![Page 1: Herat Electrification Project (HEP) (IDA Grant D208-0-AFdocuments.worldbank.org/curated/en/163221507733399617/...Signing July 12, 2017 Implementation Progress S Effectiveness Pending,](https://reader031.vdocuments.site/reader031/viewer/2022030421/5aa8b6307f8b9a86188bd858/html5/thumbnails/1.jpg)
1
Herat Electrification Project (HEP)
(IDA Grant D208-0-AF)
Implementation Support Mission
August 7-10, 2017
Aide Memoire
I. Introduction
1. The first implementation support and review mission for the Herat Electrification Project (HEP) was
carried out from August 7-10, 2017.1 The mission met with the officials of the Ministry of Finance (MOF),
Ministry of Energy and Water (MEW), and Da Afghanistan Breshna Sherkat (DABS), electricity utility and the
Project Implementing Entity. A list of officials met during the mission is in Annex 1. The team wishes to
express its deep appreciation to MOF, MEW, and DABS for the productive discussions, access to information
and excellent cooperation during the mission. The findings of the aide memoire were agreed through exchange
of emails between the mission and DABS. This Aide Memoire is classified as a Public document under World
Bank’s Access to Information Policy.
II. Key Project Data
Key Dates
IDA Grant D208-0-AF Project Performance Ratings
Board Approval June 13, 2017 Achievement of PDO S
Signing July 12, 2017 Implementation Progress S
Effectiveness Pending, Deadline – October 9, 20172 Financial Management S
Closing January 31, 2022 Procurement S
Allocation (SDR 43.8 million) US$60 million Environment and Social S
Disbursed 0 Project Management MS
Disbursed (%) 0
MS = Moderately Satisfactory; S = Satisfactory
III. Achievement of Project Development Objective (PDO)
2. The project’s progress towards achievement of PDO is Satisfactory. The PDO is to provide access to
electricity to households, institutions, and businesses in selected areas of Herat Province, Afghanistan. The
project targets to provide 230,800 people and 1600 non-residential customers with new or improved electricity
service. The contractors for Component 1 of the project, which targets to cover 90,000 people, 1,250 business
enterprises, and 350 community institutions in four districts of Herat, have been selected. DABS is preparing
plans, feasibility studies, and terms of references to operationalize Components 2 and 3.
IV. Current Implementation Status
3. The current implementation status of the project is Satisfactory. The mission requested support from
Mr. Moheb Jabarkhail, Focal Point for World Bank Funded Projects, MOF and Mr. Aman Ghalib, the new Chief
Executive Officer of DABS, to expedite signing of Subsidiary Agreement between MOF and DABS. Signing
1 The mission members were: Messrs. Hung Tan Tran (Senior Energy Specialist and Task Team Leader(TTL)), Gunjan Gautam
(Operations Officer and co-TTL), Mohammad Zubair Stanikzai (Power Engineer), Abdul Baes Akhundzada (Power Engineer), Sayed
Mujtaba Shobair (Environmental Specialist), Mohammad Yasin Noori (Senior Social Development Specialist), Ahmed Shah Ahmadzai
(Financial Management Specialist), and Wahida Kakar (Team Assistant). Rehan Hyder (Senior Procurement Specialist) and Obaidullah
Hidayat (Environmental Specialist) remotely supported the mission. 2 Effectiveness deadline is 90 days after signing the Grant Agreement, which was July 12, 2017
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
![Page 2: Herat Electrification Project (HEP) (IDA Grant D208-0-AFdocuments.worldbank.org/curated/en/163221507733399617/...Signing July 12, 2017 Implementation Progress S Effectiveness Pending,](https://reader031.vdocuments.site/reader031/viewer/2022030421/5aa8b6307f8b9a86188bd858/html5/thumbnails/2.jpg)
2
and authorization of the Subsidiary Agreement is an effectiveness condition and should be met within 90 days
of July 12, 2017, the date of signing of the project’s Grant Agreement. The mission also requested Mr. Ghalib
to expedite signing of the Project Agreement between DABS and Bank. In response, DABS has committed to
signing Project Agreement and Subsidiary Agreement by August 30, 2017. The mission advised DABS to
improve its project management by filling the key positions in Project Implementation Unit (PIU) in a timely
manner.
