high building

Upload: vas-steel

Post on 03-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 High Building

    1/104

    CHALLENGES IN COORDINATION PROCESS FOR TALL BUILDING

    CONSTRUCTION

    MOHD NASIR BIN MOHD NOOR

    UNIVERSITI TEKNOLOGI MALAYSIA

  • 7/28/2019 High Building

    2/104

  • 7/28/2019 High Building

    3/104

  • 7/28/2019 High Building

    4/104

    CHALLENGES IN COORDINATION PROCESS FOR TALL BUILDING

    CONSTRUCTION

    MOHD NASIR BIN MOHD NOOR

    A project report submitted in partial fulfilment of the requirements for the award of the

    degree of Master of Science (Construction Management)

    Faculty of Civil Engineering

    Universiti Teknologi Malaysia

    DECEMBER 2010

  • 7/28/2019 High Building

    5/104

    ii

    I declare that this project report entitled Challenges in Coordination Process for Tall

    Building Construction is the result of my own research except as cited in the references.The project report has not been accepted for any degree and is not concurrently

    submitted in candidature of any other degree.

    Signature : ..

    Name : MOHD NASIR BIN MOHD NOOR

    Date : DECEMBER 2010

  • 7/28/2019 High Building

    6/104

    iii

    Dedicated specially

    To my beloved wife Tuan Norisah Tuan A. Talib

    and my children

    Nik Mohammad Nazrin Irfan and Nik Nuradlin Izzah

  • 7/28/2019 High Building

    7/104

    iv

    ACKNOWLEDGEMENT

    I would like to acknowledge my supervisor Associate Professor Dr. Mohamad

    Ibrahim Mohamad who has given me support and guidance throughout the period of the

    study. His patience and perseverance toward the outcome of the study subject is on the

    highest standard. Without him this project report will not become reality.

    I would like to acknowledge to all my post graduate colleagues who has

    contributed toward their ideas of how to go about this study when their opinion been

    consulted.

    Finally, I would like to acknowledge all the expert panels and respondents to the

    questionnaire for participating in this study exercise and without them this study will be

    meaningless.

  • 7/28/2019 High Building

    8/104

    v

    ABSTRACT

    The coordination process for tall building construction is a very complex process.

    It involves many parties and special construction method and technology. However in

    todays current practice of tall building construction, many problems have occurred and

    contributed to the failure of the project. The common problems faced are delays in

    completion, cost over run and poor standard quality. One of the reasons is due to

    inefficient or poor coordination process especially during construction. Therefore, this

    study is carried out to investigate the challenges in coordination process in tall building

    construction. The methodologies adopted for this study include interview with expert

    panel and questionnaire survey distributed among those who are experience in tall

    building construction. The finding from this study revealed that the construction industry

    particularly in Malaysia need to be improve with regards to the coordination process.Currently, there are there are a lot of problems associated with coordination process of

    tall building construction especially during construction stage. These problems have

    been identified in this report. Then this study also makes some proposal for improving

    current coordination process. Among the proposal identified in this report are close

    tracking and monitoring for work program, implementation of quality management

    system such as ISO certificate and also implementation of new industrial building

    system (IBS).

  • 7/28/2019 High Building

    9/104

    vi

    ABSTRAK

    Proses koordinasi dalam pembinaan bangunan tinggi adalah proses yang

    kompleks. Ini adalah disebabkan banyak pihak yang terlibat serta penggunaan kaedah

    pembinaan dan teknologi yang berlainan. Walau bagaimanapun, dalam pembinaan

    bangunan tinggi pada masa kini, banyak masalah-masalah selalu timbul yang

    menyebabkan kegagalan dalam sesuatu projek. Antara masalah-masalah yang sering

    dihadapi adalah seperti kelewatan dalam menyiapkan projek, kos yang berlebihan dan

    kualiti yang tidak memenuhi piawaian. Salah satu sebab adalah kelemahan atau

    ketidakcekapan dalam proses koordinasi terutama semasa peringkat pembinaan. Oleh

    yang demikian, kajian ini dijalankan untuk menyelidik cabaran-cabaran dalam proses

    koordinasi dalam pembinaan bangunan tinggi. Kaedah-kaedah yang digunapakai dalam

    kajian ini adalah termasuk temubual dengan pakar-pakar dan juga borang soal selidik

    yang diedarkan dikalangan mereka yang berpengalaman dalam pembinaan bangunan

    tinggi. Hasil daripada kajian ini didapati industri pembinaan khususnya di Malaysia

    memerlukan penambahbaikan terutama bagi proses koordinasi. Pada masa kini terdapat

    banyak masalah-masalah berhubung dengan proses koordinasi bagi pembinaan

    bangunan tinggi. Masalah-masalah ini telah dikenalpasti di dalam laporan ini. Kajian ini

    juga menyenaraikan cadangan-cadangan bagi menambahbaikan proses koordinasi.

    Antara cadangan-cadangan yang dikenalpasti adalah seperti pengawasan dan kawalan

    yang rapi terhadap program kerja, perlaksanaan pengurusan kualiti seperti ISO dan juga

    pengunaan sistem perindustrian dalam pembinaan (IBS).

  • 7/28/2019 High Building

    10/104

    vii

    TABLE OF CONTENTS

    CHAPTER TITLE PAGE

    DECLARATION ii

    DEDICATION iii

    ACKNOWLEGDEMENT iv

    ABSTRACT v

    ABSTRAK vi

    TABLE OF CONTENTS vii

    LIST OF TABLES xii

    LIST OF FIGURES xiv

    LIST OF APPENDICES xv

    1 INTRODUCTION

    1.1 Introduction 1

    1.2 Problem Statement 2

    1.3 Aim and Objective of Study 3

    1.4 Scope and Limitation of the Study 3

    1.5 Brief Methodology 4

    1.6 Summary of Chapter 5

  • 7/28/2019 High Building

    11/104

    viii

    2 COORDINATION IN CONSTRUCTION

    2.1 Introduction

    2.2

    6

    Term and Definitions of Coordination

    2.3

    6

    Coordination

    2.4

    in Construction 7

    2.5

    Function of Coordinator 9

    Coordination Skills

    2.6

    11

    2.7

    Coordination Methods 13

    2.8

    Conflict of Coordination 14

    Informational Dimension of Coordination 16

    2.9

    2.10 The Tall Building Construction Industry 18

    Introduction of Tall Building Construction 17

    3 METHODOLOGY OF STUDY

    3.1 Introduction 20

    3.2

    3.3

    Preparation of Questionnaire 20

    3.4 Data Collection 21

    Selection of Respondent 21

    3.4.1 Questionnaire Survey 21

    3.4.2 Interview with Expert Panels 22

    3.5 Data Analysis 23

    3.5.1 Content Analysis 233.5.2 Frequency Analysis 24

    3.5.3 Relative Index Analysis 24

    3.6 Problems Faced 25

  • 7/28/2019 High Building

    12/104

    ix

    4 DATA COLLECTION AND ANALYSIS

    4.1 Introduction 26

    4.2 Content Analysis of the Interview 26

    4.3 Questionnaire Survey 36

    4.3.1 Demographic of Respondent 37

    4.3.2 Nature of Business 37

    4.3.3 Respondents Working Experience 37

    4.3.4 Respondent Projects Involvement 38

    4.4 Problem Related to Construction Coordination 39

    4.4.1 Work Schedule/Program 39

    4.4.2 Authorities Permit/Approval 40

    4.4.3 Quality Aspect 41

    4.4.4 Document Recording System 42

    4.4.5 Communication Between Project Team 42

    4.4.6 Safety Aspect 43

    4.4.7 Changes/ Variation 44

    4.5 Strategies for Improvement of ConstructionCoordination 44

    4.5.1 Work Schedule/Program 454.5.2 Authorities Permit/Approval 464.5.3 Quality Aspect 464.5.4 Document Recording System 474.5.5 Communication Between Project Team 484.5.6

    Safety Aspect 48

    4.5.7 Changes/ Variation 494.5.8 Others Strategies 49

  • 7/28/2019 High Building

    13/104

    x

    5 DISCUSSION OF THE RESULT

    5.1 Introduction 51

    5.2 Major Process in Construction Coordination 51

    5.2.1 Work Schedule/ Program 52

    5.2.2 Authorities Permit/ Approval 53

    5.2.3 Quality Aspect 53

    5.2.4 Document Controlling System 54

    5.2.5 Communication between Project Team 54

    5.2.6 Safety Aspect 54

    5.2.7 Changes/ Variation 55

    5.3 Problem in Current Construction Coordination 55

    5.3.1 Summary of Current Coordination Problem 56

    5.4 Strategies to Improve Construction Coordination 57

    5.4.1 Summary of Strategies to Improve

    Coordination 58

    6 CONCLUSION AND RECOMMENDATION

    6.1 Introduction 61

    6.2 Achievement of the Study 61

    6.2.1 Objective 1 62

    6.2.2 Objective 2 63

    6.2.3 Objective 3 64

    6.3 Conclusion 65

    6.4 Recommendation for further research study 66

  • 7/28/2019 High Building

    14/104

    xi

    LIST OF REFERENCE 67

    APPENDIX A 69

    APPENDIX B 77

  • 7/28/2019 High Building

    15/104

    xii

    LIST OF TABLES

    TABLE NO. TITLE PAGE

    4.1 Content Analysis of the Interview with ExpertPanel on Work Schedule/ Program Coordination 29

    4.2 Content Analysis of the Interview with ExpertPanel on Authorities Permit/ Approval Coordination 30

    4.3 Content Analysis of the Interview with ExpertPanel on Quality Aspect Coordination 31

    4.4 Content Analysis of the Interview with Expert Panelon Document Recording System Coordination 32

    4.5 Content Analysis of the Interview withExpert Panel on Communication between the Team

    Coordination 33

    4.6 Content Analysis of the Interview with ExpertPanel on Safety Aspect Coordination 34

    4.7 Content Analysis of the Interview with Expert Panelon Changes/ Variation Coordination 35

    4.8 Content Analysis of the Interview with ExpertPanel on Others Coordination 36

  • 7/28/2019 High Building

    16/104

    xiii

    4.9 Work Schedule/Program 414.10 Authorities Permit/Approval 414.11 Quality Aspect 424.12 Document Recording System 434.13 Communication Between Project Team 444.14 Safety Aspect 444.15 Changes/ Variation 454.16 Work Schedule/Program 464.17 Authorities Permit/Approval 474.18 Quality Aspect 484.19 Document Recording System 484.20 Communication between Project Team 494.21 Safety Aspect 494.22 Changes/ Variation 504.23 Others Strategies 51

