    HEIJUNKAAUTOMOTIVE SYSTEMS INGEENIERING

    INSTITUTO POLITCNICO NACIONALESCUELA SUPERIOR DE INGENIERA MECNICA Y

    ELCTRICAUNIDAD AZCAPOTZALCO

    SUBJECT: TPICOS SELECTOS DE INGENIERA

    TEACHER: JOS ALBERTO LPEZ ISLAS

    PRESENTERS:

    GONZLEZ ARCEO RAMN SARMIENTO HERRERA HERIBERTO SOBERANES GARCA EDREI SOLS PUEBLA SERGIO GUSTAVO YANIZ MRQUEZ ALEXIS

    TEAM 4

  • 8/14/2019 Heijunka EN INGLS.pptx

    2/14

    TOYOTAS HOUSE

    2

  • 8/14/2019 Heijunka EN INGLS.pptx

    3/14

    HEIJUNKA DEFINITON

    Leveling customer demand through the volume of production in

    a uniform period of time

    3

    HEI: PlaneJUN: LevelKA: Performance

  • 8/14/2019 Heijunka EN INGLS.pptx

    4/14

    GENERAL OBJETIVE

    Remove Mudas bystandardization ofwork.

    Reduce inventories.

    SPECIFIC OBJETIVES

    Load balance production lines, having an order ofmanufacture of the products.

    4

  • 8/14/2019 Heijunka EN INGLS.pptx

    5/14

    HEIJUNKA CHARACTERISTICS

    It can be used in conjunction with other tools of LeanManufacturing.

    Brings stability in the manufacturing process

    Product Leveling Production Leveling

    5

  • 8/14/2019 Heijunka EN INGLS.pptx

    6/14

    HEIJUNKA BOX

    Also called leveling box, is a physical tool used to level the volumeand variety of production for a certain period of time (pitch)using kanban cards.

    6

  • 8/14/2019 Heijunka EN INGLS.pptx

    7/14

    Important Concepts

    Takt time

    It refers to the rate of production of thecompany based on customer demand.

    Pitch:

    Refers to the number of pieces per unit timebased on takt time

    7

  • 8/14/2019 Heijunka EN INGLS.pptx

    8/14

    Example

    8

    Products A01 B02 C03 D04 TOTAL

    Daily Requirement 300 240 180 60 780

    Quantity Per Pack 15 15 15 15 60

    # of kanbans 20 16 12 4 52

    Production time: 8hrs x 60 min = 480 min2 breakfast 15 min= -30 minRest 10 min= -10 min

    ---------------440 min

    440 min x 60 x2 = 52,800 seconds

  • 8/14/2019 Heijunka EN INGLS.pptx

    9/14

    9

    Takt time= 52.800 seconds / 780 units =67.6 seconds

    Pitch= 67.6 sec. x 15 units = 1,014 seconds or 16.9 min.

    So:

    The leveling of the production is to be achieved as follows:

    Product Quantity

    A01 20

    B02 16

    C03 12

    D04 4

  • 8/14/2019 Heijunka EN INGLS.pptx

    10/14

    10

    Representation of a Heinjunka box

  • 8/14/2019 Heijunka EN INGLS.pptx

    11/14

    HEIJUNKA BOX CHARACTERISTICS

    One row for each product

    A column for each pitch A single kanban card in each box

    Levels of lines in order

    Check the pitch

    11

  • 8/14/2019 Heijunka EN INGLS.pptx

    12/14

    12

  • 8/14/2019 Heijunka EN INGLS.pptx

    13/14

    CONCLUTIONS

    Calcular takt time.

    Calcular el pitch decada producto.

    Establecer el ritmo deproduccin

    Crear la caja heijunka

    13

  • 8/14/2019 Heijunka EN INGLS.pptx

    14/14

    REFERENCIAS

    Manual de Lean Manufacturing gua bsica 2da.Edicin. Autores: Alberto Villaseor Contreras,Edber Galindo Cota, editorial LIMUSA. Pginasconsultadas 93 101

    LEAN MANUFACTURING pginas consultadas137-139

    Creating your lean future state, how to move

    from seeing to doing chapter 5 load leveling, orheijunka. Autores: Tom Louyster, Don Tapping,pginas consultadas: 105 - 115