“i don’t see it that way!” common mistakes lawyers make in ... · common mistakes lawyers...
TRANSCRIPT
1
American Bar Association Forum on the Construction Industry
________________________________________________________________________
“I Don’t See It That Way!” Common Mistakes Lawyers Make In Reading and
Interpreting Design Documents
Bill Quatman, FAIA, Esq. Burns & McDonnell Engineering Co.
Kansas City, MO
Sue Yoakum, AIA, Esq. Donovan Hatem LLP
Boston, MA
Presented at the 2010 Fall Meeting
We Won’t Get Fooled Again: Lessons Learned From the Economic Downturn
September 2-3, 2010 Loews Miami Beach Hotel, Miami Beach, Florida
________________________________________________________________________
©2010 American Bar Association
2
“A great matter is architecture, nor can everyone undertake it. He must be of the greatest ability, the keenest enthusiasm, the highest learning, the widest experience, and, above all, serious, of sound judgment and counsel, who would presume to call himself an architect.”
- Leon Basttista Alberti On the Art of Building in Ten Books (1450 A.D.)
I. The Evolution of Building Design.
A. From Caveman to CAD.
From the first Stone Age caveman who drew a line in the dirt, humans have been
designing the built environment. And sometimes those designs have contained errors or
omissions that have resulted in leaks, cracks, settling and structural collapses of “Biblical
proportions.” Architectural design reached its artistic peak, some believe, during the
Italian Renaissance period (1400-1600) when architects and artists were one and the
same, such as Florence’s pair of contemporaries Filippo Brunelleschi and Leon Battista
Alberti, the latter known as “the father of modern architecture;” to the artist/architects
Leonardo Da Vinci and Michelangelo. Then, as the “New World” and the Colonies began
to develop, the art of architecture was separated from the craft of the technical drawing
and we had “carpenter-architects” who drew standard details in the 1700’s. This period
was followed by the post-Civil War era’s first formal schools of architecture (MIT,
founded in 1865, and University of Illinois, founded in 1867), and people found
themselves in careers as “draftsmen.”
In the early 1980’s computer technology gave us the Computer Assisted Design
(or “CAD”), which expedited the drafting process, but even further removed the artist’s
sketchpad and replaced it with a keyboard and mouse. The design process has advanced
rapidly -- taking a cue from aerospace engineering -- to today’s Building Information
3
Modeling (or “BIM”), where buildings are shaped in a 3-D virtual world before the first
nail is driven.
While technology has advanced the speed at which we can design buildings and
other structures, the “human element” is still present in the CAD operator, the BIM
model host, and the detail designer. Despite advances in technology and over a thousand
years of experience, errors and omissions can still occur in the modern era due to
oversight or neglect of the individual architect or engineer who is responsible to draw,
click, drag or paste information into whatever media is being used to communicate design
intent to a contractor.
B. No Perfect Set of Plans.
Every set of plans has errors and omissions. This is nothing new. Design errors
and omissions are as old as the pyramids. Hammurabi’s code, written in ancient Babylon
about 1790 B.C., addressed the penalty for a builder whose structure failed. It was “strict
liability”, and death to the builder and his son, depending on the fatalities from the
collapse.1 The Old Testament is likewise full of references to the collapse of ancient
walls and houses.2 Even Christ used a poorly designed building as an analogy for a faith
based on an inadequate foundation, which would collapse and be destroyed when tested
by a storm.3
In more modern times, we have the example of the “Leaning Tower” in Pisa,
Italy, built in the 12th Century. The wonderfully detailed campanile, or bell tower,
behind the cathedral Pisa is not famous for its classical Corinthian capitals or its articulate
bell-chamber -- it is known for its structural design defect. Craftsmen and masons
worked for over 170 years to build the tower, spanning generations. However, foundation
4
design and improper soils investigation resulted in settlement that tilted the 183-foot
tower by almost 4 degrees. Any modern building would have been torn down due to such
deficiency; but the tower in Pisa stands as a reminder that design errors have always been
with us.
Plans, specifications and shop drawings play a key role in the construction
process. Contractors and subcontractors who bid on construction projects rely on the
architect/engineer’s plans and specifications as being sufficiently detailed and complete
so that accurate bids, shop drawings, material submittals, and project schedules can be
prepared. The public and owners rely on the integrity of the design of buildings and
other structures for shelter and safety.
Nonetheless, in absence of some express guaranty, the law does not hold
architects and engineers to a standard of perfection. As was held in Klein v. Catalano, a
Supreme Court of Massachusetts case from 1982:
As a general rule, an architect's efficiency in preparing plans and specifications is tested by the rule of ordinary and reasonable skill usually exercised by one of that profession . . . In the absence of a special agreement he does not imply or guarantee a perfect plan or satisfactory result.4
The Massachusetts Supreme Court explained that, just like doctors and attorneys,
design professionals are continually called upon to exercise their skilled judgment “in
order to anticipate and provide for random factors which are incapable of precise
measurement.” The court continued that, “[b]ecause of the inescapable possibility of
error which inheres in these services, the law has traditionally required, not perfect results
. . . [U]nlike a manufacturer, an architect does not impliedly guarantee that his work is fit
for its intended purpose.”5
5
The normal errors or ambiguities in project plans or specifications, as well as in
shop drawings and submittals, can give rise to unanticipated construction costs and
project delays for which owners and/or contractors seek to be reimbursed. Likewise,
delays in the shop drawing preparation and review process can result in claims for time
extensions and for additional money.
Claims are not at all uncommon since the “perfect” set of plans and specifications
has probably never been created, nor has the “perfect” project been built. While outside
forces, such as differing site conditions, contractor error, market instabilities, force
majeure, or owner naiveté of the design and construction process, can contribute to
problems with buildings, it is sometimes just a flat design error. As Alberti said in 1450:
Of the faults in both public and private buildings, some are integral and inherent, as it were, and the responsibility of the architect, while others result from some outside influence . . . But not all faults produced by outside influence are irremediable; nor does every mistake made by the architect allow some remedy. . . If a building cannot be improved without changing every line, the best remedy is demolition, to make way for something new. 6 Change orders are a normal part of the construction process and owners routinely
include “contingency” funds in the project budget to handle design changes and
unanticipated conditions encountered during construction. Architecture and engineering
are recognized by the courts as “inexact sciences”7 and, therefore, errors and omissions
are to be expected to some extent. Architects and engineers are not required to be
perfect, nor are their documents required to be flawless. Instead, they are required to
exercise “reasonable” care and skill in the preparation of plans and specifications. 8
In a 1991 survey conducted by Engineering News Record magazine, over 84% of
contractors said that project specifications “often or generally have major omissions.”9
6
That survey showed that contractors ranked the most frequent reasons for modifications
as:
1) ambiguity;
2) design consultant error;
3) conflict between specs and other contract documents; and,
4) owner changes.
The results of the survey are confirmation that there is no perfect set of plans.
II. Overview of How to Read a Set of Plans (Architecture 101)
A. Guides on Document Organization.
Two books that continue as great resources for reading and understanding
architectural plans are the “Architectural Graphic Standards” and “The Architect’s
Handbook of Professional Practice.” The Architectural Graphics Standards is published
by John Wiley & Sons, Inc. and the AIA.10 This book, now in its eleventh edition, has
been published since 1932. Architectural Graphic Standards, considered to be the
“Architect’s Bible”, contains over 8,500 architectural illustrations and is considered the
industry’s leading graphic reference. The AIA Handbook of Professional Practice is
published by John Wiley & Sons, Inc. and the AIA.11 The AIA Handbook, now in its
fourteenth edition, has been published since 1920 and is widely recognized as the leading
resource on architectural practice. The AIA Handbook has been admitted into evidence
by courts and arbitrators as evidence of the standard of care.12
The AIA Handbook refers to a system of organization for drawings called
“ConDoc”. which was developed in the late 1980’s by two architects to standardize a
uniform arrangement of drawings.13 This led to an even more detailed system called the
7
Uniform Drawing System (UDS) developed by the Construction Specification Institute
and published in 1997. The AIA itself published CAD Layer Guidelines in 1990, updated
and revised in 2001 as the U.S. National CAD Standard, Version 2.14 There are also two
more standards for organization of architectural drawings published by The National
Institute of Building Sciences (NIBS), one for CAD and another for BIM.15
For organization of specifications, the two leading standards are the AIA’s
MASTERSPEC®, and CSI’s MasterFormat® 2010. Where in the past, there were only
sixteen divisions of specifications, the new AIA guide has fifty divisions and while CSI
still has sixteen divisions, it uses multiple subparts. Suffice it to say that an explanation
of these guidelines are beyond the scope of this paper.
