High Speed 2 – Rapid Collaborative Project Planning

11th October 2012

Jon Kerbey

• Head of Management Systems, HS2• Previous employment:

Systems Architect - Major Projects, Halcrow/CH2M Hill

European Development Director, AECOM

Agenda

• Introduction & Background• Integrated Systems Environment• EPPM Cloud Solution• Lessons Learned (so far)• Q&A

HS2 INTRODUCTION & BACKGROUND

What is HS2?• Backbone of a

new transport system

• Truly national network

• Phase 1: London to Birmingham

• Phase 2: Manchester, Leeds and Heathrow

Scale: phase 1

• 140 miles long• Up to 14 trains an

hour• Reduced journey

times• Travel up to 225 mph• Will support around

40,000 jobs

HS2 organisationNot fully representative

Purpose: Phase 1• Progress next stage of engineering, design

and environmental work• Develop and consult on the Environmental

Statement• Deposit the hybrid Bill in Parliament by the

end of 2013

Goal and Strategic Objectives: Phase 1Spring 2012 Engagement programme along phase 1

route on Environmental Impact Assessment issues

After Summer recess in September 2012 Consultation with statutory bodies on the safeguarding zone for phase 1

Spring 2013 Consultation on draft Environmental Statement for phase 1 including design refinement

End of 2013 Submission of hybrid Bill

2015 Target date for Royal Assent for the Hybrid Bill, containing legal powers to construct HS2

2017-2025 Construction period (starts and ends at different times and at different points along the route)

2024-2026 Commissioning and testing

2026 Phase 1 line opens to passengers

Integrated Systems Environment

IM Challenges

Robust, flexible systems

• Stakeholder interactions• Design development• Environmental mitigation• Requirements• Change

Collaborative environment

S E T T I N G U P F O R T H E L O N G T E R M

• Efficiency savings• Integrated information model• Rapid response• Informed decision making

Interim Environment

• Hosted outside of the HS2/DfT environment Critigen (Denver) Bentley (Ireland)

• Short term solution enabling HS2 to “hit the ground running”

• ~20Tb data in 7 months

Managed Service Environment

• Hosted in the UK• Full integration between systems• Single Sign On• ~50Tb data anticipated by

October 2013• Built for the future

Integrated Systems

Primavera P6 Client

SharePoint

ESRIArcGIS

Design, production and review applications

Primavera Risk Analysis

Microsoft Office

Integratedrisk

management

Integrated cost

management

Integrated reporting

Integrated requirements management

Integrated change

management

ProjectWise

Integrated Systems

15UKOUG Primavera Conference 2012

Office applications

Design applications

ProjectWise

Enterprise Bridge (eB)

GISPrimavera(EPPM)

Cost system

Configuration ManagementAsset ManagementDocument ProductionDocument ControlChange ControlContract Administration

Geospatial functions(Environmental,

Land Referencing etc.)

CAD design2D and 3D

Schedule andprogramme controlRisk Management

Cost control

SharepointIntranetand Dashboards

Time (4D) andCost (5D) data

WebsiteReleased Documentsand Data

Publication for external consumption

Reporting and publication for internal consumption

ARM

@Risk

PRA

StakeholderManagement

Risk data

Integrated Systems

16UKOUG Primavera Conference 2012

• Simple interim systems - 100 days

• Migration of historic data creates starting point

• “Single source” of truth

• Supports quick, effective decision making

Value for money

• Reduces cost and risk of rework

• Enables the exchange of ideas and information in an open environment

• Use best practices that are scalable to future phases

• Saves cost and time in re-development

Hit the Ground Running

Accurate, Timely Reporting

Collaborative Tools

Long Term Solution for Development Phase

HS2 EPPM CLOUD SOLUTION

John Bennett

• Critigen EPPM Practice Manager• Previous employment:

Fujitsu T-Mobile Network Rail

• Introduced ‘P3e’ to Network Rail at version 3.5 in 2003

• Helped and supported many companies since with their P6 implementations

EPPM Cloud Model

Mobilisation

HS2 Requirements

& Desired Outcomes

SystemSet-Up

ToolsetConfiguration

Training

SupportService

Management

HS2 Requirements & Desired Outcomes

• Single project controls platform

• Access for the HS2 team and partners

Mobilisation

HS2 Requirements

& Desired Outcomes

SystemSet-Up

ToolsetConfiguration

Training

SupportService

Management

System Set-Up

• Infrastructure• Oracle Licenses via

BPO (subscription)• Software• HS2 IT changes (Java

versions etc)

Mobilisation

HS2 Requirements

& Desired Outcomes

SystemSet-Up

ToolsetConfiguration

Training

SupportService

Management

Toolset Configuration

• Security• EPS / WBS / OBS• Dashboards• Reports

Mobilisation

HS2 Requirements

& Desired Outcomes

SystemSet-Up

ToolsetConfiguration

Training

SupportService

Management

Training

• Dashboards• Administration• Reports

Mobilisation

HS2 Requirements

& Desired Outcomes

SystemSet-Up

ToolsetConfiguration

Training

SupportService

Management

Support

• 24x7 Helpdesk• Super User extension• No HS2 support

resources e.g. DBA

Mobilisation

HS2 Requirements

& Desired Outcomes

SystemSet-Up

ToolsetConfiguration

Training

SupportService

Management

Service Management

• Lessons Learned• Continual Improvement• Business Engagement

(users & stakeholders)• Future Requirements

Identification

Collaboration

HS2 Requirements & Desired Outcomes

SystemSet-Up

ToolsetConfigurationTraining

SupportService

Management

• 3rd party IT configuration

• Firewalls

• PSC access

• Security• Access

• Advice & Guidance• Activity Codes

• Support to increased user base

Upgrades

HS2 Requirements & Desired Outcomes

SystemSet-Up

ToolsetConfigurationTraining

SupportService

Management

• Release Management

• Internal Testing & QA

• Analyse Technical Impacts

• P6 Release 8.1 -> 8.2• Service Packs• Routine Maintenance

• Analyse Business Impacts

• Ensure no impact to layouts, reports & dashboards

• Analyse user training needs

• No user changes with this release

• Analyse technical and business support requirements

• No impact with the current upgrade

The Future• Increased User Base• Integration

• Tilos (Linear Planning)• Esri ArcGIS (Spatial Analysis)• Cost Management• Risk Management• Change Management• Bentley ProjectWise• BIM

• Increased Collaboration across Stakeholders

• Upgrades• Managed releases of Primavera P6

Proactively Address Future HS2 Requirements

Lessons Learned (so far)......

• Diverse range of user capability• Creating working practices via a

collaborative approach takes longer but receives wider adoption in the long run

• Consistency has to be enforced through formal processes and procedures - anything informal is likely not to be adhered to

UKOUG Primavera Conference 2012

Summary

• P6 is part of the HS2 Integrated System• Universal Access & Enhanced

Collaboration All working in the same environment Access from all locations

• Single Source of Truth Consistent Dashboards & Reports reflect true

progress Standardisation & Control across the major

programme

Key Message

HS2 are in the business of designing and building a rail

network not running IT applications

No need to operate data centres or setup and support applications for

specialist tools like Primavera

QUESTIONS