pole RefineryNorth Pole, Alaska

Depth toTop

Depth toBottom Length

(feet bwt) (feet BGS) (feet BGS) (feet)Monitoring wells in area of Hydropunch samples HP-45 and HP-46

MW-176B 10-55 45.6 50.1 4.5MW-176C 55-90 85.4 89.9 4.5

MW-178B 10-55 46.0 50.7 4.7MW-178C 55-90 85.2 89.9 4.8

MW-179B 10-55 45.8 50.3 4.5MW-179C 55-90 85.4 89.9 4.5

MW-180B 10-55 45.7 50.2 4.5MW-180C 55-90 85.3 89.9 4.5

Monitoring wells in area of Hydropunch samples HP-14 and HP-16MW-175 55-90 85.8 90.3 4.5

MW-186B 10-55 50.7 60.4 9.7MW-186C 55-90 90.7 100.3 9.6

MW-334-65 10-55 60.6 65.2 4.7

Downgradient Monitoring WellsMW-101 10-55 56.0 61.0 5.0

MW-154A 10-55 71.0 75.0 4.0MW-154B 55-90 90.2 94.8 4.6

Notes:BGS Below ground surfaceBWT Below water tableBTEX Benzene/Toluene/Ethylbenzene/Xylenes (total)

Well

Well Screen

Depth Zone (relative to water table)

Table 3 ‐ BTEXCharactDelin.xlsx ARCADIS Page 1 of 1

Page 34: Imagine the result 2013 On-Site Site Characterization Work Plan

Figures

Page 35: Imagine the result 2013 On-Site Site Characterization Work Plan

NORTH POLENORTH POLEREFINERYREFINERY

CIT

Y:

SF

D

IV/G

RO

UP

: E

NV

/IM

D

B: K

ER

NS

T L

D:

G F

RA

NC

E

PIC

: P

M:

T

M:

TR

:

Pro

ject

(P

roje

ct #

) B

00

819

81

.00

06.

00

00

1

0 0.5

MilesGRAPHIC SCALE

FLINT HILLS RESOURCES ALASKA, LLCNORTH POLE REFINERY, NORTH POLE, ALASKA

SITE LOCATIONFIGURE

1

2013 ON-SITE SITE CHARACTERIZATION WORK PLAN

LEGEND:

FHRA PROPERTY BOUNDARY

Pa

th:

V:\

FH

R_A

K\N

ort

hP

ole

Re

fine

ry\S

iteC

har

act

eri

zatio

n20

13

\Fig

1 S

iteL

oca

tion

.mxd

Da

te:

1/2

5/2

013

Tim

e:

8:1

9:5

3 A

M

Page 36: Imagine the result 2013 On-Site Site Characterization Work Plan

ALASKA RAILROAD

OLD RICHARDSON HWY

NORTH GRAVEL PIT

FIRE TRAINING AREA

ASPHALT TRUCK LOADINGCURRENT TRUCK LOADING RACK

FORMER TRUCK LOADING RACK

RAILCARLOADING AREA

MATERIALSSTORAGEAREA

T A N A N A R I V E R

GVEA POWER PLANT

PETROSTAR REFINERY

EXCHANGER WASH SKID

823 820821822

511 512510 514

617 616

618619

401 402

501 502403 193

515404T110

T103303 302

901

304

101

112

WILLIAMS AVE.

WEST DIESELEAST DIESEL

NAPHTHA AVE.

SAFETY LN.

TANK F

ARM

RD.

DISTR

IBUTIO

N ST.

GASO

LINE A

LY.

H & S LN.

PROCESS AVE.

FIN FA

N ALY.

ENERGY BLVD.

