Page 1: IEC 61850 Lessons Learned 2016 04-11

IEC 61850Lessons LearnedKEVIN J MAHONEYPRESIDENT

www.casco-systems.comApril 11, 2016

Page 2: IEC 61850 Lessons Learned 2016 04-11

What is 61850?AN OVERVIEW

www.casco-systems.comApril 11, 2016

Page 3: IEC 61850 Lessons Learned 2016 04-11

IEC Smart Grid Reference Architecture

Page 4: IEC 61850 Lessons Learned 2016 04-11

Where does 61850 fit in?

Page 5: IEC 61850 Lessons Learned 2016 04-11

Is 61850 a protocol, a standard, or what?

Framework for interoperabilitySubstation Data Model Suite of communication protocolsDefines performance in harsh environmentsEthernet based

www.casco-systems.comApril 11, 2016

Page 6: IEC 61850 Lessons Learned 2016 04-11

IEC-61850 Substation Data Model

www.casco-systems.comApril 11, 2016

Page 7: IEC 61850 Lessons Learned 2016 04-11

GOOSE (Generic Object Oriented Substation Event) MMS (Manufacturing Message Specification) SMV (Sampled Measured Values) FTP (File Transfer Protocol) WEB SERVICES (HTTP, XML, etc.)

IEC-61850 suite of protocols

www.casco-systems.comApril 11, 2016

Page 8: IEC 61850 Lessons Learned 2016 04-11

IEC-61850 Performance Requirements

www.casco-systems.comApril 11, 2016

Page 9: IEC 61850 Lessons Learned 2016 04-11

What were the Lessons Learned?EXPERIENCE WITH IEC-61850

www.casco-systems.comApril 11, 2016

Page 10: IEC 61850 Lessons Learned 2016 04-11

Hardware design can be greatly simplified.Software design complexity is significantly increased.Network design is critical.

What design resources are needed?

www.casco-systems.comApril 11, 2016

Page 11: IEC 61850 Lessons Learned 2016 04-11

TRADITIONAL IEC-61850

www.casco-systems.comApril 11, 2016

Page 12: IEC 61850 Lessons Learned 2016 04-11

That depends on vendor implementation.

Examples: GOOSE Message Failure Indication from SEL-421:

S99_21LA.ANN.ASVGGIO4.Ind07 = S99_21LA_GSE_FAIL GOOSE Message Failure Indication from GE-L90:

S99_87LB.GEN.GGIO1.Ind6 = S99_87LB_GSE_FAIL

Is 61850 self-documenting?

www.casco-systems.comApril 11, 2016

Page 13: IEC 61850 Lessons Learned 2016 04-11

DNP Obj 30, Var 1, Index 3 Modbus Coil 10003 IEC-61850 Relay1/XCBR1$Health$stVal

Status Value

Health

Circuit Breaker

Logical Device

Protocol Naming Conventions

www.casco-systems.comApril 11, 2016

Page 14: IEC 61850 Lessons Learned 2016 04-11

NoMPRP used IEC-61850 equipment from multiple vendors:

• GE Proficy Driver Server w/ CIMPLICITY HMI• SEL Real Time Automation Controller• SEL 400 & 487 Series Protective Relays• SEL 2411 Programmable Automation Controller • GE Multilin UR Protective Relays• Qualitrol Intelligent transformer monitor• Beckwith Digital Tapchanger Control• Calisto Gas Monitor• MESA Battery Charger

Is vendor interoperability easy and are all 61850 IED’s interoperable?

www.casco-systems.comApril 11, 2016

Page 15: IEC 61850 Lessons Learned 2016 04-11

PRODUCT FAMILY EXAMPLE BINARY POINTSEL 400 Series Relays KT1H_11KA.ANN.PLTGGIO2.Ind17SEL 487 Series Relays T3_87TA.ANN.IN1GGIO14.Ind05SEL 2411 PAC T3_74TA_2.ANN.SVTGGIO4.Ind24SEL 651R Recloser L230D1_51LR.PRO.LOPPTUV1.OpGE Multilin UR Relays T3_87TB.GEN.GGIO1.Ind105Qualitrol Intelligent Monitor T3_23TA.Relay3.GGIO0.SPCSO1.statu

sCalisto Gas Monitor T3_99TA.LDev1.GGIO40.Ind_stVal

Example MMS binary point:

www.casco-systems.comApril 11, 2016

Page 16: IEC 61850 Lessons Learned 2016 04-11

PRODUCT FAMILY EXAMPLE BINARY POINTSEL 400 Series Relays S49_21LA.MET.METMMXU1.TotW_instM

ag_fSEL 487 Series Relays T3_87TA.MET.METSMMXU1.TotW_instM

ag_fSEL 651R Recloser L230D1_51LR.MET.METMMXU1.TotWGE Multilin UR Relays T2_87TB.GEN.MMXU2.A.phsAQualitrol Intelligent Monitor T3_23TA.In6MX.STMP0.TmpBeckwith Tapchanger Control M2001.D.ATCC0.LodCtrV_mag_i