  • 7/28/2019 High Building

    17/104

    xiv

    LIST OF FIGURES

    FIGURE NO. TITLE PAGE

    1.1 Flow chart for Research Methodology 4

    4.1 Questionnaires delivered 37

    4.2 Nature of Business 38

    4.3 Respondent Working Experience 39

    4.4 Respondent Projects Involvement 40

    5.1 Construction Coordination Diagram 53

  • 7/28/2019 High Building

    18/104

    xv

    LIST OF APPENDICES

    APPENDIX TITLE PAGE

    A Interview `Question 70

    B Survey Questionnaire 78

  • 7/28/2019 High Building

    19/104

    1

    CHAPTER 1

    INTRODUCTION

    1.1 Introduction

    Demands in tall buildings are really significant nowdays especially in urban

    development. There are many reasons contributed to the increase in demand for tall

    buildings which due to the scarcity of land in urban areas, increasing demand for

    business and residential space spur by economic growth created a short supply

    situation. Other motivations for the demand of tall building are the desire for

    aesthetics in urban settings, the concept of city skyline, the cultural significance and

    prestige and simply the aspiration of human to build higher structures (Buyukozturk,

    2004). Tall building construction is a complex activity which evolved with different

    kind of construction methods and technologies. Due to the complexity of the

    construction, an efficient coordination needs in order for the project to be successful.

    In tall building construction project, the clients objective has to be the main criteria

    to be focused on. Many goals are been set and beside the building concept, building

    efficiency and etc. The main aspect to be considered in building construction are

    controlling delays, controlling the costs and ensuring the quality standard of the

    building. In construction of the project, cooperation between stakeholders involved is

    an essential factor for project success, more particularly in coordination. (Sylvain

  • 7/28/2019 High Building

    20/104

    2

    Kubicki, 2005). However in todays current practice of building construction, many

    problems has occurred and contributed to the failure of the project whether delays in

    meeting the time frame, building cost overrun, poor standard of quality. One of the

    reasons is due to the poor coordination from client representatives during

    construction stage. Since it is a common problem under a building construction

    project, it is significant to study the current practice of coordination and develop a

    suggestion to overcome and identified problem in order to achieve the goal and

    objective of the building construction.

    1.2 Problem Statement

    The construction industry performs badly with respect to low productivity,

    low degrees of innovations and learning, high degrees of delays, and poor in standard

    of quality. It is in general, believed that the present interaction between the agents in

    the building process is not optimal and hence market based interaction should be

    replaced with team collaboration and cooperation. The relationship between

    contractor and client must be improved in order to reduce the discrepancy and

    disputes in the construction works. The above mentioned associated problem can be

    solved with effective coordination between stakeholders.

    Project completion on time, standard of quality and cost within the budget allocated

    are the common goal of construction project. However, in common practice the

    contractor and consultant often do not coordinate as they been awarded the job.

    Many problems may be encounter on a larges construction project, making it

    necessary to coordinate the efforts of many involves parties, including the owner,

    contractors, designer, supplier as well as authorities. Due to the above problem, a

    study needs to be carried out to investigate on coordination of tall building

    construction.

  • 7/28/2019 High Building

    21/104

    3

    1.3 Aim and Objective of Study

    The aim of the study is to analyze the importance of coordination and its

    current state in tall building construction project. The aim is supported by the

    following objective:

    (i) To identify the major process in tall building construction coordination.

    (ii) To evaluate major problems related to coordination issues in tall building

    construction.

    (iii) To suggest the strategies for improving the coordination process in tall

    building construction.

    1.4 Scope and Limitation of the Study

    The scopes of study are as follows:-

    i) The coordination issue in tall building construction which focused on clients

    perspective.

    ii) Despite the issue in coordination are involved for the whole project life cycle,

    however only the construction stages are considered in this study.

    iii) The data collected are only limited to developers, consultants and government

    agency located within Klang Valley and Selangor.

  • 7/28/2019 High Building

    22/104

    4

    1.5 Brief methodology of Study

    In this study, the methodology adopted are involves literature review,

    interview with expert panels and questionnaire survey. An appropriate choice of

    methodology largely depends on the objective to be achieved. Figure 1.1 shown the

    flow chart of the adopted methodology that have been used.

    Figure 1.1: Flow Chart for Research Methodology

    Identified Problem Statement

    To identify the current image and weakness of construction industry

    Objectives

    Identify and introduce effective coordination in building construction

    Literature Review

    A study on materials from library, web site, interview on the need for coordination

    Data Collection

    Design, distribute and collection of questionnaire survey

    Data Analysis

    Identify facts, compare the result with objective and checks the Reliability Index

    Conclusion and Recommendation

    To recommend the strategies for improving the coordination process

  • 7/28/2019 High Building

    23/104

    5

    1.6 Summary of the Chapter

    This study will be divided into six (6) main chapters which describe as

    follows:-

    Chapter one described the introduction of the study, objective, scope and

    limitation of the study and methodology adopted in the study.

    Chapter two describes on literature review on the current coordination

    process and also describes brief of tall building construction.

    Chapter three describes in detail the methodologies of study to achieve the

    objectives. It is includes methodology for data collection and data analysis for

    interview with expert panel and questionnaire survey.

    Chapter four discussed on the analysis of the data collected from chapter 3

    with specific method of analysis.

    Chapter five discussed in detail on the analysis in the chapter four and the

    presentation of result and finding from the collected data.

    Chapter six discussed on the conclusion of the overall study and suggestion

    on the strategies for improvement the coordination process.

  • 7/28/2019 High Building

    24/104

    6

    CHAPTER 2

    COORDINATION IN CONSTRUCTION

    2.1 Introduction

    This chapter discussed on the definition, functions, methods, methodologies

    and factors lead to success of coordination process in construction process in

    construction industry.

    2.2 Term and Definitions of Coordination

    When the word coordination was first recorded in 1605, it meant orderly

    combination (Barnhart Dictionary of Etymology, 1988). Though the basic meaning

    or coordination has not change over the centuries, the contemporary meaning of

    coordination has become increasingly associated with harmonious and skillfulmovement. Definitions of coordination also can be defined as follow:

  • 7/28/2019 High Building

    25/104

    7

    a. Websters New World Dictionary (1988) coordination is defined as the

    harmonious adjustment of action, as of muscles in producing complex

    movement.

    b. In the fourth edition (1984), of Rogets International Thesaurus

    Coordination and timing are listed as synonyms of skill; and coordination

    and well-coordinated are listed as synonyms of skillful.

    c. Carnereo/ Gelernter (1990), Coordination is the process of building

    programs by gluing together active pieces

    d. Singh (1992), Coordination is the integration and harmonious adjustment of

    individual work effort towards the accomplishment of the larger goal

    e. Malone (1994), Coordination is the act of managing dependencies between

    activities

    f. Mahnke (1999) chooses a rather extensive description of coordination asa

    process through which two or 3 that these modes of coordination can be

    found as well in as between firms.

    2.3 Coordination in Construction

    The process of construction involves the organization, administration, and

    coordination of resources. The resources are labors, temporary and permanent

    materials, equipment and monetary. These must be integrated in the most efficient

    manner possible to complete construction projects on schedule, within the budget

    and according to the standards of quality and performance specified by the project

    owner or designer. An effective coordination system is needed to organize, leading

    and controlling the whole construction process to make sure it works smoothly.

  • 7/28/2019 High Building

    26/104

    8

    Coordination meant that to clearly and accurately sending and acknowledging

    information, instruction and commands with difference methods of communication

    such as site memo, letters of instruction, verbal instruction, body language and

    telecommunications within various parties involve in the construction and providing

    useful feedback.

    Coordination is responsible for program direction through cooperation and

    participatory decision-making process. Program direction includes statistical

    reporting, program budgeting, personnel placement/ utilization, management,

    training and the coordination of the activities of the others units to fulfill the goals of

    the Technical Services Program. Cooperation includes fostering an atmosphere

    where participation and communication can occur between Technical Services

    Program in order to provide service to the information seeker.

    The coordination of construction work is a difficult matter that can impose a

    severe workload on the cooperating actors. In fact, the degree of coordination works

    can become a general obstruction to works effectiveness, flexibility, or even safety.

    In such cases systematic coordination systems are often engaged as a mean of

    reducing the degree of complexity involved in coordinating the complex cooperative

    work. There are many studies illustrating the rich and seamless nature of

    coordination performed by co-located actors (e.g., Harper et al., 1991; Heath et al.,

    1993). Special attention needed to development of shared beliefs and common goals

    and their consequences for coordination, because their role is not understood well,

    especially in comparison with that of communication.

