h.tauregtb december 20041 b-field mapping. h.tauregtb december 20042 schedule install equipment: may...
TRANSCRIPT
![Page 1: H.TauregTB December 20041 B-Field Mapping. H.TauregTB December 20042 Schedule Install equipment: May 2005 Start mapping: mid June 2005 Finish mapping:](https://reader036.vdocuments.site/reader036/viewer/2022072016/56649ef55503460f94c08dd4/html5/thumbnails/1.jpg)
H.Taureg TB December 2004 1
B-Field Mapping
![Page 2: H.TauregTB December 20041 B-Field Mapping. H.TauregTB December 20042 Schedule Install equipment: May 2005 Start mapping: mid June 2005 Finish mapping:](https://reader036.vdocuments.site/reader036/viewer/2022072016/56649ef55503460f94c08dd4/html5/thumbnails/2.jpg)
H.Taureg TB December 2004 2
Schedule
• Install equipment: May 2005
• Start mapping: mid June 2005
• Finish mapping: August 2005, latest
![Page 3: H.TauregTB December 20041 B-Field Mapping. H.TauregTB December 20042 Schedule Install equipment: May 2005 Start mapping: mid June 2005 Finish mapping:](https://reader036.vdocuments.site/reader036/viewer/2022072016/56649ef55503460f94c08dd4/html5/thumbnails/3.jpg)
H.Taureg TB December 2004 3
Mapping programme
• L3 and dipole at two polarities– Only ++ and -- combination
• L3 at 0.2 and 0.5 Tesla– Dipole powered always at same level
• L3 alone – At 0.2 and 0.5 Tesla and both polarities
• In L3 – Space Frame volume– EMC, HMPID, PHOS volume
![Page 4: H.TauregTB December 20041 B-Field Mapping. H.TauregTB December 20042 Schedule Install equipment: May 2005 Start mapping: mid June 2005 Finish mapping:](https://reader036.vdocuments.site/reader036/viewer/2022072016/56649ef55503460f94c08dd4/html5/thumbnails/4.jpg)
H.Taureg TB December 2004 4
Grid size
• Dipole– 80 mm in x, y, z
• L3– 100 mm in r and z– 2° in φ for r > 2 m– 4° in φ for r < 2 m
![Page 5: H.TauregTB December 20041 B-Field Mapping. H.TauregTB December 20042 Schedule Install equipment: May 2005 Start mapping: mid June 2005 Finish mapping:](https://reader036.vdocuments.site/reader036/viewer/2022072016/56649ef55503460f94c08dd4/html5/thumbnails/5.jpg)
H.Taureg TB December 2004 5
Grid size
• Fine grid as above
• Coarse grid – Increase step size by factor 3
• In φ and z for L3• In z for dipole
![Page 6: H.TauregTB December 20041 B-Field Mapping. H.TauregTB December 20042 Schedule Install equipment: May 2005 Start mapping: mid June 2005 Finish mapping:](https://reader036.vdocuments.site/reader036/viewer/2022072016/56649ef55503460f94c08dd4/html5/thumbnails/6.jpg)
H.Taureg TB December 2004 6
Mapping scheme
![Page 7: H.TauregTB December 20041 B-Field Mapping. H.TauregTB December 20042 Schedule Install equipment: May 2005 Start mapping: mid June 2005 Finish mapping:](https://reader036.vdocuments.site/reader036/viewer/2022072016/56649ef55503460f94c08dd4/html5/thumbnails/7.jpg)
H.Taureg TB December 2004 7
Mapping work
• Continuous, 24 h / 24 h
• Team of at least 3
• Set up changes during normal working hours
• Time estimate to be worked out
![Page 8: H.TauregTB December 20041 B-Field Mapping. H.TauregTB December 20042 Schedule Install equipment: May 2005 Start mapping: mid June 2005 Finish mapping:](https://reader036.vdocuments.site/reader036/viewer/2022072016/56649ef55503460f94c08dd4/html5/thumbnails/8.jpg)
H.Taureg TB December 2004 8
Hardware
• Support structure to be adapted for dipole
• Support structure to be adapted for L3
• Measuring arms to be constructed for L3