ALASKA RAILROAD

EFFLUENT BUILDINGCRUDE UNIT #1

LAB

CRUDE UNIT #2

MAINTENANCEBUILDING ADMINISTRATIONBUILDING

CRUDE UNIT #3

CRUDE UNIT #3UTILITY BUILDING

SULFOLANE EXTRACTION UNIT

WAREHOUSE

CA4 CA6 CA7

CA3CA5ACA5B

CA2

CA1

CA9CA8

LAGOON C

LAGOON BSOUTH GRAVEL PIT

LAGOON A

R-20R

CITY: SF DIV/GROUP: ENV/IM DB: BGRIFFITH LD: PIC: PM: TM: TR: PROJECT: (PROJECT #)

0 400 800

SCALE IN FEET

PATH: V:\FHR_AK\NorthPoleRefinery\SiteCharacterization2013\Fig 2 SiteFeatures.mxd 1/30/2013 10:19:46 AM

FLINT HILLS RESOURCES ALASKA, LLCNORTH POLE REFINERY, NORTH POLE, ALASKA

CURRENT SITE FEATURESFIGURE

2

2013 ON-SITE SITE CHARACTERIZATION WORK PLANNotes:Image Date June 9, 2007

Legend

Bermed Containment Areas (CA)Approximate AreaFHRA Property Boundary

Page 37: Imagine the result 2013 On-Site Site Characterization Work Plan

S-39

S-43

S-44

S-50S-51

S-54

R-3

R-4

R-5

R-14A

R-18

R-21

R-27

R-32

R-33

R-34

R-39R-40

MW-101MW-101A

MW-102 MW-104

MW-105/105A

MW-106

MW-109

MW-113

MW-115

MW-116

MW-118

MW-124

MW-125

MW-126MW-127

MW-129

MW-130

MW-131

MW-132 MW-133

MW-134

MW-135 MW-136MW-137

MW-138

MW-139

MW-140

MW-141 MW-142

MW-143

MW-144A

MW-145MW-146A/B

MW-149A/B

O-25

O-11O-27

O-26

MW-304-70

MW-304-80MW-304-125

MW-305-70MW-305-80

MW-306-70MW-306-80

MW-306-150

MW-307

O-14

MW-154A/B

MW-173A/B

R-3N

MW-110

MW-174A/B

MW-175

MW-176A/B/C

MW-177

MW-178A/B/CMW-179A/B/C/D

IW-1MW-301-70

MW-305-100

MW-304-150

MW-303-80

MW-306-100

MW-180A/B/C

MW-186A/B/C/D/E

O-1

O-2O-3

O-4

MW-144BR

R-35R

R-20R

R-42

O-15O-21

O-20

O-8

O-16

O-28

O-18

O-17

O-6

O-5

O-19

O-10

O-9

O-29

O-22O-7

O-23

O-24O-13

O-12

MW-306-CMT-30

MW-306-CMT-40MW-306-CMT-50MW-306-CMT-60

INJ-MW-4

MW-301-CMT-10 MW-301-CMT-20MW-301-CMT-30MW-301-CMT-40MW-301-CMT-50

MW-302-CMT-10

MW-302-CMT-20

MW-302-CMT-30

MW-302-CMT-40MW-302-CMT-50

MW-303-CMT-9MW-303-CMT-19

MW-303-CMT-29MW-303-CMT-39

MW-303-CMT-49

MW-303-CMT-59

MW-304-CMT-10

MW-304-CMT-20MW-304-CMT-30

MW-304-CMT-40

MW-304-CMT-50

MW-304-CMT-60

MW-305-CMT-8

MW-305-CMT-18

MW-305-CMT-28

MW-305-CMT-38

MW-305-CMT-48

MW-305-CMT-58

MW-306-CMT-10

MW-306-CMT-20

MW-309-15/66/150

MW-321-15/65/151MW-330-20/65/150

MW-192A/B

INJ-MW-1INJ-MW-2 INJ-MW-3

MW-195A/B

MW-198

MW-199

MW-300

MW-301-60

MW-302-70

MW-302-80

MW-302-110MW-303-70

MW-303-130

O-30

MW-334-15/65

MW-304-96

MW-303-95MW-302-95

MW-197A/B

MW-306-15

MW-331-150

MW-304-15

MW-310-15/65/110

R-22

S-10S-9

S-21

S-22

S-32

MW-147A/B

R-38

MW-196

PETROSTAR REFINERY

GVEA POWER PLANT

T A N A N A R I V E R

WILLIAMS AVE.

WEST DIESELEAST DIESEL

NAPHTHA AVE.

