high purity water project presentation no unplanned downtime

59
Case Study New High Purity Water System Technologies Deliver Reliability & Sustainability for GSK 1

Upload: scwalter

Post on 02-Jul-2015

195 views

Category:

Technology


1 download

DESCRIPTION

Installation of a High Purity Water and WFI system with no unplanned downtime. Latest available technology including online monitoring Microbial Detection, Reduced water consumption with start / stop / sanitize cycles of water pretreatment equipment. Both systems designed with full redundancy to provide reliability.

TRANSCRIPT

Page 1: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting  

Case Study ‐ New High Purity Water System Technologies Deliver 

Reliability & Sustainability for GSK

1

Page 2: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   2

BRIAN LIPKO, PESenior Project Manager Hargrove Life Sciences

BRIAN TERMINE, PEMaintenance Engineering Manager GlaxoSmithKline

STEVE WALTER, CPIPProcess Systems Technology Specialist Hargrove Life Sciences

PRESENTERS

Page 3: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting  

ACKNOWLEDGMENTS

RANDY MINTO, PE,  Program Manager, GlaxoSmithKline

DAN D’AQUILA, PE, Director of Engineering & Validation, GlaxoSmithKline

ED STEVENS, Engineering Manager, GlaxoSmithKline

ALEX TANJUTCO, Validation Project Manager, GlaxoSmithKline

TED DOMBROWSKI, Senior Project Engineer, Arcadis (on behalf of GSK)

ROBERT HOEPPNER, Project Executive, Henderson Constructors, Inc.

MIKE BILLUPS, Project Manager, Henderson Constructors, Inc.

Page 4: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting  

Introduction

AGENDA

Execution Results

BackgroundObjectivesChallenges

BenefitsLessons Learned

Summary

DesignConstructionQualification

Page 5: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting  

Introduction

INTRODUCTION

Execution Results

BackgroundObjectivesChallenges

BenefitsLessons Learned

Summary

DesignConstructionQualification

Page 6: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   6

CTM (Clinical Trial Materials) 

Facility 

Manufactures purified drug substances for 

clinical trials worldwide

INTRODUCTION:  BACKGROUND

Page 7: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   7

INTRODUCTION:  BACKGROUND

Existing HPW & WFI Systems Obsolete

Parts no longer Available

Insufficient Capacity for Future 

Expansion or Production Increase

Costly Systems Not Energy Efficient

Increased             Plant downtime Risk due to insufficient 

equipment reliability

Page 8: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   8

INTRODUCTION:  BACKGROUND

ProjectScope 

Replace 2 Obsolete Water Systems

HPWHigh Purity    

Water

WFIWater for Injection

New Reliable       System Design

Supply HPW to  Biopharm   Development Pilot Plant

Change System Configuration from       3 to 2 Pumps

Replace WFI Control Panel

Install Redundant VC Stills

Page 9: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting  

INTRODUCTION:  OBJECTIVES

DELIVER SUSTAINABILITY

REDUCE WATER & ENERGY USAGE

DELIVER SUSTAINABILITY

REDUCE WATER & ENERGY USAGE

REPLACE OBSOLETE EQUIPMENT

REPLACE OBSOLETE EQUIPMENT

PROVIDE RELIABILITY THROUGH REDUNDANCY

PROVIDE RELIABILITY THROUGH REDUNDANCY

NO IMPACT TO ON‐GOING OPERATIONS

NO IMPACT TO ON‐GOING OPERATIONS

INCREASE SUPPLY& 

STORAGE CAPACITY

INCREASE SUPPLY& 

STORAGE CAPACITY

Page 10: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting  

INTRODUCTION:  OBJECTIVESRELIABILITY THROUGH REDUNDANCY

10

re∙dun∙dantserving as a duplicate for preventing failure of an entire system 

HPW WFI Multi‐Media Filters Softeners Carbon Filters RO/CDI Skid Tank Nitrogen 

Filters Distribution Pumps

Vapor Compression Stills

Tank Vent Filters Distribution 

Pumps

No Unplanned Downtime

Page 11: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   11

INTRODUCTION:  OBJECTIVESINCREASE SUPPLY & STORAGE CAPACITY

Generation and Storage Capacity

Insufficient during Maintenance Activities

Need to be Adept & Flexible

Accommodate Emerging Technologies in Manufacturing

Generation Capacity Bottlenecked

Required Daily Water Usage Planning Activities

CLINICAL TRIALSCLINICAL TRIALS

HPWHPW

WFIWFI

Page 12: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting  

Reverse Osmosis Pre‐Treatment System 

(Built c.1987)

