Page 1: Housing Project

PRESENTATION

AFOHS DETT. MALIR

Prepared & Presented by: M. Sohail Azeem

Page 2: Housing Project

SEQUENCE

• INTRODUCTION

• RECOMMENDATION FOR COST CURTAILMENT

• RECOMMENDATION FOR IMPROVEMENT

• CONCLUSION

Page 3: Housing Project

SDH

• TOTAL AREA 350 SQ. YARDS

• TOTAL COVERED AREA 3000 SFT.

• RATE PER SDH Rs.12,20,000.00

Page 4: Housing Project

I H

• TOTAL AREA 500 SQ. YARDS

• TOTAL COVERED AREA 4000 SFT.

• RATE PER I H Rs.15,50,000.00/=

Page 5: Housing Project

COST CURTAILMENT

• 01 X RCC PIPE LINE OF 6” DIAMETER MAY BE DELETED

• TOTAL PIPE IN USE 32 METER

• RATE Rs.130.00 PER METER

• TOTAL COST Rs.4,160.00

• TOTAL SAVING Rs.2,080.00

RCC PIPE

Page 6: Housing Project

• IF WE DELETE ONE RCC PIPELINE, 05 X MAIN HOLES AND 05 X C.I.COVER WOULD ALSO BE DELETED.

• COST OF 01XMAIN HOLE Rs.1500.00• COST OF 01XC.I.COVER Rs.500.00• TOTAL SAVING Rs.10,000.00

MAIN HOLES / C.I. COVER

Page 7: Housing Project

• SEPTIC TANK MAY BE DELETED FROM THE DESIGN

• COST Rs.10,000

SEPTIC TANK

Page 8: Housing Project

• STEEL RAILING OF BACK SIDE TERRACE MAY BE DELETED

• WALL OF 3’-6’’ MAY BE RAISED INSTEAD

• TOTAL RAILING IN USE 25 RFT

• RATE Rs 400/= RFT

• TOTAL COST Rs 10,000/=

• BLOCK MASONARY Rs.2000/=C.M TOTAL COST(1.5 CUM) RS.3000/=

• DIFFERENCE OF COST RS.7000/=

STEEL RAILING

Page 9: Housing Project

• BACK SIDE WALL OF FRONT TERRACE HAS A PIPE RAILING

• MAY BE REPLACED WITH BLOCK MASONARY

• RATE OF RAILING RS.500/- RFT

• COST ( 5 RFT) RS.2500/-

• BLOCK MASONARY Rs.670/-• COST SAVING RS.1830/-

PIPE RAILING

Page 10: Housing Project

• CLAD STONE MAY BE REPLACED WITH GRAFFIATTO

• RATE OF CLAD STONE RS.30/-SFT

• RATE OF GRAFFIATTO RS.12/- SFT

• TOTAL AREA 500 SFT• COST OF CLAD STONE RS.15000/-

• COST OF GRAFFIATTO RS.6000/-

• COST SAVING RS.9000/=

CLAD STONE

Page 11: Housing Project

• M S SHEET/ G I OF 16 GAUGE MAY BE REPLACED WITH 18 GAUGE DOOR FRAMES

• RATE OF 16 GAUGE Rs.75/=RFT• RATE OF 18 GAUGE Rs.65/=RFT• TOTAL USAGE 300 RFT• COST OF 16 GAUGE Rs. 22500/= • COST OF 18 GAUGE Rs 19500/=• COST SAVING Rs 3000/=

M.S. SHEET / G.I.

Page 12: Housing Project

• DEODAR WOOD IS USED FOR BIDDING/GOLAS • MAY BE REPLACED WITH PERTAL/GOLDEN

TEAK• RATE OF DEODAR WOOD RS.2500/- CFT

• RATE OF PERTAL RS.700/- CFT

• TOTAL REQUIREMENT 17 CFT

• COST OF DEODAR RS.42000/-

• COST OF PERTAL RS.12000/-

• COST SAVING RS.30,000/-

WOODEN BIDDING

Page 13: Housing Project

. WOODEN STAIR RAILING MAY BE REPLACED WITH ALLUMINIUM RAILING

• RATE OF WOOD RS.45O/-RFT

• RATE OF ALLUMINIUM RS.250/-RFT

• TOTAL REQUIREMENT 30 RFT

• COST OF WOOD RS.13500/-

• COST OF ALLUMINIUM RS.7500/-

• COST SAVING RS.6000/-

STAIR RAILING

Page 14: Housing Project

• 4’’ DIA UPVC PIPES MAY BE REPLACED WITH 3’’

• RATE OF 4’’ DIA PIPE RS.145/-R.M.

• RATE OF 3’’ DIA PIPE RS.100/-R.M.

• TOTAL CONSUMPTION 36 R.M.

• COST OF 4’’ DIA PIPE RS.5220/-

• COST OF 3’’ DIA PIPE RS.3600/-

• COST SAVING RS.1620/-

UPVC PIPE

Page 15: Housing Project

• TOTAL OF 06xUPVC PIPES ARE LAID FROM THE ROOF MAY BE DELETED

• 3’’ DIA UPVC PIPES OF THE TWO BATH ROOMS ON THE FIRST FLOOR MAY BE EXTENDED UPTO ROOF AND AN ELBOW MAY BE FIXED FOR THE RAIN WATER

• COST SAVING RS.4400/-

UPVC PIPE(RAIN WATER)

Page 16: Housing Project

• CAR PORCH ROOF OF SDH MAY BE INCREASED IN HEIGHT UPTO DRAWING ROOM SLAB

• WOODEN STAIR RAILING MAY BE REPLACED WITH ALLUMINIUM

• GRAFFIATTO OF DIFFERENT SHADES MAY BE USED FOR FRONT ELEVATION IN CASE STONE CLADDING IS DELETED

• SEPTIC TANK IN SDH MAY BE SHIFTED OUT SIDE THE BOUNDARY WALL (IF IT IS NOT DELETED)

RECOMMENDATIONS FOR IMPROVEMENT

Page 17: Housing Project

CONCLUSION

• THE RECOMMENDATIONS MADE IF INCORPORATED WILL SAVE APPROX. Rs 85000/= PER HOUSE