how to relocate a neutron beam instrument to the other
TRANSCRIPT
![Page 1: How to relocate a Neutron Beam Instrument to the Other](https://reader034.vdocuments.site/reader034/viewer/2022042417/625f672c79c1532c5d43088b/html5/thumbnails/1.jpg)
How to relocate a Neutron Beam Instrument to the Other Side of the GlobePart 2, Installation and Commissioning
Stewart Pullen, Dr. Anton Le Brun (ACNS)DEMIN 2018, PSI
16th September
![Page 2: How to relocate a Neutron Beam Instrument to the Other](https://reader034.vdocuments.site/reader034/viewer/2022042417/625f672c79c1532c5d43088b/html5/thumbnails/2.jpg)
Brief overview of Part 1 The closure of the BER-II Research Reactor in 2020 means that
the HZB are considering the transfer of their neutron scattering instruments to other institutions.
An agreement was signed between ANSTO and HZB in September 2015 for the transfer of the BioRef reflectometer (V18) to ANSTO by December 2016.
The agreement stipulates that ANSTO is responsible for the transfer of BioRef to Australia
We planed with HZB to disassemble and ship the instrument in September 2016
The instrument has been renamed SPATZ (Sparrow).
![Page 3: How to relocate a Neutron Beam Instrument to the Other](https://reader034.vdocuments.site/reader034/viewer/2022042417/625f672c79c1532c5d43088b/html5/thumbnails/3.jpg)
Brief overview of Part 1
![Page 4: How to relocate a Neutron Beam Instrument to the Other](https://reader034.vdocuments.site/reader034/viewer/2022042417/625f672c79c1532c5d43088b/html5/thumbnails/4.jpg)
What has happened since then?The instrument was delivered to ANSTO 9th February 2017.
![Page 5: How to relocate a Neutron Beam Instrument to the Other](https://reader034.vdocuments.site/reader034/viewer/2022042417/625f672c79c1532c5d43088b/html5/thumbnails/5.jpg)
What has happened since then?Building the CG2B beam line to feed SPATZ.
31m of guide160X50mm m=3 top, bottom m=2 and 2.5 sides up to 24.3m50X30mm m=3 top, bottom m=1 sides 24.3-31m
![Page 6: How to relocate a Neutron Beam Instrument to the Other](https://reader034.vdocuments.site/reader034/viewer/2022042417/625f672c79c1532c5d43088b/html5/thumbnails/6.jpg)
What has happened since then?Installation and alignment of the SPATZ Instrument.
1.Location of the Instrument Plinth
2. Installation and commissioning of the chopper system
3. Installation and alignment of the instrument guide system
4. Installation of infrastructure
5. Installation of shielding
6. Installation of enclosure walls
7. Boron lining of enclosure walls
![Page 7: How to relocate a Neutron Beam Instrument to the Other](https://reader034.vdocuments.site/reader034/viewer/2022042417/625f672c79c1532c5d43088b/html5/thumbnails/7.jpg)
What has happened since then?Installation and alignment of the SPATZ Instrument.
![Page 8: How to relocate a Neutron Beam Instrument to the Other](https://reader034.vdocuments.site/reader034/viewer/2022042417/625f672c79c1532c5d43088b/html5/thumbnails/8.jpg)
PlanningMuch like the disassembly, the assembly was planned and documented with instructions.
![Page 9: How to relocate a Neutron Beam Instrument to the Other](https://reader034.vdocuments.site/reader034/viewer/2022042417/625f672c79c1532c5d43088b/html5/thumbnails/9.jpg)
Some Technical ChallengesModification to existing infrastructure
![Page 10: How to relocate a Neutron Beam Instrument to the Other](https://reader034.vdocuments.site/reader034/viewer/2022042417/625f672c79c1532c5d43088b/html5/thumbnails/10.jpg)
Some Technical ChallengesModification to existing infrastructure
Design complied with AS1657, and associated standards.
![Page 11: How to relocate a Neutron Beam Instrument to the Other](https://reader034.vdocuments.site/reader034/viewer/2022042417/625f672c79c1532c5d43088b/html5/thumbnails/11.jpg)
Some Technical ChallengesMaintenance access / emergency egress for Bilby.