12

FRP High Purity       Water Storage Tank 

2000 Gallon (Built c.1987) 

INTRODUCTION: OBJECTIVESOBSOLETE EQUIPMENT

Page 13: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   13

Multi‐Effect WFI Still (5 MEF)(Built c. 1987)

(3) WFI Distribution Pumps One pump on each floor (Spares in Warehouse)

INTRODUCTION: OBJECTIVESOBSOLETE EQUIPMENT

Page 14: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting  

Softener RegenerationBrine Tank 

14

Softener Regeneration Salt Pellets 

Palletized 40 lb bagsConsumed 400‐800 lb/day

INTRODUCTION: OBJECTIVESOBSOLETE EQUIPMENT

Page 15: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   1

INTRODUCTION:  OBJECTIVES

SC Microbial

Microbial Fermentation

Media PrepMicrobial

Purification

Buffer Prep

Building 5Building 38

Biopharm GMP Clinical Trial Production 

Manufacturing

Building 4

BiopharmDevelopment Pilot Plant

NO IMPACT TO ON‐GOING OPERATIONS

Safety Assessment 

Manufacturing

Page 16: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   16

INTRODUCTION:  CHALLENGES

WFI CONTROL PANEL CHANGE OUT

IMPACT TO ON‐GOING 

OPERATIONS:  PHASED 

APPROACH

VENDOR COMMITMENT             

FOR EQUIPMENT DELIVERY

INSTALL WINDOW

&AVAILABLE DOWNTIME

LIMITED SPACE

Page 17: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   17

INTRODUCTION:  CHALLENGES

Generation Equipment

Access

Utilities

BUILDING 38

EXISTING MECHANICAL

ROOM

Page 18: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting  

EXECUTION

Introduction Execution Results

BackgroundObjectivesChallenges

BenefitsLessons Learned

Summary

DesignConstructionQualification

Page 19: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   19

EXECUTION:  DESIGN

SUSTAINABILITY EVALUATION

PROJECT LOCATIONS & CONSTRAINTS

EQUIPMENT EVALUATION

VISIT OTHER GSK SITES

Page 20: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting  

Site 1:  Christ System

20

Site 2: Siemens: PreVUE®

Other Site Tours (Gemba)

EXECUTION:  DESIGN

Page 21: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   21

Options Decision

HPW Single Pass vs. Double Pass RO Single Pass

Polisher vs. None Install Polisher

Carbon vs. Bi‐sulfite vs. UV Light Filtration Carbon Filtration

Service Type vs. Back Washable Carbon Filters Back Washable

Hot Water vs. Chemical Sanitization Hot Water Sanitization

FRP vs. SS HPW Storage Tank SS Tank

High Recovery RO vs.  None High Recovery RO 

Nitrogen Blanket on Storage Tank vs. None Nitrogen Blanket 

Bulk Brine vs. Day Tank Both

Redundant vs. Single Storage Tank Filters Redundant Filters

EQUIPMENT EVALUATION

EXECUTION:  DESIGN

Page 22: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   22

Options Decision

WFI Vapor Compression vs. Multi Effect Vapor Compression

Separate Pump per Floor vs. Redundant Pumps Redundant Pumps

Redundant vs. Single Storage Tank Filters Redundant Filters

EQUIPMENT EVALUATION

EXECUTION:  DESIGN

Page 23: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   23

SUSTAINABILITY EVALUATION

Systems Design

Evaluations

Operating Cost

Comparisons

Wastewater Volume

Reduction

EXECUTION:  DESIGN

Page 24: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting  

Only Feasible Solution:

Utilize existingCourtyardbetween B5 & B38 (14’ W x 110’ L)