    According to Oscar (1983), Ninety percent of all problems on site are due to

    late or inadequate information. Late of information transaction on site can cause a

    thousand of dollar losses. Malone and Crowston (1994), among others, define

    coordination some goal. Over and above what they would need to do accomplish

    the goal individually. When coordination is high, a unit of individual work will

    translate into more team output. In contrast, when coordination is low, the sane

    quality and quantity of individual work will result in less group output because of

    what Steiner (1972) calls process losses.

  • 7/28/2019 High Building

    27/104

    9

    2.4 Function of Coordinator

    The meaning or coordinator can be anyone involved in construction industry.

    For example, resident engineer or clerk of work represented Consultant, project

    manager from client or contractor. The function of coordinator is to ensure that the

    information conduction during construction progress and to ensure the project can be

    completed within the time. Each coordinator has different responsibilities and

    authorities dependent upon the organizational setup under which they are working

    and their own capabilities. They must be alert to existing conditions and be able to

    forecast the future problems. When coordinator notice through their daily inspections

    that certain phases of the work are not being done in accordance with the planning

    and schedules, cost and specifications, they should take necessary action to prevent

    and resolve these errors immediately.

    The coordinator plays the key role for communication on the project. They

    represent their organization for the project both within and outside their organization

    in addition to being the chief negotiator on all matters related to the project. In the

    final analysis, the role of the coordinator is necessary to co-ordinate all activities in

    order to assure that the project work flow smoothly within proper time and cost

    constraints. His role will be empowered if the exercise total responsibility and total

    delegated authority in area such as time scale planning and control, budget

    management, cost planning and control, value engineering and architectural

    principles corresponding to time and cost planning.

    Coordinator should maintaining a complete and accurate daily record of work

    in progress, conferences or phone conversation with contractors personnel, any

    argument or criticism of constructors operations, test result, notification of

    acceptance or rejection, quality and quantity of materials inspected and many

    corrective actions taken by the contractor.

    Progress results are dependent on good coordination amongst the team

    member. A well experience coordinator must have excellent communication skillsand knowledge of the refined art of human relationships and interaction. Such

  • 7/28/2019 High Building

    28/104

    10

    articulated knowledge will help to prevent dispute arising from miscommunication

    and misinterpretation of each others meanings, intention and aspirations.

    The team coordinator must direct and guide the activities of the other team

    members to accomplish a wide variety of tasks. There are some personal attributes an

    effective coordinator must have. These characteristics are primarily instinctive as

    opposed to being learned. An effective of the team coordinator, usually the coxswain,

    depends on the methods of coordination system to successfully demonstrate the

    following behaviors:

    a. Translation of objectives into tasks The coordinator must clearly understand

    the mission goals and objectives and translate them into team tasks. In

    assigning tasks, the coordinator seeks the best march between the team

    resources and tasks.

    b. Coordination of Information gathering Ensure that information processing is

    not reduced throughout the mission. Safe vessel operations depend upon timely

    information flow within the team. The leader should be alert to problems that

    affect information collection or the communication of information.

    c. Share common goals If group member are able to share common goal, than

    they are able to works together in the same direction for achieving the project

    objective.

    d. Coordination in team success Groups are inherently different from

    individuals performing the same tasks because of the need to coordinate.

    Whenever the work of individuals is interdependent, they must coordinate to

    achieve success (Van de Ven at el, 1976).

  • 7/28/2019 High Building

    29/104

  • 7/28/2019 High Building

    30/104

    12

    e. Knowledge Have sufficient knowledge and ability to read and interpret

    plans and specifications, modern construction practice, methods, materials

    and equipments in his/ her field of specialization.

    f. Good Judgment and Good Common Sense Applying logical and sound

    judgment based on the information available. Ability to use good judgment in

    applying the required judgment of the building laws. The inspector should

    make his decisions based on sound judgment, which requires not only

    experience, but also a lot of good common sense. There are situations that the

    inspector must make decisions without guidance from the specifications and

    rely to a large degree on common sense.

    g. Communication Good communication skills, both written and oral. Clearly

    and accurately sending and acknowledging information, instruction and

    providing useful feedback.

    h. Self Confidence and Assertiveness Coordinator should be prepared to

    justify their decisions with respect to the contractors method of operation,

    materials and equipment being used. Therefore, they must be confident in

    their knowledge of the specifications and implemented proper construction

    procedures. Coordinator must be firm and assertive but yet fair and friendly

    to achieve compliance and should avoid being confrontational, argument or

    arrogant.

    i. People Relation Skill and Negotiation Skills Coordinator should have the

    ability to work well with people and to be a negotiator. Dealing with many

    different personalities and negotiating points of contention is a day today

    activity for a coordinator. They must avoid adversarial relationship and act

    friendly to gain the respect of the contractors representatives.

    j. Unity of Command No other parties shall interrupt the command given.

  • 7/28/2019 High Building

    31/104

    13

    2.6 Coordination Methods

    The use of new technology to help communication should be considered.

    While the benefits of items such as mobile phones and two way radios (Walkie-

    Talkie) are well known, digital cameras and on site internet and e-mail access may

    also be beneficial communication tools. For example, drawings can be e-mailed

    between the site office and the architect, as can digital photographs of defects and

    progress. Internet can be used to access information such as Building Standard and

    good practice guidance documentation.

    On large scales construction projects the use of projects Internet systems

    have been shown to be valuable. These systems are based on project wide access via

    a network of personal computers to electronics (Virtual) project documents such as

    drawings, specifications and correspondence.

    Non-paper based communication methods can be described as follow:

    a. Telephone help-desk: Manufacturers provide free advice on the selection,

    properties and use of their products. Much used by site managers. Often

    followed up by a fax.

    b. Internet based advice: Product selection, technical and best advice accessible

    from a personal computer. Mainly the same information as technical

    literature.

    c. CD ROMs: Manufacturers provide product selection, technical and best

    practice advice. Personal computer required to access.

    d. Videos: Not a common method. Perhaps best used to actively demonstrate a

    new product being built.

    e. Hand held guides: Readily able to provide best practice guidance at the pointof construction. Most effective when laminated. Not a common method.

  • 7/28/2019 High Building

    32/104

    14

    f. Posters: A traditional way to communicate best practice messages. Tend to

    concentrate on Do and Do Not points of site practice. Commonly

    displayed in site canteens.

    g. Instructions printed on packaging: Manufacturers provide information on

    their products. The information is generally limited (e.g. telephone number,

    main points of good practice).

    2.7 Conflict of Coordination

    Coordination is an issue that rears it ugly head often during construction.

    Closure attention tool coordinating during the design process can prevent many

    headaches that arise during the construction phase, decrease change orders and result

    in a must happier client. These are a few of the potential coordination conflict that

    should be analyzed prior to release of construction document for bidding of

    construction.

    a. The domino effect

    Some times construction documents might change during the design process.

    It is critical when a change is made to one trade, that all trades are informed so that

    any other related changes to the documents are made. A final coordination review of

    the construction documents can eliminate most of the problems inherit in these

    changes.

    b. Multiple trades vying for limited space

    Space in buildings for MEP systems is usually limited by space of costsmoney. History has shown that the first contractor on the job makes sure that his

  • 7/28/2019 High Building

    33/104

    15

    trade makes most of the space available to install his system. It is important in the

    design process to ensure that the construction documents illustrate where the systems

    to be installed are to be installed and that there is adequate room for the concurrent

    installation of multiple trades.

    c. Background changes made without informing consultants

    Computer aided drafting has made a tremendous difference in the

    architectural and engineering fields. But while it has speeded up the process and

    made making revisions and changes enormously easier, if changes are made to

    backgrounds and all parties are not informed, it is very likely that changes will not be

    noticed and inaccurate documents will result. Communication by all parties is critical

    during the preparation of the construction documents.

    d. Code review

    When doing work in multiple states and municipalities. It is very important to

    contact the local jurisdictions to ensure that the proper codes are being designed.

    Changes to the design documents need to be made after local Building Department

    review because for biddings. Changes made by an inspector during construction due

    to lack of design to the proper codes can be costly and cause construction delays.

    e. Properly documenting existing conditions in renovations work

    There will always be hidden conditions that arise during construction.

    However, a lot of construction headaches can be avoided if the existing locations,

    sizes, operating parameters and conditions of equipment, utilities and distribution

    systems are properly documented and coordinated with the new installations.

  • 7/28/2019 High Building

    34/104

    16

    f. Operation of existing facilities in renovation work

    Does the client need to maintain operation of all or a portion of their facilities

    during the construction of a renovation? If the answer to the question is yes, careful

    study of how the construction will proceed must be planned. Phasing of the

    construction may be required, which needs to be shown on the construction

    documents so that the contractors can be properly prepare his bid.

    One means of ensuring coordination is properly performed is using what is

    termed the commissioning process, wherein an outside consulting firm is hired to

    review the construction documents to ensure their accuracy and the coordination of

    the trades.

    2.8 Informational Dimension of Coordination

    Information is required in order to make it possible for the actors to perform

    the right activity at the right time with the right people. Modes of coordination to

    tackle three different kinds of information uncertainties are:

    a. How-Uncertainty

    What is the outcome of an activity supposed to be and how can this be

    obtained? Some activities will be easy to carry out, either because they are simple or

    because the specifications are inherent in the input. Other activities again require

    more specification (i.e. more additional information needed prior to production) and

    multiple skills and consequently have a higher how-uncertainty.