![Page 12: How to relocate a Neutron Beam Instrument to the Other](https://reader034.vdocuments.site/reader034/viewer/2022042417/625f672c79c1532c5d43088b/html5/thumbnails/12.jpg)
Some Technical ChallengesLift Point Testing
Test load = measured mass X 1.25 X 1.1
In this case measured mass = 10,600kgTherefore test load minimum =14,575kg
![Page 13: How to relocate a Neutron Beam Instrument to the Other](https://reader034.vdocuments.site/reader034/viewer/2022042417/625f672c79c1532c5d43088b/html5/thumbnails/13.jpg)
Some Technical Challenges Shielding Wall between SPATZ and Bilby
![Page 14: How to relocate a Neutron Beam Instrument to the Other](https://reader034.vdocuments.site/reader034/viewer/2022042417/625f672c79c1532c5d43088b/html5/thumbnails/14.jpg)
Seismic conditions (Static equivalent):Horizontal accel. = 0.09gVertical accel. = 0.06g
Max axial Load for M20 = 98kN (Class 4.6) (AS4291)Max Shear for M20 calculated following von Mises yield criterion for pure shear = 34kN
Some Technical Challenges Shielding Wall between SPATZ and Bilby
7.5kN Axial5kN Shear
![Page 15: How to relocate a Neutron Beam Instrument to the Other](https://reader034.vdocuments.site/reader034/viewer/2022042417/625f672c79c1532c5d43088b/html5/thumbnails/15.jpg)
Some Technical ChallengesSafety Approvals One more left to gain approval for operational status of
the SPATZ Instrument, to be completed Jan 2019
Administrative
![Page 16: How to relocate a Neutron Beam Instrument to the Other](https://reader034.vdocuments.site/reader034/viewer/2022042417/625f672c79c1532c5d43088b/html5/thumbnails/16.jpg)
What will happen next? Hot commissioning licence from our regulator ARPANSA (Oct 2019) Hot commissioning activities:
Shielding integrity testing. (Is the instrument shielded adequately?) Safety system testing. (Does the SIS control access as intended?) Instrument functionality/performance testing. (Does the instrument perform
as expected?) Operating licence from our regulator ARPANSA (April 2019) Friendly user operations (June 2019) User operations (September 2019, next user round)
![Page 17: How to relocate a Neutron Beam Instrument to the Other](https://reader034.vdocuments.site/reader034/viewer/2022042417/625f672c79c1532c5d43088b/html5/thumbnails/17.jpg)
Project TeamAnton LeBrunStewart PullenJason ChristoforidisAndrew McGregorDavid RoachJohn AffleckMatthew BellMartin JonesFrank DarmannScott OlsenParis Constantine
![Page 18: How to relocate a Neutron Beam Instrument to the Other](https://reader034.vdocuments.site/reader034/viewer/2022042417/625f672c79c1532c5d43088b/html5/thumbnails/18.jpg)
Thank you to the HZB team for their support!Markus TrappWerner GrafRolf HellhammerRoland SteitzAnke Kaysser-Pyzalla
![Page 19: How to relocate a Neutron Beam Instrument to the Other](https://reader034.vdocuments.site/reader034/viewer/2022042417/625f672c79c1532c5d43088b/html5/thumbnails/19.jpg)
Companies with significant inputs!
JülichFelix MüllerGregor Lang
SwissNeutronicsChristian SchanzerNico SchäpperCollin Mueller
MirrotronLászló KrisztiánZsombor SántaZsolt Ludányi
Rörh + SolbergDiemo Schallehn
Stambe EnterprisesJoe StambeFrank Stambe
Ulrich AluminiumSimon Williams
![Page 20: How to relocate a Neutron Beam Instrument to the Other](https://reader034.vdocuments.site/reader034/viewer/2022042417/625f672c79c1532c5d43088b/html5/thumbnails/20.jpg)
Questions???Thank you
![Page 21: How to relocate a Neutron Beam Instrument to the Other](https://reader034.vdocuments.site/reader034/viewer/2022042417/625f672c79c1532c5d43088b/html5/thumbnails/21.jpg)
Lessons learnt Engage companies as early as possible! Communicate communicate communicate! Record what actually happened during installation! (Beyond
as builts) Don’t forget fittings an fixtures when preparing activities