B. Typical Sheet Organization.
Plans are organized starting with sheets containing information relating to: 1)
building site, civil engineer and landscape architect’s documents; 2) the building,
architectural documents; 3) structural systems, structural engineer’s documents; 4)
mechanical, plumbing, and electrical engineer’s documents; and for some projects; 5)
specialty consultant’s documents. Most design teams consist of multiple design
consultants who each prepare their own documents and specifications and stamp and seal
their documents. The architect, in its contract with the owner, typically agrees to deliver
a design that includes the “usual and customary structural, mechanical, and electrical
engineering services.” AIA B101 Par. 3.1 (2007 edition).
The first sheet in any set of plans is the Title Sheet which contains information
relating the project, the owner and the design team. The first series of plans in the set are
civil or landscape sheets typically designated with the letter “C” or “L” and numbered
8
sequentially starting with “C-1” and “L-1.” The second series of plans are the
architectural drawings typically designated with the letter “A” and numbered sequentially
starting with “A-1.” The third series of plans are the structural drawings typically
designated with the letter “S” and numbered sequentially starting with “S-1.” The fourth
series of plans are the mechanical drawings typically designated with the letter “M” and
numbered sequentially starting with “M-1”. The fifth series of plans are the plumbing
drawings typically designated with the letter “P” and numbered sequentially starting with
“P-1”. The sixth series of plans are the electrical drawings typically designated with the
letter “E” and numbered sequentially starting with “E-1”. The next series of plans can
include specialty design consultants such as food service, fire protection and
telecommunication. Of course, this organization of a set of plans may vary from project
to project depending on the architectural and engineering teams working on the project.
Within any given set of plans for each design discipline, the drawings are
organized from general plan information to elevations, sections, enlarged plans, enlarged
sections and finally details. Plans are prepared from the “bird’s eye” view cutting the
building at approximately five to six feet above each floor. Overall building plans are
typically drawn with north at the top of the sheet. These sheets will contain a north arrow
symbol for orientation.
Reflected ceiling plans are drawn from the viewpoint of laying on the floor and
looking at the ceiling. Exterior elevations are drawn from the viewpoint of looking
directly at each exterior side of the building and drawing the building as a “flat” drawing.
Interior elevations are drawn from the viewpoint of looking directly at each interior wall
and drawing interior walls that illustrate design features or typically demonstrating
9
interior information. Building sections and wall sections are drawn by cutting the
building along a line and the line is selected to relay important design information.
Enlarged plans and elevations are selected to give additional critical design
information and drawn at large scale in order to illustrate this additional information.
Details are also selected to relay information on a typical and unique level and again
drawn at a large scale in order to illustrate this additional information and referenced
back to the larger plans and elevation.
Symbols are used to understand where plans, elevations, sections and details are
cut and how they reference back to the larger plans and elevations drawings. Symbols
are used to illustrate various pieces and parts of the building and to relay information
about the design. There are a large variety of symbols used in any set of plans from north
arrows, to section cuts, to detail references. Each design firm may have unique symbols
they prefer to use in the preparation of their documents, however, symbols are trending
towards becoming more standardized.
Each sheet will contain a title block listing the design professionals involved on
the project, the date of the document release, an area for the various design professionals
to stamp and seal their respective documents, and sheet numbers. The title blocks are
typically created by the architect and/or prime design professional and distributed to the
design team to use on their sheets. Within each sheet and various drawings there are
symbols that assist the reader in understanding how this enlarged plan, section or
elevation relates to the project.
Some contract documents will have legend or general note sheets that can be used
to understand typical design information. Other contract documents may include this
10
information on each sheet as needed. There is really no set approach and each design
team can agree how they will include this information.
The purpose of the contract documents is to include enough information relating
to the design to enable the contractor to prepare costs, schedules, and shop drawings, and
to build the project. Conflicts, errors and omissions in the contract documents confuse
the contractor and do not provide clear understanding of the design direction. The two
dimensional (“2D”), world of plans, elevations, sections and details has limitations on the
ability to relay the design intent. Some project participants, most often the owner, cannot
read and understand 2D drawings. A three dimensional (“3D”) drawing or model can
better relay design intent because it is much easier to orient and understand a 3D versus a
2D drawing. With the advent of computers, 3D drawings are the preferred drawing type
to easily communicate design intent. Recently, the design and build industry began
embracing Building Information Modeling as the preferred 3D modeling tool.
III. Building Information Modeling (BIM) The BIM revolution allows the designer the ability to draw their design as a 3D
model that is intelligent and includes design information beyond that contained in the
lines that make up a drawing. In a BIM model, “attributes” are typically attached to the
drawing objects to assist in explaining the design. These attributes contain specific
design criteria, including cut sheets containing design criteria and specification sections.
This type of “at your finger tips” information has never been as readily accessible as it is
with BIM.
11
A. What is BIM?
BIM is a tool used by architects, engineers, contractors and subcontractors to
prepare plans and shop drawings. The National Institute of Building Sciences describes
BIM this way:
A Building Information Model, or BIM, utilizes cutting edge digital technology to establish a computable representation of all the physical and functional characteristics of a facility and its related project/life-cycle information, and is intended to be a repository of information for the facility owner/operator to use and maintain throughout the life-cycle of a facility.16 B. How is BIM Used?
BIM is not new. It is only a new tool in the design and build industry. Other
industries, such as the aerospace and automotive industries, have used BIM for decades.
BIM modeling allows the project participants to better understand the design and to make
informed decisions relating to the design, cost and scheduling. Contractors and
subcontractors can use the 4-D (scheduling) and 5-D (cost estimating) aspects of the BIM
software to produce movie type critical path models and accurate costs estimates.
There were many early BIM articles that anticipated and envisioned one model
that all project participants would collaborate on together to develop a central model. In
discussions with many design and construction professionals, the idea of one central
model is false. The design model is typically utilized by the contractors and
subcontractors only as a reference, with the contractors and subcontractors creating their
own models that input and extract information from the construction viewpoint. In
addition, software and hardware restrictions limit working efficiently in one model. The
models simply contain too much information, and therefore, for most projects the idea of
one model cannot be realized with today’s technology.
12
C. Some BIM Project Examples.
Several stadium projects have been successfully delivered with BIM. Specific
projects include two new professional baseball stadiums: the Washington Nationals
ballpark, which opened in March, 2008, and the $1.3 billion Yankee Stadium, which
opened in April, 2009, as well as the dual-team $998 million Meadowlands Stadium in
New Jersey, which will host the New York Jets and Giants beginning with the 2010
football season.17 These projects teams utilized BIM for visualizing design and
fabrication, detecting clashes, ordering steel, creating bills of materials, and expediting
schedule. The project participants stated that “sharing a building information model has
been a ‘win-win’ for the whole project team.” 18
D. BIM Benefits.
BIM allows design professionals to create a library of objects that are created as
3D objects with technical information attached and ready to insert in the model, thereby
allowing the information to show up automatically in plan, elevation and section views.
For example, a typical loading dock can be drawn in the library and ready to insert in
various drawings on various projects. The loading dock object contains generic
information relating to typical loading docks, including attributes that contain
information concerning specific loading dock criteria and specification sections. These
BIM libraries can assist in quickly understanding all the elements of a particular design
feature such as loading docks.
Shop drawing BIM models, created by the contractor and its subcontractors,
contain specific information relating to the products selected to be installed in the project.
For example, with the loading dock example above, the shop drawing will include the
13
specific loading dock to be installed at the project. This loading dock may or may not be
dimensionally the same as shown on the design documents, but more then likely, will
vary from the loading dock illustrated on the contract documents. The design
professionals review these BIM shop models for design intent, as well as for relationship
to and coordination with other shop models. The real benefit of BIM is when all
participants use the BIM tool to draw their respective drawings. This allows a review of
the project in the BIM shop model review, but only if all shop drawings are prepared in
BIM.
E. Use of the BIM Model to Create 2D Contract Documents.
The 2D drawings are extracted from the BIM models and arranged on drawing
sheets. Typically, wall sections and details can be extracted from the BIM model, but
require additional hand-drawn information to enable a complete understanding of the
design intent.
F. BIM is Here to Stay.
BIM is a powerful drawing tool and is here to stay. Many design and construction
firms that use BIM to create their documents and drawings on a project cannot imagine
participating on a project without the benefit of BIM. BIM allows all participants a better
understanding of the design. As a result, cost estimates and construction schedules can
be prepared more efficiently.
BIM will not create a “perfect” model. There will be errors and omissions in BIM
models; therefore, coordination of the contract documents and shop drawings is still a
concern. It is, however, much easier to understand 3D models and to identify “clashes”
within the contract documents and shop drawings when BIM is used to prepare the
14
drawings. It is much harder to read and identify potential "clashes" on two dimensional
plans, elevations and sections.
