Content
• Introduction to GSES
• Rooftop PV market - Growth and concerns
• Rooftop PV project development phases
• Site Assessment and Feasibility
• Design and Safety
• Operation and Maintenance
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Introduction
PROJECTS & TRAININGS
Australia 1998
China
India - 2012
New Zealand
Asia PacificAfrica
Diverse and proven experience in both government and private enterprise in: • Renewable Energy engineering Design • Consultancy • Compliance audits & Due diligence • Clean energy education
Grid connected and off grid renewable energy, energy resources and the commercial aspects of Renewable Energy technology systems and power supplies.
EXPERTISE
PORTFOLIO
Training Publications Engineering Consulting
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
More information available at www.gses.in
creating sustainable change through education, communication and leadership © 2012 GSES P/L
ROOFTOP PV - GROWTH AND CONCERNS
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Solar Power – status and target by 2022
2.12 10.3 37 941 1645 2632 3383 6763 9235
32000
48000
65000
82500
100000
0
20000
40000
60000
80000
100000
120000
FY 2008
-09
FY 2009
-10
FY 2010
-11
FY 2011
-12
FY 2012
-13
FY 2013
-14
FY 2014
-15
FY 2015
-16
FY 2016
-17 (u
ntil 31
.01.20
17)
FY 2017
-18
FY 2018
-19
FY 2019
-20
FY 2020
-21
FY 2021
-22
Installed Solar Capacity (MW) - status and target
Source: MNRE
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Source: MNRE
0
2000
4000
6000
8000
10000
12000
14000
Mahara
shtra
Uttar P
radesh
Andhra
Pradesh
Tamil N
adu
Gujarat
Rajasth
an
Karnata
ka
Madhy
a Prad
esh
West Ben
gal
Punjab
Haryan
a Delh
i Biha
r
Odisha
Telang
ana
Jharkh
and
Kerala
Chhatt
isgarh
Jammu a
nd K
ashmir
Uttarak
hand
Assam
Dadra
and N
agar
Haveli
Goa
Puduc
herry
Himach
al Prad
esh
Daman
and D
iu
Megha
laya
Chand
igarh
Manipu
r
Tripura
Mizoram
Nagala
nd
Arunach
al Prad
esh
Sikkim
Andam
an an
d Nico
bar Is
lands
Laksha
dweep
Sola
r Po
wer
cap
acity
(MW
)
RTPV Target by 2022
Total Solar Target by 2022
State wise target
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Cost trends and Grid parity
creating sustainable change through education, communication and leadership © 2012 GSES P/L
Defects & performance loss
Cause of Defects and Performance Losses in PV Power Plants
Japan follows similar tendency showing major faults at installation. Lack of JIS standard equivalent to IEC 62446 keeps non standardized inspection methods
• Over 1 GW • TÜV Rheinland Data • 200+ systems • inspected 2014 ~
Q1.2015
24 TÜV Rheinland Group
55%
25% 9%
5%
5% 1% Miscellaneous
Environmental influence
Installation faults
Product defects
Design, Documenation & planning faults
Maintenance
5
Risks influencing Mega Solar Plant Returns
Planning & Design
Construction Acceptance Operations Disposal
Provisional Final
TÜV Rheinland Group
“The land of rising risk?” – F. Martin, N. Morley [TÜV Rheinland]; PVTech 02/2015
Major Concern in Sustainable Growth
creating sustainable change through education, communication and leadership © 2012 GSES P/L
Component related defects
5
Risks influencing Mega Solar Plant Returns
Planning & Design
Construction Acceptance Operations Disposal
Provisional Final
TÜV Rheinland Group
“The land of rising risk?” – F. Martin, N. Morley [TÜV Rheinland]; PVTech 02/2015
Particularly Serious Defects in PV Power Plants in 2014 ~ Q1. 2015 – TÜV Rheinland Data
43%
21%
18% 7%
7%
4%
Modules
Cabling
Connection & distribution boxes
Inverter
Mounting structure
Transformer station
30 % of power plants show serious defects (incl. safety issues) or large number of issues
> 50 % of defects are caused by installation or planning errors
> 50 % of particularly serious defects are component related
Inspections at installation and construction will reduce failures on long term ! 27 TÜV Rheinland Group
Major Concern in Sustainable Growth
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Rooftop PV project development phases
• Inception / concept – Identify a potential PV project