SAFETY LN.

TANK F

ARM

RD.

DISTR

IBUTIO

N ST.

GASO

LINE A

LY.

H & S LN.

PROCESS AVE.

FIN FA

N ALY.

ENERGY BLVD.

OLD RICHARDSON HWY.

ALASKA RAILROAD

CITY: SF DIV/GROUP: ENV/IM DB: BGRIFFITH LD: PIC: PM: TM: TR: PROJECT: (PROJECT #)

0 400 800

SCALE IN FEET

PATH: V:\FHR_AK\NorthPoleRefinery\SiteCharacterization2013\Fig 3 SitePlanOnsite.mxd 1/11/2013 4:34:16 PM

FLINT HILLS RESOURCES ALASKA, LLCNORTH POLE REFINERY, NORTH POLE, ALASKA

SITE PLAN - ONSITEFIGURE

3

2013 ON-SITE SITE CHARACTERIZATION WORK PLANNote:Image Date June 9, 2007

Legend

Monitoring WellRecovery WellObservation WellVertical Profile Transect WellFHRA Property Boundary

Page 38: Imagine the result 2013 On-Site Site Characterization Work Plan

BADGER RD

PEEDE RD

PLACK RD

BRADWAY RD

NORD

ALE R

D

HOLMES RD

BROC

K RD

DENN

IS RD

FREEMAN RD

LAKL

OEY D

R

WOLL

RD

PERSINGER DR

BENN

LN

LAURANCE RD

PERI

DOT S

T

OWNBY RD

MISSION RD

BETH

ANY S

T

HOLL

OWEL

L RD

HOME

STEA

D DR

ROZA

K RD

OLD BADGER RD

SAINT NICHOLAS DR

HOLMES RD EXT

EIGHTH AVE E

CLOU

D RD

PORTER AVE

SANT

A CLA

US LN

RENT

ALS S

T

BAGU

ETTE

DR

HOLL

AND

AVIAT

ION

ST

ROZA

K RD

FIFTH AVE

OLD RICHARDSON HWY

OLD RICHARDSON HWY

HURST RD

BADGER RD

RICHARDSON HWY

T A N A NA

RI V

ER

MW-335-41

MW-320-20/130

MW-319-15/45

MW-332-15/150 MW-325-18/150

MW-315-15/150

MW-312-15/50 MW-327-15/150

MW-313-15/150

MW-311-15/46

MW-308-30MW-308-15

MW-193A/B

MW-187

MW-157

MW-171A/B

MW-169A/B

MW-163A/BMW-162A/B

MW-161A/B

MW-160B

MW-323-15/61

MW-184

MW-159

MW-326-15

MW-158A/BMW-156A/B

MW-155A/B

MW-153A/BMW-152A/B MW-170A/B/C/DMW-151A/B/C/D

MW-150A/B/C

MW-148A/B

MW-333-16/150

MW-318-20/135

MW-316-15/56

MW-324-15/150

MW-322-15/150ALASKA RAILROAD

MW-328-15/151

MW-314-15/150

MW-329-15/66

CHENA RIVER

MW-183

MW-182 MW-168

MW-181A/B

MW-185A/B

MW-172A/BMW-167A/B

MW-166A/B

MW-165A/B MW-164A/BMW-190A/B

MW-191A/B

MW-194A/B

MW-189A/B

MW-188A/B

CITY: SF DIV/GROUP: ENV/IM DB: K ERNST LD: G FRANCE PIC: PM: TM: TR: Project (Project #) B0081981.0006.00001

0 3,300 6,600

FeetGRAPHIC SCALE

FLINT HILLS RESOURCES ALASKA, LLCNORTH POLE REFINERY, NORTH POLE, ALASKA

SITE PLAN - OFFSITE

FIGURE4

2013 ON-SITE SITE CHARACTERIZATION WORK PLAN

Legend:

Monitoring Well

Recovery Well

Observation Well

Vertical Profile Transect Well

FHRA Property Boundary

RAIL LINE

Highway

Major Road

Local Road

Notes:Image Date June 9, 2007

Path: V:\FHR_AK\NorthPoleRefinery\SiteCharacterization2013\Fig 4 SitePlanOffsite.mxd Date: 1/25/2013 Time: 11:45:07 AM