24

Project LocationsLimited

PROJECT LOCATIONS & CONSTRAINTS

EXECUTION:  DESIGN

Page 25: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting  

Top of Courtyard          Looking NORTH

25

Bottom of Courtyard Looking SOUTH

EXECUTION:  DESIGNPROJECT LOCATIONS & CONSTRAINTS

Page 26: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   26

2‐Story Mechanical Room Design

EXECUTION:  DESIGN

Page 27: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   27

EXECUTION:  DESIGN2‐Story Mechanical Room Design

Page 28: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   28

Construct Addition

&Install HPW

System

Install WFI Pumps

& Control Panel

Demo Old HPW

System

Install WFI VC Stills

Demo Old Still

PhasedConstruction/Qualification

Approach

PHASE 1PHASE 1 PHASE 1APHASE 1A PHASE 2PHASE 2

NO IMPACT TO ON‐GOING OPERATIONS

EXECUTION:  DESIGN

Page 29: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting  

Construct 2‐Story Addition for HPW

29

Between 2 Buildings Limited AccessAdjacent GMP Operations

EXECUTION:  DESIGNPHASE 1

Page 30: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting  

Construct 2‐Story Addition for HPW

30

Between 2 Buildings Limited AccessAdjacent GMP Operations

EXECUTION:  DESIGNPHASE 1

Page 31: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   31

EXECUTION:  DESIGNSYSTEM CONSIDERATIONS

Choose Vendor that Supplies Customizable PLC Controllers: Normalized Differential Pressure to determine cleaning interval Softener Regeneration is based on Hardness Softener Regeneration Rinse is based on Conductivity

Bulk Brine Tank System

Energy Efficiency 

S3 Technology  & Pump VFDs

Reduce Water Usage 

S3 Technology & High Recovery RO

WFI:  Pump Schemes

Fathom SoftwareComplexity of Flows – Multiple Floors

Online TOC, Conductivity &  

Microbial Detection

Page 32: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   32

EXECUTION:  DESIGNPHASE 1A ‐WFI

No Redundancy

Difficult to           Control Flow 

Maintenance requires Shutdown

Single Pump affected Tank Temp and other Floor Availability

No Redundancy

Difficult to           Control Flow 

Maintenance requires Shutdown

Single Pump affected Tank Temp and other Floor Availability

OLD SYSTEMOLD SYSTEM

Page 33: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   33

EXECUTION:  DESIGNPHASE 1A ‐WFI

Redundancy

Control From         Worst Case

Pump Maintenance  = No downtime

VFD’s to manage fluctuations

Individual Loops can be Isolated

NEW SYSTEMNEW SYSTEM

Generated from      Fathom Modeling

Page 34: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   34

EXECUTION:  DESIGNWFI CONTROL PANEL

Desktop Simulation 

Only

20 Year Old System

No ‘Plan B’

Instruments = 86I/O Points = 106

Extensive        Pre‐Planning

GREATEST RISK

Page 35: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   35

EXECUTION:  DESIGNHPW GENERATION SUMMARY

Page 36: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting  

EXECUTION:  CONSTRUCTIONTIMELINE

Week 1 25 33 41 49 57 65 73 81 89 97

Phase 2 Begins Shut Down & Phase 1 End

4/21/14

Shut Down Begins

12/16/13Construction 

Begins

4/1/13

PHASE 2

PHASE 1A7 WKS

CONSTRUCTION AWARD

DESIGN 24 WEEKS

PHASE 1

9 10517

Construction Complete

6/16/14Design KO6/4/12

CM Award11/5/12

8 WKS

PROCUREMENT & DOCUMENTS29 WEEKS

44 WEEKS

CONSTRUCTION

9/3/12POs

Page 37: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   37

EXECUTION:  CONSTRUCTIONExisting Courtyard

Stone & Soil Excavation

1st Floor Slab Installation

PHASE 1

Page 38: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting  

Maintain Building Integrity during Removal of Building Façade

38

EXECUTION:  CONSTRUCTIONTEMPORARY PROTECTIONS

Removal of the façade exposed Utilities above occupied space inside

Installed Temporary Partition Walls inActive Areas & Issued Change Control

Updated Qualified Flow Drawings Continually During Construction

Page 39: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   39

EXECUTION:  CONSTRUCTION

Large Crane due to Limited Access

Building Structure Construction

PHASE 1

Page 40: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   40

EXECUTION:  CONSTRUCTION

Installation of HPW Equipment

PHASE 1

Page 41: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   41

EXECUTION:  CONSTRUCTION

Outdoor Bulk Brine Tank2nd Floor HPW

PHASE 1

Page 42: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   42

EXECUTION:  CONSTRUCTION

1st Floor Dual RO Skids

1st Floor HPW Tanks & Pumps

PHASE 1

Page 43: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   43

EXECUTION:  CONSTRUCTION

2nd Floor Dual Softeners  & Multi‐Media Filters

2nd FloorDual Carbon Filters

PHASE 1

Page 44: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   44

EXECUTION:  CONSTRUCTION

B38 Mechanical RoomNew WFI Pumps

B38 Mechanical RoomExisting WFI Pumps to Demo

PHASE 1A

Page 45: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   45

EXECUTION:  CONSTRUCTION

B38 Mechanical RoomHPW System to Demo

Access Doors to B38 Mechanical Room

PHASE 2

6’6”

8’8”