  • 7/28/2019 High Building

    35/104

    17

    b. When -Uncertainty

    At what time should an activity bee carried out? Some activities need to be

    carried out fast whereas other products have a low when-uncertainty for instance due

    to a system of buffer inventories that (obviously induce storage costs) eliminates the

    need for urgent behavior.

    c. Who-uncertainty

    With who should the activity to be coordinated (i.e.: Who are the potential

    actors providing the input or purchasing the output of an activity?)

    Products with a high specificity will opposed to standard products, have a low

    who-uncertainty because the number of potential purchasers is low. Giving people

    the right information is not enough to ensure coordination; incentives also have to be

    aligned:

    Grandori (2000). The classification [of the coordination mechanisms] is

    conducive to compare the capacity (and costs) of different mechanisms in governing

    the diversity of interests and knowledge among economic actors, under varying

    conditions of uncertainty.

    2.9 Tall Building Construction

    A tall building is a building 35 meters or greater in height, which is divided at

    multiple levels of at least 2 meters in height (EDC, 2006). To be considered as a tall,

    a building must be based on solid ground and fabricated along its full height through

    deliberate processes. Tall buildings can be for residential uses such as condominiums

    and residential apartments, or for commercial purposes such as hotels and office

  • 7/28/2019 High Building

    36/104

    18

    buildings, occasionally including retail and educational facilities. There are also for

    both residential and commercial used of tall buildings today which accommodates

    residential, office and commercial spaces. Therefore, tall buildings require flexibility

    in its design and stability on its construction.

    Tall building has been a dominant landmark from the early years from the

    towers of antiquity and the middle ages in ancient years to the famous Eiffel Tower

    in Paris, the World Trade Center in the United States and the many buildings of

    hotels and organizations today. The first tall building was an office building and said

    to be the Home Insurance Building in Chicago. Famous high-rise buildings include

    Empire State Building which is 381 meters, the United Nations Building and the

    Manhattan Building. Construction of tall buildings continuously changes as

    technology change. Evolution of tall buildings is brought about by the changes and

    development of the materials, equipments, technical conditions and methods used in

    the construction of tall buildings.

    Construction of high-rise buildings differs from ordinary construction such as

    residential houses and low-rise buildings with elements which include the

    foundation, structural systems, enclosure systems, life-safety systems, vertical

    transportation, plumbing and electrical systems different from the construction of

    low-rise buildings. All these considerations require methods and techniques in order

    to meet the requirements of a tall building.

    2.10 The Tall Building Construction Industry

    The industry consists of private companies and public authorities, with many

    individuals and organizations involved, from the manufacture of necessary

    components to the assembly and construction process. Tall building project requires

    a registered architect and civil engineer under the direction of a project manager to

    execute the design and to make sure that it complies with the regulations governing

  • 7/28/2019 High Building

    37/104

    19

    building construction, at the same time conforming to the requirements of the owner

    (Encarta, 2006). The architects or engineers convert the requirements into a set of

    drawings and written specifications that are usually sent to contractors for bidding

    (Encarta, 2006). The successful bidding contractor will be the one responsible for the

    required manpower such as the plumber, painter, electrician, carpenter and other

    manpower required for the construction. Contractors carry out the work under the

    supervision of an architect and engineer who act as agents of the owner (Encarta,

    2006).

    Scarcity in land urban areas, increasing demand for business and residential

    space and economic growth are the major reasons behind the increase in demand for

    tall building s as well as the increasing price of land aside from the above mentioned

    technological advancements and innovations in structural systems. The rapid growth

    of population also promoted the construction of tall buildings.

    One example is the modern Hong Kong which has a land area of 1,037 square

    kilometers. Hong Kong, due to its small land area has the most number of tall

    buildings in the world with about 7, 254 commercial and residential buildings. This

    followed by New York City with 5,317 and Singapore with 3, 489 (Emporis, 2004).

    By region, Asia has the most number of tall buildings with about 33.16% of the total

    tall buildings in the world while North America has 31.20% and Europe shares

    17.89% (Emporis, 2004) of the total tall buildings. Economic growth and resulting

    demand for office space is a good indication of demand for tall buildings

    (Buyukozturk, 2004).

    Other motivations for the demand of tall are the desire for aesthetics in urban

    settings, the concept of city skyline, the cultural significance and prestige and simply

    the aspiration of human to build higher structures (Buyukozturk, 2004). Most people

    perceived and associated tall buildings to the economic status of a country.

  • 7/28/2019 High Building

    38/104

    20

    CHAPTER 3

    METHODOLOGY OF STUDY

    3.1 Introduction

    The research methodology in this chapter serves as a guide to the author in

    achieving the objectives and scopes of the study. This chapter discussed in detail the

    research procedures, from how the data is collected until how it is processes and

    analyzed to achieve the objectives and scopes of the study.

    3.2 Preparation of Questionnaire

    The interview and questionnaire survey has been prepared as a method in

    collection of data in this study. It was designed to gather the information in order to

    achieve the objective of this study. In addition, information on respondents'

    background and experience in the construction are taken into account.

  • 7/28/2019 High Building

    39/104

    21

    Based on literature review and discussions with the supervisor, a draft of

    questionnaire was prepared before distributed to respondent. It has been further

    discussion with supervisor for in order to meet the criteria required for achieving the

    objectives of the study. The samples of interview and questionnaire surveys are

    attached in Appendix A and B.

    3.3 Selection of Respondent

    In this study, the author has identified selected respondents which from

    consultant firms, developers and government agencies located in Kuala Lumpur and

    Selangor. The rational of choosing the above parties because Kuala Lumpur and

    Selangor are among the developing states in Malaysia.

    3.4 Data Collection

    In this study, the author has prepared two (2) methods in gathering the

    information which in the form of questionnaire survey and interview with expert

    panels. In current practice, this both methods are commonly been used.

    3.4.1 Questionnaire Survey

    In developing the questionnaire survey, the author has divided the

    questionnaire into three (3) section which Section A, B and C. Section A is mainly to

    obtain the information on personal background such as name, position, age, nature of

    business, experience in construction industry and number of construction project

  • 7/28/2019 High Building

    40/104

    22

    been involved. The aim of section B is to gather information on the major problem

    related to coordination in tall building construction. Section C is to gather

    information on strategies to improve the coordination process in tall building

    construction.

    The data were collected through questionnaire survey which distributed to

    various parties involves in construction industry. 40 questionnaire surveys have been

    distributed to developers, consultants and government agencies, however only 23

    respondents replied. The respond is relatively moderate. The aim of this section is to

    fulfill the objective no. 2 and 3 which to evaluate major problem related to

    coordination issue in tall building construction and to suggest the strategies for

    improving the coordination process in tall building construction.

    In this method there are few steps been followed which started from initial

    planning, collection of secondary data, preparation of questionnaire survey based on

    secondary data, selection of respondent, collection of premier data, transferring of

    data, analysis and lastly conclusion and recommendation.

    3.4.2 Interview with Expert Panels

    Interview is another technique to collect factual information as well as

    opinion. It is face-to-face interpersonal role situation in which interviewer ask

    respondents questions designed to elicit answer pertinent to research hypothesis

    Nachmias and Nachmias (1996).

    The purpose of data collection is to gather information for objective number

    one (1) which to identified major process in tall building construction coordination.

    The author has carried out the interview with twelve (12) respondents with various

    experiences in the construction. The panels identified are from developers,

    consultants as well as Government agencies with most of the project handled locatedin Klang Valley and Selangor.

  • 7/28/2019 High Building

    41/104

    23

    Interview question has been structured into two (2) sections. Section A of the

    interview question contained the interviewee background such as name, position,

    age, nature of business, experience in construction industry, company address and

    number of construction project been involved.

    In Section B, the questions were structured to gather the information on major

    process in coordination for tall building construction. The author has structured the

    question based on seven (7) scopes of coordination which are work schedule/

    program, authorities permit/ approval, quality aspect, document recording system,

    communication between project team, safety aspect and changes/variation.

    3.5 Data Analysis

    After the compilation of response, every type of data received under different

    question will be separated and gathered to answer different study objectives. In this

    study, there are three (3) methods of analysis were used for analysis the data which

    content analysis, frequency analysis and relative index analysis. The data were

    summarized and presented in the form of table, graph and schedule form. The graph

    been used in this analysis is Pie Chart.

    3.5.1 Content Analysis

    The content analysis is done by comparing the respond from the different

    respondents to the structured open ended questions for interview with expert panels.

    The frequencies of agreement, disagreement, neutral and abstained opinion are

    computed in terms of percentage. Based on the outcome from content analysis,

    deducted is made to the relevant issue being investigated.