Page 39: Imagine the result 2013 On-Site Site Characterization Work Plan

SOUTH GRAVEL PIT

LAGOON C

LAGOON B

LAGOON A

GVEA POWER PLANT

CRUDE UNIT #3 UTILITY BUILDING

MAINTENANCEBUILDING

WAREHOUSE

RAIL CARLOADING AREA

ASPHALT TRUCK LOADING

CURRENT TRUCK LOADING RACK

CRUDE UNIT #3

SULFOLANE EXTRACTION UNIT

CRUDE UNIT #2

LAB

CRUDE UNIT #1

EFFLUENT BUILDING

FIREHOUSE

DISTR

IBUTIO

N

MATERIALSSTORAGE

AREA

EXCHANGER WASH SKID

GROUNDWATERTREATMENT SYSTEM

FIRE TRAININGAREA

R-42

S-540.00

MW-105A0.00

MW-192A0.00MW-1960.00

MW-173A

MW-306-15

MW-310-15

R-46R-22

S-9

S-40

MW-109

MW-113

MW-115

MW-130

MW-135

MW-139

MW-140

MW-142

MW-143

MW-144A

MW-145

O-25O-26

MW-195A

O-14MW-110

MW-178A

MW-179A

MW-180A

O-1

O-3

O-4

O-15

O-20

O-8

O-16

O-28

O-18

O-17

O-6

O-5

O-29

O-22

O-23

O-24O-12

MW-304-15

R-3

R-4 R-38

MW-125

MW-133

MW-321-15

MW-309-15

R-44

R-45R-43

S-390.63

S-43sheen

S-440.82

S-501.49

S-510.98

R-50.28

R-14A0.81

R-180.42

R-210.1

R-32*0.49

R-33*0.16

R-340.01

R-390.01

R-400.7

MW-1380.08

O-110.93

O-270.91

MW-176A2.5

MW-186A0.53

O-20.47

R-35Rsheen

R-20R0.11

O-210.05

O-190.56

O-100.96

O-90.09

O-70.01

O-130.39

MW-334-151.41

S-210.32

S-221.81

CA2CA8

CA5BCA5A

CA3

CA7CA6CA4

CA1

CA10

CA11

CA12194 189

190

198192

101

112 304

303 302

103

901

515110

502501

193403

402401

618619514510

821822

616617513511

820823

404

196 195

Old Richardson

EAST DIESEL

NAPTHA AVENUE

WEST DIESEL

FIN FA

N AL

LEY

GASO

LINE

ALLE

Y

TANK

FARM

ROA

D

PROCESS AVENUE

WILLIAMS AVENUE

ENERGY BOULEVARD

DIST

RIBU

TION

STRE

ET

O-31

O-38R-32R

O-32

O-36

O-37

O-33

O-34

O-35

CITY: SF DIV/GROUP: ENV/IM DB: BGRIFFITH LD: PIC: PM: TM: TR: PROJECT: (PROJECT #)

0 200 400

SCALE IN FEET

PATH: V:\FHR_AK\NorthPoleRefinery\SiteCharacterization2013\Fig 5 ProposedLNAPL_RW_OW.mxd 2/1/2013 10:49:10 AM

FLINT HILLS RESOURCES ALASKA, LLCNORTH POLE REFINERY, NORTH POLE, ALASKA

PROPOSED LNAPL RECOVERY AND OBSERVATION WELLS

FIGURE

5

2013 ON-SITE SITE CHARACTERIZATION WORK PLAN

Legend

MONITORING WELL

VERTICAL PROFILE WELL

OBSERVATION WELL

RECOVERY WELL

ACTIVE RECOVERY WELLS

PROPOSED LNAPL OBSERVATION OR RECOVERY WELL

ACTIVE/PROPOSED GROUNDWATER RECOVERY WELLS

MANUAL PRODUCT RECOVERY

INSTALLED PRODUCT RECOVERY SYSTEM

FHRA PROPERTY BOUNDARY

DIKED CONTAINMENT AREAS

REFINERY UNITS 0.47 LNAPL THICKNESS RANGE (FEET)

