HKATS Upgrade to OMex 17.1 HKATS Upgrade to OMex 17.1 Media BriefingMedia Briefing
提升提升 HKATSHKATS 電子交易系統軟件至電子交易系統軟件至 OMex 17.1OMex 17.1傳媒簡布會傳媒簡布會
24-09-200324-09-2003
Agenda
Introduction Objectives & Benefits Project Overview External Test Programme Results of Simulated Trading Rehearsal (STR) Fallback Contingency Plan Q & A
Introduction
Hong Kong Futures Automated Trading System’s (HKATS) OMex System Upgrade From Ver. 15.2 to Ver. 17.1 DC
Previous Upgrade January 2002 Software upgrade from Click 3 to Click 5
Prerequisite for DCASS, Derivatives Clearing and Settlement System
Objectives
Improve infrastructure of the derivatives market
Higher performance
Higher efficiencies
Prerequisite for implementation of DCASS
Benefits
1. Erroneous Order Protection Availability of Central Order Size Limit
2. Default account by instrument type
3. Customised Tick Size
4. Compatibility with DCASS for an integrated trading & clearing operation
5. Others
Project Overview
• Requirement Analysis Completed (Nov. 02)
• System Development Completed (Apr. 03)
• Internal Testing Completed (May ~Jun. 03)
• Test contents reviewed by an Completed (Jul. 03) independent third party
• External Testing Completed (Aug. ~ Sep. 03)
• OMex System17.1 DC Go-Live 6 October 2003
External Test Programme
1. 2 Production Readiness Tests (PRT); 9 August 2003 : 1st PRT with Fallback Test from 17.1 DC to 15.2 16 August 2003 : 2nd PRT with Backup System Failover Test
Selected pilot Exchange Participants were invited to join these PRTs
2. One-day Simulated Trading Rehearsal (STR); 6 September 2003: 2 Market Rehearsals with Fallback Test from 17.1
DC to 15.2
117 Exchange Participants (EP) had participated in these rehearsals
STR Results
117 Exchanges Participants had participated
System stressed to 3 times peak loading
System stressed highest to 5 times peaking transactions
Performance normal, no abnormality was identified
STR Results
Favourable evaluations from participating EPs: Average 97.5% did not encounter any PC or network
problems in both MRs
Average 98.5% viewed that system response time was comparable to current production standards in both MRs
97% viewed that the services provided by the HKATS Helpdesk meet their level of satisfaction
Over 99% believed that the OMex 17.1 DC was ready to be put on production
Fallback Contingency Plan
Overview
A stabilisation period of 2 weeks after software upgrade
Occurrence of “unexpected” system failure that is unlikely be resolved within 24 hours
Fallback from OMex v. 17.1 DC to v. 15.2-3 in 3 hours Intra day fallback: before 11:00 am, fallback in
afternoon session Next day fallback: after 11:00 am, fallback in next day
Click5.3
Click5.2
Participants Exchange IT
OMex 15.2
OMex 17.1
Fallback procedure
15.2
17.1
15.2
17.1
NetworkGateway
TunnelServer
Price Price Reporting Reporting SystemSystem
Clearing Clearing HousesHouses
Fallback Contingency PlanCommunication:
Exchange Participants will be notified via
1. Market Message Window2. HKATS Email System3. Exchange News System4. Participants Email System5. Group Paging System
Public investors will be notified via
1. Press announcement2. HKEx Website (www.hkex.com.hk)
Fallback Contingency PlanPreparation:
Well tested and drilled by the Exchange
Well rehearsed by Exchange Participants
Briefings, practices, drilled in PRTs/STR
Valid for 2 weeks until 17 October 2003
Scheduled Launch DateScheduled Launch Date
Monday, 6 October 2003Monday, 6 October 2003
Q & A