  • 7/28/2019 High Building

    42/104

    24

    3.5.2 Frequency Analysis

    Frequency analysis used a tabular form to represent the result of data analysis

    of frequency of response that respondents gave to the different variable in the

    questionnaire. The result was tabulated in the form of frequency number and

    percentages according to total respondents. For graphics result presentation, table

    and pie chart are used as summary. Frequency Analysis depends on the percentage of

    respondents giving the same answers. It is also used to measure the degree of

    agreement for certain statements. The formula of Frequency Analysis is as below:

    Percentage (%) = (n/N) x 100 %

    Where :

    n = Number of respondents

    N = Total number of respondents received

    3.5.3 Relative Index Analysis

    The result of the data collected been summarized by using relative index (RI)

    analysis. The respondents were requested to evaluate the problem in construction

    coordination and strategies to improve the construction coordination based on five-

    points scales rating starting with 1 for strongly disagree, 2 for disagree, 3 for neutral,

    4 for agree and 5 strongly agree. The relative index analysis for each variable is

    calculating by using the following formula:

    Relative Index = 1(n1) +2

    n(5)

    (n2)+31(n3) +4(n4) +5(n5)

    Whereby the application of Relative Index in questionnaire would be:

    n1 = 1, frequency of Strongly Disagree response

  • 7/28/2019 High Building

    43/104

    25

    n2

    n

    = 2, frequency of Disagree response

    3

    n

    = 3, frequency of Neutral response

    4

    n

    = 4, frequency of Agree response

    5= 5, frequency of Strongly Agree response

    3.6 Problems Faced

    Although the planning was done before the data collection process carried

    out, many problems still existed and had to be addressed. Effective and efficient

    handling should be done so as not to disrupt the process of data collection activities.

    One problem that was encountered is late feedback from respondent for the

    questionnaire survey. For those questionnaire survey delivered by postal, the

    respondents may answer generally when researcher is seeking a response on a

    specific level of analysis. Respondents may also answer according to what they think

    the researcher want to hear.

    Another problem foreseen is the industry fatigues which due to work load and

    modern business, the students questionnaire are of less priority. This will result in

    respondents not answering the questionnaire at all or answer only certain part.

    The last problem encounter is lack of commitment from respondent and it might be

    lack of interest and matters of confidentiality or sensitivity for their non-

    participation.

  • 7/28/2019 High Building

    44/104

    26

    CHAPTER 4

    DATA COLLECTION AND ANALYSIS

    4.1 Introduction

    This chapter represents data collection for the study and their analysis. Detail

    data collected from the interview and questionnaire surveys are presented and

    analyzed in this chapter.

    4.2 Content Analysis of the Interview

    Based on the respond from interview with 12 respondents with various

    experience in the industry, it can be summarized that there are seven (7) major

    processes in tall building coordination which are as follows:-

  • 7/28/2019 High Building

    45/104

    27

    i) Works Program/ Schedule

    ii) Authorities Permit/ Approval

    iii) Quality Aspect

    iv) Document Recording System

    v) Communication Between Project Team

    vi) Safety Aspect

    vii) Changes/ Variation

    The details results of content analysis are described in table 4.1 to 4.8.

  • 7/28/2019 High Building

    46/104

    28

    Table 4.1: Content Analysis of the Interview with Expert Panel on Work Schedule/ Program Coordination

    RESPONDENTR1 R2 R3 R4 R5 R6 R7 R8 R9 R10 R11 R12

    QUESTION

    1. Work schedule/program is the maindocument prepared bycontractor before

    commencement ofconstruction. In your

    experience, how longdoes it takes for client

    to approve it?

    Depending on

    advice byconsultant

    1 month 2 to 3 months

    2 weeks to- 1 month

    dependingon scale of

    project

    3 weeks 2 to 3 weeks 1 to 2 weeks 1 week 2 days 2 weeks2 weeks withamendment

    Quite long, normally it is

    only reviewed during themeeting

    2. In your experience,can contractor

    commence the worksbefore works programapproved by client?

    Please state youropinion.

    No.construction

    program shallbe confirmedbefore

    execution ofworks.

    yes

    yes. It is called

    earlycommencement

    but contractor

    have to take therisk if there arechanges indesign.

    Not yet butpreliminary

    work canbe done.

    yes

    can onpreliminary

    activities, themain task shallrefer approvedworks

    programmed

    Onlypreliminaries

    works

    yes, for

    preliminaryand

    mobilizationwork

    Nilyes butnot too

    long.

    No. Workprogram ismandatory to be

    approved byclient so as toensure all

    important keymilestone are in

    place

    yes, because in early stage,

    the works involved is notcomplicated, majorityinvolving preliminary

    work

    3. In your opinion, isthere any consequenceif client delay in

    approving Workschedule/ program?

    Yes. Oncecontractor is

    appointed, timeis running.Delay inapproving the

    work programwill contributeinto delay in

    commencementof works

    yes no yes yes

    main delay toapproved due tomain contractor

    programmed no

    comply tosequence ofworks

    If it take toolong mayaffect

    contractor'swork

    No yes

    progress

    of workcannot beidentified

    Yes, if clientdelay in

    approving workprogram- thework will be

    delays, this is acascadingeffects from this

    points on.

    Yes, it will delay and

    holding all parties withoutproper documenteddirection

    4. In your experience,did client assign anyparticular person in-charge to monitor

    progress of works? Ifyes, what is the role ofthe person?

    Yes. To ensure

    progress in linewith workschedule

    Yes,Monitorandhighlighting

    anyproblemarise

    yes, ProjectManagementConsultant to

    monitor thedesign byconsultants and

    work progressby contractor.

    Noyes, ProjectManagement

    Consultant

    Yes, to overviewworks versesworks program,

    projecting (HQand Site)material and costmonitoring,

    additional worksand progressclaim

    Yes, projectmanager or

    coordinator

    yes. Sitesupervisor -monitoroverall

    progressand qualityof works

    yes,monitoring the

    project make

    sure all theconsultant andcontractor are

    follow theschedule

    Project

    Manager- Identifythe cause

    of delaysand makereport

    Client projectmanager, If

    there is anapparent delay.PM has to call

    for moremeeting to catch

    up with thedelay

    depends, Roles normally

    evolves towards checkingactual progress against

    approved program

  • 7/28/2019 High Building

    47/104

    29

    Table 4.2: Content Analysis of the Interview with Expert Panel on Authorities Permit/ Approval Coordination

    RESPONDENTR1 R2 R3 R4 R5 R6 R7 R8 R9 R10 R11 R12

    QUESTION

    . Tall building

    onstruction project arenvolved a lot ofuthorities approval/

    ermit. In yourxperience, whicharties normally apply

    nd follow-up on the

    pproval? Consultant,lient or contractor?

    All of abovedepending on

    the subject

    Architectand client

    Consultant ConsultantConsultant &Client

    Submission by

    Consultant,however follow -up by client

    Consultant butclient and

    contractorshould assist oncertainoccasions

    All parties

    Consultant

    but criticalissue follow-

    up by client

    Client tofollow-up

    Consultant

    such asarchitect and

    engineer

    All

    . In your opinion, whicharties should beffective coordinator in

    etting approval?

    All parties

    Architect ,

    consultantsand client

    On technicalmatters should bedone by

    consultants butpolitical mattersshould be done by

    client.

    Consultant andcontractor

    Client

    Client with assist

    by the architect/consultant.

    Consultant Consultant Consultant

    Consultantand client

    should worktogetherclosely

    Architectand engineerwith the

    client projectmanageroversee the

    process

    Consultants

    . Obtain approval is onef the time line inonstruction. Did the

    eams consider givingny buffer in term of

    me to obtain thepproval?

    Yes Yes

    No. Approvalnormally forinfrastructure

    works. Duringconstruction,

    others works willstart after structureworks complete.

    There is bufferwithin this time.

    Yes Yes

    Yes, subject theapplication tomeet authoritiesrequirement.

    Should allow

    certain timeframe but need

    to follow-upregularly withauthorities

    Yes Yes Yes

    Yes, bufferis necessary

    to preventdelay

    Sometimes

    . In your opinion, how

    s the effective approachn coordinating theubmission and follow-

    p on the authoritiespproval/ permit?

    Providesufficient

    information &documents ontime. Ensure

    payment forfees (related) to

    be paid on time.

    Meet anddiscuss

    All plans,drawings and

    documents mustbe preparedaccording to

    guidelines andfollow up

    progressively.

    prepare earlyand follow-up

    closely. Createa relationshipwith them

    Createrelationship

    set organizationchart person in

    charge and flowchart. All person

    must understandscope of worksand work ahead

    time line.Immediate reportto superior for find

    solution (if foundproblem)

    Pre-discussion

    beforesubmission toknowrequirement andfollow up

    regularly

    N/A

    Require for

    following upregularly

    N/A

    Create good

    reputationwith local

    authoritiesand regularlyfollow-up on

    the status

    Improverelationship

  • 7/28/2019 High Building

    48/104

    30

    Table 4.3 : Content Analysis of the Interview with Expert Panel on Quality Aspect Coordination

    RESPONDENTR1 R2 R3 R4 R5 R6 R7 R8 R9 R10 R11 R12

    QUESTION

    1. Tall buildingproject normallyhigh-end project and

    the standard ofquality cannot be

    compromised. Inyour experience how

    to control the qualityof the buildingmaterial?

    Great supervisionimposed at site. Ensure

    only suitable materialsto be used.

    Follow Billof

    Quantitiesandspecification

    Appoint external

    party to control theQA/QC matters andthis party must be

    recognize widely. Ifthe quality meet therequirements, the

    building value

    highly increase.

    Makes amock uporsampling

    for

    material.Get the

    experienceworker/

    labour

    Follow

    specification

    Materialdeliver must

    followapprovedmaterial as

    agreed byS.O/ client.

    Providechecklist

    and testingif necessary.Refer to

    SOP/checklist

    Thoroughchecking

    duringsubmissionof sample

    Implement

    QA and QCsystem

    recommend

    SOP

    Certificationand get

    materialtested

    Themonitoring

    system needto beimplemented

    Good

    monitoring

    2. Some developers/clients introduce thelonger defect

    liability period(DLP) to attract the

    buyer and it isrelated to quality of

    end product. In yourexperience how tocontrol the quality of

    workmanship?