Draft

Notes:*LNAPL recovery systems installed in wells R-32 and R-33 are under evaluation.Manual product recovery is completed with a vacuum truck or portable product pump.LNAPL = Light non-aqueous phase liquid Image Date June 9, 2007

GFrance
Text Box
Page 40: Imagine the result 2013 On-Site Site Characterization Work Plan

MW-1380.11

O-101.00

O-130.75

R-210.60

R-320.96

R-390.01MW-186A0.83

O-20.65

R-20R0.62

R-330.03

S-210.76

S-32--

S-43Sheen1

O-110.34

O-190.54

O-210.05

O-270.71

O-70.04

O-90.14

R-14A1.01

R-35R0.09

R-400.49

S-221.98

S-390.52S-44Sheen1

S-501.42S-510.78

MW-176A2.89

R-180.52

R-340.01

R-50.31

MW-334-151.40

MW-178A--

R-3-- R-38

--

MW-139--

MW-140--MW-142

--MW-144A--

MW-145--

O-25--O-26

--

O-14--

MW-179A--

MW-180A--

O-1--

O-3--

O-4--

R-42--

O-15--

O-20--

O-8--

O-16--

O-28--

O-18--

O-17--

O-6--

O-5--

O-29--

O-22--

O-23--

O-24--O-12

--

MW-195A--

MW-196--

S-9--

O-31

O-38R-32R

O-32

O-36

O-37O-33

O-34

O-35

CITY: SF DIV/GROUP: ENV/IM DB: BGRIFFITH LD: PIC: PM: TM: TR: PROJECT: (PROJECT #)

0 400 800

SCALE IN FEET

PATH: V:\FHR_AK\NorthPoleRefinery\SiteCharacterization2013\Fig 6 PropWells_AdditionalLNAPL.mxd 1/31/2013 3:44:32 PM

FLINT HILLS RESOURCES ALASKA, LLCNORTH POLE REFINERY, NORTH POLE, ALASKA

PROPOSED WELLS FOR ADDITIONAL LNAPL COMPOSITION ANALYSIS

FIGURE

6

2013 ON-SITE SITE CHARACTERIZATION WORK PLAN

LegendMonitoring Well

Observation Well

Recovery Well

Proposed LNAPL Observation or Recovery Well

Proposed Additional LNAPL Composition Analysis

Historical LNAPL Composition Data

FHRA Property Boundary

Notes:LNAPL results posted on figure are in feet.Data measured during third quarter 2012Image date June 9, 2007

1.39--

Sheen1

LNAPL Thickness (feet)LNAPL was not detectedLNAPL not detected with air/product/water interfaceprobe: LNAPL was visually observed