V. Component-wise Implementation Status
4. The project has three main components:
a. Component 1 – Electrification of Four Districts in Herat Province (US$20 million): This component
supports investments for building a new 110 kilo-Volt (kV) transmission line, and four 110/20 kV
substations and medium and low voltage distribution networks in four districts of Herat Province -
Chesht, Obe, Karokh and Pashtun-Zarghoon. Component 1 includes:
i) Design, supply and installation of a 25 kilometer (km) tapping transmission line to the new
substation near Karokh from the existing 110 kV transmission line between the Salma Dam and the
existing Noor-ul-Jahad substation.
ii) Design, supply and installation of four 110/20 kV substations each with the capacity of 10 Mega-
Volt Ampere (MVA) in the districts of Chesht, Obe, Karokh and Pashtun-Zarghoon of Herat
Province.
iii) Supply of distribution network equipment for electrification of households, businesses, schools,
health centers and holy places in the four districts.
5. The activities under Component 1 were bid out in three lots of Bid Package Bid Package
NPA/DABS/95/W-1343/ICB of Herat Electrification Project (P162022), where each lot corresponds to a sub-
component.
a. Lot 1 - Design, Supply, Construction, Erection, Testing and Commissioning of Four Substations of
110/20kV each at Chesht, Hobai, Karokh & Pashton Zarghoon,
b. Lot 2 – Design, Supply, Construction, Erection, Testing and Commissioning of 110kV Single Circuit
tapping transmission line from Salma (Hydel) to Karokh Substation and
c. Lot 3 -Supply of Goods for the Electrification of 20/0.4kV network in four districts of Herat Province
6. DABS had submitted Bid Evaluation Report (BER) recommending contractors for Bank’s review and
clearance; and Bank provided Conditional No Objection on June 6, 2017, subject to inclusion of environmental
and social (E&S) safeguards clauses in the contracts. DABS submitted revised contracts on August 10, 2017;
and Bank reviewed the revisions and advised DABS to submit the contracts for approval by National
Procurement Authority (NPA). Signing of the contracts is expected by August 30, 2017; following which the
winning bidders will be disclosed. The inclusion of safeguards (ENV & SOC) clauses with a reference to be
made in the contract agreement to the site-specific Environmental and Social Management Plan (ESMP)
implementation would be adequate at this stage. However, the final site-specific ESMP shall be signed/initialed
by the contractor once the plan is finalized- reviewed by the WB-safeguards team.
7. The draft Technical Feasibility Study Report for electrification of four districts has been sent to DABS
in June 2017. DABS agreed to study this Report and provide feedback to the Bank by August 30, 2017.
8. The implementation progress of Component 1 is Satisfactory.
9. Component 2 – Grid Densification, Extension, and Off-grid Pilots in Herat Province (US$36
million): This component will extend, intensify, and upgrade the existing grid to provide access to new or
![Page 3: Herat Electrification Project (HEP) (IDA Grant D208-0-AFdocuments.worldbank.org/curated/en/163221507733399617/...Signing July 12, 2017 Implementation Progress S Effectiveness Pending,](https://reader031.vdocuments.site/reader031/viewer/2022030421/5aa8b6307f8b9a86188bd858/html5/thumbnails/3.jpg)
3
improved electricity service to other parts of Herat Province. Component 2 will also support piloting of solar
mini-grids and solar-hybrid mini-grids in villages. The mission requested DABS to start activities to prepare
subprojects under Component 2.
a. DABS has agreed to prepare a plan for grid densification, extension, and strengthening by August 30,
2017. This plan is will include the subproject options of installing capacitor banks in substations for
reactive power compensation, procurement of key spare parts for distribution network in Herat, and
grid extension and densification.
b. DABS has agreed to share the Terms of Reference (TOR) for feasibility study of solar-hybrid mini-
grids for Bank’s review by August 30, 2017.
10. The implementation progress of Component 2 is Satisfactory.
11. Component 3 – Technical Assistance (US$4 million): This component funds technical assistance
(TA) to ensure timely and quality completion of the project and to enhance capacity of DABS. The sub-
components of Component 3 and updates are as follows:
a. Assistance to DABS for Project Implementation: This sub-component would provide expert
assistance to DABS in key aspects of project implementation including: project planning and
supervision, procurement, financial management (FM), and feasibility assessments for candidate
subprojects under Component 2. DABS is implementing several measures, as required by the Grant
Agreement, to strengthen its fiduciary capacity. The details are explained in sections below.
