heap leaching technology implementation, lessons learned

20
Lessons Learned [email protected] Growth & Innovation Copper Group Heap Leaching Technology Implementation

Upload: omar-caceres

Post on 31-Oct-2014

549 views

Category:

Technology


8 download

DESCRIPTION

 

TRANSCRIPT

Page 1: Heap Leaching Technology Implementation, Lessons Learned

Lessons Learned

[email protected]

Growth & Innovation – Copper Group

Heap Leaching

Technology

Implementation

Page 2: Heap Leaching Technology Implementation, Lessons Learned

Processing Route Reserves Resources

Existing

Operations

Milling 83% 86%

Leaching 17% 14%

Projects

Milling 93% 89%

Leaching 7% 11%

Copper Outlook

0%

5%

10%

15%

20%

25%

2000

2001

2002

2003

2004

2005

2006

2007

2008

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

2023

2024

2025

%

% of Copper Production from Leaching

Actual Forecast

Only 20% of projects in the pipeline are

considering a Heap Leaching / SXEW circuit

Page 3: Heap Leaching Technology Implementation, Lessons Learned

Can we do something

different?

Page 4: Heap Leaching Technology Implementation, Lessons Learned

Project

Mining & Geology

Metallurgical Process

Environmental Aspects

Legal & Social Issues

Opex, Capex & Business Evaluation

Project vs. Process Development

Engineering & Infrastructure

Market Analysis

Profit, Profit, Profit

Shareholder value

Market share

Social/Environmental impacts

Page 5: Heap Leaching Technology Implementation, Lessons Learned

Process Development

Geomet

Theory Kinetics

Process Engineering

Flow Sheet

Design Criteria Testwork

Project Development

Exec Plan

Value Eng Specs

Page 6: Heap Leaching Technology Implementation, Lessons Learned

Concept Study

• Ore Body Knowledge

Pre-Feasibility

• Processing options

• Testwork

• Design criteria

• Location

• Capacity Trade-Off

Feasibility

• Value Engineering

• Main equipment selection

• Project Execution Plan

Project Development Path *Considering the metallurgical/engineering section only

6 to 12 months 2 to 3 years

Maybe 4 depending

on ore body complexity

12 to 18 months

Page 7: Heap Leaching Technology Implementation, Lessons Learned

• Exploration is not sufficiently advanced to allow a proper understanding of the ore

body

• Geometallurgical characteristics are not understood

• Mining sequencing is not clear

• Ore deposit information is just two numbers: Tons and average grade

• Urgency for getting some tests done and using assumptions to put together inputs for

business valuation without validating its real applicability/representativeness

• Benchmark data is used ignoring project-specific aspects (i.e. mineral association,

gangue minerals, location, climate, etc.)

Concept Study

Page 8: Heap Leaching Technology Implementation, Lessons Learned

• Testwork:

• Non-representative samples, or samples not linked with the mine production plan

• Wrong scale

• Site specific conditions ignored

• Sample preparation for test different from ore preparation at commercial scale

• Focus on chemistry (i.e. recovery), ignoring the physics (i.e. hydrodynamics)

• Focus only on core unitary processes in the flowsheet (i.e. leaching) but not integrated

• Done by a third party with limited contextual information, results usually late in the engineering process, lack of cross communication and follow up from the owners team

Pre-feasibility Study – Design Criteria

Page 9: Heap Leaching Technology Implementation, Lessons Learned

• Benchmark data

• Used incorrectly or at convenience

• Ignoring the project specifics (i.e. climate conditions)

• Too many processing options, complex flow sheets

• Mine production plan continuously modified without assessing the impact on process design criteria

• Technology development versus Project development

• Water balance not considered an issue, even in high rainfall environments

• Leach pad design based on assumed geotechnical / hydrodynamic characterization of the project site location

Pre-feasibility Study – Engineering

Page 10: Heap Leaching Technology Implementation, Lessons Learned

• Metallurgical test work still in progress, flowsheet is modified

• Additional resources added to the mineral inventory not covered by

previous testwork but within the payback period. Impact on risk/cost is not

assessed

• Design criteria not honored during engineering development, process

changes introduced to “improve” project economics

• Lack of metallurgical process details to support operating costs estimation

Feasibility Study

Page 11: Heap Leaching Technology Implementation, Lessons Learned

We need a plan …

Concept Study

•Understanding the Geometallurgy of the ore deposit

•Not a continuation of the exploration activities

•Narrow the processing options based on ore body knowledge

•Use range analysis to complete a probabilistic evaluation of the business case using benchmark and realistic assumptions based on the ore body knowledge

Pre-Feasibility

Study

•Selecting the preferred processing route, process flowsheet finalized

•First, define the design criteria, based on representative samples and at the right scale

•Then, complete the engineering study

•Re-do the range analysis now using the project data

Feasibility Study

•Optimizing the business case to finalize the project execution plan

•Complete the value engineering and risk management to improve chances of success

•Finalize the detail project execution plan

•Kick-off the operational readiness team

Is there enough mineral

resources to support a strong

business case?