Page 41: Imagine the result 2013 On-Site Site Characterization Work Plan

S-39

S-43

S-44

S-50S-51

S-54

R-3

R-4

R-5

R-14A

R-18

R-21

R-27

R-32

R-33

R-34

R-39R-40

MW-101MW-101A

MW-102 MW-104

MW-105/105A

MW-106

MW-109

MW-113

MW-115

MW-116

MW-118

MW-124

MW-125

MW-126MW-127

MW-129

MW-130

MW-131

MW-132 MW-133

MW-134

MW-135 MW-136MW-137

MW-138

MW-139

MW-140

MW-141 MW-142

MW-143

MW-144A

MW-145MW-146A/B

MW-149A/B

O-25

O-11O-27

MW-304-70

MW-304-80MW-304-125

MW-305-70MW-305-80

MW-306-70MW-306-80

MW-306-150

MW-307

O-14

MW-154A/B

MW-173A/B

R-3N

MW-110

MW-174A/B

MW-175

MW-176A/B/C

MW-177

MW-178A/B/CMW-179A/B/C/D

IW-1MW-301-70

MW-305-100

MW-304-150

MW-303-80

MW-306-100

MW-180A/B/C

MW-186A/B/C/D/E

O-1

O-2O-3

O-4

MW-144BR

R-35R

R-20R

R-42

O-15O-21

O-20

O-8

O-16

O-28

O-18

O-17

O-6

O-19

O-10

O-9

O-29

O-22O-7

O-23

O-13

MW-306-CMT-30

MW-306-CMT-40MW-306-CMT-50MW-306-CMT-60

INJ-MW-4

MW-301-CMT-10 MW-301-CMT-20MW-301-CMT-30MW-301-CMT-40MW-301-CMT-50

MW-302-CMT-10

MW-302-CMT-20

MW-302-CMT-30

MW-302-CMT-40MW-302-CMT-50

MW-303-CMT-9MW-303-CMT-19

MW-303-CMT-29MW-303-CMT-39

MW-303-CMT-49

MW-303-CMT-59

MW-304-CMT-10

MW-304-CMT-20MW-304-CMT-30

MW-304-CMT-40

MW-304-CMT-50

MW-304-CMT-60

MW-305-CMT-8

MW-305-CMT-18

MW-305-CMT-28

MW-305-CMT-38

MW-305-CMT-48

MW-305-CMT-58

MW-306-CMT-10

MW-306-CMT-20

MW-309-15/66/150

MW-321-15/65/151MW-330-20/65/150

MW-192A/B

INJ-MW-1INJ-MW-2 INJ-MW-3

MW-195A/B

MW-198

MW-199

MW-300

MW-301-60

MW-302-70

MW-302-80

MW-302-110MW-303-70

MW-303-130

O-30

MW-334-15/65

MW-304-96

MW-303-95MW-302-95

MW-197A/B

MW-306-15

MW-331-150

MW-304-15

MW-310-15/65/110

R-22

S-10S-9

S-21

S-22

S-32

MW-147A/B

R-38

MW-196

PETROSTAR REFINERY

GVEA POWER PLANT

MW-147A/B

8-M 8-N

T A N A N A R I V E R

WILLIAMS AVE.

WEST DIESELEAST DIESEL

NAPHTHA AVE.

SAFETY LN.

TANK F

ARM

RD.

DISTR

IBUTIO

N ST.

GASO

LINE A

LY.

H & S LN.

PROCESS AVE.

FIN FA

N ALY.

ENERGY BLVD.

OLD RICHARDSON HWY.

ALASKA RAILROAD

MW-170DMW-170C

MW-170B

MW-170A

MW-154-115

MW-334-85

MW-174-15

8-L

MW-337-20MW-336-15/20/35/55

MW-334-85

O-26

O-5

O-24O-12

8-E

8-B

8-F

8-C

8-D

8-A

8-G 8-H 8-I 8-J 8-K

CITY: SF DIV/GROUP: ENV/IM DB: BGRIFFITH LD: PIC: PM: TM: TR: PROJECT: (PROJECT #)

0 400 800

SCALE IN FEET

PATH: V:\FHR_AK\NorthPoleRefinery\SiteCharacterization2013\Fig 6 PropWells_AddCharDelineation.mxd 1/30/2013 11:02:33 AM

FLINT HILLS RESOURCES ALASKA, LLCNORTH POLE REFINERY, NORTH POLE, ALASKA

PROPOSED WELLS FOR ADDITIONAL CHARACTERIZATION AND DELINEATION

FIGURE

76

2013 ON-SITE SITE CHARACTERIZATION WORK PLAN

Note:Image Date June 9, 2007

Legend

Monitoring WellRecovery WellObservation WellVertical Profile Transect WellWells Proposed for AbandonmentProposed Downgradient WellsProposed Upgradient WellsProposed Additional Capture Evaluation Wells

Proposed Characterization WellsFHRA Property Boundary

GFrance
Text Box
Page 42: Imagine the result 2013 On-Site Site Characterization Work Plan

