Helix WellOps UK
Subsea Expo
Helix Decommissioning Support
‘New Approach to P&A’
Ekene Ogbechie
Business Development Manager
Navigating the present, focusing on the future.
Agenda
2 Navigating the present, focusing on the future .
1. P & A Overview
• Traditional MODU approach
• Alternate Approach
2. Challenges
3. New Technology
• ROAM
4. Solutions
5. Helix Decommissioning Support
P&A Overview
Navigating the present, focusing on the future .
Traditional Approach
• Use of MODU & Jack Ups
• Use of 21” Marine Riser
• BOP Stack Use
• One size fits All from simple to complex well abandonments
P&A Overview
Navigating the present, focusing on the future .
Alternate Approach
• Use Of the ROAM
• On a Heavy Well Intervention Vessel
• 8.5/8” HP Riser rather than the 21” Marine Riser
• IRS Stack rather than BOP Use
• EDP/LRP
• TRT
• Abandonment application is tailored to well type and reservoir need (no
requirement for over loading equipment spread)
Challenges
Navigating the present, focusing on the future .
1. Environmental Containment
2. ESD
3. Deck handling
4. Regulatory approval
New Technology - ROAM
6
Layout
18-3/4” Re-entry mandrel
18-3/4” 10,000psi Annular BOP
18-3/4” 10,000psi Double BOP
–Shear & Seal rams
18-3/4” H4 connector
Flow spools with 3” stabs
2” circulation lines
Emergency Disconnect
OneSubsea Subsea Control Module
Functionality
– Normal Operations = Environmental Containment • Annular BOP and circulation lines
– Pressure Test & In-flow test
– Emergency = Well Isolation • Dual Shear-Seal Rams
• EQD functions
Lower overall cost of P&A
• De-risk P&A campaign by using Cost effective HWIV
– Enable logging behind casing by pulling Upper Completion
open water
– Full Well P&A capabilities by addressing remediation scenario
• Minimize use of Drilling Rig for P&A
New Technology - ROAM
7
ROAM
Workstring
HP riser, annulus pipe, umbilical
IRS w/ SJDF
Circulation Jumper
ROAM E/H controls
Wellhead
Phase 1 Reservoir (lower) barriers
Phase 2 Intermediate (upper) barriers
Phase 3 WH removal
Bullhead tubing Mechanical Plugs
cement plugs on CT/DP
Release & Recovery
Tubing retrieval
Permanent plugs Across/ recover
casings
Surface Plug Conductor removal Seabed Clearance
P&A operational steps with ROAM
– Full bore access
– Deployed in parallel over the side
– Unset and pull TH open water
– Enabler for Intermediate Abandonment
– Well Isolation capability
Well Preparation
HWIV + IRS
LWIV LWIV Diving Well prep (Barriers, injectivity test, drift run) Bull heading/ circulation Mechanical plugs Through tubing cement VXT recovery
As per LWI + CT mechanical access + CT cement placement
Open water Services with specialized tooling for cutting + Infrastructure Decommissioning + Seabed Clearance
MODU c/w CWOR MODU c/w BOP
Through Bore Full Bore
Q7000 + ROAM
LWIV +
Solutions
Navigating the present, focusing on the future .
1. Environmental Containment
1. Fully flushed well envelop to minimum of 30ppm (NS) or client specified
cleanness levels. Bottom (wellhead monitoring as well as at surface.
2. ESD
1. 2 X Shear Seal Ram (18.3/4” BOP Rams with capacity to cut casing).
3. Deck handling
1. Hanger & pipe handling system on vessel as well as NORM including
bonded laydown areas
4. Regulatory approval
1. Submission made to BSEE (GoM)
2. Submission to HSE as part of Q7000 safety case in Q1 2018
Q7000 – Efficiency gains
10
Mobilisation, Transit , Set-up , in-field move & Demobilisation
Rig up & service change w/ Helix Tension Frame
– WL/SL/CT combined off centre, pre-stabbed & tested off-line
No dual bore riser requirement
– LRP/EDP deployment weather window is restrictive compared to IRS
ZERO man-riding & over side working
– Safe access gangway +/- 17° (+/– 4m hve) W2W system
– No requirement for Standby vessel to carry out close over
Deck skidding & auto pipe handling
Modular well test system in bunded area
ROV Deployment / Recovery
– Via cursor system to 18.5m water depth
Dedicated Multi skilled crew
11 Navigating the present, focusing on the future .
Helix Decommissioning Support
Helix Decommissioning Support
• All Inclusive Service Offering
• We own the assets
• Including vessels, SIL, IRS, ROV, Trenchers,
• Have relevant experience
• In house crew not 3rd party – many with 20yrs+ experience
• Includes marine, intervention, diving, ROV
• Single contracting
• Helix Well Ops ↔ Canyon ↔ One Subsea ↔ Schlumberger
• Contractual flexibility
• Risk/reward, lump sum, qualified TCE etc.
PM & Engineering │Pipeline Survey │Hot tap │Pipeline flushing │Pipeline
recovery │Pipeline trenching│Mattress recovery │Sat diving │Jacket diving │
Well work │ Facility removal │Structure Cutting │ Heavy lifts │ Wellhead removals │
│Seabed clean up │Overtrawl │Clearance certificate
12
Thank you
HLX Listed NYSE®
Follow Helix on Twitter - @Helix_ESG
www.linkedin.com/company/helix-energy-solutions-group
Navigating the present, focusing on the future .
30 Years as the leader in
Rigless Well Intervention
and P&A Services