    Great supervisionimposed at site i.e.divide specialty(architectural works,

    MSE works). Toappoint reliable &

    proven contractors(s).

    To implementCONQUAS/QLASSICto maintain/ retain

    quality.

    Follow

    specification

    Appoint externalparty to control theQA/QC matters and

    this party must berecognize widely. Ifthe quality meet the

    requirements, thebuilding value

    highly increase.

    Procurequality ofmaterial

    and get theexpertise

    worker

    Teamworkandunderstanding

    of sequenceand

    specification

    Refer toSOP,checklist.

    Standard tomethodstatement.Monitoring

    theactivities,requirement

    for skillworker andexperience

    to the task

    Use skillworkersand

    monitoredbysupervisor

    Controlspecification

    and as in thedrawing

    ProjectTeam

    regularlymonitor

    Sufficientno ofsupervisor,

    tool andprovidetraining

    Extending theDLP will

    improve thequality ofworkmanship.

    The longerthe period ofconstruction,

    the better isthe quality

    Assigngoodcoordinator

  • 7/28/2019 High Building

    49/104

    31

    Table 4.4 : Content Analysis of the Interview with Expert Panel on Document Recording System Coordination

    RESPONDENTR1 R2 R3 R4 R5 R6 R7 R8 R9 R10 R11 R12

    QUESTION

    1. Tall building project iscomplicated project and involved

    a lot of correspondencedocuments. In your experience,did you apply any system in

    documentation managementsystem? (manual or IT system)

    No. But in my opinion,

    having a proper IT systemwith a proper documentscontroller system shall help

    in facilitating the process.

    nono

    experience

    Yes,shoulduse

    Microsoftaccessand excel

    Manual

    On site ismanual, on

    HQ shall be ITsystem

    Apply bothmanual and ITsystems

    Both Manual ManualIT

    systemManual

  • 7/28/2019 High Building

    50/104

    32

    Table 4.5 : Content Analysis of the Interview with Expert Panel on Communication Between the Team Coordination

    RESPONDENTR1 R2 R3 R4 R5 R6 R7 R8 R9 R10 R11 R12

    QUESTION

    1. Communication is

    the importantprocess incoordination. In

    your experience howto communicate

    between teams?

    (Thru meeting,telephone, email orany IT program)

    Clients-consultants/

    technicals meeting.Telephone, faxes, memos,letters. Emails.

    CCM

    Meeting andsite meeting,telephone,email,

    conference,

    sms etc

    All of the aboveThroughtelephoneand email

    All

    Meeting -CCM,Technical

    meeting,programmeeting, site

    meeting, specialmeeting.Coordination

    and distributethroughtelephone-emailletter.

    All of abovemethod or tools

    can be used

    All aboveMeetingand

    telephone

    All, no

    specificIT

    program

    Client

    consultantmeeting andsite meeting

    All

    2. In your opinion,what is the effective

    approach whichproduce the mosteffective to

    communicationbetween projectteams?

    Meetings, emails,telephone, memos, letters

    Meeting anddiscuss

    Conductingcoordinationmeeting, design

    meeting andconsultants -subcontractors

    meeting.

    N/A

    Meeting

    anddiscussion

    When receivedinstruction infoimmediate

    distribute,delegate tosubordinateteam.

    By email andtelephone,

    formalise withletter and onsidedecisions.

    Email and

    telephonecall

    Coordinat

    ionmeeting

    Meeting

    Clientconsultantmeeting, sitemeeting

    All

    3. Do you think theClient ConsultantMeeting (CCM) andSite Meeting are

    sufficient forum tocommunicate

    between project

    team? If not stateyour reason

    Yes & to be minuttedefficiently, so that all

    important point & detailscould be disseminated toall respective parties.

    Yes

    Not sufficient.This is more on

    progress

    meeting onlyand not thetechnical

    aspects.

    Yes Yes

    Not. Shall addspecial meeting, technical

    meeting.

    Yes, but stillcommunicate in

    between themeetings if any

    problem arises

    No

    Yes, allparties

    know thestatus

    update

    Yes

    No. but it is

    mostimportant toset pace forthe project to

    progress.Othermethod

    shouldcomplementthe above

    Normally,person

    attendingmeetings arefor the sake ofmeeting only,

    not comingwith full spiritof resolving

    issue

    4. Do you think ITplayed significantroles to supportcoordination process

    at site and howcould it be?

    Yes. Nowadays,communication via emailsis being the fastest way ofconveying messages. A

    proper system connectingclients office, consultants'& site office will help to

    ensure efficientcommunication.

    Yes,

    festering theprocess

    Yes. Drawing

    and instructionscan be send viaemail and the

    info receivedeffectively.

    Makes works

    move easyand fastespecially

    for documentmanagement

    Yes

    Yes. Short timethe process to

    delegateinformation to

    project team.

    Yes, by conveyingmessage,instructions.

    Drawing via IT

    Yes, leteverybody

    involve tohave a accesssystem to

    know thecause of

    delay

    Yes,helping

    the workto be done

    faster

    Appropria

    teprogram

    mightexpeditethe

    searchingofdocument

    For the speedof

    coordinationbut cannotreplace CCM

    and SiteMeeting

    New ITsoftware are

    designed toease the work

    process but itmust be

    regularly usedand applied tocreate a

    culture'

  • 7/28/2019 High Building

    51/104

    33

    Table 4.6: Content Analysis of the Interview with Expert Panel on Safety Aspect Coordination

    RESPONDENTR1 R2 R3 R4 R5 R6 R7 R8 R9 R10 R11 R12

    QUESTION

    1. If contractorfailed to fulfill the

    safety precautionmeasure in the job

    site. How to imposeit?

    To impose or bind

    safety measures whichrelates to Malaysiagovernment (part of

    the SOP). To makecompulsory for the

    measure to be taken upas the authorities haveright to give stop work

    order.

    Straight in

    enforcement

    and penalty

    Worksmust besuspenduntilcompetent

    safetyofficerappointed.

    Thru warning

    and penalty

    system

    Penaltysystem

    Shall comply to CIDB,

    Niosh, DOSH beforeimposed to contractor. Site

    complain practice on safety

    induction, safety briefing thesafety committee to make

    decision for SO approval.

    Imposepenalties -suspension or

    financially

    PenaltyFine thecontractor

    Penalty, retain

    their

    progress claim

    Penalty andeducateworker on

    site

    Penaltysystem

    2. Based on yourexperience, what is

    the most effectiveapproach to ensure

    the safety ofconstruction site?

    Create safety division.To have regular checkwith respective bodyin imposing safetyregulations at site.

    Penalty N/A

    Set a penaltysystem and

    those ignore itcan't entrancethe site

    Penalty

    Person or machine not

    complies with safetyrequirement do not allowenter project site. Those

    cross the rules, remove fromthe site.

    Full time safetyofficer andconducted

    trainings andawareness and

    imposingpenalties foroffenders

    Penaltyandstop

    workorder

    Contractor haveto more aware

    of safety issueotherwise

    imposedpenalty

    Allworker

    shall bewelltrained

    Safety

    awarenessand

    educatingworker onsite follow

    by penalty

    Assigncompetent

    officer andemploy skillworker

  • 7/28/2019 High Building

    52/104

    34

    Table 4.7: Content Analysis of the Interview with Expert Panel on Changes/ Variation Coordination

    RESPONDENTR1 R2 R3 R4 R5 R6 R7 R8 R9 R10 R11 R12

    QUESTION

    1. In your experience, doyou foresee any changes

    of design especiallyduring construction of

    tall building? If yes how

    frequent?

    Yes, depending onthe un-expected

    rising on cost orchanges in designi.e. design faulty.

    Veryfrequent

    Very frequentYes,always

    Yes, alwaysYes. Veryfrequent

    May need

    changes butnot veryfrequent as it

    will affect theprogress of

    work

    Yes Yes N/AYes, veryfrequent

    Depending oncompleteness ofdesign, loosedesign result inmany variations

    2. Which partiesnormally contribute tothe changes/ variation of

    design duringconstruction? Pleasestate your opinion

    Client, they mighthave others directionwhile dealing either

    on-goingdevelopments i.e.materials or fittings

    might changes along1-2 years during

    construction period.

    Client and

    consultants

    M & E

    consultants. Dueto localauthorities

    requirement andthey failed toadvice duringdesign stage.

    ClientClient and site

    condition

    Client andconsultant

    drawingdiscrepancy.

    Client's needand design

    changes

    Client and

    consultant

    Consultantand

    contractors

    Client and

    Architect

    All partiescontribute to thechanges. Some

    design detailscannot beimplemented,

    whilst othersdue to poor

    detailing

    Depends,sometimes clientand sometimes

    consultant.Generally it is dueto lack of

    coordinationduring early

    process

    3. Errors in design byconsultants are also

    contributed to changes/variation. Based on yourexperience, how to

    handle this issue?

    To ensure proper

    documentations &instructions by arch,engineers. To ensure

    proper approvalsobtained fromclients

    Re-checkand re-look

    Conduct designmeeting and findthe simplest and

    best way toovercome.

    Confirm

    theshapes

    early ormakes ameeting

    every 2weeks

    re-check

    For any

    discrepancy,contractor toissue RFI to

    requestconsultantfor approval.

    Thorough

    checking byindependentchecker

    Alternativeproposal orVO shall be

    borne byconsultant

    N/A

    Project team shall

    check and studythe drawing priorfinalize for

    approval. It willrequired

    sufficient time

    All drawing and

    detail are to becheck beforeconversion to

    BQ andcommencement

    on site.