The "clashes", or errors and omissions, in the contract documents occur where
two or more objects occupy the same space and a decision must be made regarding which
objects trump the others and get to occupy the space. Typically "clashes", whether on
BIM projects or projects not using BIM, are not identified during the design phase, but
instead are identified through Requests For Information (“RFIs”) and,change orders
which can impact costs and schedule and are often the center of attention in claims and/or
lawsuits. The BIM tool allows for the reduction of errors and omissions in the contract
documents and shop drawings and allows the project participants to “see” the project in
the same way.
IV. Shop Drawings.
Shop drawings are a controversial area for design professionals. Federal contract
provisions define “shop drawings” in FAR 52.236-21(d) as “drawings, submitted to the
Government by the Contractor, subcontractor, or any lower tier subcontractor pursuant to
a construction contract, showing in detail, (1) the proposed fabrication and assembly of
structural elements, and, (2) the installation (i.e., fit, and attachment details) of materials
or equipment.”19 These documents are the fabricator’s set of documents and the
documents that are used in the construction of the project. Shop drawings are prepared
by others, not under the architect’s supervision, but are, by custom and by contract,
reviewed by the architect and “approved” for fabrication and for construction. The level
of review varies depending on the complexity of the submittal and the practice of the
reviewing professional. Some engineers do a complete check of each weld symbol,
15
measurement and calculation, while other professionals only do a cursory review.
Several courts have found design professionals liable for negligent shop drawing
review.20
Shop drawing review and approval has been debated around the country,
especially since the collapse of the Hyatt skywalks in Kansas City in 1981 and the
resultant litigation. A review of this issue starts with understanding the purpose of shop
drawings.
A. Purpose of Shop Drawings.
Contrary to some beliefs, architects and engineers do not design each and every
component of the project. Some items are manufactured products, such as elevators,
cooling towers, toilet partitions, light fixtures, windows, etc., and some items are
specified as design-build by the contractor, such as fire sprinkler systems, curtain walls,
wood trusses, and precast panels. With manufactured products, the design professional
selects and specifies a particular model, make, color, and size appropriate for the project.
The contractor is then required to submit information verifying that a specific product
will be supplied that meets the design criteria. Still other building components are
custom fabricated for the project, such as millwork, fritted glass, and structural steel.
Rather than design each aspect of these components, the detailing is left up to
others -- typically the fabricator itself --, who are more familiar with the dimensions and
assembly processes of thr components. The fabricator’s drawings are then given to the
fabrication shop for use in making each component, thus the name “shop drawing.”
Under AIA form documents, the submittal process requires that the fabricator’s
drawings are first submitted to the contractor, who is to review "and approve” the shop
16
drawing. The contractor’s approval represents that the materials have been verified, field
measurements taken, and field criteria checked and coordinated with the requirements of
the Contract Documents. AIA A201 Par. 3.12.6 (2007 edition). The approved shop
drawing is then submitted to the architect, or its consulting engineers, for review. The
architect’s review and approval is to check “conformance with information given and the
design concept expressed in the Contract Documents.” AIA A201 Par. 4.2.7 (2007
edition). When the shop drawing is returned “approved” by the architect, the contractor
can begin fabrication. Since delayed reviews can hold up fabrication, design
professionals need to act promptly on submittals, keeping a log of the date received, the
action taken, and the date returned to the contractor. The AIA publishes a form, AIA
Doc. No. G712 (1972 edition), to use in logging in shop drawings and other submittals.
B. Liability for Negligent Review and Approval of Submittals.
One court has stated that, “shop drawings are the final word as to how the work
should proceed on the job, and supersede the architectural plans.”21 Given the
importance of shop drawings, negligent review and approval by the design professional
may result in liability, depending on the facts and the contractual duties of the reviewing
professional.
The meaning of architect approval was discussed in a 1977 Nebraska case where
the specifications called for “solid wood doors”, but the contractor supplied “particle
board doors”. The court held that the architect’s approval of the shop drawing did not
sanction the use of nonconforming doors. The contract language defining the architect’s
“approval” was a key factor in the court holding that the contractor was not entitled to
additional compensation for replacing the doors.22 Under the AIA form documents, the
17
contractor is not relieved of responsibility for deviations from the contract requirements
by virtue of the architect’s approval of shop drawings and submittals, unless the
contractor has: 1) specifically informed the architect in writing of the deviation; 2) the
architect has given written approval of the specific deviation; and, if a cost change is
involved, 3) a change order has been issued. AIA A201, par. 3.12.8 (2007 edition). The
same clause also states that the contractor is liable for errors and omissions in shop
drawings despite approval by the architect.
In the absence of such a contract clause, a design professional may be held liable
for negligent review and approval of a shop drawing. In Jaeger v. Henningson, Durham
& Richardson, 714 F.2d 773 (8th Cir. 1983), the specifications called for use of 10 gauge
steel on a stair landing. Shop drawings were submitted which called for thinner 14 gauge
steel and were approved by the architect. The landing pan was fabricated of 14 gauge
steel and collapsed when two workers stepped onto it to perform welding. The architect
was found negligent and held liable for injuries to the workers. In a follow up case, the
architect then sued the contractor for indemnity for submitting the defective shop
drawing. The court denied the indemnity claim, however, based on a South Dakota “anti-
indemnity” statute.23
By contrast, in Lutz Engineering Co. v. Industrial Louvers, Inc., 585 A.2d 631
(R.I. 1991), the court found that the project architect/engineer owed no duty to a
subcontractor based on the contract shop drawing language. The architect’s duty was
owed only to the general contractor, not to the subcontractor.
Where the submittal contains information relating to the means and methods of
construction, AIA-type contract language may shield the design professional from
18
liability. For example, in a 1982 Oklahoma case, an architect was found not liable for the
deaths of two workers and the injury of another allegedly caused by negligent approval of
shop drawings for steel erection.24 The court held that under the AIA General Conditions
the contractor, not the architect, was responsible for temporary field connections and for
the means and methods of construction.
C. No Action Taken.
A design professional’s failure to take action on a submittal does not necessarily
mean “approval.” That very issue came up in a 1946 Missouri case.25 In that case, the
specifications provided that the contractor should furnish shop drawings when required
by the specifications, but that no shop drawings should be submitted except as required.
It was further stated that shop drawings submitted without being required would be
returned “without action.” The tile section of the specifications made no provision for
shop drawings. Nonetheless, the tile supplier sent shop drawings to the subcontractor
who made corrections and forwarded the drawings to the general contractor.
The contractor then submitted the shop drawings to the owner (the government).
The owner returned the shop drawings with the notation, “Shop drawings are not required
for this work; however, contract requirements should be followed in all cases.” When the
subcontractor started to install the tile presuming approval of the submittal, the owner’s
engineer stopped the work and directed that different “bull nose” tile be used as required
by the specifications. As a result, the subcontractor sued the general contractor for
additional compensation. In denying recovery, the court pointed out that silence doesn’t
necessarily mean “acceptance.” The court stated that,
The fallacy of [the subcontractor’s] contention regarding shop drawings lies in their assumption that the damages they sustained resulted from
19
failure of the [owner] or [the contractor] to approve or disapprove the shop drawings submitted. When the drawings were returned, [the subcontractors] were warned that the contract requirements should be followed.
. . . In view of the above facts and the further fact that the shop drawings originally submitted to [subcontractor], and before they were corrected by them, provided for general use of [the proper tile type], we cannot say that failure to approve or disapprove the shop drawings misled [subcontractor]. Furthermore, the specifications did not require shop drawings, and when the [owner] returned those submitted with the notation attached, it was not for [the general contractor] to assume to approve them.26
Under the AIA A201 General Conditions (2007 edition), architects are given the
right to request certain “informational” submittals without the need to approve those
documents. Paragraph 3.12.4 states that,
Informational submittals upon which the Architect is not expected to take responsive action may be so identified in the Contract Documents.
Contractors should not assume that the absence of action on such submittals means
“approval.” Design professionals who use such clauses should add a “no action taken”
box to the shop drawing review stamp, noting that the contractor should follow the
contract requirements.