How will the mineral

resources be developed to

deliver the most value?

How can the business

case be optimized to

minimize risk and ensure

value realization?

Page 12: Heap Leaching Technology Implementation, Lessons Learned

Concept Study

• Ore Body Knowledge

Pre-Feasibility

• Processing options

• Testwork

• Design criteria

• Location

• Capacity Trade-Off

Feasibility

• Value Engineering

• Main equipment selection

• Project Execution Plan

Project Development Path

6 to 12 months 2 to 3 years

Maybe 4 depending

on ore body complexity

12 to 18 months

Page 13: Heap Leaching Technology Implementation, Lessons Learned

1. Ore Body Knowledge

• Finish the exploration program first, at least having it sufficiently advanced to

ensure enough information is available to define viable options for processing

• Change management must be applied every time a new mineral inventory is

issued to validate that the process design criteria is still applicable. Same

with any new mine production plans

Lessons Learned

Page 14: Heap Leaching Technology Implementation, Lessons Learned

2. Testwork

• Select the right scale for your tests

o Reactor tests, bottle roll tests, mini column tests are just indicative and must not be used to define any process design criteria – Common for Process Development

o Define upfront the purpose of every tests and the information that will be provided to be used later in the design.

o Understand first the process drivers (i.e. liquid/air permeability, gangue reactivity, ore/liquid temperature, etc.) then define the scale

o The more complex the metallurgical system; the higher the scale that must be used to produce the required data (i.e. temperature dependent, high rate of gangue reactions)

o Full height columns / cribs / pilot heap tests are necessary to reduce scale-up risks. The lower the scale the highest the scale up penalty

Summary of Lessons Learned

Page 15: Heap Leaching Technology Implementation, Lessons Learned

Operational

Parameter Units

Commercial

Scale

Pilot / Large

Scale Test

Medium

Scale Test

Small

Scale Tests

Heap Height m 10 10 5 1

Solution Application

Rate L/m2/h 5 5 5 5

Solution to Ore Ratio L / h / t 0.28 0.28 0.56 2.78

Example

Page 16: Heap Leaching Technology Implementation, Lessons Learned

2. Testwork

• If you don’t have the right samples (type and quantity), wait for them…

• Technology development is different than project development. In projects, tests are

done to produce the design criteria; not to understand the technology. Keep them

separated

• Differences in ore preparation between the lab scale tests and the commercial scale

design can introduce significant risk to the project

• Lab test conditions must be aligned with the future operational conditions

Summary of Lessons Learned

Page 17: Heap Leaching Technology Implementation, Lessons Learned

2. Testwork

• Getting hydrodynamic and geotechnical data from testing fresh ore samples is a huge

mistake

• Maintain consistency in the way tests are done to be able to do comparison and

validation

• Accept the results as they are; use ranges to evaluate the feasibility of the project.

• Numerical models cannot replace the metallurgical test work program

Summary of Lessons Learned

Page 18: Heap Leaching Technology Implementation, Lessons Learned

3. General

• Heap Leaching cannot be fast-tracked; the way to shorten the development

time is by doing the right things in the right order

• Benchmark data is indicative only, be careful with copy and paste

• Keep the level of technology innovation under control managing the risk

profile

• Maintain focus on what needs to be done in each stage of project

development

• Do not outsource the definition of the process design criteria and flow sheet

Summary of Lessons Learned

Page 19: Heap Leaching Technology Implementation, Lessons Learned

• Define the mineral resources

• Short list the processing options based on ore body knowledge

Concept Study

• Define the processing route and its design criteria

• Define the production capacity, location and general layout

• Complete the range analysis to evaluate the probabilistic outcomes

Pre-Feasibility Study

• Finalize the risk management plan and value engineering

• Complete the project execution plan

Feasibility Study

Study deliverables

Page 20: Heap Leaching Technology Implementation, Lessons Learned

Questions ? Comments ?