    Appoint goodconsultants who

    posed competentofficer/

    professional

    4. When changes/variation in construction,

    it will involve the costand create a dispute. Inyour experience how this

    matter been solved?

    To ensure properdocumentations i.e.

    AI, EI, VO forms,etc. To ensurecapping of amount

    in every VO.

    Recheck

    and relook/monitorclosely

    The variation

    cost is clarifiedwhere it camefrom which

    discipline anddeducted ionfees

    N/ADiscussionand

    understanding

    N/A

    May penalizethe party at

    fault butminimize

    changes/variation all

    parties should

    collaboratefrom start of

    project.

    Coordinatio

    n andproper

    recordkeeping

    Checking

    Study thevariance and

    request consultantto write reportand

    recommendation.

    VO of cost usethe set control

    form.

    By professional

    attitude andpartneringapproach

  • 7/28/2019 High Building

    53/104

    35

    Table 4.8 : Content Analysis of the Interview with Expert Panel on Others Coordination

    RESPONDENTR1 R2 R3 R4 R5 R6 R7 R8 R9 R10 R11 R12

    QUESTION

    1. In your experience,what are the most

    challenges in tallbuilding project

    coordination? How tohandle the challenge?

    Safety measures, siteconstraints. Tall building

    normally tends to be in alimited & packed site. It'simportant to impose proper

    site managementprocedure, materials

    management, etc. to ensuresafety (100% measures) to

    be applied i.e. proper seatfolding, safety equipments,etc.

    Drawing andsequences of

    coordination

    N/A N/ATeamworkand

    coordination

    Must havecompetent

    staff/sequence of

    works/ sitemonitoring.

    Construction

    technique -propercoordinatorof method

    statement ofconstruction

    Lot of sub-

    contractor

    Complicated- handle bymonitoring

    N/A

    by looking

    seriously on 3constraintswhich time,

    cost and quality

    Handlingpartiesinvolved inthe project.

    Goodcoordinatorand

    selection ofpartiesinvolved

    will help

    2. Please state the

    strategies to improve thecoordination process?

    To have propercommunications among

    parties. To ensure proper& efficient planning forthe entire development.

    Meet and

    discussregularly

    N/A N/A Workshop

    Set systemand complyto thesystem.

    All parties towork as ateam and the

    team shouldhave acompetentleader

    Meeting withallsubcontractors

    involves in theproject.

    Arrangemeeting

    regularly

    Educate allparties

    involved toplay theirroll wisely

    and alwaysmeet timeframe given

    Simulation ofbuilding and

    constructionbeforeimplementation

    Applypartnering

    concept,appointcompetent

    parties andmonitorclosely

  • 7/28/2019 High Building

    54/104

    36

    Based on the detail result from content analysis, it can be summarized that

    there are a lot of process involves in tall building construction. Among the major

    process is coordination of work program/ schedule. In general it is shown that the

    current tall building coordination requires for improvement in order to achieve the

    project objective. The details of the result will be described in Chapter 5 which

    thorough discussion on the data analysis.

    4.3 Questionnaire Survey

    The author has distributed forty (40) questionnaire surveys to various

    respondents involved directly in the tall building construction project. There are from

    client, consultant as well as government agency (JKR). Out of 40 questionnaire

    survey, 23 questionnaires survey were returned or equivalent to 57% which can be

    classified as moderate respond. The reason for the rest of the respondents failed to

    return the questionnaire survey because of busy with routine works. This is normal

    situation for construction industry. Sample of Questionnaire Survey is shown in

    Appendix B. The details of the respond delivered are tabulated in Figure 4.1

    Figure 4.1 : Questionnaires delivered

    Respond of Questionnaire Survey

    43%

    57%

    Responded

    Unreply

  • 7/28/2019 High Building

    55/104

    37

    4.3.1 Demographic of respondents

    The demographic of the respondents are as follow:-

    4.3.2 Nature of Business

    Figure 4.2 shown the respondent segregation based on nature of business.

    Majority of respondent are from developer which 65% of total respondent. 23% and

    13% respondent are from consultant and government agency respectively.

    Figure 4.2 : Nature of Business

    4.3.3 Respondents Working Experience

    Based on Figure 4.3, it is shown that majority of respondent are having a

    working experience between 5 to 10 years which 35%, followed by 30% of

    respondent having 10 to 15 years working experience. The others are between more

    than 20 years and less than 5 years working experience.

    Nature of Business

    65%

    22%

    13% Developer

    Consultant

    Government Agency(JKR)

  • 7/28/2019 High Building

    56/104

    38

    Figure 4.3 : Respondent Working Experience

    Respondent Working Experience

    26%

    35%

    30%

    9%

    Less than 5 years

    5 to 10 years

    11 to 15 years

    More than 20 years

    4.3.4 Respondent Projects Involvement

    Based on the feedback from questionnaire, it is shown that the majority of

    respondent have involved with the numbers of project between 4 to 6 which

    contribute 44% of the respondent. The Figure 4.3 has shown the result of the

    respondent projects involvement.

  • 7/28/2019 High Building

    57/104

    39

    Figure 4.4 Respondent Projects Involvement

    No. of Project Invo lve

    26%

    44%

    26%

    4%

    1 to 3 projects

    4 to 6 projects

    7 to 10 projects

    More than 10 projects

    4.4 Problem Related to Construction Coordination

    In Section B, the questionnaire surveys are divided into seven (7) categories.The questions designs are to seek the opinion from respondents on the major problem

    related to coordination issue in tall building project from client perspective.

    4.4.1 Work Schedule/Program

    Based on the respond from respondents which shown in Table 4.9, it is shown

    majority of respondent agreed that failure of contractor to follow approved work

    program are the most common problem related to the work program coordination.

    83% of the respondent agreed on the problem and 9% of respondent disagreed and

    neutral. It is contribute to the relative index of 0.8. Beside that late approval from

    client to approve the work program and unreliable work program submitted by

  • 7/28/2019 High Building

    58/104

    40

    contractor also a problem related to coordination of work program most agreed by

    respondents.

    Table 4.9: Work Schedule/Program

    4.4.2 Authorities Permit/Approval

    Table 4.10 shown that majority of respondent agreed that poor reputation

    with authorities is the most common problem related to the work program

    coordination. 78% of the respondent agreed and 9% disagreed on the problem. It is

    contribute the relative index of 0.8. Beside that bureaucracy procedure with

    authorities are among the problem given high relative index which 0.8. Among the

    question asked, a late respond from consultant is the lowest average index responded

    by respondent which 0.6 (relative index).

    No Problem

    Score

    RIDisagree Neutral Agree Total

    1 2 % 3 % 4 5 % f %

    1Contractor failed to follow work

    schedule/ program as agreed 0 2 9% 2 9% 15 4 83% 23 100% 0.8

    2 Late approval obtain from client 1 2 13% 5 22% 10 5 65% 23 100% 0.7

    3Unreliable of work schedule/ program

    submitted by contractor 1 4 22% 3 13% 10 5 65% 23 100% 0.7

    4 Uncompleted work program submitted 2 6 35% 5 22% 8 2 43% 23 100% 0.6

  • 7/28/2019 High Building

    59/104

    41

    Table 4.10 : Authorities Permit/Approval

    No Problem

    Score

    RIDisagree Neutral Agree Total

    1 2 % 3 % 4 5 % f %

    1 Poor reputation with authorities 1 1 9% 3 13% 8 10 78% 23 100% 0.8

    2 Bureaucracy procedure 1 2 13% 3 13% 7 10 74% 23 100% 0.8

    3 Delay in obtain approval by authorities 0 1 4% 6 26% 11 5 70% 23 100% 0.8

    4 Inefficient in Follow-up the approval 0 2 9% 6 26% 10 5 65% 23 100% 0.8

    5 Compliance of Authorities requirement 0 2 9% 5 22% 13 3 70% 23 100% 0.7

    6 Late submission by consultants 3 6 39% 3 13% 8 3 48% 23 100% 0.6

    7 Late respond from consultant 3 5 35% 7 30% 6 2 35% 23 100% 0.6

    4.4.3 Quality Aspect

    Table 4.11 shown that majority of respondent agreed that poor workmanship/

    standard of quality is the most common problem related to the work programcoordination. 70% of the respondent agreed on the problem and 9% of the

    respondent disagree. There are respondent given neutral respond which 22% and

    contribute the relative index of 0.8. Failure to identify the defect on material is also

    among the main problem agreed by respondent which given high relative index of

    0.8.

    Table 4.11: Quality Aspect

    No Problem

    Score

    RIDisagree Neutral Agree Total

    1 2 % 3 % 4 5 % f %

    1 Poor workmanship/ standard of quality 2 0 9% 5 22% 9 7 70% 23 100% 0.8

    2 Fail to identify material defect 0 2 9% 6 26% 10 5 65% 23 100% 0.8

    3 Poor quality control 0 2 9% 5 22% 13 3 70% 23 100% 0.7

    4 Incompetent worker from contractor 1 2 13% 9 39% 9 2 48% 23 100% 0.7

    5 Too much defect 4 9 57% 2 9% 6 2 35% 23 100% 0.5

    6 Incompetent quality control officer 6 7 57% 4 17% 5 1 26% 23 100% 0.5

  • 7/28/2019 High Building

    60/104

    42

    4.4.4 Document Recording System

    Poor record keeping is the most problem agreed by respondent which

    contribute to highest relative index which is 0.9. Table 4.12 is shown result of the

    question from the questionnaire survey.