D. The Hyatt Skywalk Case.
No single case has had the dramatic effect on the construction industry as that
involving the collapse of the Hyatt skywalks in 1981 during which 114 people were
killed and over 180 more were injured. In the wake of this disaster, the industry engaged
in a decade of review of the entire process of shop drawings and design delegation. The
personal injury and wrongful death cases were mostly settled out of court. The Missouri
licensing board held months of hearings and ultimately, disciplinary action was taken
against the structural engineers who designed the skywalks. The administrative law
20
judge who conducted the hearings issued a lengthy 442-page opinion in which he found
violations of the state licensing laws sufficient to permanently revoke the licenses of two
engineers, as well as the Certificate of Authority of the engineering firm. The engineers
appealed the Board’s action.27
In affirming, the Court of Appeals held that although, by custom, the structural
engineer elected to have the steel fabricator design the steel connections, this did not
relieve the engineer of responsibility for the design of those connections. The Court
stated that under the Missouri licensing statute, once an engineer seals the design for a
project, he becomes responsible for the “whole engineering project” unless he disclaims
liability as permitted by statute.28 Absent such a disclaimer, the engineer is not relieved
of responsibility for engineering decisions made by fabricators. The Court found that
the reviewing engineer was aware of a design change made by the steel fabricator
(switching a single rod suspension system to a double rod design for ease of fabrication);
however, the engineer did not review the hanger connection proposed for the double rod
design despite representing to the architects that a review had been done. The Court
found that such conduct was a willful act with wrongful intention, constituting “gross
negligence” by a professional. The Court stated that, “[s]hop drawing review by the
engineer is contractually required, universally accepted and always done as part of the
design engineer’s responsibility.”
E. The AIA Shop Drawing Clauses.
As a result of the post-Hyatt litigation and industry awareness of risks associated
with the shop drawing review process, the 1987 edition of the AIA General Conditions
greatly expanded the coverage of this topic. The 1997 and 2007 editions carry forward
21
the expanded language, but add a potentially dangerous twist. Paragraph 3.12 and its ten
subsections detail the shop drawing process. Paragraph 3.12.7 states that the contractor is
not to perform work which requires a shop drawing “until the respective submittal has
been approved by the Architect.” Since the contractor must wait on architect approval,
there is a potential for project delay caused by inaction in the approval process. The
architect has a duty to take action on shop drawings “with such reasonable promptness as
to cause no delay in the Work . . . while allowing sufficient time in the Architect’s
professional judgment to permit adequate review.” AIA A201 par. 4.2.7 (2007 edition).
The time for review of shop drawings should be established in the contractor’s
schedule of submittals, which is “coordinated with the Contractor’s construction schedule
and allows the Architect reasonable time to review submittals.” AIA A201 par. 3.10.2
(2007 edition). Any submittals not approved in a timely manner should be brought to the
architect/engineer’s attention, especially those relating to long lead-time components of
the Project.
The expanded language of A201’s shop drawing review clause, paragraph 4.2.7,
includes at least four disclaimers of what the architect’s approval “is not.” The new twist
relates to design-build components of the project, such as items required by a
“performance specification”, or sprinkler systems, curtain walls, precast or other building
components to be designed by the contractor. Paragraph 3.12.10 of the 2007 A201
General Conditions requires the contractor to submit shop drawings signed and sealed by
a licensed design professional for such work. The clause goes on to state that, “[t]he
Owner and Architect shall be entitled to rely upon the adequacy, accuracy and
completeness of the services . . . by such design professionals.” Time will tell whether
22
delegation of design to the contractor is a cost effective procedure or an invitation for
disaster. Maybe we haven’t learned much from the Hyatt collapse after all.
F. Shop Drawing Stamps.
There is a wide variety of wording used on shop drawing stamps. During the
mid-1980’s, there was a push to avoid using the word “approved” on shop drawing
stamps. Design professionals thought, or were advised, that if they avoided using the
“A” word during their review, they might not have liability for action taken by them on
submittals. Phrases such as “reviewed”, “no exceptions noted”, “authorized to proceed”,
and the like became common. In fact, one of the major professional liability insurers
required their insureds to use “reviewed” on their stamps. Despite this, time has shown
that the courts still equate the review and passage of judgment by the design professional
with “approval”, regardless of the wording used on the stamp.
Interestingly, the AIA’s Handbook of Professional Practice contained a
recommended stamp until the 2008 edition which recommended that the word
“approved” be used by both the contractor and architect. The AIA’s "recommended"
stamp as published in 1994 had these four boxes as choices29:
________________________________________________________________________
APPROVED Fabrication/installation may be undertaken. Approval does not authorize changes in the Contract Sum or Contract Time.
APPROVED AS CORRECTED _________________________________________________________________ REVISE AND RESUBMIT Fabrication/installation MAY NOT be undertaken. In
resubmitting, limit corrections to the items marked.
23
REJECTED _________________________________________________________________ Review/approval neither extends nor alters any contractual obligations of the Architect or Contractor.
FIRM NAME
By _____________________________ Date _____________________
________________________________________________________________________
For those wanting more comfort, and a really big stamp, the AIA also had a longer
version with a 142 word disclaimer at the bottom.
The AIA contracts state that the architect is to “review and approve, or take other
appropriate action” (i.e. reject, require revision, etc.). As a result, the courts find that
"review" equals "approval". In the opinion of the Administrative Law Judge issued in the
Hyatt case, he observed that,
Although the contract documents require that shop and erection drawings be submitted to the engineer of record for “review and approval”, testimony at trial indicates that engineers never use the term “approved” when indicating review and approval of these drawings. This custom apparently rests upon the dubious basis that most engineers’ insurance carriers have directed that the word “approve” not be used.30
The judge went on to note that although the steel shop drawings did not indicate
“approval”, based upon all the evidence, the “Commission finds that the 'review stamp' of
the structural engineer of record on the Hyatt project, placed on shop and erection
drawings, functionally indicates both review and approval of such drawings.”
Specific definitions within the contracts may, however, deflect liability from the
design professional. For example, in a 1995 Virginia case, the court held that the
engineer’s stamp which stated that “review does not relieve the contractor from
complying with all requirements of the contract documents” meant that the contractor
was liable for the failure of certain post-tensioning components and that the engineer’s
24
approval did not waive the original contract requirements.31 As a result, the contractor,,
not the owner, was liable for the error.
G. Industry Changes.
The post-Hyatt fallout continues to affect the industry today.32 In October 1985,,
the American Society of Civil Engineers (ASCE) published its Final Report and
Recommendations on Assignment of Authority & Responsibility for Design of Steel
Structures. Many state licensing boards have since restricted the practice of design
delegation, while others have authorized it. New York has been a particular hot-bed of
activity surrounding the delegation of design responsibility to contractors. In late 1996,
building contractors and steel fabricators filed suit in New York to challenge a state
agency rule that allowed the principal designer to delegate design responsibility through
unlicensed contractors to secondary licensed designers.33
As mentioned above, the 1997 and 2007 AIA documents allow the architect to
delegate design responsibility to the contractor. AIA A201 par. 3.12.10 (2007 edition).
The key concern, regardless of who performs the design, is to make sure that the client
gets a quality building and that the public is safe. Shop drawing review cannot be based
upon disclaimers and avoidance. Since these are the drawings actually used to build
from, careful review is required by a licensed professional familiar with the project.
VI. Legal Issues in Interpreting Design Documents.
A. “Contract Documents.”
The phrase “contract documents” is widely used in the construction industry to
include not only the signed contract between the parties, but a host of other documents,
drawings, specifications, reports, surveys, exhibits, and conditions. All of these pieces of
25
information make up the construction contract. Most are not attached to the contract, but
are merely mentioned and incorporated by reference. What may escape immediate
attention is that the drawings and specifications are as much a part of the contract as the
payment or dispute clauses.
1. Not Just the Agreements and General Conditions.
As one New York court stated, “[i]n the context of the performance of a
construction contract, the term ‘contract documents’ generally refers to ‘architectural
plans, drawings, surveys, specifications, engineering reports, change orders, and the like
... applicable to the work to be performed.’” 34 Standard AIA General Conditions define
the contract documents as:
the Agreement, Conditions of the Contract (General, Supplementary and other Conditions), Drawings, Specifications, Addenda issued prior to execution of the Contract, other documents listed in the Agreement and Modifications issued after execution of the Contract.
AIA A201, Par. 1.1.1 (2007 edition). The AIA contracts then go on to explain that, “[t]he
Contract Documents form the Contract for Construction” and that the “Work means the
construction and services required by the Contract Documents.” AIA A201, Par. 1.1.2
and 1.1.3 (2007 edition). Therefore, the contract documents are the essence of the
agreement, forming the contract and describing all work to be performed.
2. Specs Equal to Drawings.
Under the AIA forms, there is no priority given as between the terms of the
written agreement, the drawings, or the specifications. AIA’s A201 General Conditions
states only that, “[t]he Contract Documents are complementary, and what is required by
one shall be as binding as if required by all,” which from a legal perspective puts the
drawings and specifications on equal footing. AIA A201 Par. 1.2.1 (2007 edition).