Additionally, DABS PIU is hiring three local consultants to work at Herat sites. These comprise of a
Civil Engineer, an Environmental Specialist, and a Social Development Specialist. These consultants
are expected to join PIU by September 10, 2017.
b. Supervision Consultant: This sub-component allows DABS to hire consultant to support Project
Implementation Unit (PIU) in the supervision of the project. DABS is in the process of hiring an
international Electrical Engineer with the expected on-boarding date of September 30, 2017.
c. Environmental and Social Safeguards Measures: This sub-component funds DABS to conduct site
specific Environmental and Social Impact Studies (ESIA) and prepare and oversee/implement
corresponding Environmental and Social Management Plans and Resettlement Action Plans. The
DABS team will be reinforced by two additional local staff (one male and one female) to help manage
safeguards from the DABS office in Herat. Details of safeguards instruments and processes are in the
sections on Safeguards below.
d. Institutional Strengthening for DABS: This sub-component finances technical support and training
to DABS personnel in areas where additional capacity building is required. This component also
supports DABS in implementing awareness programs, especially targeted to women, on electricity uses
as well as on health and safety aspects of electricity use and infrastructure. DABS has agreed to submit
a Training and Capacity Building Plan for Bank’s review by September 30, 2017. DABS and Bank’s
teams working in Afghani energy sector have faced difficult procurement challenges. To increase
DABS’ capacity in procurement, a training is being organized in Sri Lanka between September 18-21,
2017.
e. Studies for further Grid Extension: This sub-component supports feasibility studies to investigate
synchronization options and further grid extension studies in Herat Province including geo-spatial
analysis and load flow study of the system. Studies will be commissioned based on DABS’ plan to
implement Component 2.
f. Development of a Grid Code: This sub-component supports the review of existing standards and
procedures and the preparation of a Grid Code for the Afghan power system consistent with best
international practices. DABS has shared the TOR for hiring the consultant for development of Grid
Code with the Bank. Bank will review the TOR; and the Bank will provide its comments and No
Objection by August 30, 2017.
g. Financial Modelling for DABS: This sub-component supports development of a financial planning
![Page 4: Herat Electrification Project (HEP) (IDA Grant D208-0-AFdocuments.worldbank.org/curated/en/163221507733399617/...Signing July 12, 2017 Implementation Progress S Effectiveness Pending,](https://reader031.vdocuments.site/reader031/viewer/2022030421/5aa8b6307f8b9a86188bd858/html5/thumbnails/4.jpg)
4
model that can be used to prepare pro-forma financial statements, cash flow projections, debt service
obligations and financial ratios for DABS under alternative scenarios relating to capital investment,
investment financing, sales forecasts, tariffs and input costs.
12. The implementation progress of Component 3 is Moderately Satisfactory. DABS can improve this
rating by staffing the PIU is a timely manner and by complying with requirements of the Grant Agreement.
VI. Safeguards and Fiduciary
Environment and Social Safeguards
13. The E&S safeguards performance of the project is Satisfactory.
14. The contracts for Lots 1, 2, and 3 of Bid Package NPA/DABS/95/W-1343/ICB of Component 1 will
include provisions of ESMP and Resettlement Action Plan (RAP) in line with the approved Environmental and
Social Management Framework (ESMF) and Resettlement Policy Framework (RPF) and findings of ESIA.
Revisions have been introduced to contracts for Lots 1 and 2 to state: (i) DABS will be responsible for
preparation of ESIA, ESMP, and RAP; and (ii) the contractors will be responsible for implementation of ESMP
for transmission line and substations. For RAP preparation, DABS shall engage qualified staff (national and
international) and will need to coordinate the activities of agencies contributing to RAP preparation, such as
Afghanistan Independent Land Authority (AILA)- Arazi- Herat to be engaged to conduct land Tasfiya (or
clearance) process. The final draft RAP for lot-2- TL will be subject to meaningful consultation with affected
persons and community and it shall also be shared with the WB for review. The final RAP after Bank review
shall be disclosed in-country on DABS website and shall also be available at locations that are convenient to
the affected communities. Construction work cannot begin in areas with displacement impacts until
compensation to affected persons is made.
