1 SIMON FRASER PPP Transaction Manager – Inland Rail IAQ Qld Infrastructure Summit 14 September 2018 The Australian Government is delivering Inland Rail through the Australian Rail Track Corporation (ARTC), in partnership with the private sector.

Upload: others

Post on 04-Jul-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: IAQ Infrastructure Summit Inland Rail presentation · IAQ Infrastructure Summit Inland Rail presentation Author: Simon Fraser Created Date: 9/21/2018 1:45:48 PM

1

SIMON FRASERPPP Transaction Manager – Inland Rail

IAQ Qld Infrastructure Summit14 September 2018

The Australian Government is delivering Inland Rail through the Australian Rail Track Corporation

(ARTC), in partnership with the private sector.

Page 2: IAQ Infrastructure Summit Inland Rail presentation · IAQ Infrastructure Summit Inland Rail presentation Author: Simon Fraser Created Date: 9/21/2018 1:45:48 PM

2

AGENDA Why Inland Rail?

Rationale for PPP

Indicative timeline for PPP

Inland Rail PPP Team

Current status of ‘Whole of Programme’ opportunities

Questions

What is Inland Rail?

2

Page 3: IAQ Infrastructure Summit Inland Rail presentation · IAQ Infrastructure Summit Inland Rail presentation Author: Simon Fraser Created Date: 9/21/2018 1:45:48 PM

ENHANCING THE NATIONALSUPPLY CHAIN

inlandrail.com.au3

Page 4: IAQ Infrastructure Summit Inland Rail presentation · IAQ Infrastructure Summit Inland Rail presentation Author: Simon Fraser Created Date: 9/21/2018 1:45:48 PM

4

KEY OUTCOMES OF INLAND RAIL

FASTStraight and flat

NOW33hrs

BENEFICIAL30%

CONNECTED

FUTURE

24<MELBOURNE

TO BRISBANE

16,000 JOBS

BILLION IN ECONOMIC ACTIVITY$16

COST REDUCTION

COMPARED TO TRUCKS

RELIABLE98%

4

Page 5: IAQ Infrastructure Summit Inland Rail presentation · IAQ Infrastructure Summit Inland Rail presentation Author: Simon Fraser Created Date: 9/21/2018 1:45:48 PM

5

The 126km section from Toowoomba to Kagaru, including large scale tunneling, will be delivered through a Public Private Partnership (PPP)

PPP – GEOGRAPHICAL CONTEXT

5

Page 6: IAQ Infrastructure Summit Inland Rail presentation · IAQ Infrastructure Summit Inland Rail presentation Author: Simon Fraser Created Date: 9/21/2018 1:45:48 PM

artc.com.au | Simon Thomas, Programme Delivery Director – Inland Rail |

artc.com.au

PPP – GEOGRAPHICAL CONTEXT

6

Page 7: IAQ Infrastructure Summit Inland Rail presentation · IAQ Infrastructure Summit Inland Rail presentation Author: Simon Fraser Created Date: 9/21/2018 1:45:48 PM

7

Cut to Fill -

11,700,000m3 cut

to 10,400,000m3

fill Formation

(capping) layer –

194,327m3

131 culverts of

various sizes

51 bridges

totalling 3.94km

in length

11 viaducts totalling

8.07km in length

6 road over

rail grade

separations

Active – 10

Passive – 11

8.51km in

length

PPP – INNOVATION WHERE IT MATTERS THE MOST

133.6km of new dual gauge

track, 11 passing loops to

cater for 1.8km trains

Local road realignment

4.7km

New road access 7.3km

Page 8: IAQ Infrastructure Summit Inland Rail presentation · IAQ Infrastructure Summit Inland Rail presentation Author: Simon Fraser Created Date: 9/21/2018 1:45:48 PM

8

RATIONALE FOR PPP

COMMONWEALTH GOVERNMENT ANNOUNCED IN 2017 GOWRIE TO KAGARU SECTION TO BE DELIVERED AS A PPP.

Commonwealth Government analysis

Technical Complexities and desire for smart, innovative solutions from private sector

Value for Money

Risk Optimisation

8

Page 9: IAQ Infrastructure Summit Inland Rail presentation · IAQ Infrastructure Summit Inland Rail presentation Author: Simon Fraser Created Date: 9/21/2018 1:45:48 PM

9

PPP – INDICATIVE TIMELINE

9

Page 10: IAQ Infrastructure Summit Inland Rail presentation · IAQ Infrastructure Summit Inland Rail presentation Author: Simon Fraser Created Date: 9/21/2018 1:45:48 PM

10

PPP – INLAND RAIL TEAM – INTERNAL

Also supported by specialists and support resources within the organisation

Approximately 40 people dedicated to the PPP Project

Projected to grow

10

Page 11: IAQ Infrastructure Summit Inland Rail presentation · IAQ Infrastructure Summit Inland Rail presentation Author: Simon Fraser Created Date: 9/21/2018 1:45:48 PM

11

PPP – INLAND RAIL TEAM – EXTERNAL Technical

and Approvals Consultants

Future Freight JV (AECOM +

Aurecon)

Technical Advisors

SMEC + Arup JV

Probity Advisor

BDO

Commercial and Financial

Advisors

KPMG

Legal Advisors

KWM

Transaction Advisor

Calcutta Group

Geotechnical Advisors

TBC

11

Page 12: IAQ Infrastructure Summit Inland Rail presentation · IAQ Infrastructure Summit Inland Rail presentation Author: Simon Fraser Created Date: 9/21/2018 1:45:48 PM

12

MARKET TESTING TIMING (NON PPP)

12

Page 13: IAQ Infrastructure Summit Inland Rail presentation · IAQ Infrastructure Summit Inland Rail presentation Author: Simon Fraser Created Date: 9/21/2018 1:45:48 PM

13

‘WHOLE OF PROGRAMME’ OPPORTUNITIES

inlandrail.com.au/register

13

Page 14: IAQ Infrastructure Summit Inland Rail presentation · IAQ Infrastructure Summit Inland Rail presentation Author: Simon Fraser Created Date: 9/21/2018 1:45:48 PM

14