26
2. What if in Conflict?
If there is a conflict with the numerous contract documents, and there often is,
how is this to be resolved? Under the AIA forms, conflicting documents would be
submitted to the architect for interpretations, as in a “request for information”. AIA A201,
Par. 4.2.11 and 4.2.12 (2007 edition). The architect will then respond to such written
request with a decision that is to be, “consistent with the intent of, and reasonably
inferable from, the Contract Documents,” and will be impartial and issued in “good
faith”. If either party disagrees with the architect’s interpretation, the intent appears to be
that the matter becomes a “dispute” which is then submitted back to the architect as the
Initial Decision Maker (or IDM) for a second bite at the apple. Failure to resolve the issue
at that stage leads to mediation and arbitration. AIA A201, Article 15 (2007 edition).
B. Ambiguities in Plans and Specs.
A contract is ambiguous if it is susceptible of two different and reasonable
interpretations, each of which is found to be consistent with the contract language.35
Stated otherwise, “where, from the four corners of the contract, the terms are susceptible
of more than one meaning so that reasonable persons may fairly and honestly differ in
their construction of the terms.”36 If the language of the contract is unambiguous, then
words “are to be given their plain and ordinary meaning.”37 Since plans and
specifications are incorporated into the construction contract by reference, they are
subject to the same rules of interpretation as the terms of the agreement itself. Courts
have held that whether a plan or specification is ambiguous is a question of law for the
court to decide.38 The rules of interpretation can be summarized in the following
sections:
27
1. Construed Against the Drafter.
Once a contract is found to be ambiguous, legal rules of contract construction
provide that the ambiguity is to be construed against the drafter. As one state Supreme
Court has stated,
A basic principle in the construction of contracts is that an ambiguity in the language of the contract will be strictly construed against the party who drafted the provision.39
The rationale for this rule is that, “doubtful and uncertain language in a contract is
construed against the party preparing the contract, for he has created the troublesome
ambiguity.”40 When that “drafter” is an architect or engineer who has prepared
documents for use by the project owner in obtaining bids, courts generally construe
ambiguities against the owner.
2. Application of Rules to Construction Documents.
Many courts have applied these rules of contract construction to bid documents,
holding that the documents are to be construed in favor of a contractor’s reasonable
interpretation against the owner. The construction case often cited is Blount Brothers
Construction Co. v. United States, 346 F.2d 962 (Ct. Cl. 1965), in which the
government’s plans and specifications for certain concrete work were in conflict. The
court laid out certain rules for dealing with ambiguities created by conflicts between
plans and specifications. Those include,
a. A contractor’s interpretation of the documents will be adopted if within the “zone of reasonableness”;
b. Contractors have a duty to inquire and to seek a clarification as to a
“patent” ambiguity; c. Contractors are not expected to seek clarification of hidden (“latent”)
ambiguities; and,
28
d. Ambiguities in contracts drawn by the government are construed against
the drafter.41
The rule of law that any ambiguity is construed most strongly against the party
who drafted the specification is known as the rule of “contra proferentem.”42 The
rationale for the rule is that,
it puts the risk of ambiguity, lack of clarity, and the absence of proper warning on the drafting party which could have forestalled the controversy; it pushes the drafters toward improving contractual forms; and it saves contractors from hidden traps not of their own making.43
Many courts have stated that any ambiguity in a contract must be resolved most strongly
against the party who prepared it.44 The idea is that the drafting party has the
responsibility to make the contract terms clear, and if he fails to do so, the other party’s
reasonable interpretation will control. This rule applies equally to the plans and
specifications which become a part of the contract and the contract documents.
Since the owner provides and furnishes the plans and specifications to the
contractor, the owner is deemed to be the party who “drafted” the documents. If the
plans and specifications are ambiguous, the courts will construe the documents in favor
of the contractor’s interpretation -- if reasonable -- and against the owner’s. The
contractor need not show that his interpretation is the best, only that it is within the “zone
of reasonableness.”45 For example, in Neal & Co., Inc. v. U.S., 945 F.2d 385 (Fed. Cir.
1991) the contractor claimed that government specifications for shipping certain precast
concrete elements were ambiguous. The court agreed, holding that,
The Government’s interpretation is not unreasonable, but neither is the interpretation put upon it by [the contractor] and by the trial judge. If the Government wants a particular interpretation to be made of a contract provision, it can write the provision to make that meaning clear.46
29
The contractor was awarded the extra costs incurred for shipping.
3. Patent vs. Latent Ambiguities.
Court cases hold that a “patent ambiguity” is one that is recognized as “an
obvious omission, inconsistency, or discrepancy of significance.”47 A “latent ambiguity”,
by contrast, exists when the ambiguity is “neither glaring nor substantial nor patently
obvious.”48
When a conflict of interpretation is presented, the meaning of the words included
in a contract is determined by a two-step process. The Court must first determine
whether an ambiguity exists. If an ambiguity is immediately apparent, it is a “patent” or
obvious ambiguity, and the contractor is under a duty to seek clarification. If a contractor
does not inquire about a clearly patent ambiguity, the ambiguity will be construed against
the contractor, not the drafter.
4. The Zone of Reasonableness.
Far-fetched interpretations of the documents will not be allowed. The
contractor’s interpretation of an ambiguous provision or detail must be within the “zone
of reasonableness.”49 “The Government, as the author, has to shoulder the major task of
seeing that within the zone of reasonableness the words of the agreement communicate
the proper notions . . .”50 A party seeking to have its interpretation adopted must
demonstrate that it actually and reasonably relied upon that interpretation when it entered
into the contract.51
5. Contract Authority of A/E To Interpret.
One way to resolve contract ambiguities is to designate an official interpreter of
the documents. Some construction contracts provide that a third party, usually the
30
architect or engineer has the final authority to determine the meaning or interpretation of
the plans and specifications. These clauses are generally upheld and the design
professional’s decision is conclusive in the absence of fraud or gross mistake. These
provisions have been held to give a third party (such as an architect) the power to resolve
any ambiguities in the specifications.52
C. Contractor’s Review of Documents.
The AIA’s A201 General Conditions are also structured to defer the initial
decision of ambiguities in the documents to the architect. Under § 3.2.1, the contractor is
to carefully study the contract documents before starting any work, and to report any
errors, inconsistencies, or omissions discovered to the architect with a request for
interpretation. §3.2.2 further states that the contractor’s review is made “in the
Contractor’s capacity as a contractor and not as a licensed design professional” and that
the contractor is not responsible to determine if the design is in compliance with building
codes and regulations, though any discovered errors are to be reported. By failing to
report noted errors and proceeding with the work, the contractor becomes liable to the
owner for any costs and damages that would have been avoided had the error been
reported. AIA A201 Par. 3.2.4 (2007 edition).
This concept is not new. Courts have adhered to these same rules for many years.
In 1931, a New York court held that a contractor who is bound to follow fixed plans and
specifications “owes the duty to examine such plans and judge of their sufficiency; that
he is bound to discover defects that are reasonably discoverable or patent; and, where he
knows or had reason to believe that the plans are defective, and follows them without
pointing out such defects to the owner or architect, he is not entitled to recover if the
31
building proves insufficient because of such defects.”53 Stated another way by an Indiana
court, the contractor is required, “to utilize his expertise and to notify even an architect of
reasonably discovered defects.”54
D. Superfluous Specifications or Details.
One cause of errors or ambiguities in contract documents is the re-use of details or
specifications from Project A to Project B. Without proper review, additional details or
requirements can be included in the contract documents which have no application to the
current project. In one such case involving a federal prison, the drawings contained a
“legend” with notes and graphic symbols for portions of the work. Note 9 said: “New
Manhole For Primary Service. See Detail 1/E–5”; however, the detail on sheet E-5 was
for a “pull box” not necessarily for a manhole; and the electrical site plan on sheet E-1
showed no Note 9 symbols for new manholes. Instead, the site plan erroneously referred
to Note 6 in four places. The contractor assumed no manholes were required, but did not
seek any clarification prior to submitting its bid. The Board of Contract Appeals found
that there was no ambiguity and that the plans did not require installation of any
manholes. In reaching its conclusion, the Board stated that,
[A]rchitect-engineers do not prepare perfect plan and specifications. No one expects them to do so. They often do contain errors, one of the more common of which is for plans and specifications to contain superfluous language, language which may at one time during the birth pangs of the project have related to a proposed feature, which feature was subsequently deleted. Therefore, a contractor should not be expected to run to the Contracting Officer every time a lack of perfection is uncovered; the obligation to inquire arises only if there is an ambiguity.55
The Board reasoned that if the mistake in the plans is relatively minor, a bidder
might not catch it and may ignore it altogether. Despite the reference to “manhole” in the
32
drawing legend, the Board found this language in the solicitation merely “superfluous”.
All this for a claim totaling less than $6,000.