• Project model – Revenue based (PPA), Net / gross metering/captive use
• Site Assessment and feasibility - site survey, project capacity, project cost,
economic assessment
• EPC - Engineering design, Procurement Construction
• Operation and maintenance - Preventive maintenance, monitoring &
evaluation and troubleshooting
creating sustainable change through education, communication and leadership © 2012 GSES P/L
SITE ASSESSMENT AND FEASIBILITY
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Objectives of Site Assessment
• Installation costs and timeline are minimized
• Maintenance costs are reduced
• System is safe and reliable
• Power plant generates maximum output at location
• Return on investment is high
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Main tasks during site assessment
• Assess occupational health and safety requirement
• Determine PV array location and suitable area conducting shadow analysis
• Determine placement of PV arrays – row spacing
• Determine number of modules can be installed
• Determine suitable location for inverters and other electrical equipment
• Prepare site and system layout planning
• Identify cabling routes and therefore the required cable run distances
• Study of site parameters that likely to affect the design considerations
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Site Assessment Tools
• Site survey format (questionnaire) • A Solar Pathfinder • A compass • A measuring tape/ digital distance meter • A camera • An angle measuring equipment • A notebook • A working partner
Site Assessment Tools
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Site Assessment Tools
creating sustainable change through education, communication and leadership © 2012 GSES P/L
1. In case of RCC flat roof: Usable area for installation of solar modules, load bearing capacity, accessibility to the roof, building orientation
1. In case of pitched/ slanted roof: Roof orientation, roof tilt angle, roof material, roof age, roof structure – type, material, load bearing capacity, accessibility and convenience to work on the roof
1. Shadow analysis: Assess potential source for near and far shadow, shadow from trees and vegetation, shadow from other buildings, shadow from objects like overhead tanks, poles and pipes etc., shadow from natural landscape in hilly areas
2. General environment - amount of dust, industrial smoke, pollution etc. 3. Solar radiation and climate data (wind and temperature) 4. Grid connectivity – voltage level, distance, cable routing
Site survey questionnaire
creating sustainable change through education, communication and leadership © 2012 GSES P/L
Determine PV array location
creating sustainable change through education, communication and leadership © 2012 GSES P/L
• Free from shadow in all days of the year – Use solar path finder
• Access for array maintenance
• Provide ample space for air cooling
• Prevails aesthetic of the building or premises
• Not far from the charge controller/ inverter/ battery bank
• Protect array from theft and vandalism
Determine PV array location
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Installation without shadow analysis
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Installation without shadow analysis
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Installation without shadow analysis
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Shadow Analysis - Use Solar Pathfinder
Determine PV array location
creating sustainable change through education, communication and leadership © 2012 GSES P/L
Determine PV array location
Shadow Analysis - Use Solar Pathfinder
creating sustainable change through education, communication and leadership © 2012 GSES P/L
Hei
ght
Distance
Critical Angle
Shadow analysis – analysing sun position
Determine PV array location
𝑆ℎ𝑎𝑑𝑜𝑤 𝐿𝑒𝑛𝑔ℎ𝑡 = 𝐻𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑡ℎ𝑒 𝑜𝑏𝑗𝑒𝑐𝑡 𝑥 𝐶𝑜𝑠 (𝐴𝑧𝑖𝑚𝑢𝑡ℎ 𝐴𝑛𝑔𝑙𝑒
𝑇𝑎𝑛 (𝐴𝑙𝑡𝑖𝑡𝑢𝑑𝑒 𝐴𝑛𝑔𝑙𝑒
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Sun Position at Chennai
Time 21st December 20th June Azim. Alt. Azim. Alt.