S-44

S-50

R-21

R-32

R-33

R-39

R-40

MW-101A

MW-105A

MW-106

MW-109

MW-113

MW-115

MW-116

MW-124MW-125

MW-126MW-127

MW-131

MW-132MW-133

MW-134

MW-135MW-136

MW-137

MW-138

MW-139

MW-140MW-141 MW-142

MW-143

MW-144A

MW-145

MW-148A MW-148B MW-149A

O-14

MW-149B

MW-153AMW-153B

MW-110MW-176A MW-179A

MW-180A

O-2

R-35R

R-20R

R-42

O-16

O-18

O-17

O-12

MW-192AMW-196

MW-334-15

S-9MW-101

MW-154A MW-154B

MW-175

MW-176B

MW-178BMW-178CMW-179B

MW-179CMW-180B

MW-180C

MW-186BMW-186C

MW-176C

MW-334-65

CITY: SF DIV/GROUP: ENV/IM DB: K ERNST LD: G FRANCE PIC: PM: TM: TR: Project (Project #) B0081981.0006.00001

0 400 800

FeetGRAPHIC SCALE

FLINT HILLS RESOURCES ALASKA, LLCNORTH POLE REFINERY, NORTH POLE, ALASKA

PROPOSED LOCATIONS FOR BTEXCHARACTERIZATION AND DELINEATION

FIGURE87

2013 ON-SITE SITE CHARACTERIZATION WORK PLANLEGEND:

MONITORING WELL

OBSERVATION WELL

RECOVERY WELL

PROPOSED SAMPLING LOCATION

FHRA Property Boundary

Image Date June 9, 2007

Path: V:\FHR_AK\NorthPoleRefinery\SiteCharacterization2013\Fig 7 ProposedLocationsBTEX.mxd Date: 1/30/2013 Time: 11:02:13 AM

GFrance
Text Box
Page 43: Imagine the result 2013 On-Site Site Characterization Work Plan

MATERIAL STORAGE

SB-188 (0.0-2.0)<0.00854

SB-189 (0.0-2.0)<0.00900

SB-190 (0.0-2.0)5.22

SB-191 (0.0-2.0)72.0JSB-192 (7.0-9.0)0.0235

SB-193 (0.0-2.0)27.4

SB-194 (3.6-5.6)97.0J

SB-195 (0.0-2.0)1.27

SB-196 (5.1-7.1)0.0535

SD-197 (5.0-6.6)0.00819J

SB-235 (5.9-7.0)<0.00744

SB-236 (0.0-2.0)0.0729

SB-237 (5.0-5.8)0.122

SB-238 (5.8-6.8)724SB-239 (7.4-8.8)52.3

SB-240 (7.4-8.8)8.18

SB-241 (0.0-2.0)0.375

SB-242 (7.2-8.4)0.574

SB-243 (0.0-2.0)0.153

SB-244 (8.2-9.0)23.3

SD-245 (5.0-6.7)0.0316

SB-246 (7.0-9.0)76.0

SB-247 (6.9-8.9)0.0960

SD-248 (5.0-6.5)194

SB-249 (5.0-6.4)121

SB-250 (5.0-6.0)1.63

SB-251 (0.0-2.0)0.736

SB-143 (3.0 - 5.0)18.4

CITY: SF DIV/GROUP: ENV/IM DB: BGRIFFITH LD: PIC: PM: TM: TR: PROJECT: (PROJECT #) B0081981.0032.00001

0 30 60

SCALE IN FEET

PATH: V:\FHR_AK\NorthPoleRefinery\SiteCharacterization2013\Fig 9 ProposedSoilBoringLocations_FormerWashPad.mxd 1/31/2013 1:31:11 PM

FLINT HILLS RESOURCES, ALASKA, LLCNORTH POLE REFINERY, NORTH POLE ALASKA

PROPOSED SOIL BORING LOCATIONSTHE SOUTHWEST AREA (FORMER EU WASH AREA)

FIGURE

9

2013 ON-SITE SITE CHARACTERIZATION WORK PLAN

Legend:Soil Boring Sulfolane Results

Non Detect

0.0043 - 0.043 mg/kg

0.043 - 0.43 mg/kg

0.43 - 4.3 mg/kg

4.3 - 43 mg/kg

>43 mg/kg

Proposed Soil Boring for Vertical Characterization

Proposed Soil Boring for Lateral Delineation

Notes:All results are measured in milligrams per kilogram (mg/kg)

Result posted is the highest sulfolane concentration detected at that boring location

J - Result is considered estimated