E. Contract Clauses.
Clever lawyers have figured out ways to put order into the chaos of interpreting
contract documents. Courts generally uphold bargained-for contract allocations of risk,
absent special legislation which prohibits certain clauses. Construction lawyers need to
check the state in which the project is located for any “fairness in contracting” statutes
which have been passed nationwide in the past decade to prevent onerous contract
clauses from being forced onto weaker parties by those with the upper hand in
negotiations.
1. Order of Precedence Clauses.
Though it may not be possible to entirely avoid ambiguities, it is possible to
minimize them by providing a way to resolve them in the contract. In one construction
case, the court held that provisions of a construction contract will generally control in the
event of a conflict with the specifications, but where the contract and general conditions
of the specifications contain clauses on the same issue, the court will try to harmonize the
provisions and construe them together.56 Rather than leave the resolution and
interpretation of conflicting provisions to a court, most contract documents contain a
“precedence clause” in either the general conditions or specifications. A typical
precedence clause reads:
Drawings, Specifications, General and Supplementary Conditions are essential parts of the Contract, and a requirement occurring in one is as binding as though occurring in all. They are intended to be complementary and to describe and provide for a complete work. In the event of any discrepancy between the drawing and figures written thereon, the figures, unless obviously incorrect, are to govern over scaled
33
dimensions. In the case of any discrepancy between the Drawings and the Specifications, the Specifications are to govern. If there is a discrepancy between large and small scale details, the larger scale details are to govern. Special provisions shall govern over Specifications, Drawings and General Conditions.
The standard federal contract provision for Specifications and Drawings for Construction,
FAR 52.236-21, states, in part, as follows:
In case of difference between drawings and specifications, the specifications shall govern. In case of discrepancy in the figures, in the drawings, or in the specifications, the matter shall be promptly submitted to the Contracting Officer, who shall promptly make a determination in writing.57
Courts have dealt with the effect of such clauses. For example, in 1967 the Eighth
Circuit evaluated a precedence clause which provided that special provisions took
precedence and governed in the event of a conflict with the standard specifications.58
The Court found that special provisions provided for a fixed price contract, and that the
precedence clause was enforceable. In another case it was held that a provision stating
that HUD contract provisions took precedence over AIA General Conditions eliminated
any conflict.59
The following are sample precedence clauses used by the City of Los Angeles,
Department of Public Works, in their Standard General Conditions (2007 edition):
00204 PLANS AND SPECIFICATIONS (9/18/07) As shown on the Plans or described in the Specifications, each element of the Work must be furnished complete, finished and functional. Whether shown or not, include all materials and ancillary equipment necessary to provide a complete installation. The Plans, Specifications and other Contract Documents are intended to be complementary and cooperative to describe and provide for a complete project. Anything in the Specifications and not on the Plans, or on the Plans and not in the Specifications, shall be as though shown or mentioned in both. Details
34
shown for an item of Work are typical and shall apply to similar items of Work. The Engineer does not warrant the accuracy of scaled dimensions. Dimensions indicated by figures or numerals shall govern. Larger scale drawings shall take precedence over smaller scale drawings. Detailed drawings will take precedence over general drawings. 00205 PRECEDENCE OF CONTRACT DOCUMENTS (9/18/07) In resolving inconsistencies or ambiguities among two (2) or more components of the Contract Documents, the more stringent requirements shall prevail. The secondary priority will be based upon the precedence of the documents. The precedence shall be: . . . [then follows a list of 13 documents in order of priority]. Supplemental Agreements, Change Orders, Engineer’s written interpretations and clarifications, and Addenda, will take precedence over all other components of the Contract Documents.
There are as many ways to write these clauses as there are practicing lawyers, but the
basic premise is always the same (i.e. to establish some order or priority in the event of
conflicts).
2. Incorporation by Reference.
Construction documents would be several feet thick if every technical reference,
ASTM, and federal regulation applicable to the project was attached. To avoid this,
almost all contracts and specifications incorporate other documents by reference. Courts
have held that, “matters incorporated into a contract by reference are as much a part of
the contract as if they had been set out in the contract in haec verba [meaning in full].”
Jim Carlson Const., Inc. v. Bailey, 769 S.W.2d 481 (Mo. App. W.D. 1989)(finding the
AIA General Conditions were incorporated by reference into the contract by reference).
Owners will often incorporate their own custom-drafted general conditions into the
contract with the design professional.
35
Since documents which are incorporated by reference become a part of the
contract, it is important for the parties to review all refernced documents prior to signing
the contract, to ensure nothing objectionable is included within the general conditions,
supplementary conditions, or other documents incorporated into the contract. Failure to
read all such referenced documents can result in unknown conditions sneaking into the
contract. As one court has stated, “[c]ontracting parties have a duty to learn the contents
of a written contract before signing it, and such duty includes reading the contract and
obtaining an explanation of its terms.”60 In that case, the court added that a party who
signs a contract is bound by its provisions regardless of whether he reads or understands
it terms.
E. The Spearin Doctrine.
While we have seen that design professionals are not held to a standard of
perfection and do not warrant their plans as perfect, the law is different as between an
owner and a contractor. Federal courts have held that on public projects, when a
contractor bids on a set of plans and specifications, the government warrants the
adequacy of the design specifications, and if such specifications are deficient, it is the
government that bears the risk, not the contractor.61 There are numerous cases across the
country dealing with the issue of whether a contractor can rely on the plans and
specifications provided by the owner.62
Most of these cases cite the “Spearin doctrine” as derived from the U.S. Supreme
Court’s landmark decision in U.S. v. Spearin, 248 U.S 132 (1918). The Spearin doctrine
holds, generally, that when the owner furnishes detailed specifications to a contractor, the
owner is deemed to impliedly warrant that those plans and specifications are accurate and
36
suitable for their intended use. A majority of state jurisdictions recognize Spearin as
controlling law.63
The Spearin case held that, “if the contractor is bound to build according to plans
and specifications prepared by the owner, the contractor will not be responsible for the
consequences of defects in the plans and specifications.” Id., 248 U.S. at 136. The
Spearin court held that the owner’s implied warranty is not negated by a contractual
requirement providing that the contractor must examine the site and check the plans.. In
Spearin, the US Supreme Court stated that “[t]he duty to check plans did not impose the
obligation to pass upon their adequacy to accomplish the purpose in view.” Id. at 248.
1. Lower Courts’ Recognition of Spearin.
The Spearin doctrine has been recognized by multiple state courts.64 In a 1985
Missouri case, the court cited Spearin in holding that, “[g]enerally, when a contractor is
to construct a project according to another’s plans it does not insure that the plans are
sufficient to obtain the result sought. The contractor should be paid when it does what it
is required to do under the plans.”65 In other words, the contractor is not responsible for
design errors. This would be different, of course, if the contract passed design
responsibility to the contractor.
In Housing Authority v. E.W. Johnson Construction Co., Inc., 573 S.W.2d 316
(Ark. 1978), a contractor sued the project owner for breach of implied warranty of plans
and specifications which resulted in delay damage to the contractor. The Arkansas
Supreme Court held that, “We are persuaded that where, as here, the owner supplies
plans and specifications to a contractor detailing the work to be performed, the owner
37
implicitly warrants the adequacy and suitability of the plans and specifications for the
purpose for which they are tendered.”66
If there is a design error or omission, contractors often argue that they are not
responsible for the design, but only to build it as it is drawn. For example, in Teufel v.
Wiener, 411 P.2d 151 (Wash. 1966), the court dealt with the issue of whether a contractor
was liable for leaks in the curtain wall of a high rise building. The court found that the
problem was a design defect and ruled that, “if an item is installed in accordance with the
specifications [for that project], the contractor is not liable if the item’s failure to function
properly is due to its design being improper for the intended use.”67
2. Actual Knowledge of Design Defects.
As long as the contractor’s work meets the requirements of the specifications, and
the contractor had no knowledge of the defect, he will generally not be held responsible
for any damage caused by design error. However, if the contractor has actual knowledge
of a defect in the plans and specifications, and fails to raise that issue upon discovery, the
contractor cannot rely on the owner’s implied warranty. In some cases, withholding such
information can even amount to fraud. As stated in the E.W. Johnson case, above,
However, a competent and experienced contractor cannot rely upon submitted specifications and plans where he is fully aware, or should have been aware, that the plans and specifications cannot produce the proposed results.68
3. Express Warranty By Contractor.
An express warranty by the contractor as to the results to be achieved will
override the owner’s implied warranty. For example, in Home Furniture, Inc. v. Brunyell
Constr. Co., 440 P.2d 398, 401 (Nev. 1968), the court stated, “[t]he law is well settled in
practically every American jurisdiction that, where a contractor has followed the plans
38
and specifications furnished by the owner and his architect, he will not be responsible to
the owner, at least after the work is completed, for any loss or damage which results
solely from the defects or insufficient plans or specifications, in the absence of any
negligence on the part of the contractor or any express warranty by him as to their being
sufficient or free from defects.”69
The Tenth Circuit Court of Appeals has held that a contractor's “acquies[ence] in
the use of a particular material or system” and guarantee of his work does not make the
contractor a guarantor of the design. “The person who designs the structure is
responsible for insufficiencies in the effectiveness for the purpose intended.”70
4. Duty to Warn of Defects.
Some courts have found that contractors have a “duty to warn” when they have
reason to believe that the plans are defective. The contractor cannot proceed with
construction with such knowledge and then make a claim for damages later as a result.