05:45 - - 67° 0° 06:00 - - 68° 3° 06:30 116° 0° 69° 10° 07:00 117° 7° 71° 16° 07:30 120° 13° 71° 23° 08:00 123° 20° 72° 30° 08:30 126° 26° 72° 37° 09:00 130° 32° 71° 44° 09:30 135° 37° 70° 51° 10:00 141° 42° 68° 57° 10:30 148° 47° 64° 64° 11:00 157° 50° 57° 70° 11:30 168° 52° 43° 76° 12:00 179° 53° 14° 79° 12:30 190° 53° 338° 79° 13:00 201° 51° 315° 74° 13:30 211° 48° 303° 68° 14:00 219° 44° 297° 62° 14:30 226° 39° 294° 55° 15:00 231° 34° 292° 49° 15:30 235° 28° 291° 42° 16:00 239° 22° 291° 35° 16:30 242° 16° 291° 28° 17:00 245° 10° 292° 21° 17:30 247° 3° 293° 14° 18:00 247° 0° 294° 7° 18:30 - - 295° 1° 18:45 - - 296° -3°
Shadow analysis – analysing sun position
Determine PV array location
creating sustainable change through education, communication and leadership © 2012 GSES P/L
Determining space between two rows
Row in the South Row in the North
Determine placement of PV array
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Determining Array Capacity
• Availability of shadow free area
• Installation purpose and budget
• Government program and incentive guidelines
• State Electricity Regulation
• Distribution Transformer capacity
• Connected load
creating sustainable change through education, communication and leadership © 2012 GSES P/L
DESIGN AND SAFETY
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
PV System Design Requirements
1. Determine system capacity – area, budget, policy and regulation
2. PV array system configuration – matching of inverter & array
3. Mechanical design – thermal, wind loading, corrosion
4. Safety issues – Personnel and system safety
5. Selection / rating of electrical equipment
6. Operation and Maintenance – procedure and recommendations, support system
and infrastructure
7. Marking and Signage - Equipment marking, signs and labelling
8. Documentation : IEC 62446: Grid-Connected Photovoltaic Systems—Minimum
Requirements for System Documentation, Commissioning Tests and Inspection
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Performance of Solar Modules
Efficiency and Performance of a PV module primarily depends on
• Solar Irradiance
• Operating Temperature
Cell Operating Temperature
For c-Si, changes is about 0.4 − 0.5% / 1°C variation in temperature away from STC.
There is almost a linear relationship between the variation in irradiance and variation of the short circuit current.
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Calculating Cell Temperature
Under international standards all modules are tested the following standard test conditions (STC).