15. For Lot 1 covering four sub-stations, DABS will finalize the ESMP, which will be annexed to the
contract. DABS submitted the draft ESMP for Bank’s review and has received comments from Bank on August
24, 2017.
16. For Lot 2 covering the transmission line, DABS will initiate ESIA with the target of submitting ESIA
and associated ESMP and RAP by November 14, 2017 for Bank’s review and clearance. The draft terms of
reference for the ESIA and RAP shall be shared with the WB for review.
17. For Lot 3 covering supply of distribution network equipment, DABS will prepare and implement ESMP
as DABS will be installing the distribution grid with its own resources. If contractors are mobilized by DABS
for installing the distribution grid, DABS will oversee the implementation of ESMP by the contractors. ESMP
for Lot 3 will be submitted for Bank’s review and clearance by November 20, 2017.
18. The mission requested DABS to work towards compliance of E&S safeguards conditions of the Grant
Agreement, which are due within 90 days after the project is effective. The Grant Agreement requires DABS
to: (i) hire one international Safeguard Specialist, whose terms of reference shall be agreed between the DABS
and the Bank, to be part of the PIU; and (ii) establish and thereafter maintain throughout project implementation,
a project grievance redress mechanism (GRM), with staffing and operating procedures acceptable to the Bank,
for monitoring and addressing the concerns of people affected by the project and building public and stakeholder
support for the project. DABS has agreed to:
a. Hire international Safeguards Consultant by September 15, 2017. The candidates for this position have
been shortlisted. Final interviews and contract signing is expected to complete by the end of August
2017. The international Safeguards Consultant is expected to contribute in ESIA and RAP preparation
of the transmission line.
b. Establish effective GRM under HEP by September 15, 2017, the key tasks will include: (i)
establishment of Grievance Redress Committee (GRC) at project and districts level; (ii) training of GRC
![Page 5: Herat Electrification Project (HEP) (IDA Grant D208-0-AFdocuments.worldbank.org/curated/en/163221507733399617/...Signing July 12, 2017 Implementation Progress S Effectiveness Pending,](https://reader031.vdocuments.site/reader031/viewer/2022030421/5aa8b6307f8b9a86188bd858/html5/thumbnails/5.jpg)
5
members on grievance handling-disseminating public information among local communities in all four
districts to use grievance service; (iii) establishment of multiple uptake channels for grievance
registration; and (iv) registration of all grievances at both central database (or excel sheet) and project
logbooks to enable tracking and review.
Fiduciary
19. The performances on procurement and financial management are rated Satisfactory.
Financial Management (FM)
20. DABS is expected to comply with the FM conditions of the Grant Agreement within 90 days of
effectiveness of the project. To fulfill the conditions, DABS has agreed to:
a. Hire an Internal Audit Consultant by September 25, 2017; and publish the notice for hiring of a cashier
by November 22, 2017.
b. Submit draft FM Manual for Bank’s review by August 30, 2017. Bank had earlier reviewed the first
draft of the FM Manual and suggested revisions.
21. Additionally, DABS is exploring the option of hiring an international Senior Finance Officer, who will
improve the FM processes of Bank’s projects; review and improve FM Manual; and build capacity of the DABS
team in FM. DABS has agreed to share the draft TOR for Senior Finance Officer by August 30, 2017 for Bank’s
review.
22. DABS has agreed to create Designated Account (DA) of the project by August 30, 2017. The mission
requested DABS PIU to coordinate with MOF-Aid Coordination Unit to set-up the DA and with Bank’s FM
Specialist and Loan Officer to set up client connection interface for the project.
Procurement
23. DABS is expected to comply with the procurement related condition of the Grant Agreement within 90
days of effectiveness of the project. To fulfill the condition, DABS has agreed to:
a. Submit the draft Procurement Processing Manual for Bank’s review by September 30, 2017. The
Procurement Processing Manual will cover procurement processes and procurement services standards
for DABS. This manual will also align DABS processes with Bank’s New Procurement Framework
and Procurement Regulations. The manual will be discussed during the procurement training planned
in September 2017.