    Table 4.12: Document Recording System

    No Problem

    Score

    RIDisagree Neutral Agree Total

    1 2 % 3 % 4 5 % f %

    1 Poor Record keeping 0 1 4% 2 9% 8 12 87% 23 100% 0.9

    2 Taking time to trace document 0 2 9% 6 26% 11 4 65% 23 100% 0.7

    3No proper room (unsafe) for filingsystem

    1 3 17% 4 17% 9 6 65% 23 100% 0.7

    4 No document recording system 2 7 39% 5 22% 7 2 39% 23 100% 0.6

    4.4.5 Communication Between Project Team

    Table 4.13 shown the result of the problem related to communication

    between the projects teams which late in delivery information is the main problem

    agreed by respondent. It is shown that 83% agreed on the problem and 9% disagree

    and neutral of that problem.

  • 7/28/2019 High Building

    61/104

    43

    Table 4.13: Communication Between Project Team

    No Problem

    Score

    RIDisagree Neutral Agree Total

    1 2 % 3 % 4 5 % f %

    1 Late in deliver information between team 0 2 9% 2 9% 16 3 83% 23 100% 0.8

    2Lack of monitoring and controlling

    during construction1 2 13% 2 9% 13 5 78% 23 100% 0.8

    3 Low motivation among teams 1 1 9% 3 13% 15 3 78% 23 100% 0.8

    4 Misunderstanding between teams 1 3 17% 2 9% 12 5 74% 23 100% 0.7

    5Unclear instruction between project

    teams2 1 13% 3 13% 14 3 74% 23 100% 0.7

    6 Potential works individually betweenteams

    2 2 17% 2 9% 14 3 74% 23 100% 0.7

    7Late approval/ endorsement from client

    site2 2 17% 4 17% 11 4 65% 23 100% 0.7

    4.4.6 Safety Aspect

    Table 4.14 shown the result of the problem related to safety aspect.

    Table 4.14: Safety Aspect

    No Problem

    Score

    RIDisagree Neutral Agree Total1 2 % 3 % 4 5 % f %

    1 No safety committee 1 2 13% 0 0% 14 6 87% 23 100% 0.8

    2 Uneducated worker on safety procedure 1 0 4% 2 9% 18 2 87% 23 100% 0.8

    3Contractor failed to follow safety

    procedure1 2 13% 0 0% 17 3 87% 23 100% 0.8

    4 Unsafe site 0 2 9% 5 22% 14 2 70% 23 100% 0.7

  • 7/28/2019 High Building

    62/104

    44

    4.4.7 Changes/ Variation

    Changes in design required by authorities is most problem related to

    coordination of tall building. Table 4.15 shown that majority of respondent agreed onthe above problem which indicated relative index of 0.8.

    Table 4.15: Changes/ Variation

    No Problem

    Score

    RIDisagree Neutral Agree Total

    1 2 % 3 % 4 5 % f %

    1 Change in design required by Authorities 2 0 9% 5 22% 9 7 70% 23 100% 0.8

    2 Error in design by consultant 0 2 9% 2 9% 17 2 83% 23 100% 0.8

    3 Change in design by Client 0 2 9% 6 26% 10 5 65% 23 100% 0.8

    4Change in design because of site

    constrain0 2 9% 3 13% 13 5 78% 23 100% 0.8

    5 Inconsistent design among consultant 1 2 13% 4 17% 13 3 70% 23 100% 0.7

    6 Additional cost contribute from changes 1 2 13% 5 22% 12 3 65% 23 100% 0.7

    7 Insufficient information in drawing 1 2 13% 4 17% 14 2 70% 23 100% 0.7

    4.5 Strategies for improvement of Construction Coordination

    In Section C, the questionnaire surveys are also divided into seven (7)

    categories and the questions designs are to seek the opinion from respondents on the

    strategies for improving the coordination issue in tall building project from client

    perspective. Table 4.16 to 4.23 are the shown the result from respondent perspective.

  • 7/28/2019 High Building

    63/104

    45

    4.5.1 Work Schedule/Program

    Based on the respond from respondents which shown in Table 4.16, it is

    shown majority of respondent agreed that ability of developer to do the tracking are

    the popular strategies of the work program coordination. 83% of the respondent

    agreed and 13% of the respondent disagreed. It is contribute to the relative index of

    0.8. Besides that, reliable works schedule also among the strategies agreed by

    respondents.

    Table 4.16: Work Schedule/Program

    No Strategies

    Score

    RIDisagree Neutral Agree Total

    1 2 % 3 % 4 5 % f %

    1 Client able to do tracking and monitoring 1 2 13% 0 0% 14 6 87% 23 100% 0.8

    2 Reliable works schedule/ program 2 0 9% 5 22% 9 7 70% 23 100% 0.8

    3 Expedite approval by Client 0 2 9% 2 9% 17 2 83% 23 100% 0.8

    4Consultants able to advised on alternativeoption if delay occurred

    1 2 13% 0 0% 17 3 87% 23 100% 0.8

    5 Back-up plan/ alternative approach 0 1 4% 5 22% 14 3 74% 23 100% 0.8

    6 Appoint Competent project team 0 2 9% 3 13% 15 3 78% 23 100% 0.8

    7 Introduce dateline strategy 0 2 9% 5 22% 13 3 70% 23 100% 0.7

    8Sufficient information prepared in work

    program1 2 13% 4 17% 13 3 70% 23 100% 0.7

    9Appoint capable contractors/

    subcontractors1 2 13% 4 17% 14 2 70% 23 100% 0.7

    10Imposed penalty system to ensure the

    plan implemented i.e LAD1 3 17% 6 26% 10 3 57% 23 100% 0.7

  • 7/28/2019 High Building

    64/104

    46

    4.5.2 Authorities Permit/Approval

    Table 4.17 shown that majority of respondent agreed that implementation of

    penalty system to consultant is among the highest relative index on the work program

    coordination which 0.8. 87% of the respondent agreed and 9% of the respondent

    disagreed. Beside that implementation of penalty s system to contractor also among

    the highest relative index which 0.8.

    Table 4.17: Authorities Permit/Approval

    No Strategies

    Score

    RIDisagree Neutral Agree Total

    1 2 % 3 % 4 5 % f %

    1 Imposed penalty system to consultant 0 2 9% 1 4% 16 4 87% 23 100% 0.8

    2 Imposed penalty system to contractor 0 2 9% 2 9% 16 3 83% 23 100% 0.8

    3

    Assign coordinator to follow-up the

    confirmation/ approval of approval/ permit

    matters

    2 0 9% 5 22% 9 7 70% 23 100% 0.8

    4Ensure all requirement full fill before

    submission1 3 17% 2 9% 12 5 74% 23 100% 0.7

    5 Establish reputation with authorities 0 2 9% 6 26% 11 4 65% 23 100% 0.7

    6 Regularly follow-up of the status 1 3 17% 4 17% 9 6 65% 23 100% 0.7

    7Prompt respond if additional information

    required by authority2 1 13% 3 13% 14 3 74% 23 100% 0.7

    4.5.3 Quality Aspect

    Table 4.18 shown that majority of respondent agreed that sufficient training

    for contractors workers is the most agreed by respondent on the strategies of the

    work program coordination. 87% of the respondent agreed and 9% of the respondent

    strongly agreed and contribute the relative index of 0.8. Regular testing for building

    material is also among the strategies agreed by respondent which given relative indexof 0.8.

  • 7/28/2019 High Building

    65/104

    47

    Table 4.18: Quality Aspect

    No Strategies

    Score

    RIDisagree Neutral Agree Total

    1 2 % 3 % 4 5 % f %

    1 Sufficient training for contractors worker 0 2 9% 1 4% 16 4 87% 23 100% 0.8

    2 Regular testing for building material 0 1 4% 3 13% 16 3 83% 23 100% 0.8

    3 Appoint knowledgeable quality control staff 0 2 9% 2 9% 16 3 83% 23 100% 0.8

    4 Hired reputable/ establish contractor 1 2 13% 2 9% 13 5 78% 23 100% 0.8

    5 Set a quality procedure 1 1 9% 3 13% 15 3 78% 23 100% 0.8

    6 Implement ISO certificate 1 3 17% 2 9% 12 5 74% 23 100% 0.7

    7Hired reputable/ establish supplier for

    building material2 2 17% 2 9% 14 3 74% 23 100% 0.7

    8 Regularly checking during construction 2 2 17% 4 17% 11 4 65% 23 100% 0.7

    4.5.4 Document Recording System

    Implementation of ISO certificate and all project team must aware of related

    matters are the most strategies agreed by respondent which contribute to highest

    relative index which 0.8. Table 4.19 is shown result of the question from the

    questionnaire survey.

    Table 4.19 : Document Recording System

    No Strategies

    Score

    RIDisagree Neutral Agree Total

    1 2 % 3 % 4 5 % f %

    1 Implement ISO certificate 1 0 4% 2 9% 18 2 87% 23 100% 0.8

    2All project team must aware of related

    matters1 1 9% 2 9% 17 2 83% 23 100% 0.8

    3Implement Information Technology (IT) in

    record system 0 2 9% 5 22% 14 2 70% 23 100% 0.7

  • 7/28/2019 High Building

    66/104

    48

    4.5.5 Communication Between Project Team

    Table 4.20 are shown the result of the strategies on the communication

    between the project teams which the project team must be in contact all the time isthe most strategies agreed by respondent. 91% of the respondent agreed on the

    strategies and 9% of respondent respond neutral score.

    Table 4.20: Communication between Project Team

    No Strategies

    Score

    RIDisagree Neutral Agree Total

    1 2 %