Example MMS analog point:

www.casco-systems.comApril 11, 2016

Page 17: IEC 61850 Lessons Learned 2016 04-11

More so than ever!New types of documents are necessary.Much of the hardwired complexity has moved to the software,

how will you document this?

Is documentation important?

www.casco-systems.comApril 11, 2016

Page 18: IEC 61850 Lessons Learned 2016 04-11

GOOSE Message Maps

www.casco-systems.comApril 11, 2016

Page 19: IEC 61850 Lessons Learned 2016 04-11

GOOSE Message Multicase Address Maps

IMAGE REDACTED FOR SECURITY

www.casco-systems.comApril 11, 2016

Page 20: IEC 61850 Lessons Learned 2016 04-11

IED Logic Diagrams

www.casco-systems.comApril 11, 2016

Page 21: IEC 61850 Lessons Learned 2016 04-11

SCADA & IED Data Maps

www.casco-systems.comApril 11, 2016

Page 22: IEC 61850 Lessons Learned 2016 04-11

NoNew skills are requiredAdditional functionality creates added complexityClosely linking protection and integration functions via CID fileAdded 61850 computing overhead requirements exposed

weaknesses in protective relay, RTU & HMI platforms.

Does 61850 make integration simpler?

www.casco-systems.comApril 11, 2016

Page 23: IEC 61850 Lessons Learned 2016 04-11

YesStandardization of specific hardware platforms and firmwareStandardization of specific software versionsAdded cost to track, evaluate and install upgrades

Is firmware & software control needed?

www.casco-systems.comApril 11, 2016

Page 24: IEC 61850 Lessons Learned 2016 04-11

Not in all casesSome data not available via communication interfaceOther data needed to be remapped to make it available

Is all of the required data exposed?

www.casco-systems.comApril 11, 2016

Page 25: IEC 61850 Lessons Learned 2016 04-11

Everything!!Device HealthDevice Communication HealthNetwork HealthTrip PathsMore problems or just better monitoring???

What do we need to monitor?

www.casco-systems.comApril 11, 2016

Page 26: IEC 61850 Lessons Learned 2016 04-11

Do you need a lab?

Yes, a lab is essential!

www.casco-systems.comApril 11, 2016

Page 27: IEC 61850 Lessons Learned 2016 04-11

YesTest SetsBrowsersNetwork AnalysisIED & SCL Config

Do you need different tools?

www.casco-systems.comApril 11, 2016

Page 28: IEC 61850 Lessons Learned 2016 04-11

YesNetworksSoftware ToolsIEC StandardData Model

Do you need any training?

www.casco-systems.comApril 11, 2016

Page 29: IEC 61850 Lessons Learned 2016 04-11

YesOnly way to ensure consistencyOnly way to capture lessons learnedOnly way to reduce costs through reuse

Are standards & examples necessary?

www.casco-systems.comApril 11, 2016

Page 30: IEC 61850 Lessons Learned 2016 04-11

Is vendor support necessary?

YesIncreasing vendor count adds complexity & integration issuesVendor selection should include consideration of supportKey vendors for tools, RTU, & HMI must be willing to help with

problems encountered with 3rd party products

www.casco-systems.comApril 11, 2016

Page 31: IEC 61850 Lessons Learned 2016 04-11

Yes on detailed design, hardware, and installationNo on relay and integration settings design & programmingNo on network design, hardware and supportNo on increased NERC/CIP compliance costs

Will we save money?

www.casco-systems.comApril 11, 2016

Page 32: IEC 61850 Lessons Learned 2016 04-11

IEC-61850 is a multifaceted standard covering the full range of communication services necessary for substation automation

While physical design needs decrease somewhat, virtual design complexity increases dramatically

New documentation, tools, test beds, training, and vendor support are keys to project success

Opportunity for costs reduction, in particular with GOOSE.Opportunity for enhanced functionality and data collection.

Enhanced flexibility and expandabilityMore complicated to design and support

Conclusion

www.casco-systems.comApril 11, 2016

Page 33: IEC 61850 Lessons Learned 2016 04-11

Thank You!