Page 46: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   46

EXECUTION:  CONSTRUCTION

New WFI Stills in B38 Mechanical Room

New WFI Stills at FATSugarland, TX

PHASE 2

Page 47: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   47

EXECUTION:  CONSTRUCTIONLEVERAGED QUALIFICATION APPROACH

Vendor Qualification Documents Reformatted to GSK Standards PRIOR to Factory Acceptance Test (FAT)

PEOPLE

Qualification Team:ValidationEngineeringFacilitiesQA

EQUIPMENT CHECK

Resolve issues prior to shipment Equipment Still at Factory

DURATION

Reduced Document Development Time by 3 weeksDuplicated FAT during SAT

Page 48: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   48

EXECUTION:  CHALLENGESCONSTRUCTION

Constrained Area within the Middle of Operating Buildings

Delivery of High Purity Equipment

S3 Design Not Turn‐Key

Polisher Tank Delivery

Sartorius Filter Housings

DI Tank Filters

Failure of PQ1 Testing (Plan B)

Installation of High Purity Equipment

Page 49: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   49

EXECUTION:  QUALIFICATIONVALIDATION DOCUMENTATION

1 Validation Master Plan (HPW/WFI) including              3 Validation Interim Reports

5 User Requirement Specs

14 Change Controls

27 Installation Operation Qualification Documents

10 Standard Operating Procedure Updates

22 Functional Design Specifications

3 Factory Acceptance Test / Site Acceptance Test

2 Design Qualifications

EXTENSIVE

 DOCU

MEN

T MAN

AGEM

ENT

Page 50: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting  

RESULTS

Introduction Execution Results

BackgroundObjectivesChallenges

BenefitsLessons Learned

Summary

DesignConstructionQualification

Page 51: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   51

RESULTS:  BENEFITS

INCREASED SUPPLY & CAPACITY

IMPROVED RELIABILITY 

& DELIVERED 

SUSTAINABILITY

LOWER OPERATING EXPENSE

Page 52: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   52

IMPROVED SUPPLY TO CLINICAL OPERATIONS

RESULTS:  BENEFITS

Increased Capacity & Reliability

Redundant HPW & WFI

B38 B5 B4

Page 53: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting  

RESULTS:  BENEFITS Reduced ~11,000 gallons per day / ~4,050,000 gallons per year  Cost savings of ~$32K per year (Water & Sewer)  Supports GSK’s strategic goal to reduce Water Consumption

Annual carbon emissions reduction of 348 TONNES CO2 Supports GSK’s strategic goal to reduce Carbon Footprint

New System supplying HPW to Biopharm Development Pilot Plant Eliminated Resin Bed Train Service New Bulk Brine & Online Microbial Detection Systems Cost Savings of ~$147,500 per year

Water                   Consumption

Electrical Energy

Carbon Emissions

Operations

Pumping operations reduced by 88% Cost Savings of ~$28k per year

53

Page 54: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting  

54

FUTURE OPERATING SAVINGS

RESULTS:  BENEFITSOnline Microbial Detection System

Synchronized Optical 

Monitoring

Particulate Size

Microbial Fluorescence

Reduces Regulatory Sampling

Doesn’t Eliminate

Similar EvaluationTOC/Conductivity

1,980 Samples/YearOnly 4th System Installed in US

Page 55: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   55

RESULTS:  LESSONS LEARNED

Full Control Replacement: 

Demo Simulation of functionality   

Integration of Automation Contractor 

Selection of Construction Contractor

WHAT WENT WELL

Procurement Management

WFI Batcher Orifices

WFI Still & Clean Steam Supply Pressure 

PQ1 Failure / ‘Plan B’

COULD HAVE DONE BETTER

Page 56: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   56

SUCCESS!

RESULTS:  SUMMARY

CONSTRUCTED   & VALIDATED           IN LESS THAN 

1 YEAR

TWOVALIDATED SYSTEMS & NEW 

GENERATION EQUIPMENT

MINIMAL IMPACT TO ON‐GOING OPERATIONS

Page 57: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   57

RESULTS:  SUMMARY

INCREASED RELIABILITY

DELIVEREDSUSTAINABILITY

MINIMIZED DOWNTIME

DELIVEREDSUSTAINABILITY

LOWEROPERATINGEXPENSE

INCREASED RELIABILITY

OBJECTIVES EXCEEDED!

Page 58: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   58

RESULTS:  SUMMARY

INCREASD RELIABILITY

DELIVERED SUSTAINABILITY

OBJECTIVES EXCEEDED!

We kept the Trains on the Tracks 

Page 59: High Purity Water Project Presentation No Unplanned Downtime

2014 ISPE Annual Meeting   59

QUESTIONS