Cell temperature 25˚C Irradiance of 1000W/m2 Air mass of 1.5
Normal Operating Cell Temperature (NOCT) has the following reference conditions:
Ambient air temperature 20˚C Irradiance of 800W/m2
Where, S = insolation in W/m2 Where, S = insolation in , S = insolation in W/m2
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Matching PV Array & Inverter
1. Matching of PV array to the voltage specification of an inverter
2. Matching of PV array to the inverter’s current rating
3. Matching of PV array to the inverter’s power rating
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Example of Technical Specifications of Inverters
Matching PV Array & Inverter
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Matching PV Array & Inverter
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Matching PV Array & Inverter
1. Matching of PV array minimum voltage to MPPT minimum input
2. Matching of PV array maximum voltage to inverter maximum DC input
3. Matching of PV array maximum current to MPPT maximum input current
4. Matching PV array maximum capacity to inverter maximum DC power input
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
1. Protection against electric shock • Equipotential bonding to avoid uneven potentials across an installation
• Functional earthing for electronic equipment
2. Protection against overcurrent
• Resulted from: earth faults or short circuits • Causes: Multiple parallel strings, external source, application circuit
4. Protection against overvoltage and effect of lightening
• PV array maximum voltage for minimum temperature • Rating of electrical equipment for PV array maximum voltage
System Protection
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Protection against electric shock
You never know who’s going to wind up touching the exposed metal of your PV system
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Protection against over current
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Protection against over current
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Protection against over current
PV String Overcurrent Protection:
As per IEC 62548: Design requirements for Photovoltaic (PV) arrays sizing Fault Current Protection is derived as below: Where: ISC-MOD = short circuit current of the module ITRIP = rated trip current of the fault current protection device
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
PV Array Maximum Voltage
• All protection devices are rated at “PV Array Maximum Voltage” • As per IEC 62548 PV Array Maximum Voltage is calculated:
1. Using the temperature coefficient given by the manufacturer
M = No. of modules in series
Protection against overvoltage
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
System Installation Min Voltage Rating per pole
Min Voltage Rating Overall
Non-earthed array with isolated inverter
0.5 x VMAX OC ARRAY V OC ARRAY
Earthed array with isolated inverter
V MAX OC ARRAY 2 x V MAX OC ARRAY
Non-earthed array with non-isolated inverter
V MAX OC ARRAY 2 x V MAX OC ARRAY
Earthed array with non-isolated inverter
NOT ALLOWED
Voltage Rating of Array Isolator
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Preventing Arcing and Fire
TS 62548 © IEC:2013(E) – 57 –
Annex D (informative)
Arc fault detection and interruption in PV arrays
Unlike traditional electrical products PV modules and wiring do not have an overall enclosure to contain arcs and fires resulting from component or system faults. Many PV systems operate at d.c. voltages which are very capable of sustaining d.c. arcs.
There are three main categories of arcs in PV systems (refer to Figure D.1):
Series arc which may result from a faulty connection or a series break in wiring.
A parallel arc which may result as a partial short circuit between adjacent wiring which is at different potentials.
Arcs to earth which result from failure of insulation.
If an arc develops due to a fault in a PV array this can result in significant damage to the array and may also result in damage to adjacent wiring and building structures. The most serious arc is likely to be a parallel arc because of the energy that is available to feed this type of arc, especially when the arc is between the main PV array conductors. This standard requires double insulation on cables used in PV array wiring and because of this double insulation requirement parallel arcs are very unlikely unless caused as a result of significant insulation damage due to fire damage or severe mechanical damage to cables. The most likely type of arc to occur in a PV system is a series arc. This is because PV systems typically contain a very large number of series connections. Series arcs are generally able to be stopped quickly by removing the electrical load from the PV array. In the case of grid connected systems this can be accomplished easily by shutting down the inverter system. Parallel arcs are much more difficult to extinguish but are also much less likely to occur.
PV
Series arcs
Arcs to earth
Parallel arcs
PV
PV
PV
PV
PV
Figure D.1 – Examples of types of arcs in PV arrays
If a series arc is not extinguished quickly it may propagate to involve other conductors and produce parallel arcs. It is therefore desirable to have a method of detecting and interrupting arcs in PV systems quickly. A new standard has been developed by Underwriters Laboratories UL1699B: Photovoltaic (PV) DC Arc-Fault Circuit Protection and manufacturers are in the process of developing equipment to meet this standard. The purpose of the arc fault circuit protection equipment is to detect and discriminate accurately arcs in PV arrays and to take action to interrupt the arc.
IEC 1845/13
Lice
nsed
to J
oan
Beal
on
07 A
ug 2
013
for C
omm
ittee
EL-
042
and
Stan
dard
s Au
stra
lia in
tern
al u
se o
nly.
Lic
ense
d to
Joa
n Be
al o
n 07
Aug
201
3 fo
r Com
mitt
ee E
L-04
2 an
d St
anda
rds
Aust
ralia
inte
rnal
use
onl
y. L
icen
sed
to J
oan
Beal
on
07 A
ug 2
013
for C
omm
ittee
EL-
042
and
Stan
dard
s Au
stra
lia in
tern
al u
se o
nly.