24. DABS and the Bank had agreed on taking several measures to resolve the procurement challenges faced
by several Bank projects at DABS. Implementation of HEP is expected to benefit from these measures. The
planned Consultative Workshop on the Procurement Reforms for DABS & Introduction to New Procurement
Framework in September will provide a structured roadmap to implementation of these reforms
VII. Key Agreed Actions
25. A detailed table of actions agreed between the mission and DABS is attached as Annex 3. Below are
some of the key actions agreed:
Agreed Action Responsibility Deadline
1 Signing of Project Agreement between DABS and Bank DABS and Bank SIGNED
2 Signing of Subsidiary Agreement between MOF and DABS MOF and DABS August 30, 2017
3 Legal Opinion by Ministry of Justice (MOJ) to Project MOF and MOJ September 30, 2017
![Page 6: Herat Electrification Project (HEP) (IDA Grant D208-0-AFdocuments.worldbank.org/curated/en/163221507733399617/...Signing July 12, 2017 Implementation Progress S Effectiveness Pending,](https://reader031.vdocuments.site/reader031/viewer/2022030421/5aa8b6307f8b9a86188bd858/html5/thumbnails/6.jpg)
6
Agreement and to Subsidiary Agreement and DABS
4 Signing of contracts for Lots 1, 2, and 3 of Bid Package
NPA/DABS/95/W-1343/ICB
DABS SIGNED
5 Hiring of international Safeguards Specialist DABS September 20, 2017
6 Hiring of Cashier DABS November 20, 2017
7 Submit first draft of plan for instituting a GRM DABS August 30, 2017
8 DABS provide feedback on Technical Feasibility Study
Report and plan for enhancing the stability of the network
DABS August 30, 2017
9 Preparation of TOR for Grid Code DABS Prepared
VIII. Timing of Next mission
26. The next implementation support mission is planned for January/February 2017.
![Page 7: Herat Electrification Project (HEP) (IDA Grant D208-0-AFdocuments.worldbank.org/curated/en/163221507733399617/...Signing July 12, 2017 Implementation Progress S Effectiveness Pending,](https://reader031.vdocuments.site/reader031/viewer/2022030421/5aa8b6307f8b9a86188bd858/html5/thumbnails/7.jpg)
7
Annex 1
List of Officials Met
Ministry of Finance (MOF)
1. Mr. Moheb Jabarkhail, Coordinator for the World Bank and ARTF Portfolio, MOF
2. Mr. Zahiruddin Kharotai, Budget Specialist, MOF
Da Afghanistan Breshna Sherkhat (DABS)
1. Mr. Aman Ghalib, Chief Executive Officer, DABS
2. Mr. Hazrat Shah Hameedi, PIU Director, DABS
3. Mr. Saifullah Lodin, National Procurement Specialist, DABS
4. Mr. Sayed Jawad Hadi, Herat Electrification Project Manager, DABS
5. Mr. Fawad Ahmad Ibrahimi, Finance Specialist, DABS
6. Mr. Mohammad Tawoos Wafa, Social Safeguard Specialist, DABS
![Page 8: Herat Electrification Project (HEP) (IDA Grant D208-0-AFdocuments.worldbank.org/curated/en/163221507733399617/...Signing July 12, 2017 Implementation Progress S Effectiveness Pending,](https://reader031.vdocuments.site/reader031/viewer/2022030421/5aa8b6307f8b9a86188bd858/html5/thumbnails/8.jpg)
8
Annex 2
Results Framework for Herat Electrification Project
Project Development Objective: Provide access to electricity to households, institutions, and businesses in selected areas of Herat Province, Afghanistan.