The contractor has a duty to warn in order to protect himself from liability for
deficiencies caused by such defects.71 In one such case, Lewis v. Anchorage Asphalt
Paving Co., 535 P.2d 1188 (Alaska 1975), a paving contractor placed asphalt paving on
unsuitable soil. The contractor argued that he had no duty to warn of the soil condition;
however, the court ruled that,
this duty to inform the owner, regardless of his personal expertise, of potential defects in his project which come to the contractor’s knowledge or should come to his knowledge, is an essential element of performing any contract in a workmanlike manner according to acceptable standards.
The court went on to state that a contractor has no duty to warn of defects unless they are
likely to cause a failure in the contractor’s work and are of such a nature as to place the
39
contractor on notice of their existence. In other words, a contractor cannot “sandbag” the
owner, by holding back on knowledge of a defect in order to make a claim later.
5. Contractor’s Duty to Investigate.
As to whether the contractor has a duty to investigate the compatibility of
materials or the adequacy of the design, there are various cases reaching different
decisions depending on the contracts, the nature of the error, and the contractor’s
expertise. For example, in Our Lady of Victory College v. Maxwell Steel Co., 278
S.W.2d 321 (Tex. App. 1955), a tower collapsed when the contractor installed a new steel
tank on top of it. The court held that the contractor was not liable for damages because
the work had been completed according to the plans. The court further held that, “[i]t is
immaterial that [the contractor] may have known more about the carrying capacity of
towers than did [the owner].”
In W.H. Lyman Construction Co. v. Village of Gurnee, 403 N.E.2d 1325, 1332
(Ill. App. 2d Dist. 1980), the court held that the contractor’s duty is to perform his part of
the contract in a workmanlike manner, not to evaluate the suitability of the specifications
or, in the language of Spearin, “to pass upon their adequacy to accomplish the purpose in
view.” The Illinois court held that the contractor had a duty to build in accordance with
the plans and specifications and that the owner impliedly warranted their adequacy.
In light of the Spearin doctrine, a contractor has no common law duty to analyze
the specifications for design adequacy. If however, in reviewing the plans and
specifications for bidding, the contractor notices a design defect as a result of his
specialized background, he cannot close his eyes to the defect, but must instead notify the
architect or engineer before proceeding. The duty to warn comes about only when the
40
contractor has, or should have, knowledge of defects in the design. Stated another way,
“the contractor is required to bring his expertise into play and to notify even an architect
(expert) of reasonably discovered defects.”72
F. Risk Shifting Clauses.
There are contractual methods to shift the risk of design errors or omissions away
from the owner or design professional, including those based upon the Spearin doctrine.
One recent 2007 Ohio case held that a contractor could not rely upon the Spearin doctrine
to assert a claim of implied warranty in the plans since the contract contained a no-
damages-for-delay clause. The Ohio Supreme Court held that, “[i]n order to hold in favor
of Dugan & Meyers, we would need, first, to find that the state had implicitly warranted
that its plans were buildable, accurate, and complete, and, second, to hold that the implied
warranty prevails over express contractual provisions.”73 A dissenting judge argued that
Spearin was applicable because, “the principal cause of the delay, as determined by the
finder of fact, was an excessive number of errors, omissions and conflicts in the design
documents furnished to bidders by the state . . . There were no shifting sands, no acts of
God, no surprising aquifers. As in Spearin, the designs themselves were the root of the
problem.” 74
The following is an example of a risk-shifting clause used by the City of Los
Angeles, Department of Public Works, in its Standard General Conditions (2007 edition).
This clause purports to make the contractor review all plans and specifications for errors
and notify the engineer, and to waive claims if the contractor fails to give notice:
00303 FAMILIARITY WITH PLANS AND SPECIFICATIONS (9/18/07) It shall be the responsibility of the Contractor to be thoroughly familiar with all details of the Project, including the work of the Contractor’s
41
forces and all Subcontractors. The Contractor shall call the following to the attention of both the Engineer and the Inspector in writing within twenty-four (24) hours of discovery, before any Work is performed: 1) Errors and omissions in the Plans and Specifications, including, but not limited to, code violations, typographical errors and notational errors where ambiguity or inadequate description exists; 2) Work on the Plans or in the Specifications which, if so constructed, would result in a conflict or interference with other Work or the Work of other trades, including the location of fixtures and equipment; 3) Existing improvements visible at the job site, for which no existing disposition is made on the Plans or in the Specifications but which could reasonably be assumed to interfere with the satisfactory completion of the improvements contemplated by the Plans and Specifications. Failure to notify shall constitute a waiver by the Contractor of any claim for delay or other damages occasioned by such defect. If the Contractor proceeds with the Work without instructions from the Engineer, the incorrect Work shall be removed and corrections made to comply with the Engineer’s instructions, at no cost to the City.
V. Conclusion. While it helps to have an undergraduate degree in architecture or engineering to
understand and read plans and specifications, most experienced construction lawyers
learn through practice. Once you know how to read the symbols and section marks, a set
of blueprints reveals itself as a well-organized road map to the construction of a project.
But just as lawyers cannot guarantee that their contracts will be free of ambiguities,
design professionals cannot warrant that a set of documents will be free of imperfections.
Contract language can add clarity to the process; however, construction lawyers need to
be familiar with the wide body of case law that has developed over the past century to
address the daily conflicts, errors and omissions contained in contract documents. While
technology has come a long way since the days of Alberti and the “Leaning Tower,” at
the end of the day we rely on humans, who are imperfect and who will continue to
produce documents which contain some degree of flaws.
42
Endnotes: 1 The Code of Hammurabi stated that, “If a builder builds a house for someone, and does not construct it properly, and the house which he built falls in and kills its owner, then the builder shall be put to death.” Another variation of this added that, “ If the owner's son dies, then the builder's son shall be put to death.” 2 See, e.g., 1 Kings 20:30 (New International Version). (a wall collapsed in the city of Aphek, killing 27,000 people); Job 1:18-20 (New International Version). (a house collapsed when struck by a “mighty wind,” killing the sons and daughters of Job) 3 Luke 6:49 (New International Version). (“But the one who hears my words and does not put them into practice is like a man who built a house on the ground without a foundation. The moment the torrent struck that house, it collapsed and its destruction was complete.”) 4 Klein v. Catalano, 437 N.E.2d 514, 525 (Mass. 1982). 5 Id. 6 Leon Basttista Alberti, On the Art of Building in Ten Books, pp. 320-321 (The MIT Press, 1988). 7 See e.g., Chubb Group of Ins. Co. v. C.F. Murphy Assoc., Inc., 656 S.W. 766, 780 (Mo. App. 1983). 8 Stanley Consultants, Inc. v. H. Kalicak Constr. Co., 383 F. Supp. 315, 319 (E.D. Mo. 1974); Rowe v. Moss, 656 S.W.2d 318, 321-22 (Mo. App. 1983). 9 Engineering News Record, p. 24 (June 17, 1991). 10 Architectural Graphics Standards, The American Institute of Architects (Eleventh edition). 11 The Architect’s Handbook of Professional Practice, John Wiley & Sons, Inc. (2008 edition). 12 See, e.g, Ford Hull-Mar Nursing Home, Inc. v. Marr, Knapp, Crawfis & Assoc., Inc., 740 N.E.2d 729, 733 (Ohio App. 7 Dist. 2000); Taylor, Thon, Thompson & Peterson v. Cannaday, 749 P.2d 63, 66 (Mont. 1988). 13 The Architect’s Handbook, note 11, supra, p. 541. 14 Id. 15 http://www.nibs.org/index.php/resources/standards
43
16 Robert Miller, “National BIM Standard Version 1, Part 1 – Out for Industry Review,” National Institute of Building Sciences. Retrieved February 20, 2009, from http://www.nibs.org/nbims.html. 17 Mike Squarzini, Mark Tamaro, Anjana Kadakia, Erleen Hatfield, and Tom Scarangello, “Changing the Way We Deliver Stadiums: Successes with the Washington Nationals, Yankees and Meadowlands Projects,” GoStructural.com, July 31, 2008. 18 Id.
