hesr 2 electron cooling
DESCRIPTION
HESR 2 Electron Cooling. Björn Gålnander The Svedberg Laboratory Uppsala University. Midterm Review, DIRACsecondary-Beams December 8, 2006 GSI, Darmstadt. Outline. HESR Electron cooler Present project status Outlook. High Energy Storage Ring. - PowerPoint PPT PresentationTRANSCRIPT
HESR 2 Electron Cooling
Björn Gålnander
The Svedberg LaboratoryUppsala University
Midterm Review, DIRACsecondary-Beams
December 8, 2006
GSI, Darmstadt
Outline
• HESR Electron cooler
• Present project status
• Outlook
• Antiproton momentum, 1.5 –15 GeV/c
• Cooling to counteract PANDA pellet target
• Electron cooling up to 8.9 GeV/c(4.5 MeV electron energy)
• Stochastic cooling above 3.8 GeV/c
High Energy Storage RingHESR is presently being designed in a consortium formed between FZ-Jülich, GSI and UU
The electron cooler is the main responsibility of Uppsala University.
HESR Electron Cooler
e-beam parameters: HESR FermilabEnergy (MeV) 0.45 - 4.5 4.3Current (Amp) 1 0.5Solenoid field (T) 0.2 0.01Straightness (µrad rms) 10 200
The cooling force needs to be stronger than at Fermilab to counteract the internal target
• Higher magnetic field
• Better straightness
Parameters for the HESR cooler:
Objective of Design StudyTask 12, HESR 2: Electron cooling
Description of work:
An important part of the work will be to construct prototypes of several construct prototypes of several critical parts of the systemcritical parts of the system. The exact content of the prototyping work will be determined in the course of the study. The CELSIUS electron cooling CELSIUS electron cooling systemsystem, which will then be taken out of use for its purpose at the CELSIUS ring, will be used as a test benchwill be used as a test bench, and will be used to test electron beam diagnostic equipment as well as to make tests related to the high-voltage behaviour of the system.
Other aspects of the electron cooling system, including the method to charge the high-voltage terminal, the problems to create the requiredthe problems to create the required quality of the magnetic field and stability of the high voltagequality of the magnetic field and stability of the high voltage, the required ultra-high vacuum and the electron beam optics and stability of the electron beam transport will be investigated.will be investigated.
In the final reportfinal report all experience will be summarized, drawings will reflect the status of the component development, and a first design of a control system for this high power device will be suggested on the basis of the accumulated experience.
Present Project Plan
Different sub-projects, responsible persons
• Design high-voltage column G. Norman, A Shemyakin
• Test prototype high-voltage solenoid G. Norman
• Design magnet system for electron beam transport
K. Rathsman, D. Reistad
• Design and test magnet field measurement systemT. Bergmark
• Design vacuum chamber, make prototypeT. Bergmark, O. Byström
• Design and test prototype scraperB. Gålnander, T. Lofnes,
• Design electron gun and collectorG. Norman
• Tests on high-voltage regulation at Uppsala Tandem PelletronT. Bergmark
High Voltage Column
GunCollector
Pellet chain
HV solenoid
High voltage solenoid prototype
• Cover delivered
• Coils mounted and delivered Feb. 2007
• Sections of 3 metres (24 m total length)• Pancake coils (normal conducting), individually adjustable to achieve 10 μrad rms straightness
Magnet system
• Scraper and pick-up electrodes.
• Horizontal and vertical dipole windings.
Deliverable 29, Report on solenoids and toroids, delayed
• Design revised, making coils smaller and less expensive,
saving about 30 % of copper.
• Superconducting alternative is also considered
Measurement carriageand sensor head
• Prototypes are being manufactured
• Test will be performed during 2007
Magnetic Field Measurement System
needed for pancake alignment
Prototype test set-up
Carriage prototype
Vacuum Chambers
with rails for the Magnetic Field Measuring System
Test tube of 1 m, two sections of 2.8 m will be delivered week 5, 2007
Scraper tests at the CELSIUS coolerModification of CELSIUS cooler for scraper tests with electron beam
• Scraper prototype delivered next week
• Coils are being manufactured, delivered week 5, 2007
Outlook
• During spring 2007 several prototype tests will take place
• Autumn 2007, test evaluation and final report work
• No overall delay expected, HESR 2 will be finished by Feb. 2008.
• However, the Deliverable D29, “Report on solenoids and toroids”, is delayed until 1 March, 2007, since this sub-project has been given more weight compared to the original planning.
ID Task Name
1
2 Solenoids and toroids
3 design pancakes
4 design solenoids and toroids, including supports
5 D29 Report on solenoids and toroids
6 design correctors
7 design magnetic circuits
8 report on magnet system
9 preliminary design of high voltage tank
10
11 HV solenoid
12 design prototype HV solenoid
13 build prototype HV solenoid
14 mount HV solenoid test
15 perform HV solenoid tests
16 report on HV solenoid tests
17
18 Vacuum and neutralisation
19 prel. design vacuum chambers and clearing electrodes
20 understand neutralisation and vacuum
21 final design vacuum chambers and clearing electrodes
22
23 Magnetic measurement system
24 design tube and cart for m m system
25 build tube and cart for m. m. system
26 design prototype sensor head
27 build prototype sensor head
28 design and build optical and electronic system
29 design and build set-up for m. m. system
30 test prototype magnetic straightness measuring system
31 report on magnetic straightness measuring system
32
33
34 Diagnostics
35 design prototype scraper
36 build prototype scraper
37 test prototype scraper
38 design pick-up/scraper
39 build prototype pick-up/scraper
40
41 Test set-up for scraper
42 design changes in CELSIUS cooler for tests
43 build magnets/box/stands
44 make changes in CELSIUS cooler for tests
45 take CELSIUS cooler into operation
46
47 Gun and collector
48 design electron gun
49 design collector
50 Heat transfer calculations collector
51
52 HV regulation tests
53 make tests on hv regulation at Tandem Lab
54 discussions with Fermilab and NEC
55 report on hv regulation
56
57 final report
58 D32 (delivery of final report)
51%
100%
70%
03-02
30%
0%
0%
0%
63%
100%
51%
0%
0%
0%
61%
100%
100%
0%
61%
100%
79%
81%
0%
80%
44%
0%
0%
60%
100%
95%
0%
39%
0%
59%
100%
24%
30%
100%
73%
100%
63%
20%
77%
100%
20%
20%
0%
0%
01-31
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2006 2007 2008
Dag Reistad, Task Leader
Torsten Bergmark
Björn Gålnander, Deputy
Tomas Johnson
Tor Lofnes
Gunnar Norman
Olle Byström
Stefan Johnson
Tord Peterson
Karin Rathsman
Present group members
Collaboration with IKP (Ziemann, beam dynamics), MSL (Danared, magnetic field calculations), BINP Parkhomchuk et al., Fermilab, A. Shemyakin et al.
Thank you!
4.5 MeV tank
8 MeV tank
Layout