Project Development Objective Indicators FY
Indicator Name Unit Baseline
YR1 (as of
August 11,
2017)
YR2 YR3 YR4 YR5 End
Target
People provided with new or improved electricity service Number 0 0 0 30000 150000 230800 230800
Achievement 0
Number of non-residential consumers provided with new or improved
electricity service Number 0 0 0 600 1600 1600 1600
Intermediate Results Indicators FY
Indicator Name Baseline
YR1 (as of
August 11,
2017)
YR2 YR3 YR4 YR5 End
Target
Transmission line constructed under the Project kilometers 0 0 0 25 25 25 25
Achievement 0
Capacity of new substations constructed and commissioned Mega Volt
Ampere 0 0 0 20000 40000 40000 40000
Achievement 0
Grid extension study prepared
Yes
(Y)/No
(N)
N Y Y Y Y Y Y
Achievement N
Grid code prepared Y/N N N Y Y Y Y
![Page 9: Herat Electrification Project (HEP) (IDA Grant D208-0-AFdocuments.worldbank.org/curated/en/163221507733399617/...Signing July 12, 2017 Implementation Progress S Effectiveness Pending,](https://reader031.vdocuments.site/reader031/viewer/2022030421/5aa8b6307f8b9a86188bd858/html5/thumbnails/9.jpg)
9
Achievement N
Indicator Name Baseline
YR1 (as of
August 11,
2017)
YR2 YR3 YR4 YR5 End
Target
Additional distribution grid asset created Y/N N N N Y Y Y Y
Achievement N
Off-grid pilots implemented Y/N N N N Y Y Y Y
Achievement N
Percentage of grievances satisfactoriy resolved within stipulated
timeframe Percent 0 0 60 60 60 60 60
Achievement 0
Percentage of CDCs consulted on project activities affecting them in the
project intervention areas Percent 0 0 100 100 100 100 100
Achievement 0
Number of girl schools with electricity service Number 0 0 0 1 3 5 5
Achievement 0
Awareness campaigns targeted to women on uses of electricity and safety
aspects Y/N N Y Y Y Y Y Y
Achievement N
![Page 10: Herat Electrification Project (HEP) (IDA Grant D208-0-AFdocuments.worldbank.org/curated/en/163221507733399617/...Signing July 12, 2017 Implementation Progress S Effectiveness Pending,](https://reader031.vdocuments.site/reader031/viewer/2022030421/5aa8b6307f8b9a86188bd858/html5/thumbnails/10.jpg)
10
Annex 3
List of Agreed Actions
S.No Actions Responsibility Deadline Remarks
Legal Agreements
1 Signing of Project Agreement between Bank and
DABS DABS and Bank August 30, 2017 SIGNED
1.a Authorization of Project Agreement DABS and MOJ September 13, 2017
DABS and MOF will obtain legal
opinion from MOJ on Project
Agreement.
2 Signing and Authorization of Subsidiary
Agreement between DABS and MOF DABS and MOF August 30, 2017
Effectiveness Condition of the
Grant Agreement
2.a
DABS to prepare Subsidiary Agreement and send
for Bank's review DABS PIU August 20, 2017 DONE
Bank to provide feedback World Bank August 25, 2017 DONE
DABS and MOF to execute the
Subsidiary Agreement DABS and MOF August 30, 2017
2.b Authorization of Subsidiary Agreement MOF September 30, 2017
MOF will obtain legal opinion on
Subsidiary Agreement.
S.No Actions Responsibility Deadline Remarks
Component 1
1 Inclusion of ESMP provisions in contracts for
Lots 1 and 2 DABS PIU August 30, 2017
Bank clears ESMP provision in the
contracts World Bank August 20, 2017 DONE
![Page 11: Herat Electrification Project (HEP) (IDA Grant D208-0-AFdocuments.worldbank.org/curated/en/163221507733399617/...Signing July 12, 2017 Implementation Progress S Effectiveness Pending,](https://reader031.vdocuments.site/reader031/viewer/2022030421/5aa8b6307f8b9a86188bd858/html5/thumbnails/11.jpg)
11
NPA clears EMSP provision in the
contracts DABS PIU August 30, 2017 DABS - PIU to follow up with NPA
2 Signing of contracts for Lots 1,2, and 3 DABS August 30, 2017 SIGNED
3
Study on Technical Feasibility Study Report and
preparation of plan for enhancing the stability of
the network of 4 districts DABS August 30, 2017
S.No Actions Responsibility Deadline Remarks
Component 2
1 DABS prepares the plan for grid extension,
strengthening, densification DABS PIU August 30, 2017
2
Prepare TOR for hiring consultant for feasibility
study of solar-hybrid mini-grids and shares with
Bank DABS PIU August 30, 2017
S.No Actions Responsibility Deadline Remarks
Component 3
1 Training and Capacity Building Plan - including
capacity building of Heart Office staff DABS PIU August 30, 2017