19 FAR 52.236-21 - Specifications and Drawings for Construction (Feb 1997). 20 U.S. for Use of Los Angeles Testing Lab v. Rogers & Rogers, 161 F. Supp. 132 (S.D. Calif 1958) (concrete mix approved by architect, later found to be defective); Shoffner Industries, Inc. v. W.B. Lloyd Constr. Co., 257 S.W.2d 50 (N.C. App. 1979) (roof trusses collapsed after approved by architect); Detweiler Bros., Inc. v. John Graham & Co., 412 F. Supp. 416 (D.C. Wash. 1976) (steam pipes approved by architect, later rejected); Berkel & Co. Contractors, Inc. v. Providence Hospital, 454 S.2d 496 (Ala. 1984) (owner found to be responsible for architect’s negligent approval of concrete mix submitted by contractor, because architect is owner’s agent). 21 First National Bank of Akron v. Cann, 503 F.Supp. 419, 426 (N.D.Ohio 1980). 22 Fauss Construction, Inc. v. City of Hooper, 249 N.W.2d 478 (Neb. 1977). 23 Henningson, Durham & Richardson, Inc. v. Swift Bros. Constr. Co., 739 F.2d 1341 (8th Cir. 1984). 24 Waggoner v. W&W Steel Co., 657 P.2d 147 (Okla. 1982). 25 United States vs. Henke Construction Co., 157 F.2d 13 (8th Cir. 1946). 26 157 F.2d at 22. 27 Duncan v. Missouri Board for Architects, Professional Engineers and Land Surveyors, 744 S.W.2d 524 (Mo. App. 1988). 28 R.S.Mo. § 327.411 (note, this statute has since been revised). 29 The Architect’s Handbook of Professional Practice, section 3.92, John Wiley & Sons, Inc., p. 772 (1994 edition). 30 Case No. AR-84-0239, Hon. James A. Deutsch, Administrative Law Judge Opinion, State of Missouri, pp. 31-32, Nov. 15, 1985. 31 D.C. McClain, Inc. v. Arlington County, 452 S.E.2d 659 (Va. 1995).
44
32 See, e.g. “In Hyatt’s wake, greater caution,” Engineering News Record, Sept. 27, 1984, pp. 10-11; “Liability on Shop Drawings Still Unresolved”, Engineering Times, Nov. 1993. 33 Engineering News Record, Oct. 21, 1996, p. 17. 34 FCI Group, Inc. v. City of New York, 54 A.D.3d 171, 176, 862 N.Y.S.2d 352, 355-356 (N.Y.A.D. 1 Dept. 2008). 35 Dodson Aviation v. Rollins, Burdick, et al., 807 P.2d 1319, 1323 (Kan. App. 1991); Community Heating & Plumbing Co., Inc. v. Kelso, 987 F.2d 1575, 1579 (Fed. Cir. 1993). 36 Lobo Painting, Inc. v. Lamb Const. Co., 231 S.W.3d 256, 258 (Mo. App. E.D. 2007); Central Security Mutual Ins. Co. v. DePinto, 681 P.2d 15, 17 (Kan. 1984). 37 Thanet Corp. v. U.S., 591 F.2d 629, 633 (Ct. Cl. 1979). 38 See, e.g. Honey v. Barnes Hospital, 708 S.W.2d 686, 694 (Mo. App. 1986); Kennedy & Mitchell, Inc. v. Anadarko Prod. Co., 754 P.2d 803 (Kan. 1988). 39 Central SecurityMutual Ins. Co., 681 P.2d at 17. 40 Foltz v. Begnoche, 565 P.2d 592, 597 (Kan. 1977); see also Shelter Mutual Insurance Co. v. Williams, 804 P.2d 1374, 1379 (Kan. 1991). 41 346 F. 2d at 972-973. 42 Newsom v. U.S., 676 F.2d 647, 649 (Ct. Cl. 1982); WPC Enterprises, Inc. v. U.S., 323 F.2d 874, 876-77 (Ct. Cl. 1963). 43 Sturm v. U.S., 421 F.2d 723, 727 (Ct. Cl. 1970). 44 Twin River Construction Co. v. Public Water District, 653 S.W.2d 682, 692 (Mo. App. 1983); Structural Systems, Inc. v. Hereford, 564 S.W.2d 62 (Mo. App. 1978). 45 WPC Enterprises, Inc., 323 F.2d 874, 876-77. 46 945 F. 2d at 390. 47 Beacon Const. Co. v. U.S., 314 F.2d 501, 504 (Ct. Cl. 1963). 48 Mountain Home Contractors v. U.S., 425 F.2d 1260, 1264 (Ct. Cl. 1970). 49 Interwest Const. v. Brown, 29 F.3d 611, 614 (Fed. Cir. 1994).
45
50 WPC Enterprises, Inc., 323 F.2d at 877. 51 Randolph Engineering Co., v. U.S., 367 F.2d 425, 430 (Ct. Cl. 1966). A subcontractor’s reliance can be imputed to the prime contractor if the prime contractor can show that it reasonably relied on the subcontractor’s interpretation at the time of bidding. J.W. Bateson Co., Inc., VABCA No. 3482, 93-3 BCA 26,115. 52 Walnut Creek Elec. v. Reynolds Const. Co., 263 Cal.App.2d 511, 515, 69 Cal.Rptr. 667, 669 (Cal. App. 1968). 53 Rubin v. Coles, 253 N.Y.S. 808, 811 (City Ct. N.Y. 1931). 54 Luxurious Swimming Pools, Inc. v. Tepe, 379 N.E.2d 999, 995 (Ind. App. 3d Dist. 1978); see also, Allied Contractors, Inc. v. U.S., 381 F.2d 995, 1000 (Ct. Cl. 1967) (contractor who knows or should know of obvious error in plans or specifications must call error to owner’s attention). 55 Appeal of Mayer Construction Company, DOTCAB No. 1688, 1986 WL 19629 (D.O.T.C.A.B.). 56 Southwest Engineering Co. v. Reorganized School District R-9, 434 S.W.2d 743 (Mo. App. 1968).
57 FAR 52.236-21 - Specifications and Drawings for Construction (Feb 1997). 58 St. Louis Testing Laboratories, Inc. v. Mississippi Valley Structural Steel Co., 254 F. Supp. 47 (E.D. Mo. 1966), aff’d, 375 F.2d 565 (8th Cir. 1967). 59 McCarthy Brothers Construction Co. v. Pierce, 832 F.2d 463 (8th Cir. 1987). 60 Albers v. Nelson, 809 P.2d 1194 (Kan. 1991). 61 See, e.g. Big Chief Drilling Co. v. U.S., 26 Cl. Ct. 1276 (1992). 62 See, e.g., The Owner’s Warranty of the Plans and Specifications for a Construction Project, Pub. Contract L.J., Vol. 14, No. 2, p. 240 (Feb 1984). 63 Construction Drawings that Work – or Maybe Not? 3 Liberty U. L. Rev. 183, 191 (2009); Leaderman, The Spearin Doctrine: It Isn't What It Used To Be, 16:4 The Construction Lawyer (Oct. 1996). 64 See, e.g., Kansas Turnpike Auth. v. Abramson, 275 F.2d 711, 713 (10th Cir. 1960); Kelley v. Bank Bldg. & Equip. Corp., 453 F.2d 774, 777 (10th Cir. 1972); Miller v. City of Broken Arrow, 660 F.2d 450, 457 (10th Cir. 1981). 65 Sanders Company Plumbing & Heating, Inc. v. City of Independence, 694 S.W.2d 841, 848 (Mo. App. 1985).
46
66 573 S.W. 2d at 322. 67 411 P. 2d at 154-55. 68 573 S.W.2d at 322 (emphasis added). 69 Accord, Kubby v. Crescent Steel, 466 P.2d 753, 754 (Ariz. 1970). (emphasis added). 70 Kelley v. Bank Building & Equip. Co., 453 F.2d 774, 779 (10th Cir. 1972), citing Spearin. 71 Nordin Constr. Co. v. City of Nome, 489 P.2d 455, 470 n. 26 (Alaska 1971). 72 Lewis v. Anchorage Asphalt Paving Co., 535 P.2d 1188, 1199 (Alaska 1975).
73 Dugan & Meyers Constr. Co., Inc. v. Ohio Dept. of Adm. Servs., 864 N.E.2d 68, 75 (Ohio 2007). 74 Id. at 79. Ohio enacted a law barring no-damages-for-delay clauses in 1998, which did not apply to this case. See Ohio Rev. Code Ann. § 4113.62 (C)(1).