Lic
ense
d to
Joa
n Be
al o
n 07
Aug
201
3 fo
r Com
mitt
ee E
L-04
2 an
d St
anda
rds
Aust
ralia
inte
rnal
use
onl
y. L
icen
sed
to
Joa
n Be
al o
n 07
Aug
201
3 fo
r Com
mitt
ee E
L-04
2 an
d St
anda
rds
Aust
ralia
inte
rnal
use
onl
y. L
icen
sed
to J
oan
Beal
on
07 A
ug 2
013
for C
omm
ittee
EL-
042
and
Stan
dard
s Au
stra
lia in
tern
al u
se o
nly.
Lic
ense
d to
Joa
n
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Hot spot can cause fire
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Even a loose connection may cause fire
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
A damage in cable can cause fire
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Fire in PV system can be devastating
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Connecting solar modules
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Signage
Examples of Signs
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Signage
Examples of Signs
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Signage
Examples of Signs
creating sustainable change through education, communication and leadership © 2012 GSES P/L
OPERATION AND MAINTENANCE
creating sustainable change through education, communication and leadership © 2012 GSES P/L
Preventive maintenance plan
Maintenance Work Frequency Ensure security of the power plant Day-to-day Cleaning of solar PV panels to free from dust and other dirt like bird’s dropping etc. Weekly
Monitor power generation and export Daily (Remotely) Keep the inverters clean to minimise the possibility of dust ingress. Quarterly Ensuring all electrical connections are kept clean and tight. Half-yearly
Check mechanical integrity of the array structure. Annually
Check all cabling for mechanical damage. Annually Check output voltage and current of each string of the array and compare to the expected output under the existing conditions. Annually
Check the operation of the PV array DC isolator Annually
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Cleaning of modules
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Cleaning of Module
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Cleaning of modules
Safety of personnel: • String voltage + 700V DC is lethal
• Inspect array thoroughly for cracks, damage, loose connections before cleaning
• Cleaning personnel shall wear Personal Protective Equipment (PPE)
Cleaning time: • Recommended time - during low light conditions
• The best time - from dusk to dawn Quality of water: • De-ionized water
• Water should be of low mineral content with total hardness less than 75ppm
• Water with mineral content of more than 200ppm should NOT be used.
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Cleaning of modules
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Cleaning of modules
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Cleaning of modules
Use of cleaning agent:
• A mild, non-abrasive, non-caustic detergent with deionized water may be used.
• Abrasive cleaners or de-greasers should not be used.
• Acid or alkali detergent must not be used.
Removing stubborn marks: • Stubborn dirt such as birds dropping, dead insects, tar etc.,
• Use a soft sponge, micro-fiber cloth or non-abrasive brush.
• Rinse the module immediately with plenty of water.
Water pressure: • Water pressure should not exceed 35 bar at the nozzle.
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Cleaning of modules
Drying: • Modules should be dried after rinsing using a chamois or rubber wiper with a
plastic frame on an extension pole.
• Wipe the module surface from top to bottom to remove any residual water from
the module.
Water temperature: • Temperature of water used for cleaning should be same as ambient temperature
at the time of cleaning.
• Cleaning should be carried out when the modules are cool to avoid thermal
shock which can potentially cause cracks on the modules.
creating sustainable change through education, communication and leadership © 2012 GSES P/L creating sustainable change through education, communication and leadership © 2012 GSES P/L
Essential Elements of Quality System
Quality of Hardware
Quality of Management
creating sustainable change through education, communication and leadership © 2012 GSES P/L
THANK YOU
Contact Details: GSES India Sustainable Energy Pvt. Ltd., F-7B, Pocket F, Okhla Industrial Area Phase 1, New Delhi - 110020, Phone: +91-11-40587622; Mobile: +91 9560550075 e-mail: [email protected]; www.gses.in