2 Hire Consultant for preparing Grid Code DABS PIU
DABS prepares TOR and shares with Bank DABS PIU August 30, 2017 1st draft has been submitted
Bank reviews and clears the TOR WB September 5, 2017
DABS publishes Request for Proposal DABS PIU September 15, 2017
Consultants are shortlisted October 15, 2017
NPA approves the shortlist DABS October 30, 2017
Issuance of RFP to consultant DABS November 1, 2017
Consultant submits proposal November 30, 2017
DABS evaluates the proposal DABS December 15, 2017
Contract is signed with consultant DABS January 1, 2018
On-boarding of consultant January 15, 2018
3 Hiring Cashier at DABS for WB PIU DABS PIU November 20, 2017
![Page 12: Herat Electrification Project (HEP) (IDA Grant D208-0-AFdocuments.worldbank.org/curated/en/163221507733399617/...Signing July 12, 2017 Implementation Progress S Effectiveness Pending,](https://reader031.vdocuments.site/reader031/viewer/2022030421/5aa8b6307f8b9a86188bd858/html5/thumbnails/12.jpg)
12
TOR has been prepared and cleared by
the Bank August 9, 2017 DONE
DABS will advertize the vacancy for
cashier
DABS - Mr. Fawad
Ahmad Ibrahimi September 9, 2017
Final Interview of Shortlisted Candidates DABS PIU September 20, 2017
Selection of Cashier DABS PIU October 21, 2017
On-boarding of Cashier
DABS - PIU and
Management November 20, 2017
4
Hiring of Environmental Specialist, Social
Development Specialist, and Civil Engineer in
DABS - Herat Office DABS PIU September 15, 2017
TORs approved by Bank
WB Safeguards
Specialists and TTL Completed
Advertise positions DABS PIU Completed
Final Interview of Shortlisted Candidates DABS PIU September 15, 2017
Selection of local staff DABS PIU September 30, 2017
On-boarding of the local staff in Herat
Office DABS PIU October 10, 2017
5 Hiring of International Safeguards Consultant DABS PIU September 15, 2017
Condition of Grant Agreement, due
within 90 days of project
effectiveness.
DABS will finalize the ToR for
International Safeguards Consultant and submit for
Bank's Clearance DABS PIU COMPLETED
WB will clear the ToR International
Safeguards Consultant
WB Safeguards
Specialists and TTL COMPLETED
![Page 13: Herat Electrification Project (HEP) (IDA Grant D208-0-AFdocuments.worldbank.org/curated/en/163221507733399617/...Signing July 12, 2017 Implementation Progress S Effectiveness Pending,](https://reader031.vdocuments.site/reader031/viewer/2022030421/5aa8b6307f8b9a86188bd858/html5/thumbnails/13.jpg)
13
DABS will advertise the vaccancy for
International Safeguards Consultant DABS PIU COMPLETED
Final Interview of Shortlisted Candidates DABS PIU August 30, 2017
Contract Signing of International
Safeguards Consultant DABS PIU September 10, 2017
On-boarding of International Safeguards
Consultant DABS PIU September 20, 2017
S.No Actions Responsibility Deadline Remarks
Procurement
1 DABS shares first draft of Procurement
Processing Manual with Bank DABS PIU September 30, 2017
2 DABS participates in Procurement Training in
Srilanka
DABS PIU and World
Bank September 18, 2017
S.No Actions Responsibility Deadline Remarks
Financial Management
1 Disbursement Readiness: Designated Account
(DA) and Client Connection September 10, 2017
Submit Grant Agreement and
Disbursement Letter to Ministry of Finance (MoF)
- Aid Coordinating Unit (ACU) along with Request
Letter to create DA
DABS - Mr. Fawad
Ahmad Ibrahimi August 12, 2017
MoF has allocated US$11.667
million to DABS under HEP for
Afghanistan Fiscal Year 1316
MoF-ACU will forward the request for
creating DA to Da Afghanistan Bank (DAB) MOF August 13, 2017
DABS will set up a DA DAB August 30, 2017
![Page 14: Herat Electrification Project (HEP) (IDA Grant D208-0-AFdocuments.worldbank.org/curated/en/163221507733399617/...Signing July 12, 2017 Implementation Progress S Effectiveness Pending,](https://reader031.vdocuments.site/reader031/viewer/2022030421/5aa8b6307f8b9a86188bd858/html5/thumbnails/14.jpg)
14
DABS will request WB to set up Client
Connection
DABS - Mr. FSawad
Ahmad Ibrahimi August 30, 2017
DABS - Mr. Fawad Ahmad
Ibrahimi is FM Specialist at DABS
PIU
Client Connection to be set up by World
Bank WB - Chennai September 10, 2017
2 Financial Management Manual (FMM) October 20, 2017
Condition of Grant Agreement, due
within 90 days of project
effectiveness.
DABS will submit draft FMM for WB's
review
DABS - Mr. Fawad
Ahmad Ibrahimi August 30, 2017
Bank will provide comments on draft
FMM
WB: Ahmed Shah
Ahmadzai September 15, 2017
FMM is finalized with WB comments
and submitted for Bank's Clearance DABS PIU September 30, 2017
Bank Clears FMM
WB: Ahmed Shah
Ahmadzai October 5, 2017
DABS Management Approves Final
FMM
DABS PIU and
Management October 15, 2017
DABS will submit Approved FMM for
Bank's records DABS PIU October 20, 2017
3 Hiring Internal Audit Consultant for DABS PIU October 15, 2017
Condition of Grant Agreement, due
within 90 days of project
effectiveness.
DABS will finalize the ToR for Internal
Audit Consultant and submit for Bank's Clearance
DABS: PIU and Mr.
Fawad Ahmad Ibrahimi COMPLETE
WB will clear the ToR for Internal Audit
Consultant
WB FM Specialist and
TTL COMPLETE
DABS will advertise the vaccancy for
Internal Audit Consultant DABS PIU COMPLETE
Candidates shortlisted DABS PIU COMPLETE
Written test conducted by DABS DABS PIU September 15, 2017
Final Interview of Shortlisted Candidates
DABS PIU and
Management September 30, 2017
![Page 15: Herat Electrification Project (HEP) (IDA Grant D208-0-AFdocuments.worldbank.org/curated/en/163221507733399617/...Signing July 12, 2017 Implementation Progress S Effectiveness Pending,](https://reader031.vdocuments.site/reader031/viewer/2022030421/5aa8b6307f8b9a86188bd858/html5/thumbnails/15.jpg)
15
Selection of Internal Audit Consultant
DABS PIU and
Management October 10, 2017
On-boarding of Internal Audit Consultant
DABS PIU and
Management October 15, 2017
S.No Actions Responsibility Deadline Remarks
Environmental and Social Safeguards
1 DABS operationalized GRM DABS PIU September 15, 2017
Condition of Grant Agreement, due
within 90 days of project
effectiveness.
DABS will provide a plan for GRM DABS PIU August 30, 2017
WB to review and clear World Bank September 5, 2017
DABS to start implementation of GRM DABS PIU September 15, 2017
2 Capacity Building Plan for E&S Supervison and
Management September 15, 2017
Draft Plan to be shared with Bank August 30, 2017
Finalize Capacity Building Plan September 15, 2017
3
DABS to finalize site specific ESMP for four
substations and include in contract for Lot 1 of
Component 1 DABS PIU September 1, 2017
WB reviews and comments on draft ESMP World Bank August 16, 2017 DONE
DABS will finalize ESMP DABS PIU August 30, 2017 DONE
Bank will review contract with ESMP World Bank August 30, 2017 DONE
ESMP will be included in contract DABS PIU September 10, 2017
4 ESIA and ESMP for transmission line is finalized November 30, 2017
Draft ToR for ESIA with RAP and ESMP DABS PIU August 30, 2017
WB clears World Bank September 4, 2017
DABS will prepare ESIA inhouse DABS PIU November 25, 2017
ESIA and ESMP cleared by WB World Bank November 30, 2017
5 Draft ESMP for Lot 3 - Distribution work December 10, 2017
DABS shares draft ESMP for Lot 3 -
Distribution work with Bank DABS PIU November 20, 2017
![Page 16: Herat Electrification Project (HEP) (IDA Grant D208-0-AFdocuments.worldbank.org/curated/en/163221507733399617/...Signing July 12, 2017 Implementation Progress S Effectiveness Pending,](https://reader031.vdocuments.site/reader031/viewer/2022030421/5aa8b6307f8b9a86188bd858/html5/thumbnails/16.jpg)
16
WB reviews and finalizes World Bank November 30, 2017
DABS will finalize ESMP DABS PIU December 10, 2017
![Page 17: Herat Electrification Project (HEP) (IDA Grant D208-0-AFdocuments.worldbank.org/curated/en/163221507733399617/...Signing July 12, 2017 Implementation Progress S Effectiveness Pending,](https://reader031.vdocuments.site/reader031/viewer/2022030421/5aa8b6307f8b9a86188bd858/html5/thumbnails/17.jpg)
17